RESOLUTION NO. 26-
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SANTA CLARITA,
CALIFORNIA, DECLARING THAT IT HAS ADOPTED A LIST OF PROJECTS FOR FISCAL YEAR 2026-27 FUNDED BY SENATE BILL 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017, LOCAL STREETS AND ROADS, ROAD
MAINTENANCE AND REHABILITATION FUNDS INTO THE CAPITAL IMPROVEMENT
PROGRAM
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to address the significant multi-modal transportation funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of our City of Santa Clarita (City) are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and
WHEREAS, the City must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and
WHEREAS, the City, will receive an estimated $6,690,689 in RMRA funding in Fiscal Year 2026-27 from SB 1; and
WHEREAS, this is the tenth year in which the City is receiving SB 1 funding and will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City has undergone a robust public process to ensure public input into our community’s transportation priorities/the project list; and
WHEREAS, the City used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the community’s priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate numerous streets/roads, bridges, add active transportation infrastructure throughout the City this year and hundreds of similar projects into the future; and
WHEREAS, the 2023 California Statewide Local Streets and Roads Needs Assessment found that the City streets and roads are in an “at-risk” condition and this revenue will help us increase the overall quality of our road system and over the next decade will bring our streets and roads into a “good” condition; and
WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting-edge technology, materials and practices, will have significant positive co-benefits statewide.
NOW, THEREFORE by the City Council of the City of Santa Clarita, California, does hereby resolve as follows:
SECTION 1. The foregoing recitals are true and correct.
SECTION 2. The following list of newly proposed projects will be funded in-part or solely with Fiscal Year 2026-27 Road Maintenance and Rehabilitation Account revenues:
Project Title: 2026-27 Overlay and Slurry Seal Program Design and Construction;
Project Description: Generally, the scope of work to be performed includes, but is not limited to, asphalt resurfacing of various streets Citywide;
Project Location: Citywide. Specific streets were selected from locations identified through the City’s Five-Year Pavement Preservation Program and are identified in the attached Proposed Fiscal Year 2026-27 SB 1 Project List;
Estimated Project Schedule: Pre-construction: July 2026 – May 2027, Construction: June 2027 – June 2028 based on the component being funded with RMRA funds; and
Estimated Project Useful Life: Streets selected for preventative maintenance will have a pavement life expectancy of 3-7 years, and streets selected for rehabilitation will have a life expectancy of 10-15 years.
SECTION 3. The following previously proposed and adopted projects may also utilize Fiscal Year 2026-27 Road Maintenance and Rehabilitation Account revenues in their delivery.
With the relisting of these projects in the adopted fiscal year resolution, the City is reaffirming to the public and the State our intent to fund these projects with Road Maintenance and Rehabilitation Account revenues:
Project Title: 2025-26 Overlay and Slurry Seal Program Design and Construction;
Project Description: Generally, the scope of work to be performed includes, but is not limited to, asphalt resurfacing of various streets Citywide;
Project Location: Citywide. Specific streets were selected from locations identified through the City’s Five-Year Pavement Preservation Program and are identified in the attached Proposed Fiscal Year 2026-27 SB 1 Project List;
Estimated Project Schedule: Pre-construction: July 2025 – May 2026, Construction: June 2026 – June 2027 based on the component being funded with RMRA funds: and
Estimated Project Useful Life: Streets selected for preventative maintenance will have a pavement life expectancy of 3-7 years, and streets selected for rehabilitation will have a life expectancy of 10-15 years.
SECTION 4. The City Clerk shall certify to the adoption of this resolution.
PASSED, APPROVED, AND ADOPTED this day of 2026.
MAYOR
ATTEST:
CITY CLERK
DATE:
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES )
ss. CITY OF SANTA CLARITA )
I, Melody Bartlette, City Clerk of the City of Santa Clarita, do hereby certify that the foregoing Resolution No. 26- was duly adopted by the City Council of the City of Santa Clarita at a regular meeting thereof, held on the day of 2026, by the following vote:
AYES: COUNCILMEMBERS:
NOES: COUNCILMEMBERS:
ABSENT: COUNCILMEMBERS:
CITY CLERK
Project Title Project Description
Project Road Name
(Locations listed are
projected estimates
and have yet to be
finalized) Project Location
Pre‐
Construction
Start
Construction
Start
Proposed
Schedule of
Completion
Useful
Life
Min
Useful
Life
Max
2026‐27 Overlay
and Slurry Seal
Program Design
and Construction
The Annual Overlay and
Slurry Seal Program
reflects the City's
commitment to roadway
infrastructure by
resurfacing streets in
need of attention.
Decoro Drive From Copper Hill
Drive to McBean
Parkway
Jul‐26 Jun ‐27 Jun ‐28 3 15
2026‐27 Overlay
and Slurry Seal
Program Design
and Construction
The Annual Overlay and
Slurry Seal Program
reflects the City's
commitment to roadway
infrastructure by
resurfacing streets in
need of attention.
Avenue Scott From McBean
Parkway to Rye
Canyon Road
Jul‐26 Jun ‐27 Jun ‐28 3 15
2026‐27 Overlay
and Slurry Seal
Program Design
and Construction
The Annual Overlay and
Slurry Seal Program
reflects the City's
commitment to roadway
infrastructure by
resurfacing streets in
need of attention.
Rye Canyon Road From Avenue
Stanford to
Avenue Scott
Jul‐26 Jun ‐27 Jun ‐28 3 15
2025‐26 Overlay
and Slurry Seal
Program Design
and Construction
The Annual Overlay and
Slurry Seal Program
reflects the City's
commitment to roadway
infrastructure by
resurfacing streets in
need of attention.
Via Princessa From Sierra
Highway to Lost
Canyon Road
Jul‐25 Jun ‐26 Jun ‐27 3 15
2025‐26 Overlay
and Slurry Seal
Program Design
and Construction
The Annual Overlay and
Slurry Seal Program
reflects the City's
commitment to roadway
infrastructure by
resurfacing streets in
need of attention.
McBean Parkway From Alegro Drive
to Avenida
Navarre
Jul‐25 Jun ‐26 Jun ‐27 3 15
City of Santa Clarita
Proposed Fiscal Year 2026‐27 SB 1 Project List