Cities Index.
Bid Proposal for C.A. Rasmussen, Inc. (available in the City Clerk's Reading File)

Santa Clarita City Council
April 28, 2026

Document
Bid Proposal for C.A. Rasmussen, Inc. (available in the City Clerk's Reading File)
Meeting
April 28, 2026
Body
Santa Clarita City Council
Original file
14.7 MB
Text extracted from the city's file for reading and search. Open the original on santaclaritacityca.iqm2.com. That file is the official record.

C.A.RASMUSSEN INC.

GENERAL ENGINEERING CONTRACTORS
February 23, 2026
City of Santa Clarita -ATTN : Purchasing
23920 Valencia Blvd Suite 120
Valencia, CA 91355
LICENSE NO. 254681A
RE: EEO Certifications of Subcontractors for 2025-26 Federal Circulation Improvement Program CIP-25-26-C1018
Enclosed are the EEO Certifications for the subcontractors for the above-mentioned project that bid on Monday February 23, 2026@ 11 AM. If you have any questions, please contact me at 661-367-9062 or [email protected] .

Estimating Coordinator
C.A. Rasmussen, Inc.
28548 LIVINGSTON AVENUE I VALENCIA CA 91355
661.367.9040 PH I 661.367.9099 FAX I WWW.CARASMUSSEN.COM

EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION
Bid #CIP-25-26-Cl018
2025-26 Federal Circulation Improvement Program
City Project No. Cl018
City of Santa Clarita, ~alifornia
This bidder (.A. ~<;,n, v<;<en I Inc.., proposed subcontractor CAT TRACKING INC. , hereby certifies that it has X has not __ ~ participated in a previous contract or subcontract subject to the equal opportunity clause, as required by Executive Orders 10925.11114, or 11246, and that it has _x__, has not __J filed with the Joint Reporting Committee, and Director of Office of Federal Contract Compliance, a Federal Government contracting or administering AGENCY, or the former President's Committee on Equal Employment Opportunity, all reports that are under the applicable filing requirements.

Company:

By: ARTHUR GARRA TT
Title: LEAD ESTIMATOR
Date: 02/23/2026
Note: The above certification is required by the Equal Employment Opportunity of the Secretary of Labor (41 CFR 60-1.7(b)(l)) and must be submitted by bidders and proposed subcontractors only in connection with contracts and subcontracts which are subject to the equal opportunity clause as set forth in 41 CFR 60-1.5, (Generally only contracts or subcontracts of $10,000 or under are exempt.) Currently, the Standard Form 100 (EEO-1) is the only report required by the Executive Orders or their implementing regulations .

Proposed prime CONTRACTORS/BIDDER and subcontractors who have participated in a previous contract or subcontract subject to the Executive Orders and have not filed the required reports should note that 41 CFR 60-1.7(b)(l) prevents the award of contracts and subcontracts unless such BIDDER submits a report covering the delinquent period or such other period specified by the Federal Highway Administration or by the Director, Office of Federal Contract Compliance, U.S. Department of Labor.

EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION
Bid #CIP-25-26-C1018
2025-26 Federal Circulation Improvement Program
City Project No. C1018
City of Santa Clarita, California
This bidder C.A Rassmussen , Inc. proposed subcontracto r GreenCoast Landsca pes Inc. hereby certifies that it has x has not __ __, participated in a previous contract or subcontract subject to the equal opportunity clause, as required by Executive Orders 10925.11114, or 11246, and that it has _ x __ , has not __, filed with the Joint Reporting Committee , and Director of Office of Federal Contract Compliance, a Federal Government contract ing or admin istering AGENCY, or the former President's Committee on Equal Employment Opportunity , all report s that are under the applicable filing requirements .

Company: GreenCoast Lands capes Inc.

By: Jessica Jauregui
Title : CFO
--------------- - - -
Date: _0_2,_2_31_2_02_6 ____ ___ ______ _
Note : The above certification is required by the Equal Employment Opportunity of the Secretary of Labor (41 CFR 60-l.7(b)(l)) and must be submitted by bidders and proposed subcontractors only in connection with contracts and subcontracts which are subject to the equal opportunity clause as set forth in 41 CFR 60-1.5, (Generally only contracts or subcontracts of $10,000 or under are exempt.) Currently, the Standard Form 100 (EE0-1) is the only report required by the Executive Orders or their implementing regulations .

Proposed prime CONTRACTORS/BIDDER and subcontractors who have participated in a previous contract or subcontract subject to the Executive Orders and have not filed the required reports should note that 41 CFR 60-1.7(b)(l) prevents the award of contracts and subcontracts unless such BIDDER submits a report covering the delinquent period or such other period specified by the Federal Highway Administration or by the Director , Office of Federal Contract Compliance, U.S. Department of Labor.

EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION
Bid #CIP-25-26-Cl0lS
2025-26 Federal Circulation Improvement Program
City Project No. C1018
City of Santa Clarita, California
This bidder c.A . ~srnvc.<er 1i I (II:'. I proposed subcontractor Crosstown Electrical & Data, Inc, hereby certifies that it has X has not--~ participated in a previous contract or subcontract subject to the equal opportunity clause, as required by Executive Orders 10925.11114, or 11246, and that it has X has not ___, filed with the Joint Reporting Committee, and Director of Office of Federal Contract Compliance, a Federal Government contracting or administering AGENCY, or the former Pre'sldent's Committee on Equal Employment Opportunity, all reports that are under the applicable filing requirements.

Company: a, Inc
By: Dave Heermance
Title: President
Date: 02/23/2026
Note: The above certification is required by the Equal Employment Opportunity of the Secretary of Labor (41 CFR 60-1.7(b)(1)) and must be submitted by bidders and proposed subcontractors only in connection with contracts and subcontracts which are subject to the equal opportunity clause as set forth in 41 CFR 60-1.5, (Generally only contracts or subcontracts of $10,000 or under are exempt.) Currently, the Standard Form 100 (EEO-1) is the only report required by the Executive Orders or the ir Implementing regulations.

Proposed prime CONTRACTORS/BIDDER and subcontractors who have participated in a previous contract or subcontract subject to the Executive Orders and have not filed the required reports should note that 41 CFR 60-1.7(b)(1) prevents the award of contracts and subcontracts unless such BIDDER submits a report covering the delinquent period or such other period specified by the Federal Highway Administration or by the Director, Office of Federal Contract Compliance, U.S. Department of Labor.

Bid Schedule
Code Description UOM Quantity Price Total Cost
1 MOBILIZATION/DEMOILIZATIONLump-Sum 1 200,000.00 $ 200,000.00$ 2 CONSTRUCTION SURVEY &

MONUMENT PRESERVATION
Lump-Sum 1 25,000.00 $ 25,000.00$
3 WATER POLLUTION CONTROL,

IMPLEMENTATION AND
MAINTENANCE OF BMP’S
Lump-Sum 1 25,000.00 $ 25,000.00$
4 CLEARING AND GRUBBING (LS)Lump-Sum 1 50,000.00 $ 50,000.00$ 5 REMOVE TRAFFIC STRIPE Linear Foot/Feet 14943 1.60$ 23,908.80$ 6 REMOVE PAVEMENT MARKINGSEach 28 155.00 $ 4,340.00$ 7 REMOVE SIGN Each 6 52.00 $ 312.00$ 8 REMOVE SIGN AND POST Each 1 103.00 $ 103.00$ 9 REMOVE PCC CURB & GUTTER, TYPE
A2-8, W=2'
Linear Foot/Feet 700 20.00$ 14,000.00$ 10 REMOVE PCC CURB & GUTTER, TYPE
A2-8, W=1'
Linear Foot/Feet 440 11.90$ 5,236.00$ 11 REMOVE PCC CURB & GUTTER, TYPE
A2-6, W=1'
Linear Foot/Feet 265 29.00$ 7,685.00$ 12 REMOVE PCC CURB & GUTTER,
BURIED, W=1'
Linear Foot/Feet 405 18.00$ 7,290.00$ 13 REMOVE PCC WALK, 4" THICKSquare Foot/Feet 3461 6.10$ 21,112.10$ 14 REMOVE STAMPED & COLORED
CONCRETE, 4" THICK
Square Foot/Feet 365 8.30$ 3,029.50$ 15 REMOVE MEDIAN PAVERS Square Foot/Feet 1803 6.20$ 11,178.60$ 16 REMOVE AC PAVEMENT Square Foot/Feet 6970 2.80$ 19,516.00$ 17 SAW CUT PAVEMENT Linear Foot/Feet 1990 8.30$ 16,517.00$ 18 UNCLASSIFIED EXCAVATION Cubic Yard 440 338.00 $ 148,720.00$ 19 REMOVE PCC CURB RAMPS Each 4 3,943.00 $ 15,772.00$ 20 TRAFFIC CONTROL, Phase 1 Lump-Sum 1 72,920.00 $ 72,920.00$ 21 TRAFFIC CONTROL, Phase 2 Lump-Sum 1 100,000.00 $ 100,000.00$ 22 TRAFFIC CONTROL, Phase 3 Lump-Sum 1 53,030.00 $ 53,030.00$ 23 TRAFFIC CONTROL, Phase 4 Lump-Sum 1 17,620.00 $ 17,620.00$ 24 CRUSHED AGGREGATE BASECubic Yard 574 280.00 $ 160,720.00$ 25 AC B PG 64-10 (BASE COURSE)Ton 442 285.00 $ 125,981.40$ 26 AC C2 PG 64-10 (FINISH COURSE)Ton 350 290.00 $ 101,630.50$ 27 CONCRETE CURB, TYPE A1-6 Linear Foot/Feet 80 152.00$ 12,160.00$ 28 CONCRETE CURB & GUTTER, TYPE
A2-8 , W=1'
Linear Foot/Feet 415 72.00$ 29,880.00$ 29 CONCRETE CURB & GUTTER, TYPE
A2-8 , W=2'
Linear Foot/Feet 540 83.00$ 44,820.00$ 30 CONCRETE CURB & GUTTER, TYPE
A3-8 , W=1'
Linear Foot/Feet 400 74.00$ 29,600.00$ 31 ADJUST MANHOLE TO GRADEEach 1 2,400.00 $ 2,400.00$ 32 SIDEWALK CONCRETE, 4” THICK Square Foot/Feet 2855 17.00$ 48,535.00$ 33 STAMPED & COLORED CONCRETE,
4" THICK
Square Foot/Feet 85 223.00$ 18,955.00$ 34 CONCRETE CURB RAMPS Each 4 9,023.00 $ 36,092.00$ 35 COLD MILL AC PAVEMENT (2") Square Foot/Feet 18665 2.80$ 52,262.00$ C. A Rasmussen, Inc.

Line Items (Bid Schedule)
2025-26 Federal Circulation Improvement Program
Project C1018
Bid Schedule
36 CONCRETE UNIT PAVERS ATOP

CONCRETE (INCL MORTAR AND

CONCRETE BASE)
Square Foot/Feet 1247 55.00$ 68,585.00$ 37 REBOUNDABLE TYPE K OBJECT
MARKER
Each 5 57.00 $ 285.00$
38 PAVEMENT MARKERS (FIRE

HYDRANT)
Each 19 10.30 $ 195.70$
39 TRAFFIC LANE LINES, DETAIL12Linear Foot/Feet 7180 0.77$ 5,528.60$ 40 LEFT EDGE LINES, DETAIL 24 Linear Foot/Feet 2610 0.77$ 2,009.70$ 41 RIGHT EDGE LINES, DETAIL 27BLinear Foot/Feet 325 0.77$ 250.25$ 42 RIGHT EDGE LINES, DETAIL 27CLinear Foot/Feet 275 0.67$ 184.25$ 43 MEDIAN ISLANDS, DETAIL 29Linear Foot/Feet 290 2.58$ 748.20$ 44 CHANNELIZING LINE, DETAIL 38Linear Foot/Feet 3360 1.03$ 3,460.80$ 45 CHANNELIZING LINE, DETAIL 38ALinear Foot/Feet 1534 1.03$ 1,580.02$ 46 TYP LANE LINE OR RIGHT EDGE LINE
CONTRAST (OPTION 1)
Linear Foot/Feet 322 1.29$ 415.38$ 47 LANE LINE EXTENSIONS THROUGH
INTERSECTIONS, DETAIL 40
Linear Foot/Feet 1205 3.61$ 4,350.05$ 48 TYPE IV (L/R) ARROW Each 42 88.00 $ 3,696.00$ 49 PAVEMENT MARKINGS WORDS,
DETAIL "NO"
Each 3 155.00 $ 465.00$
50 PAVEMENT MARKINGS WORDS,
DETAIL "TRUCKS"
Each 3 464.00 $ 1,392.00$
51 PAVEMENT MARKINGS LIMIT LINE
(STOP LINE)
Linear Foot/Feet 555 5.20$ 2,886.00$ 52 PAVEMENT MARKINGS

CROSSWALKS, DETAIL CONTINENTAL
Square Foot/Feet 4250 5.20$ 22,100.00$ 53 12" WIDE, WHITE DIAGONAL

PAVEMENT MARKINGS
Linear Foot/Feet 317 5.10$ 1,616.70$ 54 12" WIDE, YELLOW DIAGONAL

PAVEMENT MARKINGS
Linear Foot/Feet 425 5.20$ 2,210.00$ 55 FURNISH AND INSTALL SIGN ONLY Each 12 180.00 $ 2,160.00$ 56 FURNISH AND INSTALL SIGN AND
POST
Each 2 489.00 $ 978.00$
57 STREET LIGHTING SYSTEM Lump-Sum 1 40,000.00 $ 40,000.00$ 58 TRAFFIC SIGNAL MODIFICATIONS AT

THE INTERSECTION OF VALENCIA

BLVD AND MCBEAN PWKY
Lump-Sum 1 475,000.00 $ 475,000.00$
59 IRRIGATION SYSTEM Lump-Sum 1 48,990.00 $ 48,990.00$ 60 PLANTING AREA SOIL PREP AND

AMENDMENTS (INCL TESTING OF

IMPORT SOIL)
Square Foot/Feet 5780 0.77$ 4,450.60$ 61 FURNISH AND PLANT 1 GALLON
SHRUBS
Each 330 20.00 $ 6,600.00$
62 FURNISH AND PLANT 5 GALLON
SHRUBS
Each 234 35.00 $ 8,190.00$
63 TREE PIT AUGERING (4 HOLES PER
TREE)
Each 1 489.00 $ 489.00$
64 FURNISH AND PLANT 48" BOX TREE Each 1 2,009.00 $ 2,009.00$ 65 TREE REMOVAL (25"+ DIAMETER) Each 6 2,168.00 $ 13,008.00$ 66 PROTECTION OF EXISTING TREES TO
REMAIN
Each 8 464.00 $ 3,712.00$
2025-26 Federal Circulation Improvement Program
Project C1018
Bid Schedule
67 ROOT PRUNE TREE Each 4 695.00 $ 2,780.00$ 68 ROOT / MOISTURE BARRIER Linear Foot/Feet 238 33.00$ 7,854.00$ 69 3” ORGANIC MULCH Cubic Yard 43 88.00 $ 3,784.00$ 70 FIRST PLANT MAINTENANCE AND
ESTABLISHMENT PERIOD (DAYS 1 -
90)
Lump-Sum 1 6,026.00 $ 6,026.00$
Code Description UOM Quantity Price Total Cost
71 Irrigation Mainline RelocationN/A 1 10,000.00 $ 10,000.00$ Project Total : $ 2,263,315.15
Irrigation Mainline Relocation (Allowance) (Cost Allowance) 2025-26 Federal Circulation Improvement Program
Project C1018

← All documents from this meeting