2023 Citywide Pavement
Management System Update
CITY

COUNCIL

MEETING

JUNE
20,2023

SUMMARY

Objective is to provide a brief education, history, and insights into our Pavement Management in order to inform decisions.

Overview of Asphaltic Concrete (AC) and Pavement Condition Index
(PCI of 65)

Funding Overview

Maintenance Activities (City Maintenance Efforts)

Planned projects for
FY2023

and
FY2024

(Contractor
Maintenance Activities)

STREET NETWORK SYSTEM
DATA
Pavement Area (square miles): 1.89 Centerline Miles: 232.42 Lane Miles: 535.9

PAVEMENT

CONDITION

INDEX (PCI)
Developed by the U. S. Army Corp of Engineers during World War II and standardized by ASTM, the PCI is an objective and rational basis for determining pavement condition and establishing maintenance priorities.

PCI = 100
PCI = 28
COMMON

PAVEMENT

DISTRESSES
Block
Cracking
Alligator
Cracking
Transverse or
Longitudinal
Cracking
Weathering or
Raveling
IMPACT
OF

WEATHER
AND
HEAVY
LOADS

PAVEMENT

MANAGEMENT

STRATEGIES
($.22/sf, 8 yrs )
($.32/sf, 5 - 7 yrs )
($.45/sf, 5 - 7 yrs )
($5-$7/sf,
8 - 15 yrs)
($10-$15/sf,
15 – 20 yrs)

FUNDING
Available Budget limited scope of work in prior years
FY 21-22 FY 22-23 FY 23-24
Gas Tax/SB1 $3,027,616 $3,863,320 $3,340,970
Grants/LSTP $285,000 $600,123 $287,000
Measure A $437,524 $1,350,000 $1,345,000
General Fund $2,075,468 $2,000,000
$3,750,140 $7,888,911 $6,972,970

FUNDING REQUIRED TO MAINTAIN PCI
Year Rehabilitation Cost
Preventative
Maintenance
Cost
Total Cost
Total Deficit
with Existing
Funding
2024 $10,542,701 $249,660 $10,792,361 $3,819,391
2025 $13,714,953 $302,728 $14,017,682 $7,044,712
2026 $15,606,608 $910,144 $16,516,752 $9,543,782
2027 $16,975,388 $952,161 $17,927,550 $10,954,580
- Total System Value $1,080,729,776
- Amount Needed to get system to PCI 80 $106,901,420

POTHOLES & MAINTENANCE
 Potholes –
 How do they form?
 How do we fix?
 Temporary and permanent treatment options?
- Maintenance Activities
- Crack Sealing
- Skin Patching (hot)
- Cold Patch
- Crew of 5
- 500 TONS of placed AC 100 Tons per person!
- New Pothole Truck
- New Emulsion Tank
- Purchasing a Paver & Grinder for Streets Maintenance Crews - Fleet staff completed an overhaul of Crack Sealer

HOW DO WE DECIDE
Major Factors to help us decide what Roads?
- Safety, PCI, and Traffic Volumes. Highest impact to driver - Collaboration between Operations (Ops) & Engineering
- What Streets are taking the most time for Ops to maintain - ADA requirements
- Drainage Issues – Such as Miller
- City Ops Crews on Lower traffic streets
- Approximately 14% of Arterial & Collector Roadway will be treated this year

FY
2023
REPAIR

STRUCTURAL DEFECTS
North of Main
South of Main
Betteravia
Blosser
Bradley
Carlotti
Depot
Hidden Pines
Jones
Railroad
Suey
Bradley-Southside Roundabout
Hidden Pines Way Roundabout

FY
2024

REHABILITATIONS
AND
CHIP
SEAL

North of Main
South of Main
Boone
Chapel
College
Donovan
El Camino
Enos
Fesler
McCoy
Miller
Preisker
Railroad
Stowell
Taylor
Thornburg
Western
Boone St
Drainage Improvements
Miller St
Drainage Improvements
Donovan ATP
Improvements
Fesler ATP
Improvements
Western St Concrete
Improvements
WHAT’S

CHANGING

Emphasizing City maintenance. Flatten the curve.

New Equipment

Increased budget
$3.75 Million

to $7.9 Million

Correcting structural issues

On
-
Call Paving Contracts

In
-
House portions of Engineering and Inspection

Collaboration Meetings held with Operations

Reviewed past projects

Reviewed past maintenance methods

Curb Ramps, Curb & Gutter, and Sidewalk deficiencies (ADA Implications)

Drainage deficiencies

8 -
year budget cycle

Innovations
-

real time PCI

Reducing Pavement