Text extracted from the city's file for reading and search. Open the original on santaclaritacityca.iqm2.com. That file is the official record.

February 21, 2025
City of Santa Clarita
Attention: Carla Callahan, PE, Senior Engineer
23920 Valencia Boulevard, Suite 300
Santa Clarita, CA 91355
SUBJECT: Amendment #1 (Additional Service Request #5) Dockweiler Drive Extension Dear Carla,
The City of Santa Clarita (City) would like to redesign 13th Street from Railroad Avenue to Dockweiler Drive and Dockweiler Drive from 13th Street to Placerita Canyon Road to match the future Shadow Box offsite improvements. The improvement changes consist of the following:
• Wider 13th Street / Railroad Avenue intersection to accommodate a WB-67 vehicle and a separate bike path at grade railroad crossing
• Wider 13th Street for three (3) westbound lanes and five (5) eastbound lanes • Interim curve/future four-legged signalized 13th Street/Dockweiler Drive intersection • Dockweiler Drive with six (6) lanes between 13th Street and 12th Street • Signalized intersection at Dockweiler Drive/12th Street • Dockweiler Drive/Placerita Canyon Road intersection with revised water quality basin locations
• Dockweiler Drive transition south of Placerita Canyon Road • Dockweiler Drive Storm Drain realignment and modifications with new street alignment • Infiltration basin north of the wider 13th Street
• 2400 linear feet open concrete channel for existing pass-thru stormwater flows from 13th Street to the Railroad Avenue bridge over Little Placerita Creek These proposed improvements will be reviewed by the City at the 30%, 60%, 90%, 100% and Final phases.

The project will need to obtain new Railroad permits and approvals from CPUC and SCRRA for the 13th Street at Grade Railroad Crossing. Environmental permitting will be required for open channel outlet to Little Placerita Creek.

The City also would like to complete the Dockweiler Drive Plans, Specifications and Estimates (PS&E) and environmental permitting for the rest of the project from south of Placerita Canyon Road to the existing upper Dockweiler Drive. This segment has minor adjustments and changes.

MNS submitted the 100% PS&E package in June of 2021. Thereafter, the project was put on hold due to the impending Shadow Box and the Master’s University developments. MNS will need to address the City’s 100% comments, submit the final PS&E and address the City’s final comments.

Scope of Work
Task 1 – Project Management/Meetings
MNS will perform project management for a 9-month time period. This task will include:

1.1 Project Management – MNS will allocate 8 hours per month to perform project management responsibilities including City coordination, project schedule preparation, review and update, monthly invoicing and project progress report.

MNS Team member Railpros will manage the project and perform Client Coordination, Team coordination and project controls including managing cost, reviewing and submitting invoices, managing scope, developing and updating design and construction schedules, and managing the QA/QC process for approximately 8 months.

Deliverables:
• Project Schedule, Invoicing and Progress Reports

1.2 PDT Meetings – MNS will continue to conduct monthly PDT meeting. We will prepare a meeting agenda and send out meeting minutes for each meeting. (Total of 9 meetings).

Railpros will attend up to five (5) PDT Meetings.

Deliverables:
• Meeting Agenda and Minutes

1.3 Project Meetings – MNS will meet with City Staff, utility agencies, adjacent developers and stakeholders during the prosecution of the project. We will prepare a meeting agenda and send out meeting minutes for each meeting. (Total of 6 meetings) Deliverables:
• Meeting Agenda and Minutes

1.4 Additional Project Coordination and Meetings – The City anticipates bringing this project to construction in December 2026, MNS will allocate up to 8 hours per month for the additional 10 months to coordinate and meet for this project.

Task 2 – Preliminary Engineering

2.1 Utility Coordination/Potholing – MNS will perform utility coordination and potholing for the Shadow Box improvements and continue utility coordination for the original improvements south of Placerita Canyon Road to Upper Dockweiler Drive.

A. Utility Research and Coordination – MNS will coordinate with City staff and utility agencies during the prosecution of the project.

We will contact and coordinate with utility companies and update utility mapping if needed. We will map the utilities for the proposed Shadow Box improvements.

We will update and provide the existing utility matrix to the City when requested.

We will prepare final utility letters to notify the utility companies to relocate and/or adjust facilities and utility letters of no conflict.

B. Utility Potholing - MNS Team Member C Below, Inc. (C Below) will perform five (5) utility potholing for the proposed signal pole foundations at 12th Street to confirm no conflicts. The potholes are assumed to be 0 to 5’ deep. A standard pothole is 12 in x 12 in, performed to the top of pipe or encasement with slurry backfill and a hot surface patch. Service includes DigAlert coordination & delineation, no cost encroachment permit coordination and preparation, vacuum excavation to top of utility, encasement or stop depth, standard traffic control and engineered traffic control plans, removal of debris and pothole report.

MNS will coordinate the utility potholing, meet the C Below in the field to mark out the proposed pothole locations.

Deliverables:
• Utility Letters and Correspondences
• Utility Matrix
• Utility Potholing Report

2.2 Geotechnical Services – MNS team member – RT Frankian, Inc. (RT Frankian) will perform geotechnical investigation in support the approximate 2,350 feet of open concrete channel on Shadow Box Property.

In addition, RT Frankian will review and approve the revised grading plans associated with the Shadow Box Improvements.

Geotechnical Review – RT Frankian will review the LGC Valley, Inc. Geotechnical Report that was prepared in support of EIR for the Shadow Box Studio project.

Report P reparation – RT Frankian will update the Geotechnical Report to provide recommendations for trenching, backfilling and compacting material for the concrete channel.

Plan Approval – R T Frankian will review and approve the revised Grading and Retaining Wall Plans on 13th Street from Railroad Avenue to Dockweiler Drive and Dockweiler Drive from 13th Street to the Weste Property.

Deliverables:
• Updated Geotechnical Report
• Grading Plan Approval

2.3 30% Design (Preliminary Plans) – MNS and team member Pacific Coast Land Design (PCLD) will prepare 30% preliminary plans. The following plan sheets in 1” = 40’ scale are anticipated:
• Geometric Approval Drawing (GAD) including typical sections, roadway improvements, centerline, road profile, and right-of-way alignment and connection/tie-in (2 Sheets)
• Preliminary Rough Grading Plan (2 Sheets)
• Preliminary Drainage Plan (4 Sheets)
• Landscaping Plan (2 Sheets)
• Oak Tree Protection Plan (1 Sheet)
PCLD will update the Oak Tree Protection Plans and report based on the Shadow Box Improvements.

We will prepare a 30% construction cost estimate for the proposed Shadow Box improvements.

We will update the Technical Design Memorandum to discuss design parameters and design elements.

We will update the GAD based on the City’s comments.

The street configuration and footprint will be based on the Shadow Box Preliminary Plans, EIR and Traffic Study.

Deliverables:
• 30% Plans and Estimate
Task 3 – Final Design

3.1 Construction Documents and Plan Review - MNS team will prepare 60%, 90%, 100% and Final Submittals for the City’s review.

A. 60%, 90%, 100% and Final Plans – MNS team will prepare the following plan sheets (approximately 110 Sheets):
• Update Title Sheet, General Notes, Key Maps, etc. (4 Sheets) • Demolition and Utility Disposition Plans (2 Sheets)
• Utility Pothole Location Plans (2 Sheets)
• Typical Sections (2 Sheets)
• Street Improvement Plan & Profile - Dockweiler (1 Sheet) • Street Improvement Plan & Profile - 13th Street (1 Sheet) • Update Street Improvement Plan & Profile - Railroad Avenue (1 Sheet) • Street Improvement Plan & Profile - 12th Street (1 Sheet) • Street Improvement Plan & Profile - Placerita Canyon Road (1 Sheet) • Construction Details Curb Ramps - 3 intersections (3 Sheets) • Construction Details - Parking Lots and Driveways (6 Sheets) • Grading Plan (2 Sheets)
• Grading Sections/Details (2 Sheets)
• Update Retaining Wall Plan (1 Sheet)
• Update Storm Drain Title Sheets, General Notes, Key Map (1 Sheet) • Dockweiler Dr Storm Drain Improvement Plan & Profile (4 Sheets) • Dockweiler Dr Storm Drain Bioretention Areas (1 Sheet) • Dockweiler Dr Storm Drain Improvement Details (2 Sheets) • Shadow Box Storm Drain Improvement Plan & Profile (2 Sheets) • Shadow Box Storm Drain Improvement Details (2 Sheets) • Shadow Box Infiltration Basin Plan (1 Sheet)
• Shadow Box Infiltration Basin Profile (1 Sheet)
• Shadow Box Infiltration Basin Sections (1 Sheet)
• Shadow Box Infiltration Basin Details (2 Sheets)
• 13th St & Dockweiler Signing and Striping Plan (2 Sheets)

• Traffic Signal Plan at 12th Street (1 Sheet)
• Revise Traffic Signal Plan at Placerita Cyn Rd (1 Sheet) • Traffic Signal Details (1 Sheet)
• Interconnection Plan (1 Sheet)
• Interconnection Details (2 Sheet)
• Street Lighting Plan (1 Sheet)
• Circuit Diagram (1 Sheet)
• Street Lighting Details (1 Sheet)
• Lighting Photometric Analysis (1 Sheet)
• Hardscape/Planting/Irrigation Plans & Details (11 Sheets) • Stage Construction Plan (1 Sheet)
• Traffic Control Plans (10 Sheets)
• Revise Detour Plan (3 Sheets)

Railpros Plans:
• Railroad Crossing - General (6 Sheet)
• Railroad Crossing - Const Phasing & Constructability Review (2 Sheets) • Railroad Crossing - Civil Grading (6 Sheets)
• Railroad Crossing – Demolition and Utilities (1 Sheet) • Railroad Crossing - Trackwork (6 Sheets)
• Railroad Crossing - Traffic Signal/Signing and Striping (6 Sheets) Railpros will revise General Sheets that are detailed, which include project overview sheets and general notes from City/Metro and Railroad Owners, special directions to the contractor, vicinity, and project location maps.

Railpros will revise the Basis of Design report (related to RailPros specific scope of work- related items.)
Railpros will revise the Railroad Phasing Plans that define the limits and type of work at each phase and required work windows (up to 2 sheets). Phasing Plans will be designed in accordance with engineering standards and typical construction approach of SCRRA, and the recommended practices of the American Railroad Engineering and Maintenance of Way Association (AREMA) and include discussion and determination of acceptable work windows with SCRRA, identification of proposed laydown area limits, and constructability analysis to assure the best application of construction technology and simplify the design in order to reduce cost and accelerate the schedule.

Railpros will revise Grade Crossing Improvements and Shared Use Path at Crossing (including demolition, plan layouts, cross sections, crossing details, crosswalks, sidewalk, ADA Ramps, Railroad access points), identify utility conflicts at the crossing and prepare specifications, quantities, and engineers estimate.

Railpros will coordinate with SCRRA for dry utilities crossing the railroad and check for impact to project.

Railpros will revise the track alignment design plan and profile for the grade crossing using new survey data (including demolition, removal and disposal) including 2 Plan and Profile sheets including tabular presentation of curve data, 1 Track Geometry Table Sheet, 3 Typical Section Sheets with station limits Roadway Modeler and grading tie-ins, and earthwork cross sections. We will prepare specific design standards, specifications, quantity take off and cost estimate. We will update the Track Chart.

Railpros will revise Traffic Signal Modification Plans for 13th Street at Railroad Avenue including calculations. We will prepare specific design standards, specifications, quantity take-off and cost estimate, update 13th Street Grade Crossing Preemption Calculations and Measurement Exhibit and update the Signing and Striping Plans. Signing and Striping Plans will be for 13th Street from Railroad Ave up to BCR of Arch Street and Railroad Avenue from 1000 feet to the north and 400 feet to the south on Railroad Avenue from the 13th St intersection.

Railpros will provide submittal compilation and comment resolution. We will attend and respond to 3 CRM meetings per submittal. Submittal stages include 60%, 90% and 100% Design. RailPros will provide responses to comments from SCRRA, City and Stakeholders. Railpros will attend intra disciplinary review meetings.

RailPros will gather the final approved plans from SCRRA, LA Metro and other stakeholders and prepare any technical exhibits.

Merge and Revise Improvement Plans from south of Placerita Canyon Road to Upper Dockweiler Drive - MNS Team will update the improvement plans per City Comments, Property Owner Coordination and latest Master University Improvement and Grading Plans (approximately 67 Sheets). We will merge these plan sheets with the revised improvement plans from Railroad Avenue to Placerita Canyon Road.

Final Plans - B ased on the City’s 100% Comments, MNS Team will revise and prepare the Final Plans.

Deliverables:
• Basis of Design Report (Railroad)
• 60% Plans and Estimate
• 90% Plans, Specifications and Estimate
• 100% Plans, Specifications and Estimate
• Final Plans, Specifications and Estimate
B. Update Specifications – MNS team will update the specifications at the 90% submittal.

Based on the City’s comments, we will prepare the 100% and Final specifications.

Deliverables:
• 90%, 100% and Final Specifications
C. Engineer’s Construction Estimate – MNS team will update engineer’s construction estimate at 60%, 90%, 100% and Final Phases.

Deliverables:
• 60%, 90%, 100% and Final Engineer’s Construction Estimate D. Update Hydrology and Hydraulic Report – MNS will update the Hydrology and Hydraulic Report for the Shadow Box improvements. The report will be submitted to the City and LACDPW for review. We will update the report based on the City’s and LACDPW comments. We anticipate three (3) iterations for approval.

Deliverables:
• Hydrology and Hydraulic Report
E. Update SWPPP and Temporary Water Pollution Control (TWPC) Plan – Based on the latest NPDES Permit, MNS will update the SWPPP and TWPC Plan for the Shadow Box improvements. The report will be submitted to the City for review. We will update the SWPPP based on the City’s comments. We anticipate three (3) iterations for approval.

Deliverables:
• SWPPP including TWPC Plans
F. Update SUSMP – MNS will update the SUSMP for the Shadow Box improvements.

The report will be submitted to the City for review. We will update the SUSMP based on the City’s comments. We anticipate three (3) iterations for approval.

Deliverables:
• SUSMP

3.2 Legals & Exhibits – MNS will finalize the remaining legal description and plats for permanent and temporary use. This scope includes preparing up to 6 legal descriptions needed along Arch Street and Placerita Canyon Road to finalize any remaining revisions or acquisitions for the project.

Assumption:
• New title reports will not be required.

Deliverables:
• Legal & Exhibits

3.3 Plan Approvals and Permits
A. Railroad (CPUC, SCRRA, Metro & UPRR) Coordination, Agreement & Permits – Railpros will coordinate with stakeholders and include up to 20 virtual meetings with the City of Santa Clarita, Metro, UPRR, SCRRA, FRA, CPUC, third party utilities and other private businesses. Coordination will include submitting SCRRA Request for Special Design considerations, working with SCRRA on the Construction and Maintenance (C&M) agreement, coordination and meetings between CPUC, SCRRA and the City, addressing public crossing review questions, coordination with and review of the 100% SCRRA Signal Design.

Railpros Assumptions and Exclusions:
• 8 Client Coordination meetings and 8 monthly coordination meetings. • 8 technical and design meetings including a kickoff meeting. Railpros project manager will prepare and complete Agendas and minutes for technical and Design meetings only.
• Up to 20 combined Virtual meetings between the City of Santa Clarita, LA Metro, UPRR, SCRRA, FRA, CPUC, Third-party utilities and other private businesses. • Up to 1 SCRRA RFSDCs at 1 iteration each.
• 1 new CPUC Field Diagnostic meeting will be required for the crossing. • RailPros will only review the 100% Signal design related with 13th Street crossing.

SCRRA to perform design.
• Plan checking and permit fees will be paid by the City.

B. LACDPW Permit - MNS will submit via EPIC-LA the Hydrology, Hydraulics and Storm Drain Plans which will include the Shadow Box storm drain system to obtain approval from LACDPW (MTD). We will coordinate and meet with LACDW staff and revise the

reports and storm drain plans per the LACDPW comments. We assume three (3) iterations.

The City will pay all plan checking and permit fees.

Deliverables:
• LACDPW MTD Permit
Task 4 – Environmental Permitting
MNS team member Rincon Consultants, Inc. (Rincon) will prepare the reports and obtain the required environmental permits.

To date, Rincon has prepared the following technical reports to support the permitting effort for the project:
• Jurisdictional Delineation Report (July 2021)
• Coastal California Gnatcatcher Report (July 2021)
• Rare Plant Survey and Report (July 2021)
• Biological Resources Assessment (December 2021)
Due to several regulatory changes and the Project redesign, the Jurisdictional Delineation Report will need to be updated. In addition, the 2021 Coastal California Gnatcatcher Report and Rare Plant Survey Report will be updated with more recent data collected during the proposed 2025 survey.

Rincon also prepared the Biological Resources Assessment, which will require updates to reflect the redesign of 13th Street. To accurately reflect the re-design and meet the anticipated needs of the regulatory agencies, the text and figures outlining the project description, project footprint, and impacts to jurisdictional waters will be updated.

Additionally, the results of the Jurisdictional Delineation Report, Coastal California Gnatcatcher Survey Report, and Rare Plant Survey Report will be summarized in the Biological Resources Assessment.

Project impacts to jurisdictional waters are anticipated during the construction of the 13th Street improvements and the pedestrian bridge over Newhall Creek. Rincon will prepare the appropriate permit application packages.

Rincon proposes the following tasks:

4.1 Project Re-initiation/Management - Up to two Rincon staff will attend up to two virtual 1-hour project team meetings with MNS and the City to review the Project’s newly proposed design and project schedule. Rincon will prepare notes following the meetings and distribute them to the project team.

Rincon will be highly responsive to project management and coordination with the various parties involved to ensure all project requirements described above are met in an efficient and cost-effective manner. Rincon will provide regular communication to MNS and City staff as needed, throughout the course of the permitting process regarding project needs, changes, schedule, budget, and deliverables. This task includes miscellaneous activities required to manage the various tasks above such as regular e- mail and telephone communications and other tasks associated with contract administration and client coordination.

4.2 Technical Reports
A. Jurisdictional Delineation Report Update - Rincon will conduct a jurisdictional delineation survey of the Project area and 100-foot buffer to verify the extent/condition of aquatic resources delineated in 2021. Rincon will prepare an updated Jurisdictional Delineation Report that will reflect the survey findings and regulatory changes that have occurred since 2021, including text and figures. In addition, the previous vegetation community and land cover mapping will be verified.

Assumptions:
• A Rincon Senior Biologist and Associate Biologist will conduct the jurisdictional delineation field survey on one calendar day.
• Rincon will address one round of comments from MNS and City staff (one round total) on the report.
• The report will be included in the permit application packages. • • If the 2023 jurisdictional delineation data from Shadowbox Studios becomes available for use on this Project, a jurisdictional delineation field survey would not be required upon direction of the City. The Jurisdictional Delineation Report would then be updated utilizing the 2023 delineation data from Shadowbox Studios for the drainage at 13th Street, the 2021 delineation data from Rincon at Newhall Creek, and the text and figures would be updated to address the recent regulatory changes.

B. Protocol Coastal California Gnatcatcher Surveys and Report Update - Rincon will conduct protocol surveys for Coastal California Gnatcatcher (CAGN) and prepare an updated report. Per U.S. Fish and Wildlife (USFWS) CAGN survey protocol (USFWS

1997), Rincon will notify the appropriate USFWS office in writing, at least ten working days prior to the anticipated start date of survey work and receive approval prior to beginning work. If surveys are conducted during the breeding season (March 15 - June 30), a minimum of six (6) surveys are required, to be conducted at least one week apart.

If conducted between July 1 and March 14, a minimum of nine (9) surveys are required, to be conducted at least two weeks apart. The surveyor must hold a Recovery Permit issued by USFWS under Section 10(a)(1)(A) of the Endangered Species Act authorizing CAGN survey efforts.

After conducting the required focused surveys, Rincon will prepare a survey report for submittal to MNS and City staff for review, prior to submittal to USFWS. The survey area will include the Project disturbance area and a 100-foot buffer.

Assumptions
• Rincon will conduct nine field surveys with one biologist in areas of suitable habitat.

Each survey will be conducted by a local and permitted biologist within a 4-hour timeframe, including travel. Our estimated cost would decrease if surveys were to be conducted during the breeding season (only six surveys required). • We assume that survey results will be negative based on the 2021 negative survey results. This task does not include preparation of a Biological Assessment (BA) or other documentation addressing the presence of listed species. • Rincon will address one round of comments from MNS and City Staff and one round from USFWS staff (two rounds total) on the report.
• The report will be included in the permit application packages.

C. Protocol Rare Plant Survey and Report Update - Rincon will conduct a protocol rare plant survey and prepare an updated report. Prior to conducting the protocol rare plant field survey, Rincon will conduct a desktop review of the CDFW California Natural Diversity Database (CNDDB); USFWS Critical Habitat Portal; CDFW Special Vascular Plants, Bryophytes, and Lichens List; the CDFW State and Federally Listed Endangered, Threatened, and Rare Plants of California; and the California Native Plant Society (CNPS) online Inventory of Rare and Endangered Vascular Plants of California to determine if any additional special status plants were recorded on-site or in the Project vicinity.

A Rincon Senior Botanist and Associate Biologist will conduct one protocol rare plant field survey of the Project area and a 100-foot buffer, conducted in the appropriate season when detection of potentially occurring rare plants would be present and

flowering (spring). The survey will be conducted to determine the presence or absence of rare plants in general accordance with CDFW (2018) and CNPS (2001) survey guidelines. The survey will include an evaluation of habitat suitability to support rare plant species based on site conditions and the characteristics of rare plant species that may occur in the vicinity. A Rare Plant Survey Report will be prepared to present the results of the desktop review and field survey.

Assumptions
• A Rincon Senior Botanist and Associate Biologist will conduct one protocol rare plant field survey on one calendar day in spring (seasonally timed to allow for detection). • We assume that survey results will be negative based on the 2021 negative survey results.
• Rincon will address one round of comments from MNS Engineers and City staff (one round total) on the report.

4.3 Biological Resources Assessment
A. Biological Resources Assessment Update - In order to accurately reflect the Project redesign and meet the anticipated needs of the regulatory agencies, the existing Biological Resources Assessment will be updated so that the text and figures outlining the project description, footprint, and impacts to jurisdictional waters will reflect the redesign. Additionally, the report will be updated with the survey results and regulatory and jurisdictional updates from the Jurisdictional Delineation Report. The report will be updated with the results of the protocol surveys for Coastal California Gnatcatcher and Rare Plants. Lastly, an updated literature review will be conducted to identify and analyze the potential impacts for any newly identified sensitive species to occur on-site, and the report will be updated to provide additional or revised avoidance and minimization measures. Notably, since the preparation of the Biological Resources Assessment in 2021, the Crotch’s bumble bee (Bombus crotchii) has become a candidate species under the California Endangered Species Act and will be addressed in the updated report.

Assumptions:
• The Biological Resources Assessment will be updated to reflect a single project design (redesign).
• Any additional changes to the project design are outside of this scope of work. • No fieldwork will be necessary for this task as the fieldwork needed to inform the BRA is included in Tasks 2.1, 2.2, 2.3, and 3.2.

• Rincon will address one round of comments from MNS Engineers and City Staff and one round from CDFW staff (two rounds total) on the report. • The report will be included in the permit application packages.

B. Crotch’s Bumble Bee Habitat Assessment - Rincon will conduct an on-site assessment per CDFW guidelines (2023) of foraging, nesting, and overwintering habitat for Crotch’s bumble bee. The area assessed will include the Project disturbance area and a 100-foot buffer. At this time, Rincon does not suggest conducting a protocol-level survey for the species as it is already known to occur in the project vicinity as documented in CDFW’s CNDDB and is likely present within the Project area; impacts to underground nests can likely be avoided with sufficient avoidance and minimization measures that will be discussed in the Biological Resources Assessment, including but not limited to pre-construction surveys and avoidance of active nests if found.

Assumptions:
• Includes 4 hours of fieldwork for two Rincon Biologists combined conducted on the same day of the jurisdictional delineation survey or rare plant survey, plus 4 hours of office-based support and analysis.

4.4 Regulatory Permitting - As described above, Rincon understands that impacts to jurisdictional waters will occur as a result of construction of the 13th Street improvements, specifically an ephemeral unnamed drainage that is located in the Shadowbox property. In addition, impacts to jurisdictional waters will occur as a result of construction of the proposed pedestrian bridge over Newhall Creek. Due to the design of the bridge, no direct impacts will occur within jurisdictional waters. i.e., the channel bed, banks, and riparian; however, shading impacts to a sensitive natural community are anticipated. Rincon will prepare a California Department of Fish and Wildlife (CDFW) Lake or Streambed Alteration (LSA) Notification and a Los Angeles Regional Water Quality Control Board (RWQCB) Waste Discharge Requirement (WDR) application for the Project. A Clean Water Act Section 404 permit is not required and will not be prepared for the USACE, as waters of the U.S. are not present at the 13th Street improvements, and the waters of the U.S. in Newhall Creek will be avoided and not impacted by the construction of the pedestrian bridge.

A. CDFW Streambed Alteration Agreement - Project impacts to the CDFW- jurisdictional streambed (bed, banks, and riparian vegetation) within the ephemeral drainage near 13th Street due to the proposed construction of the stormwater conveyance system and within Newhall Creek due to the proposed shading associated

with the pedestrian bridge will require a LSA Notification pursuant to § 1600 et seq. of the California Fish and game Code (CFGC). Rincon will prepare the CDFW LSA Notification and supporting documentation, provide it to MNS and the City for review and comment, incorporate any requested changes, and upon your approval, submit the application to CDFW via their Environmental Permit Information Management System (EPIMS). Rincon will attend a pre-application meeting on-site with CDFW if requested by CDFW to discuss the Project and confirm notification requirements. Rincon will review the draft SAA issued and provide recommendations to the project team on any suggested revisions and submit the revisions to CDFW on behalf of the City.

Assumptions:
• The SAA Notification will reflect a single project design (redesign). Any additional changes to the project design are outside of this scope of work. • One senior regulatory specialist (or Project Manager) will attend one pre-application meeting onsite with CDFW staff (not to exceed 6 hours total on-site, plus travel). • Existing documentation and survey reports completed previously and as part of this scope of work will be adequate, and no additional biological surveys or reports will be needed other than what is stated herein.
• Rincon will incorporate one round of comments on the SAA Notification package from MNS and City staff (one round total).
• Rincon will incorporate one round of comments on the SAA notification package from CDFW (not to exceed 8 hours).
• The City will provide payment for application fees to CDFW directly. Rincon will calculate the final fee based on the cost of the work in the CDFW-jurisdictional streambed, which is assumed to be provided by MNS.
• The City will provide a copy of the completed CEQA document, proof of payment of CEQA filing fees, and a copy of the Notice of Determination to include in the notification.

B. RWQCB Water Discharge Requirement - Impacts to waters of the State within the ephemeral drainage near 13th Street due to the proposed construction of the stormwater conveyance system will require a WDR pursuant to the Porter-Cologne Water Quality Control Act. The Los Angeles RWQCB requires notification through submittal of a WDR application package. Rincon will prepare the WDR application package and supporting documentation, provide it to MNS and the City for review and comment, incorporate any requested changes, and upon your approval, submit the application to Los Angeles RWQCB electronically. Rincon will attend a pre-application meeting on-site with Los

Angeles RWQCB to discuss the Project and confirm permit application requirements; a pre-application meeting request will be submitted at least 30 days prior to submittal of the application to Los Angeles RWQCB. Rincon will review the draft WDR issued and provide recommendations to the project team on any suggested revisions and submit the revisions to Los Angeles RWQCB on behalf of the City.

Assumptions:
• The WDR application package will reflect a single project design (redesign). Any additional changes to the project design are outside of this scope of work. • One senior regulatory specialist (or Project Manager) will attend one pre-application meeting onsite with Los Angeles RWQCB staff (not to exceed 6 hours total on-site, plus travel).
• Existing documentation and survey reports completed previously and as part of this scope of work will be adequate, and no additional reports will be needed other than what is stated herein.
• Rincon will incorporate one round of comments on the WDR application package from MNS and City staff (one round total).
• Rincon will incorporate one round of comments on the WDR application package from Los Angeles RWQCB (not to exceed 8 hours).
• The City will provide payment for application fees to Los Angeles RWQCB directly.

The final fee is calculated based on the impacted acreage of waters of the State. • The City will provide a copy of the completed CEQA document, proof of payment of CEQA filing fees, and a copy of the Notice of Determination to include in the application.

C. Compensatory Mitigation Planning - Based on the results of the jurisdictional delineation and associated impact analysis, Rincon will facilitate purchasing mitigation credits at Petersen Ranch Mitigation Bank to meet expected CDFW and Los Angeles RWQCB requirements for permanent impacts to jurisdictional waters as a result of the Project. Compensatory mitigation for permanent impacts is a required element of the permit packages. Payment of a fee to the bank is dependent on the acreage and type of mitigation credit needed, which Rincon assumes that the City will pay directly.

Assumptions:
• Facilitation with Petersen Ranch Mitigation Bank will not exceed 10 hours, to be conducted by Rincon Senior Staff.

• The City will provide payment to Petersen Ranch Mitigation Bank directly. The final fee is calculated based on the impacted acreage and type of mitigation credit needed.

Deliverables:
• Jurisdictional Delineation Report Update
• Protocol Coastal California Gnatcatcher Surveys and Report Update • Protocol Rare Plant Survey and Report Update Compensatory Mitigation Plan • Biological Resources Assessment Update
• Crotch's Bumble Bee Habitat Assessment
• CDFW Streambed Alteration Agreement
• RWQCB Waste Discharge Requirement
• Compensatory Mitigation Planning
Fee
The fee for the scope of work is included in the attached fee spreadsheet, which includes the fee breakdown details.

Please let us know if we can provide any more information and feel free to call me to discuss this request at (805) 719-9807 or if you prefer, via email at [email protected].

Sincerely,
MNS Engineers, Inc.

Brandon Reyes, PE
Vice President

Principal
Engineer
Lead Engineer
Senior Project
Engineer
Project Engineer
Associate Engineer
Assistant
Engineer
Principal Surveyor
Assistant
Project Surveyor
Task Descriptions $325 $285 $245 $220 $200 $185 $295 $170 Task 1. Project Management

1.1 Project Management 72 36 108 $32,220 $2,310 $33,528 $68,058 $68,058

1.2 PDT Meetings (9) 27 14 41 $12,205 $5,429 $27,543 $45,177 $45,177

1.3 Project Meetings (6) 12 6 18 $5,370 $4,208 $18,362 $27,940 $27,940

1.4 Additional Project Coordination and Meetings 40 40 80 $22,800 $22,800 $22,800 Task 2. Preliminary Engineering

2.1 Utility Coordination/Potholing $59,390
A. Utility Research & Coordination 40 64 40 144 $36,080 $1,500 $37,580 B. Utility Potholing 2 4 8 14 $3,110 $18,700 $21,810

2.2 Geotechnical Services 8 4 12 $3,580 $33,000 $36,580 $36,580

2.3 30% Design $82,736
Geometric Approval Drawings (2 Sheets) including Typical Sections 8 20 12 40 $9,720 $9,720 Preliminary Rough Grading Plan (2 Sheets) 4 16 12 32 $7,440 $7,440 Preliminary Drainage Plan (4 Sheets) 8 32 12 52 $12,660 $12,660 Preliminary Landscape Plans (2 Sheets) $14,289 $14,289
30% Construction Cost Estimate 4 16 8 28 $6,700 $3,388 $10,088 Update Technical Design Memorandum 8 16 24 $6,520 $6,520 Update Oak Tree Report 2 2 $650 $5,709 $6,359
Update Oak Tree Protection Plan (1 Sheet) $7,480 $7,480 GAD and Estimate Updates 4 16 16 36 $8,180 $8,180
Task 3. Final Design

3.1 Construction Documents and Plan Review $1,096,174
A. 60%, 90%, 100% and Final Plans (110 Sheets)
Update Title Sheet, General Notes, Key Maps, Etc. (4 Sheets) 4 8 16 28 $6,020 $50 $6,070 Demolition and Utility Disposition Plans (2 Sheets) 8 16 32 56 $12,040 $50 $12,090 Utility Pothole Location Plans (2 Sheets) 1 4 8 13 $2,685 $50 $2,735 Typical Sections (2 Sheets) 6 12 20 38 $8,590 $50 $8,640 Street Improvement Plan & Profile - Dockweiler Drive (1 Sheet) 4 12 12 28 $6,460 $25 $6,485 Street Improvement Plan & Profile - 13th Street (1 Sheet) 4 12 12 28 $6,460 $25 $6,485 Street Improvement Plan & Profile - Railroad Avenue (1 Sheet) 2 4 8 14 $3,110 $25 $3,135 Street Improvement Plan & Profile - 12th Street (1 Sheet) 2 12 8 22 $5,070 $25 $5,095 Street Improvement Plan & Profile - Placerita Canyon Road (1 Sheet) 2 12 8 22 $5,070 $25 $5,095 Construction Details Curb Ramps - 3 intersections (3 Sheets) 12 24 48 84 $18,660 $75 $18,735 Total Costs
MNS Engineers, Inc. - Team Resource Estimate
Dockweiler Drive Extension Project — Amendment #1 (Additional Service Request #5) Task Costs
C-Below
RT Frankian &
Associates, Inc.

SummaryMNS Engineers Subconsultants & Reimbursables
MNS Resource Costs
Pacific Coast
Land Designs, Inc.

MNS Resource Hours
Reimbursables
Rincon Consultants, Inc.

Railpros

Principal
Engineer
Lead Engineer
Senior Project
Engineer
Project Engineer
Associate Engineer
Assistant
Engineer
Principal Surveyor
Assistant
Project Surveyor
Task Descriptions $325 $285 $245 $220 $200 $185 $295 $170 Total Costs
MNS Engineers, Inc. - Team Resource Estimate
Dockweiler Drive Extension Project — Amendment #1 (Additional Service Request #5) Task Costs
C-Below
RT Frankian &
Associates, Inc.

SummaryMNS Engineers Subconsultants & Reimbursables
MNS Resource Costs
Pacific Coast
Land Designs, Inc.

MNS Resource Hours
Reimbursables
Rincon Consultants, Inc.

Railpros
Construction Details - Parking Lots and Dwys (6 Sheets) 20 40 80 140 $31,100 $125 $31,225 Grading Plan (2 Sheets) 8 24 20 52 $12,180 $50 $12,230
Grading Sections/Details (2 Sheets) 8 24 24 56 $12,920 $50 $12,970 Update Retaining Wall Plan (1 Sheet) 1 2 4 7 $1,555 $25 $1,580 Update Storm Drain Title Sheet, General Notes, Key Map (1 Sheet) 1 2 8 11 $2,295 $25 $2,320 Dockweiler Dr Storm Drain Improvement Plan & Profile (4 Sheets) 16 40 24 80 $19,440 $100 $19,540 Dockweiler Dr Storm Drain Bioretention Areas (1 Sheet) 6 12 12 30 $7,110 $25 $7,135 Dockweiler Dr Storm Drain Improvement Details (2 Sheets) 12 24 24 60 $14,220 $50 $14,270 Shadow Box Storm Drain Improvement Plan & Profile (2 Sheets) 10 24 36 70 $15,790 $50 $15,840 Shadow Box Storm Drain Improvement Details (2 Sheets) 10 24 36 70 $15,790 $50 $15,840 Shadow Box Infiltration Basin Plan (1 Sheet) 6 12 8 26 $6,370 $25 $6,395 Shadow Box Infiltration Basin Profile (1 Sheet) 6 12 8 26 $6,370 $25 $6,395 Shadow Box Infiltration Basin Sections (1 Sheet) 6 12 8 26 $6,370 $25 $6,395 Shadow Box Infiltration Basin Details (2 Sheets) 12 24 24 60 $14,220 $75 $14,295 13th St & Dockweiler Signing and Striping Plan (2 Sheets) 8 16 20 44 $9,820 $50 $9,870 Traffic Signal Plan at 12th Street (1 Sheet) 2 12 38 32 84 $18,830 $25 $18,855 Revise Traffic Signal Plan at Placerita Cyn Rd (1 Sheet) 2 12 40 32 86 $19,270 $25 $19,295 Traffic Signal Details (1 Sheet) 2 4 8 8 22 $5,150 $25 $5,175 Interconnection Plan (1 Sheet) 2 8 24 12 46 $10,610 $25 $10,635 Interconnection Details (2 Sheets) 4 8 16 24 52 $11,900 $50 $11,950 Street Lighting Plan (1 Sheet) 2 8 20 14 44 $10,130 $25 $10,155 Circuit Diagram (1 Sheet) 2 6 16 8 32 $7,480 $25 $7,505 Street Lighting Details (1 Sheet) 2 4 8 6 20 $4,750 $25 $4,775 Lighting Photometric Analysis (1 Sheet) 1 3 8 4 16 $3,740 $3,740 Hardscape/Planting/Irrigation Plans & Details (11 Sheets) $41,289 $275 $41,564 Stage Construction Plan (1 Sheet) 4 8 8 8 28 $6,140 $25 $6,165 Traffic Control Plans (10 Sheets) 24 64 48 48 184 $40,360 $300 $40,660 Revise Detour Plan (3 Sheets) 8 16 16 16 56 $12,280 $75 $12,355 Railroad Crossing - General (6 Sheets) $29,813 $25 $29,838 Railroad Crossing - Const Phasing & Constructability Review (2 Sheets) $53,681 $75 $53,756 Railroad Crossing - Civil Grading (6 Sheets) $102,127 $150 $102,277 Railroad Crossing - Utilities (1 Sheet) $1,613 $25 $1,638 Railroad Crossing - Trackwork (6 Sheets) $106,729 $225 $106,954 Principal
Engineer
Lead Engineer
Senior Project
Engineer
Project Engineer
Associate Engineer
Assistant
Engineer
Principal Surveyor
Assistant
Project Surveyor
Task Descriptions $325 $285 $245 $220 $200 $185 $295 $170 Total Costs
MNS Engineers, Inc. - Team Resource Estimate
Dockweiler Drive Extension Project — Amendment #1 (Additional Service Request #5) Task Costs
C-Below
RT Frankian &
Associates, Inc.

SummaryMNS Engineers Subconsultants & Reimbursables
MNS Resource Costs
Pacific Coast
Land Designs, Inc.

MNS Resource Hours
Reimbursables
Rincon Consultants, Inc.

Railpros
Railroad Crossing - Traffic Signal/Signing and Striping (6 Sheets) $79,048 $150 $79,198 Railroad Crossing - Submittal Compilation, Comment Resolution $74,623 $74,623 Railroad Crossing - Final Plan Approval, Review & Technical Exhibits $3,226 $3,226 Merge/Revise 100% Plans per City Comments & TMU (67 Sheets) 16 4 24 48 10 48 150 $33,660 $8,910 $750 $43,320 Prepare Final Plans - Original Segments ( 67 Sheets) 8 2 12 24 6 40 92 $19,990 $9,658 $750 $30,398 B. Update Specifications 20 24 40 84 $23,140 $16,280 $150 $39,570 C. Engineer's Construction Estimate 16 30 32 40 118 $28,990 $12,073 $41,063 D. Update Hydrology & Hydraulic Report 24 48 16 88 $22,520 $22,520 E. Update SWPPP/Temporary Erosion Control Plan 8 40 20 68 $16,100 $16,100 F. Update SUSMP 8 16 8 32 $8,000 $8,000

3.2 Legal & Exhibits 2 16 40 58 $12,170 $12,170 $12,170

3.3 Plan Approvals and Permits $83,320
A. Railroad (CPUC, SCRRA, Metro & UPRR) Coordination & Permits 10 10 $3,250 $52,670 $55,920 B. LACDPW Permit 24 80 104 $27,400 $27,400
Task 4. Environmental Permitting

4.1 Project Reinitiation & Project Management $15,356 $15,356 $15,356

4.2 Technical Reports $56,087
A. Jurisdictional Delineation Report Update 2 2 $650 $18,476 $19,126 B. Protocol Coastal California Gnatcatcher Surveys and Report Update 2 2 $650 $18,341 $18,991 C. Protocol Rare Plant Survey and Report Update 2 2 $650 $17,320 $17,970

4.3 Biological Resources Assessment $21,858
A. Biological Resources Assessment Update 2 2 $650 $18,252 $18,902 B. Crotch's Bumble Bee Habitat Assessment 2 2 $650 $2,306 $2,956

4.4 Regulatory Permitting $41,167
A. CDFW Streambed Alteration Agreement 2 2 $650 $20,658 $21,308 B. RWQCB Waste Discharge Requirement 2 2 $650 $15,334 $15,984 C. Compensatory Mitigation Planning 2 2 $650 $3,225 $3,875 Total Staff Hours 621 125 940 382 228 860 16 40
Total Staff Costs $201,825 $35,625 $230,300 $84,040 $45,600 $159,100 $4,720 $6,800 $33,000 $1,668,812$5,850

GRAND TOTAL
$1,668,812$131,021 $18,700$768,010 $129,268$582,9643212 Hours
Project SummaryMNS Engineers Staff Summary

2025 STANDARD SCHEDULE OF FEES

PROJECT/PROGRAM MANAGEMENT
Principal-In-Charge .............................. $375 Senior Project/Program Manager ..... 340
Project/Program Manager ................... 290
Assistant Project/Program Manager 265
Senior Project Coordinator .................. 210
Project Coordinator ................................ 175

ENGINEERING
Principal Engineer ................................. $325 Lead Engineer ........................................... 285 Supervising Engineer ............................. 270
Senior Project Engineer ........................ 245
Project Engineer ...................................... 220 Associate Engineer ................................. 200 Assistant Engineer .................................. 185

SURVEYING
Principal Surveyor ................................. $295 Lead Surveyor ........................................... 285 Supervising Surveyor ............................. 245
Senior Project Surveyor ........................ 220
Project Surveyor ...................................... 195 Associate Project Surveyor .................. 185
Assistant Project Surveyor ................... 170
Party Chief (PW) ....................................... 200 Chainperson (PW) ................................... 170 One-Person Survey Crew (PW) ........... 240

TECHNICAL SUPPORT
CADD Manager ...................................... $210 Supervising Technician ......................... 185
Senior Technician .................................... 175 Engineering Technician ......................... 140

CONSTRUCTION MANAGEMENT
Principal Construction Manager ...... $360
Senior Construction Manager ............ 310
Senior Resident Engineer ..................... 285
Resident Engineer ................................... 275 Structure Representative ...................... 270
Construction Manager .......................... 250
Assistant Resident Engineer ................ 220
Sr. Construction Inspector (PW) ....... 200
Construction Inspector (PW) ............. 188
Office Administrator .............................. 140

PLANNING
Planning Director .................................. $250 City Planner/Planning Manager ......... 230
Principal Planner ...................................... 215 Senior Planner .......................................... 200 Associate Planner .................................... 170 Assistant Planner ..................................... 140 Planning Technician ............................... 120

ADMINISTRATIVE SUPPORT
Senior Management Analyst ............ $210
Management Analyst ............................ 180
IT Technician ............................................. 150 Graphics/Visualization Specialist ....... 160
Administrative Assistant ....................... 110

GOVERNMENT SERVICES
City Engineer .......................................... $280 Deputy City Engineer ............................. 250
Assistant City Engineer ......................... 235
Plan Check Engineer .............................. 195
Permit Engineer ....................................... 185 City Inspector ........................................... 175 Senior City Inspector (PW) ................. 200
City Inspector (PW) ................................. 188 Principal Stormwater Specialist ......... 240
Senior Stormwater Specialist .............. 210
Stormwater Specialist ............................ 180
Stormwater Technician ......................... 160
Building Official ....................................... 275 Senior Building Inspector ..................... 210
Building Inspector ................................... 185 Senior Grant Writer ................................ 200 Grant Writer .............................................. 190 Associate Grant Writer .......................... 170
Assistant Grant Writer ........................... 155

DIRECT EXPENSES
Use of outside consultants as well as copies, blueprints, survey stakes, monuments, computer plots, telephone, travel (out of area) and all similar charges directly connected with the work will be charged at cost plus fifteen percent (15%). Mileage will be charged at the current federal mileage reimbursement rate.

PREVAILING WAGE RATES
Rates shown with Prevailing Wage “(PW)” annotation are used for field work on projects subject to federal or state prevailing wage law and are subject to increases per DIR.

ANNUAL ESCALATION
Standard fee rates provided for each classification are subject to 5% annual escalation or the most recent US Bureau of Labor Statistics Consumer Price Index, whichever is higher.

OVERTIME
Overtime for non- exempt employees will be charged at 1.5 x hourly rate; overtime for exempt employees and other classifications will be charged at 1 x hourly rate.