CITY OF SANT A CLARIT A

Haskell Canyon Bike Park Project

MITIGA TION MONITORING AND REPORTING PROGRAM

Lead Agency: City of Santa Clarita
23920 Valencia Boulevard,
Suite 120
Santa Clarita, CA 91355
(661) 284-1414
Contact: Amber Rodriguez

Prepared by:

3760 Kilroy Airport Way, Suite 270
Long Beach, CA 90806
Office: (562) 200-7165

JUNE 2025

M ITIGATION MONITORING AND REPORTING PROGRAM
City of Santa Clarita Haskell Canyon Bike Park Project June 2025 Mitigation Monitoring and Reporting Program

1 The Mitigation Monitoring and Reporting Program (MMRP) for the Haskell Canyon Bike Park Project (Project) has been prepared in conformance with Public Resources Code (PRC) Section 21081.6 and CEQA Guidelines Section 15097, which require all state and local agencies to establish monitoring or reporting programs whenever approval of a project relies upon a Mitigated Negative Declaration or an Environmental Impact Report. The MMRP ensures implementation of the measures being imposed to mitigate or avoid the significant adverse environmental impacts identified through the use of monitoring and reporting. Monitoring is generally an ongoing or periodic process of project oversight; reporting generally consists of a written compliance review that is presented to the decision-making body or authorized staff person.

This MMRP provides a framework to document implementation of the required mitigation measures, identifies monitoring/reporting responsibility for each mitigation measure, and provides a record of the monitoring/reporting to ensure compliance with the mitigation measures identified in the Haskell Canyon Bike Park Project Initial Study/Mitigated Negative Declaration (IS/MND) that are required to minimize impacts associated with the Project.

The mitigation measures identified in the table below were incorporated into the approval for this Project in order to reduce potentially significant environmental impacts. A signature and compliance date for each mitigation measure indicates that the measure has been implemented and fulfills the City of Santa Clarita’s monitoring requirements with respect to Public Resources Code Section 21081.6. The mitigation measures are numbered as presented in the IS/MND for the Project.

Any modifications to the terms and/or timing of the mitigation measures in this MMRP shall provide a level of environmental protection equal to, or greater than the approved mitigation measure.

The City of Santa Clarita Department of Neighborhood Services, in conjunction with any appropriate agencies or city departments, shall determine the adequacy of any proposed modifications and, if necessary, may refer said determination to the City Council. No changes to the MMRP shall be permitted unless the MMRP continues to satisfy the requirements of CEQA as determined by the City of Santa Clarita, the lead agency for the Project.

M ITIGATION MONITORING AND REPORTING PROGRAM
City of Santa Clarita Haskell Canyon Bike Park Project
June 2025 Mitigation Monitoring and Reporting Program

2 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
Biological Resources
MM BIO-1 Prior to the construction of the proposed Project, a preconstruction survey shall be conducted by qualified
botanists within the appropriate blooming period(s) to ensure no special-status plant species are present or will be
impacted within the proposed impact areas. If no special- status plant species are found during the preconstruction survey, no further mitigation is required and there will be no impact to special-status plant species.

If populations of special-status plants are found during the preconstruction survey and they are located within permanent or temporary impact areas, avoidance and minimization
measures shall be explored to protect the special-status plant population(s). If avoidance is not possible, consultation with California Department of Fish and Wildlife (CDFW) will be required prior to project initiation to identify suitable compensatory mitigation for the unavoidable loss of these species. Preparation of a Habitat Mitigation and Monitoring Plan (HMMP) detailing relocation, salvage, and/or restoration of impacted species and subsequent maintenance and
monitoring; payment of an in-lieu fee to an agency approved mitigation bank; or acquisition of off-site lands to be held in a restrictive deed for perpetuity would be required to
compensate for the loss of habitat occupied by any non-listed special-status plant species found onsite. In the unlikely event a State or federally-listed plant species is present and avoidance is not feasible, consultation with CDFW and/or U.S.

Fish and Wildlife Service (USFWS) would be required prior to initiating any onsite project activities to coordinate any take permits pursuant to State and/or federal regulations and requisite compensatory mitigation. With implementation of these actions, impacts to special-status plant species would be reduced to less than significant.

Prior to
construction
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services and, if
needed,
CDFW and/or
USFWS

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

3 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
MM BIO-2 Prior to the start of construction, every individual working on the Project must attend a Worker’s Environmental Awareness Program training session delivered by the project biologist.

The biological awareness training shall include a description of special-status species and sensitive habitats, species
identification characteristics, best management practices to be implemented, project-specific avoidance measures that must be followed, and the steps necessary if special-status species are encountered at any time.

Prior to
construction
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

MM BIO-3 A qualified biological monitor shall be present during vegetation clearing and ground disturbance activities to conduct daily clearance surveys of work areas for special- status reptile species. If any wildlife species are found, the project biologist shall relocate the animal(s) to appropriate habitat off-site. Daily monitoring logs will be prepared to document work activities and any relocations that were
conducted.

During
vegetation
clearing and
ground
disturbance
activities
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

MM BIO-4 All construction pipes, culverts, or similar structures that are stored in the Project area during construction for one or more overnight periods shall be either securely capped prior to storage or thoroughly inspected by the contractor and/or the biological monitor for special-status wildlife species or other animals before the pipe is subsequently buried, capped, or otherwise used or moved in any way.

During
construction
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

MM BIO-5 To prevent inadvertent entrapment of special-status wildlife species or other animals during construction, the project biologist and/or construction foreman/manager shall ensure all excavated, steep-walled holes or trenches more than 6 inches deep are provided with one or more escape ramps
constructed of earthen fill or wooden planks. Before such holes or trenches are filled, they shall be thoroughly
inspected for trapped animals by the project biologist and/or construction foreman/manager.

During
construction
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

4 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
MM BIO-6 If vegetation removal is required during the migratory bird nesting season (February 15 to August 31), a preconstruction nesting bird survey shall be conducted within one week prior to vegetation removal.

A minimum 300-foot no-disturbance buffer shall be
established around any active nest of migratory birds and a minimum 500-foot no-disturbance buffer shall be established around any nesting raptor or California Endangered Species Act/Endangered Species Act listed species. A reduced buffer can be established if determined appropriate by the project biologist. The contractor shall immediately stop until the appropriate buffer is established and is prohibited from conducting work that could disturb the birds until a qualified biologist determines the young have fledged or the nest is inactive. In the unlikely event that a State and/or federally listed species is detected, the buffer shall not be reduced and CDFW and/or USFWS shall be notified immediately to coordinate any further measures to avoid impacts to a listed species. The project biologist shall monitor any known identified nest site(s) within or adjacent to the project site to confirm buffers are sufficient to avoid impacts to nesting birds and track nesting status.

Prior to
construction
during the
migratory bird
nesting
season
(February 15
to August 31)
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services and, if
needed,
CDFW and/or
USFWS

MM BIO-7 Temporary and/or permanent impacts to jurisdictional features resulting from the proposed Project shall require a Water Discharge Requirement from the Regional Water Quality
Control Board (RWQCB) pursuant to the California Porter- Cologne Water Quality Control Act prior to impacts occurring within jurisdictional areas. Compensatory mitigation for impacts would be determined during the formal notification process and must be approved by RWQCB prior to work
occurring. Mitigation is anticipated to include one or more of the following: restoration of impacted features and /or preservation of unaffected features onsite; payment of an in- lieu fee to an agency approved mitigation bank; or acquisition Prior to
construction
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services and, if
needed,
RWQCB
and/or CDFW

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

5 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
of off-site lands that contain similar jurisdictional features that would be held in a restrictive deed for perpetuity.

The CDFW regulates alterations to lakes, streambeds, and riparian habitats pursuant to Section 1600 et seq. of the California Fish and Game Code. Therefore, formal notification to and subsequent authorization from the CDFW shall be
required prior to commencement of any construction activities within the CDFW jurisdictional areas. Compensatory
mitigation for impacts would be determined during the formal notification process and must be approved by CDFW prior to work occurring. Mitigation is anticipated to include one or more of the following: restoration of impacted features and /or preservation of unaffected features onsite; payment of an in- lieu fee to an agency approved mitigation bank; or acquisition of off-site lands that contain similar jurisdictional features that would be held in a restrictive deed for perpetuity.

MM BIO-8

Project materials shall not be cast from the Project Site into nearby habitats; further, project-related debris, surplus spoils, and trash shall be contained and removed to a proper disposal facility.

During
construction
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

MM BIO-9 All construction equipment shall be cleaned prior to use in the Project Site footprint and inspected by the project biologist to confirm it is free of non-native plant material in order to minimize the importation of such material into the Project Site.

All mulch, topsoil, and seed mixes used during post-
construction landscaping activities and erosion control best management practices shall be free of invasive plant species propagules. A weed abatement program shall be implemented should invasive plant species colonize the area within the project footprint post-construction.

During
construction
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

6 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
Cultural Resources

MM CUL-
1 Archaeological monitoring shall occur in the area of potential effect during all soil-disturbing and grubbing/grading/excavation/ trenching activities, which could impact archaeological resources. The monitor will observe construction activities to determine if cultural resources are present below the surface.

The Principal Investigator (PI) will submit a request to the City during construction, requesting a modification to the
monitoring program when field conditions occur that could reduce or increase the potential for resources to be present.

Such field conditions may include modern disturbance post- dating the previous grading/trenching activities, presence of fossil formations, or when native soils are encountered.

Ground-disturbing activities include, but are not limited to, geotechnical boring, trenching, grading, excavating, and the demolition of building foundations. Monitoring shall be conducted by an archaeological monitor who is working
under the guidance of a qualified archaeologist meeting the Secretary of the Interior’s Professional Qualification
Standards for archaeology (48 Federal Register 44738). The archaeological monitor shall observe ground-disturbing
activities in all areas with the potential to contain significant cultural deposits. The archaeological monitor shall maintain and submit monitoring logs at the conclusion of monitoring. If discoveries are made during ground-disturbing activities, additional work may be required in accordance with the terms specified in the cultural resources monitoring and discovery plan.

At the completion of grading, excavation, and ground-
disturbing activities on the site, a monitoring report shall be submitted to the City that documents monitoring activities conducted by the Project archaeologist within 60 days of completion of monitoring. This report shall document the daily archaeological monitoring results; describe how each mitigation measure was fulfilled; document the type of
During
ground-
disturbance
activities
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

7 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
cultural resources recovered and the disposition of such resources; and, in a confidential appendix, include the daily/weekly monitoring notes from the qualified
archaeologist. Final monitoring reports will be submitted to the City and the South Central Coastal Information Center.

Any unanticipated archaeological finds and subsequent
evaluation or data recovery efforts will be documented in the report.

MM CUL-
2 In the event an archaeological resource is unearthed during excavation, all excavations shall be halted within 50 feet of the find. Work shall stop immediately, and the discovery shall be evaluated by a qualified archaeologist meeting the Secretary of the Interior’s Professional Qualification Standards for archaeology (48 Federal Register 44738), pursuant to the procedures set forth at CEQA Guidelines Section 15064.5 and 36 Code of Federal Regulations Part 60.4. Depending on the nature of the find, the determination of significance may require additional excavation, potentially including the preparation and execution of a Phase II Archaeological
Testing Plan. As the lead agency, the City shall make a determination of significance on the basis of the
recommendations of the qualified archaeologist.

If the resource is determined not to be significant, then resource-specific work shall be completed, and construction may proceed. If the resource is determined to be significant and avoidance is not feasible, then a resource-specific archaeological resources treatment plan shall be prepared and executed in accordance with Mitigation Measure CUL-3 prior to recommencing ground-disturbing activities that may impact the resource.

During
construction, if
archaeological
resources are
discovered
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

MM CUL-
3 Avoidance and preservation-in-place are the preferred treatment for historical resources, but avoidance is not always feasible. In the event that a historical resource is discovered and disturbance to such a resource cannot be avoided, one of the following treatments shall be implemented: avoidance, site During
construction if
cultural
resources are
discovered
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

8 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
capping, creation of conservation easements, or
archaeological data recovery.

If avoidance, site capping, or creation of a conservation easement is determined infeasible, then a Phase III data recovery excavation will be required, pursuant to CEQA
Guidelines Section 15064.5 and Section 106 36 Code of
Federal Regulations 800.13, to document the resource’s
scientifically consequential information. The Phase III data recovery plan shall be prepared in consultation with the consulting tribe(s) if the discovery is associated with a precontact or ethnohistoric context. The Phase III study shall consist of the recovery and analysis of a statistically significant sample of the site through archaeological excavation,
radiocarbon dating of organic materials or other kinds of dating, cataloging, specialist analysis, and report writing designed to document the resource in perpetuity.

During the course of construction, all discovered resources shall be temporarily curated in a secure location onsite or at the offices of the qualified archaeologist. The removal of any artifacts from the area of potential effect for cataloging and analysis will need to be thoroughly inventoried with tribal monitor oversight of the process if the discovery is associated with a precontact or ethnohistoric context. The landowner shall relinquish ownership of all cultural resources, including sacred items, burial goods, and all archaeological artifacts and non- human remains, as part of the required mitigation for impacts to cultural resources. The applicant shall relinquish the artifacts through one or more of the following methods and provide the City with evidence of final disposition of the cultural material collection:
 Accommodate the process for onsite reburial of the
discovered items with the consulting tribe(s). This shall include measures and provisions to protect the future
reburial area from any future impacts. Reburial shall not

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

9 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
occur until all cataloguing and basic recordation have
been completed.
 A curation agreement with an appropriate qualified
repository in Los Angeles County that meets federal
standards per 36 Code of Federal Regulations Part 79,
and therefore will be professionally curated and made
available to other archaeologists/researchers for further study. The collections and associated records shall be
transferred, including title, to an appropriate curation facility in Los Angeles County, to be accompanied by
payment of the fees necessary for permanent curation.
 If more than one Native American tribe is involved with the Project and the tribes cannot come to a consensus as to the disposition of cultural materials, they shall be curated at an appropriate qualified repository determined by the City.

MM CUL-
4 If human skeletal remains are found during earth-moving activities, work shall be suspended and the Los Angeles County Coroner’s Office shall be notified. Standard
guidelines set by California law provide for the treatment of skeletal material of Native American origin (California Public Resources Code, Sections 5097.98 et seq.; Health and
Safety Code, Section 7050.5). If the remains are found to be archaeological in their disposition, then after the coroner releases the site, the qualified professional archaeologist, in consultation with the most likely descendant, shall prepare an archaeological treatment plan in accordance with
Mitigation Measure CUL-3 that also incorporates the
guidance in “A Professional Guide for the Preservation and Protection of Native American Remains and Associated
Grave Goods,” published by the California Native American Heritage Commission.

During ground
disturbance
activities if
human
remains are
found
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

10 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
Hazards and Hazardous Materials

MM HAZ-
1 Prior to commencement of construction activities, a
Construction Fire Prevention Plan shall be prepared for the Project to specify the construction phase restrictions and fire safety requirements that would be implemented to reduce risk of ignitions and pre-plans for responding to an unlikely ignition. Prior to bringing lumber or combustible materials onto the Project Site, improvements within the active
development area shall be in place, including an approved, temporary roadway surface and fuel modification zones
established. These improvements shall also be included in the Construction Fire Prevention Plan, which shall be
submitted to the Los Angeles County Fire Department
(LACoFD) for review and approval.

Prior to
construction
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services and, if
needed,
LACoFD

MM HAZ-
2 Three (3) days prior to a scheduled event at the Project Site with more than 50 visitors (including riders, spectators, staff, and volunteers), the City will coordinate LACoFD to
determine the fire danger. If there is a red flag warning issued for the Project area within 24 hours of a scheduled event, the event shall be cancelled in accordance with Santa Clarita Municipal Code Section 14.06.230, Emergency or
Temporary Closure of Parks, Public Places, Trails, and
Recreational Areas, which states that, in an emergency or when the City Manager determines that the public interest, public health, public morals, maintenance purposes, or public safety demands such action, any park, public place, grounds, trails, or recreation facility, or any part or portion thereof, may be closed to the public, and all persons may be excluded therefrom until such emergency or other reason upon which such determination of the City Manager is based has ceased, at which time the park, public place, grounds, trails, or recreation facility, or part or portion thereof so closed shall be reopened to the public by the City Manager.

Three (3)
days prior to a
scheduled
event at the
Project Site
with more
than 50
visitors
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services and, if
needed,
LACoFD

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

11 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
Tribal Cultural Resources

MM TCR-
1 Document Release: Any and all archaeological documents created as a part of the Project (isolate records, site records, survey reports, testing reports, and monitoring reports) shall be provided to the Fernandeño Tataviam Band of Mission
Indians.

Prior to
construction
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services

MM TCR-
2 Cultural Resources Monitoring and Mitigation Plan: In the event of an inadvertent discovery of Tribal Cultural Resources, its importance will be determined by the Tribal Monitor, the Project archaeologist, and the City. If determined to be important, a Cultural Resources Monitoring and Mitigation Plan (CRMMP) shall be prepared, in consultation with the Fernandeño Tataviam Band of Mission Indians. The CRMMP
will provide details regarding the process for in-field treatment of inadvertent discoveries and the disposition of inadvertently discovered non-funerary resources.

During ground
disturbance
activities
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services and, if
needed,
Fernandeño
Tataviam Band
of Mission
Indians

MM TCR-
3 Full Time Monitoring, Initial Pass, (1) Monitor: The Project applicant shall retain a professional Tribal Monitor procured by the Fernandeño Tataviam Band of Mission Indians to observe all ground-disturbing activities including, but not limited to, clearing, grubbing, grading, excavating, digging, trenching, plowing, drilling, tunneling, quarrying, leveling, driving posts, auguring, blasting, stripping topsoil or similar activity during the initial pass (the first disturbance of all soil to the total depth of which it will be disturbed). If cultural resources are not encountered after observing the initial pass of all ground- disturbance, additional Tribal Monitoring is not required. If cultural resources are encountered during the initial pass, they shall be assessed by the Tribal Monitor, the Project
archaeologist, and the City. If determined to be important, the Tribal Monitor(s) shall continue observing ground disturbing activities to the satisfaction of the Tribal Monitor, Project archaeologist, and the City to ensure important Tribal Cultural Resources are identified. Tribal Monitoring Services will continue until confirmation is received from the Project During ground
disturbance
activities
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services and, if
needed,
Fernandeño
Tataviam Band
of Mission
Indians

2.0 MITIGATION MONITORING REQUIREMENTS
City of Brea DJT4 Parcel Delivery Facility Project
June 2025 Mitigation Monitoring and Reporting Program

12 Mitigation Measures Timing
Responsible
Party
Monitoring
Agency or
Party
Signature/Date
of Compliance
applicant, in writing, that all scheduled activities pertaining to Tribal Monitoring are complete, be it initial pass or all disturbance, dependent upon inadvertent discovery. If the Project’s scheduled activities require the Tribal Monitor(s) to leave the Project for a period of time and return, confirmation shall be submitted to the Tribe by Client, in writing, upon completion of each set of scheduled activities and 5 days notice (if possible) shall be submitted to the Tribe by Project applicant, in writing, prior to the start of each set of scheduled activities. If cultural resources are encountered, the Tribal Monitor will have the authority to request that ground- disturbing activities cease within 60 feet of discovery and a qualified archaeologist meeting Secretary of Interior standards retained by the Project applicant as well as the Tribal Monitor shall assess the find.

MM TCR-
4 In the Event of an Inadvertent Discovery: If cultural resources are discovered during project activities, all work in the immediate vicinity of the find (within a 60-foot buffer) shall cease and a qualified archaeologist meeting Secretary of Interior standards retained by the Project applicant shall assess the find. Work on the portions of the Project outside of the buffered area may continue during this assessment period.

The Fernandeño Tataviam Band of Mission Indians shall be contacted about any pre-contact and/or post-contact finds and be provided information after the archaeologist makes their initial assessment of the nature of the find, to provide Tribal input with regards to significance and treatment.

During
construction if
cultural
resources are
discovered
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services and, if
needed,
Fernandeño
Tataviam Band
of Mission
Indians

MM TCR-
5 Human Remains: In the inadvertent discovery of human
remains or funerary objects during any activities associated with the Project, work in the immediate vicinity (within a 100- foot buffer of the find) shall cease and the County Coroner shall be contacted pursuant to State Health and Safety Code §7050.5 and that code shall be enforced for the duration of the Project.

During
construction if
human
remains are
found
City of Santa
Clarita,
Department of
Neighborhood
Services
City of Santa
Clarita,
Department of
Neighborhood
Services