agenda-report VALENCIA GLEN PARK POOL RE-PLASTER P0026 PLANS, SPECIFICATIONS, AND CONSTRUCTION CONTRACT

Santa Clarita City Council
April 28, 2026

Document
agenda-report VALENCIA GLEN PARK POOL RE-PLASTER P0026 PLANS, SPECIFICATIONS, AND CONSTRUCTION CONTRACT
Meeting
April 28, 2026
Body
Santa Clarita City Council
Pages
3
Original file
92 KB
Text extracted from the city's file for reading and search. Open the original on santaclaritacityca.iqm2.com. That file is the official record.
Page 1 ends

Agenda Item: 8

CITY OF SANTA CLARITA

AGENDA REPORT

CONSENT CALENDAR
CITY MANAGER APPROVAL:

DATE: April 28, 2026
SUBJECT: VALENCIA GLEN PARK POOL RE-PLASTER P0026 PLANS,

SPECIFICATIONS, AND CONSTRUCTION CONTRACT
DEPARTMENT: Neighborhood Services
PRESENTER: Susan Nelson

RECOMMENDED ACTION

City Council:

1. Approve the plans and specifications for the Valencia Glen Park Pool Re-Plaster Project P0026.

2. Award a construction contract to National Pools Inc. for pool re-plaster services in the amount of $277,160 and authorize a contingency in the amount of $27,716, for a total contract amount not to exceed $304,876.

3. Find the Valencia Glen Park Pool Re-Plaster Project P0026 exempt from review under the California Environmental Quality Act (CEQA) pursuant to Title 14 of the California Code of Regulations, Article 19, Section 15301.

4. Authorize the City Manager or designee to execute all contracts and associated documents, subject to City Attorney review.

BACKGROUND
The pool re-plaster project at Valencia Glen Park (VGP) was identified as a component of the Annual Parks Facilities Improvements and Repairs Program. Each year, this program identifies rehabilitation projects within the City of Santa Clarita’s (City) park system.

Over time, the pool plaster at VGP has deteriorated, developing numerous cracks and, more recently, exhibiting water leakage. The pool was originally constructed in 1970 and has been repaired numerous times. The pool was re-plastered in 1997, the deck was replaced in 2001, and in 2015, the north end of the pool was re-plastered after repairs to the drain and fill lines were completed. Temporary repairs to the pool shell have taken place to prevent leaking and to

Page 2 ends

maintain use of the site during summer programming.

A consultant specializing in commercial pool systems was hired to provide plans and specifications for the re-plaster project. A complete set of plans were developed by the consultant encompassing the most current pool codes to comply with the Los Angeles County Health Department requirements.

The scope of work for this construction contract includes repairing the cracks in the pool shell, replacing the broken skimmer housings, installing new lane line anchors, and re-plastering the pool, along with installing updated depth markers and main drain covers. Construction is expected to have a duration of nine weeks and will commence immediately after summer programming concludes.

Supporting the theme of Sustainable Public Infrastructure in Santa Clarita Pathway Forward, the City’s five-year strategic plan, the proposed contract will provide vital repairs for the pool at Valencia Glen Park. This project is necessary to maintain the pool in good serviceable condition.

An invitation to bid was published and circulated on the City’s e-procurement system, BidNet, on February 24, 2026. The City transmitted the solicitation to 2,655 vendors on BidNet, of which 37 vendors downloaded the materials. A total of six bids were submitted and opened on March 31, 2026. Each bid total included a base bid and bid alternate 1. In addition, bid alternate 2 was issued by addendum in the process of solicitation to obtain additional pricing for potential supplemental work. The basis for the award, as specified in the bid documents, was the total of the base bid and bid alternate 1. The results of the bids based on this criteria are shown below:

Company Location Bid Amount
National Pools Inc. Sylmar, CA $251,960
Ultimate Pool Remodeling Inc. Riverside, CA $292,330
California Waters Yorba Linda, CA $319,998
USA Construction LLC Cumming, GA $369,899
Adams Pool Specialties Sacramento, CA $377,814
Ankor Associates Inc. Los Angeles, CA $380,982

Staff recommends awarding the contract to National Pools Inc. (NPI) as the lowest responsive and responsible bidder in the amount of $251,960, consisting of $167,960 for the base bid and $84,000 for bid alternate 1, which formed the basis of the award. While bid alternate 2 was not included in the basis of award, staff recommends its inclusion at a cost of $25,200, as it provides additional improvements within the available project budget, bringing the total contract amount to $277,160. Staff further recommends authorizing a contingency of $27,716, for a total not-to- exceed amount of $304,876, to address unforeseen site conditions, field adjustments, additional work requested by the City or permitting agencies, and necessary field investigations.

The contractor possesses a valid contractor’s license and is in good standing with the Contractor’s State License Board. The contractor’s bid was reviewed for accuracy and conformance to the contract documents and was found to be complete. The bid proposal adheres to the project’s plans and specifications and is available in the City Clerk’s reading file.

Page 3 ends

ALTERNATIVE ACTION
Other action as determined by the City Council.

FISCAL IMPACT

Adequate funds were appropriated as part of the Fiscal Year 2025-26 budget in expenditure account P0026601-516101 to support the recommended contract and related administrative and miscellaneous costs for this project.

ATTACHMENTS
Location Map
PPOS-25-26-P0026 BID (available in the City Clerk's Reading File) NPI Response (available in the City Clerk's Reading File)