AGREEMENT FOR PROFESSIONAL SERVICES
US 101/MAIN STREET INTERCHANGE PROJECT STUDY REPORT
This Agreement is made on August 15, 2023, by and between Dewberry Engineers Inc., a California Corporation (“Consultant”), and the City of Santa Maria, a California Municipal Corporation and charter city (“City”), in Santa Maria, California, based on the following recitals:

WHEREAS, City has determined it is in the public interest to proceed with the work hereinafter described as "Project"; and WHEREAS, City has determined the Project involves the
performance of construction services of a temporary nature; and

WHEREAS, City does not have available employees to perform the services for the Project; and
WHEREAS, City has requested the Consultant to provide
manpower to complete the Project; and
WHEREAS, Consultant is registered or licensed in California to perform construction services for the Project.

NOW, THEREFORE, IT IS AGREED:

1. Recitals true. The above recitals are true.

2. General.

2.01. Term and Termination. The term of this contract is 13 months, beginning on the date first written above. This contract may be extended by mutual consent of the parties. This contract may be terminated for breach of its terms or conditions, or because of discovery of any act which violates local, state, or federal law. Termination is effective 14 days after deposit of notice as specified in this Agreement.

2.02. Services to be Performed. Consultant shall determine the method, details, and means of providing engi neering studies and design services. More specifically, Consultant agrees to perform the specific services listed in Exhibit “A.”

2.03. City’s Duties. City’s duties under this Agreement are to cooperate with Consultant in the performance of the contract and timely pay invoices.

2.04. Payment. Payment terms under this Agreement are listed in Exhibit “B.”

2.05. Insurance. Consultant shall provide insurance as listed in Exhibit “C.”

2.06. Exhibits. Exhibits “A,” “B,” and “C” are attached and incorporated.

3. Consultant’s Obligations.

3.01. Minimum Amount of Service. Consultant shall devote sufficient time to perform services under this agreement efficiently and effectively. Consultant may represent, perform services for, and be employed by additional individuals or entities, in Consultant’s sole discretion, as long as the performance of these extra-contractual services does not interfere with or present a conflict with City's business.

3.02. Tools and Equipment. Except as otherwise stated in this Agreement, Consultant will supply all tools and equipment necessary to perform this Agreement.

3.03. Status. Consultant (including its employees) is an independent consultant. No employer/employee relationship exists between Consultant and the City.

Consultant's assigned personnel shall not be entitled to any benefits payable to employees of the City. The City i s not required to make any deductions or withholdings from the compensation payable to Consultant under this agreement. Consultant (as a business entity, including its employees) is a “design professional” as defined by California Civil Code section 2782.8(c)(3).

3.04. Indemnification. To the fullest extent permitted by law, the Consultant shall indemnify, defend (with independent counsel approved by the City) and hold harmless the City, and its directors, officers, and employees from and against all liabilities (including without limitation all claims, losses, damages, penalties, fines, and judgments, associated investigation and administrative expenses, and defense costs, including but not limited to reasonable attorneys’ fees, court costs and costs of alternati ve dispute resolution) regardless of nature or type that arise out of, pertain to, or relate to the negligence, reckless, or willful misconduct of the Consultant (including its employees).

The provisions of this paragraph survive completion of the services or the termination of this contract. The provisions of this Section are not limited by the provisions of the Section relating to insurance.

4. Miscellaneous

4.01. Notices. All communication relating to the day -to-day activities of this Agreement shall be exchanged between a designated representative of the CITY and a representative of CONSULTANT, listed below. All notices shall be addressed as follows unless a written change is filed with the City:

To City:

Attn.: David Beas
Public Works/Engineering
110 S. Pine Street, Suite 221
Santa Maria, CA 93454
To Consultant:

Attn.: Jose Silva
Dewberry Engineers Inc.
11060 White Rock Road, Suite 200
Rancho Cordova, CA 95670
If the designated Representative or address of either party changes during the term of this agreement, a written notice shall be given to the other party prior to the effective date of change. Any written notices required under this agreement shall be effective five (5) days after deposit into United States mail, postage prepaid, addressed to the designated Representative, or upon confirmation of receipt of delivery if another notification process is used.

4.02. Compliance With Laws, etc. Consultant shall comply wi th all laws, including but not limited to the rules and policies of the City, in performing this agreement.

4.03. Integration. This agreement constitutes the entire agreement of the parties with respect to the subject matter. All modifications, amendments, or waivers of the terms of this agreement must be in writing and signed by the appropriate representatives of the parties.

4.04. Interpretation. This agreement shall be interpreted in accordance with the laws of the State of California.
2 Atty. Rev. 2021

4.05. Jurisdiction. Jurisdiction and venue of all disputes over the terms of this agreement shall be in the County of Northern Santa Barbara, State of California.

4.06. Warranty of authority. Each person signing this agreement on behalf of a party warrants that he or she has authority to do so.

4.07. No Waiver. Failure to enforce with respect to a default shall not be construed as a waiver.

4.08. Severability. The provisions of this agreement are severable. If any part of this agreement is held invalid by a court of competent jurisdiction, the remainder of the agreement shall remain in full force and effect unless amended or modified by mutual written consent of the parties.

4.09. Submittals. In addition to any other submittals required by this agreement, Consultant shall submit copies of its current business license and current certificate of workers’ compensation coverage to the City before beginning work on this project.

4.10. Prevailing Wage. Prevailing Wage. If applicable, Consultant and all Subcontractors are required to pay the general prevailing wage rates of per diem wages and overtime and holiday wages determined by the Director of the Department of Industrial Relations under Section 1720 et seq. of the California Labor Code. The Director's determination is on file and open to inspection at www.dir.ca.gov and is referred to and made a part hereof; the wage rates therein ascertained, determined, and specified are referred to and made a part hereof as though fully set forth herein.

IN WITNESS WHEREOF, this agreement is executed by the parties on the date first written above.

CONSULTANT CITY OF SANTA MARIA, a political
subdivision of the State of California
By: VICE PRESIDENT
Jose Silva
By: JASON STILWELL
City Manager
ATTEST:

Rhonda M. White, CMC
Chief Deputy City Clerk
APPROVED AS TO FORM:
_
City Attorney
_
Risk Manager
3 Atty. Rev. 2021

EXHIBIT “A”

SERVICES TO BE PERFORMED
This scope of this project consists in the preparation of a Project Study Report-Project Development Support (PSR-PDS) in support of the redesign of the US 101/Main Street (SR 166) Interchange. The PSR-PDS will serve as the project’s Project Initiation Document (PID).

Collectively, the City of Santa Maria (CITY) is working with the California Department of Transportation (Caltrans), and the Santa Barbara County of Associated Governments (SBCAG) to proactively address circulation concerns at the subject interchange.

ASSUMPTIONS / EXCLUSIONS
When developing this scope and fee, the following assumptions were made:
 Detailed information such as geometric approval drawings, design standard decision documents, structure planning studies, right of way analysis, and detailed environmental analysis will be deferred until the Project Approval & Environmental Document (PA&ED) phase.

The PSR-PDS will be developed in accordance with Caltrans PSR-PDS Guidance and Project Development Procedures Manual – Appendix S. This includes but is not limited to the requirements for developing the PSR-PDS under the latest Caltrans standards and guidance.

The Traffic Engineering Performance Assessment (TEPA) will build off previous performed work available.

The total anticipated duration of the project to obtain Caltrans PSR-PDS acceptance is 18 months.



TASK 1 - PROJECT MANAGEMENT, STAKEHOLDER COORDINATION AND MEETINGS (WBS 100.05)
CONSULTANT will manage the project team through the PID phase. CONSULTANT Project Manager will plan, organize, direct and monitor project work activities and resources in accordance with contracted scope, schedule, and budget.

TASK 1.1 – Coordination/Meetings/Administration
This task will include managing the team, working with CITY, Caltrans, and SBCAG and includes preparing contract paperwork, memo's, letters, and e-mail, making phone calls and maintaining project files. This activity commences with receiving the Notice-To- Proceed, continues through submittal of the key final project deliverables, and concludes when the project's PID is signed.
4 Atty. Rev. 2021

CONSULTANT will take the lead in conducting meetings including preparation and distribution of the meeting agenda, arrangement of attendance of meeting participants, and preparation and distribution of meeting minutes, including the recap of actions to be taken prior to the next meeting. Meetings will generally be held centered on or near key project milestones. Meetings are assumed to be virtual (up to 12 virtual meetings).

CONSULTANT also assumes up to 2 in-person meetings as part of this scope of work.

Coordination would also include one focus meeting with Caltrans Structures Office of Special Funded Projects (OSFP) to obtain Caltrans input on the structure concepts.

Formal approvals for the Advanced Planning Studies (APSs), Type Selection, and design will be done in the PA&ED phase after the PSR-PDS is complete.

CONSULTANT will also establish a password protected FTP site throughout the duration of the project. Current project information and design data will be uploaded to the FTP site to allow the Team instant access to up-to-date project information.

CONSULTANT will also assist the CITY by reviewing and providing information needed to complete the Caltrans/CITY Cooperative Agreement.

CONSULTANT will work with the CITY and Caltrans to develop a mini project charter.

Task 1.2 Quality Management Plan & Compliance
The CONSULTANT Project Manager will develop and monitor compliance with a Quality Management Plan (QMP) that meets the standards of professional practice and satisfies requirements of the project scope and schedule. The CONSULTANT Project Manager will work with the team to use the Quality Control/Quality Assurance (QC/QA) elements as described in this document during the production and review of the PSR- PDS. QC/QA will be performed before deliverables are submitted to CITY and Caltrans for review.

Deliverables:





Project updates to CITY Project Manager via email
Meeting agenda sent in advance of meeting
Meeting minutes sent within one week of meeting
Quality Management Plan (QMP)
Mini Project Charter
TASK 2 – BASE MAP (WBS 150.05)
The CITY will assist the team by providing available as-built plans, and other data, and by identifying locations or agencies of "known" information. Topographic field surveys or boundary survey work will not be conducted for this project.

TASK 2.1 – Base Mapping / Data Research and Collection
5 Atty. Rev. 2021

CONSULTANT will gather information from the CITY, Caltrans, County, other agencies, and local developers to prepare a comprehensive base map for the project. It is anticipated that CONULTANT will collect the following:
• Aerial photograph from various sources
• GIS information
• Preliminary development maps showing proposed roadways and access • US 101 and Interchange As-Builts
• Right of way record maps and as-builts from CITY and Caltrans • Transportation Plan concepts from CITY General Plans
• Available utility information
TASK 3 - GEOMETRY DEVELOPMENT AND REFINEMENT (WBS 150.10) The geometrics for the interchange will be prepared as line drawings and will show basic information (i.e., typical cross sections, structure widening limits, retaining walls, weave lengths, etc.) needed for the CITY and Caltrans to review and understand what is being proposed. The exhibits will clearly show what is proposed; however, they do not need to be to Geometric Approval Drawing level. The exhibits can be scaled-down to fit in to the PSR-PDS document.

TASK 3.1 – Initial Geometry Development
This scope assumes that available aerial photography will be used as the base map for the exhibits.

During the development of the geometrics, the following will be considered:
environmental compliance, structures, materials, landscaping, permits, local and regional input, right of way, compliance with design standards, traffic operations, and alternative transportation modes already in place.

Potential delegated (advisory) and non-delegated (mandatory) design exceptions will be identified. CONSULTANT will attend design focus meetings with Caltrans staff to discuss and evaluate the geometrics and potential design exceptions. From these meetings, we will also assess the risk level of design exceptions being accepted/rejected and include in the risk register.

The geometric exhibits will be prepared at a scale of 1"=50' and will be prepared to adequately support the PEAR. Again, the exhibits will clearly show what is proposed; however, they do not need to be to Geometric Approval Drawing level.

TASK 3.2 – Structures Concept Development
6 Atty. Rev. 2021

With a PSR-PDS, Caltrans would typically complete a Structure PSR-PDS Cost Estimate to develop a rough order of magnitude estimate of the construction cost and associated project risks for the proposed structure improvements.

The efforts that would be required for completion of the Structure PSR-PDS Cost Estimates includes attendance at project meetings, coordination within the team and with Caltrans, site visits, conceptual layouts, and development of the preliminary cost estimates as follows.

Task 3.2.1 Background Research & Review
CONSULTANT will obtain the Caltrans Bridge Inspection Records Information System (BIRIS) files for each of the interchange bridges and review the as-built data, maintenance history and current maintenance recommendations.

Task 3.2.2 Field/Site Review
CONSULTANT will complete a site visit to verify as-built data and maintenance needs outlined in the Caltrans Bridge Inspection Reports, and identify existing conditions that could impact the structure concepts such as utilities that could be impacted by the proposed improvements.

Task 3.2.3 PSR-PDS Concepts and Cost Estimates
Both the US 101 bridge and nearby culvert for the Bradley Channel are anticipated to be impacted by the project. CONSULTANT will develop structure concepts and PSR-PDS cost estimates for these structures. The structure concepts will include typical sections, approximate layout limits, and other graphics needed to support the roadway alternatives. Standalone structure sheets such as APSs are not anticipated and are assumed to be part of the next PA&ED phase. PSR-PDS level cost estimates will also be developed for the structure concepts investigated. These cost estimates will follow Caltrans Memo to Designers 1-8. Structure concept support graphics and PSR-PDS structures costs will be developed for up to 3 bridge concepts and 3 culvert concepts.

Deliverables:


PSR-PDS Concept Graphics
PSR-PDS Cost Estimates
TASK 4 - TRAFFIC ENGINEERING PERFORMANCE ASSESSMENT (TEPA) (WBS 150.15)
TASK 4.1 – Data Collection
CONSULTANT will use the multimodal volume data in the US 101 / SR 166 (Main Street) the Intersection Control Evaluation Report (including ramp terminal intersections, local intersections, and 120 mainline) and determine the gaps in the data that would need to be filled by new data collection. Given that the Existing Year traffic data was from 2015, 7 Atty. Rev. 2021

it is likely that very limited additional / new volume data collection would be required to provide a traffic volume data basis for study intersections; as such, this task includes counts at the two ramp terminal intersections for the 2 -hour weekday AM and 2-hour weekday PM periods. Mainline volumes will be developed using count information from the PeMS database for US 101. The Caltrans Traffic Accident Surveillance and Analysis System collision database (last three complete years of data not affected by the COVID- 19 pandemic) will also be reviewed and summarized.

TASK 4.2 – Travel Demand Modeling
The refined SBCAG Regional Travel Demand Forecasting Model for the City of Santa Maria will be used to develop the future year traffic forecasts. The main elements of the traffic forecasting process for the PID stage will include:
 Study area model review to year 2022 conditions. This review will consist of a review of the regional freeway and local roadway network, traffic analysis zone centroid connectors, and land use information for the study area. If major differences exist, adjustments will be made to the model to improve model performance. Differences in model volumes versus previous counts will be documented for consideration in the future year volume forecasting process.  Design year land use and roadway network verification/checks with adopted plans. The SBCAG Regional Transportation Plan (2022) will be the primary source for determining regional improvements to assume in the future. The City of Santa Maria Proposed General Plan land use and transportation network, as well as the City of Santa Maria Capital Improvement Plan (CIP) will be used to identify planned and funded local street improvement projects that may affect either the traffic forecasts or operations analysis.
 Design year AM and PM peak hour traffic forecasts for the study corridors and intersections will be developed by calculating the traffic growth projected in the study area between the base year and the future year model, and applying that growth to the existing volumes to develop construction year (2028-2030) and design year (2048-2050) forecasts (i.e. delta method).

Forecast volumes will be delivered in a tabular format as an initial step for review and discussion. Final forecast volumes for inclusion in the TEPA will be provided in a graphical format.

TASK 4.3 – Alternative Development, Analysis and Refinement CONSULTANT will collaborate with the project team to develop and refine up to three (3) build alternatives (diverging diamond, roundabout, or single point urban interchange). It is anticipated that build alternatives will include common elements such 8 Atty. Rev. 2021

as improved on- and off-ramps, new roadway connections, and upgraded intersection control devices. The build alternatives will be analyzed and refined based on maximizing the benefits associated with the following complementary principles:





Multimodal Connectivity and Safety
Improving the Quality of Life for Residents, Employees and Visitors Congestion Relief & Vehicle Demand Redistribution to Promote Livable Streets Ability to Compete for Federal and State Funding
Constructability and Approvability
CONSULTANT will evaluate intersection and ramp operations under the no build and build alternatives using a combination of the Synchro/SimTraffic software package and Sidra software package. Study intersection will include the interchange ramp terminal intersections and one local intersection on either side of the study interchange. The traffic operations analysis will be used to inform geometric decisions and to demonstrate the benefits of key elements of each build alternative. Mainline US 101 analysis will be performed using the HCS 7 software package. Study segments will include basic, on- ramp merge, off-ramp diverge, and weave segments on northbound US 101 and southbound US 101 under Existing Conditions, and under Design Year conditions. The suitability of the build alternatives to pass through the Caltrans Headquarters Induced VMT process will be qualitatively evaluated at this stage. Depending on the most up-to- date Caltrans Induced VMT guidelines and requirements at the time, a quantitative VMT analysis may be completed in the PA&ED phase.

Using the existing count data and field observations of study facility operations, CONSULTANT will build Existing Conditions traffic operations models for weekday AM and PM peak hours and calibrate/validate the models to typical District 5 standards.

Design Year (2048-2050) models will be built off of the validated Existing Conditions models and serve as the testing models for the alternative analysis and refinement of alternatives. Measures of Effectiveness (MOEs) will include the following:

As part of this task, the refined Phase 1 and Phase 2 Intersection Control Evaluation (ICE) analysis will be performed as part of the tight-diamond with roundabout alternative to confirm intersection control devices for project intersections in the Caltrans right of way or under Caltrans control. The results of the ICE process will be documented in the Traffic Engineering Performance Assessment (TEPA).
9 Atty. Rev. 2021
Study Intersection MOEs SimTraffic Network MOEs

Intersection delay
Level of service (LOS)
95th percentile queue lengths

Vehicle Hours of Delay (VHD)
Total Stops
Vehicle Miles of Travel (VMT)
Vehicle Hours Traveled (VHT)
Average Speed (mph)
Total Fuel Consumption (gallons)
Total Vehicle Emissions (pounds)
Denied Entry After

TASK 4.4 – Traffic Engineering Performance Assessment
The results of the traffic analysis will be documented in the Draft TEPA and will be submitted to Caltrans for review. CONSULTANT will respond to one round of written comments and prepare the Final TEPA. Based on PSR/PDS guidelines, the TEPA will also include a preliminary scope of work for the traffic engineering studies to be completed in the PA&ED phase. The preliminary scope of work will be developed in consultation with CITY and Caltrans. This deliverable will also include completion of the new VMT Decision Document required by Caltrans Headquarters and District 5.

Deliverables:


Draft TEPA (PDF)
Final TEPA (PDF)
TASK 5 – Preliminary Environmental Analysis Report (PEAR) (WBS 150.20) CONSULTANT will prepare a Mini-Preliminary Environmental Analysis Report (Mini- PEAR) in accordance with the Caltrans Standard Environmental Reference template/guidance dated June 2020. The Mini-PEAR will identify environmental issues that could affect a project scope, schedule, or cost (i.e., environmental document and supporting technical studies, seasonal survey constraints, special jurisdictions, mitigation measures and costs, permitting requirements).

CONSULTANT will review existing studies, mapping resources, and other available data to gather the information to complete the Mini-PEAR. CONSULTANT will also conduct a reconnaissance-level windshield survey of the proposed project area.

Additionally, CONSULTANT will complete the following tasks for specific resources.  Cultural Resources: CONSULTANT will order a background records search and literature review at the regional Information Center of the California Historical Resources Information System (CHRIS) for the proposed project area and a 1- mile radius.

Biological Resources: CONSULTANT will obtain species lists from the California Department of Fish and Wildlife, U.S. Fish and Wildlife Service, and the California Native Plant Society for the proposed project area and vicinity.

Paleontological Resources: CONSULTANT will prepare a pale ontological literature review and locality search through an appropriate institution that maintains records of paleontological resources.

Hazardous Materials: CONSULTANT will conduct a Phase 1 ISA in accordance with Caltrans' procedures. The ISA will contain a description of the work performed, record search of government files and databases, windshield survey deviations from normal ISA procedures, a summary of findings, the opinions of the preparer regarding the property or site, data gaps, additional investigation and services recommended, conclusions, and recommendations. 10 


Atty. Rev. 2021

The information gathered from the tasks listed above will be incorporated into the Mini- PEAR with sufficient mapping to illustrate potential environmental issues associated with the project. The draft Mini-PEAR will be submitted to the PDT for review. Once comments have been received and changes have been incorporated, CONSULTANT will prepare a final Mini-PEAR.

TASK 6 - STORM WATER DATA REPORT (PID PHASE) (WBS 150.25) CONSULTANT will prepare the streamlined PSR/PDS-level Storm Water Data Report (SWDR). The SWDR prepared during the PSR/PDS phase provides the initial documentation of potential water quality impacts to receiving water bodies and anticipated best management practices (BMP) to minimize or mitigate these potential water quality impacts.

The PSR/PDS SWDR identifies the project receiving water bodies and describes the existing water quality limitations. In addition, the PSR/PDS SWDR describes the general geotechnical conditions of the project area for identification of BMPs that may be required for the project.

The report will provide an understanding of potential impacts that result from the disturbed soil area created by the project, in addition to potential downstream impacts and water quality impacts related to the increase in impervious area created by the project.

The feasibility of appropriate treatment BMPs will be documented in the PSR/PDS SWDR. The PSR/PDS SWDR initiates the process of identifying the minimum temporary and permanent BMPs required for the project to allow for proper allocation of funds during the development of the preliminary project cost estimate.

Deliverables:
 Draft and Final PSR/PDS Stormwater Data Report (PDF) TASK 7 – PRELIMINARY DRAINAGE, FLOODPLAIN AND WATER QUALITY STUDY (WBS 150.15)
CONSULTANT will review the available data for the drainage, floodplain, and water quality, and:




Identify potentially impacted floodplain areas;
Identify waterways with noted water quality impairments; Document appropriate stormwater and hydraulic design criteria; Identify major drainages and develop preliminary hydrologic and hydraulic calculations for these drainages (if any);
Identify and assess preliminary drainage needs for the proposed alternatives studied in the PSR/PDS; and
Determine and list the next steps for project development about water resources. 

11 Atty. Rev. 2021

Preliminary calculations (if needed) will be developed to identify feasibility of crossing alternatives. CONSULTANT will prepare a Draft and Final Preliminary Drainage, Floodplain, and Water Quality Study Report to be included in the PSR/PDS document.

The Preliminary Drainage, Floodplain, and Water Quality Study Report will include:
 General location and description of the project, including a statement of design assumptions.

Documentation of regulatory floodplain and floodways that may impact the development of the project.

A list of 303(d) listed waterways potentially impacted by the project.

Documentation of National Pollutant Discharge Elimination System (NPDES) stormwater quality criteria.

Documentation of on- and off-site drainage design criteria.

Key existing drainages (swales, culverts, streams, creeks, and canals) that cross or impact the design of the project.

Preliminary hydrologic and hydraulic analyses of key existing drainage features at crossings of the project.

A list of special concerns or issues that may come up regarding the various drainages.







Deliverables:
 Draft and Final Preliminary Drainage, Floodplain, and Water Quality Study Report (PDF)
TASK 8– UTILITY RESEARCH AND VERIFICATION (WBS 150.05)
CONSULTANT will conduct research of available utility information to initially verify utilities within the project area for the PIDE Phase which will document the major affected facilities. Information will be summarized in the PSR-PDS.

TASK 9 – RIGHT OF WAY REQUIREMENTS AND RIGHT OF WAY DATA SHEETS (WBS 150.15)
CONSULTANT will provide right of way and cost estimating support services for the PSR-PDS as described below.

CONSULTANT will analyze the parcels outlined as being impacted by the proposed improvements at the interchange. Based on the preliminary right of way mapping, APN’s and permanent and temporary impact area square footages obtained, CONSULTANT will prepare an order of magnitude cost using comparable recent sale square foot cost data. Parcel acquisitions that may cause project delays will be identified. CONSULTANT will evaluate potential solutions to eliminate or minimize these impacts. An assessment of impacts, including costs, will be documented in a right of way data sheet. Scope of work assumes one right of way data sheet. 12 Atty. Rev. 2021

Deliverables:
 Right of way Data Sheets - PDF
TASK 10 - OTHER SUPPORTING DOCUMENTATION (WBS 100.05)
The CONSULTANT team will prepare supporting documentation required for the PSR- PDS based upon the requirements of the Caltrans Project Development Procedures Manual (PDPM). This includes the following:

Task 10.1 Risk Register - Memo documentation of the potential risks associated with the project.

Task 10.2 Division of Engineering PSR/PDS Scoping Checklist.

Task 10.3 Transportation Planning Scoping Information Sheet.

Task 10.4 Traffic Management Plan
Task 10.5 Design Scoping Index- Discussion of anticipated alignments and alternatives and identification anticipated design exceptions.

Task 10.6 PSR/PDS Surveys Needs Questionnaire.

Task 10.7 Order of Magnitude Capital Cost Estimate Sheets.

Task 10.8 Milestone Schedule
TASK 11 - DRAFT AND FINAL PSR-PDS (WBS 100.25)
The CONSULTANT team will prepare a Draft PSR/PDS for circulation to the CITY, Caltrans, and other PDT members. The document will be based on the revised Caltrans guidance on the PSR/PDS process. Following Caltrans and external reviews of the Draft PSR/PDS, CONSULTANT will coordinate with the PDT to address significant issues affecting the project's cost, scope or schedule and revise the PID.

Deliverables
• Draft PSR/PDS - 15 Copies, Black and White, 30 pages assumed • Final PSR/PDS - 15 Copies, Black and White, 30 pages assumed

OPTIONAL TASKS
The following tasks are optional (Task 12 and 13) and are not part of the PSR-PDS scope of work. If requested by the CITY, the level of effort and fee will be determined during a scoping meeting with the CITY to better define the scope:

TASK 12 – FUNDING AND PHASING STRATEGY (Optional) (WBS 150.10) 13 Atty. Rev. 2021

Phasing options will be developed and summarized to reduce the project costs.

CONSULTANT funding strategy will be centered around the following:
 Accelerate the schedule to get the project shovel ready to facilitate obtaining construction funding.
 Cost Reduction/Value Engineering: Value Engineering will continue to be performed to keep the project within the available funding. This will position the project to secure additional revenue or financing.
 Position the project for Federal Funding Opportunities by Identifying and Securing Non-Federal Revenue: The current Administration has put an emphasis on funding projects that are already 70-80% locally funded and only need federal funding to close the funding gap. It will be critical to identify and secure as much local and state funds as possible to position the project for a future federal BUILD or INFRA grant.

In addition, the likely and potential funding grants will be summarized.

Deliverables
• Potential Funding Summary - PDF
TASK 13 – PUBLIC OUTREACH (Optional) (WBS 150.10)
CONSULTANT will assist in public outreach activities including:






Stakeholder database
Preparation of newsletter/fact sheet
Provide website support
Preparation of exhibits and renderings
One-on-one meetings and community presentations
Open house public meetings
14 Atty. Rev. 2021

EXHIBIT “B”

PAYMENT
I. Progress Authorization
Written authorization to proceed from the City authorizes the Consultant to generate the not -to- exceed cost of FIVE HUNDRED FIFTY THOUSAND FORTY FIVE WITH SIXTY-TWO CENTS ($550,045.26) in fees for all work.

Task 1: Project Management, Stakeholder
Coordination and Meetings
Task 2: Base Map
Task 3: Geometry Development and Refinement
Task 4: Traffic Engineering Performance Assessment
Task 5: Preliminary Environmental Analysis Report
Task 6: Storm Water Data Report (PID Phase)
Task 7: Preliminary Drainage, Floodplain and Water
Quality Study
Task 8: Utility Research and Verification
Task 9: Right of Way Reqiurements and Right of Way
Data Sheets
Task 10: Other Supporting Documentation
Task 11: Draft and Final PSR-PDS
$66,183.88
$19,676.39
$168,789.01
$39,085.00
$24,520.82
$23,706.28
$34,532.88
$6,006.48
$31,391.41
$26,944.90
$99,648.19
Other Direct Cost $9,560.00
Total Not-To-Exceed Cost: $550,045.26
II. Invoice procedure.

A. Payment shall be at the conclusion of the Project based on the billable charges.

B. The Consultant shall present the bill for charges by the second day of the month.

C. The Consultant's bill shall be substantiated by
appropriate documentation, and include an itemized
listing of personnel, subcontractors, and other direct
costs incurred.

III. Maximum billable amounts
EXHIBIT “B”
Atty. Rev. 2021

Under no circumstance shall the total of all payments to the Consultant exceed ninety percent (90%) of the maximum not-to-exceed cost, prior to acceptance by the City of all items to be completed as noted within Exhibit "A".

EXHIBIT “B”
Atty. Rev. 2021

US 101 / Main St (SR 166)
City of Santa Maria
6/9/2023
EXHIBIT “B”
Dewberry

HOURS COST
Fehr & Peers

HOURS COST
Hamnew Jewell

HOURS COST

HDR - WRECO

HOURS COST
TOTAL

HOURS COST

1.0 Project Management, Stakeholder Coordination and Meetings (WBS 100.05)

1.1 Coordination/Meetings/Administration 161 $42,528.58 161 $42,529

1.2 Quality Managemet Plan & Compliance 81 $23,655.30 81 $23,655 Total Task 1 242 $66,183.88 242 $66,184

2.0 Base Map (WBS 150.05)

2.1 Base Mapping/Data Reasearch and Collection 110 $19,676.39 110 $19,676 Total Task 2 110 $19,676.39 110 $19,676

3.0 Geometry Development and Refinement (WBS 150.10)

3.1 Initial Geometry Development 592 $111,264.82 592 $111,265

3.2 Structures Concept Development

3.2.1 Background Research & Review 6 $1,241.94 6 $1,242

3.2.2 Field/Site Review 33 $7,347.58 33 $7,348

3.2.3 PSR-PDS Concepts and Cost Estimates 260 $48,934.67 260 $48,935 Total Task 3 891 $168,789.01 891 $168,789

4.0 Traffic Engineering Performance Assessment (TEPA) (WBS 150.15)

4.1 Data Collection 10 $1,980.00 10 $1,980

4.2 Travel Demand Modeling 40 $7,100.00 40 $7,100

4.3 Alternatives Development, Analysis and Refinement 116 $22,575.00 116 $22,575

4.4 Traffic Engineering Performance Assessment (TEPA) 37 $7,430.00 37 $7,430 Total Task 4 203 $39,085.00 203 $39,085

5.0 Preliminary Environmental Analysis Report (PEAR) (WBS 150.20)

5.1 Preliminary Environmental Analysis Report (PEAR)

5.1.1 Research/Record Searches 22 $3,955.99 22 $3,956

5.1.2 Recon Site Visit 14 $1,941.75 14 $1,942

5.1.3 Phase I ISA 73 $10,998.07 73 $10,998

5.1.4 Draft/Final Document Prep 46 $7,625.02 46 $7,625 Total Task 5 155 $24,520.82 155 $24,521

6.0 Storm Water Data Report (PID Phase) (WBS 150.25)

6.1 Storm Water Data Report (PID Phase) 51 $10,271.28 89 $13,435.0 140 $23,706 Total Task 6 51 $10,271.28 89 $13,435.00 140 $23,706

7.0 Preliminary Drainage, Floodplain and Water Quality Study (WBS 150.15)

7.1 Preliminary Drainage, Floodplain and Water Quality Study 53 $10,762.88 154 $23,770.00 207 $34,533 Total Task 7 53 $10,762.88 154 $23,770.00 207 $34,533

8.0 Utility Research and Verification (WBS 150.05)

8.1 Utility Research and Verification 35 $6,006.48 35 $6,006 Total Task 8 35 $6,006.48 35 $6,006

9.0 Right of Way Reqiurements and Right of Way Data Sheets (WBS 150.15)

9.1 Right of Way Reqiurements and Right of Way Data Sheets 53 $9,591.41 120 $21,800.00 173 $31,391 Total Task 9 53 $9,591.41 120 $21,800.00 173 $31,391

10.0 Other Supporting Documentation (WBS 100.05)

10.1 Risk Register 6 $1,655.92 6 $1,656

10.2 Division of Engineering PSR/PDS Scoping Checklist 14 $3,313.92 14 $3,314

10.3 Transportation Planning Scoping Information Sheet 14 $3,313.92 14 $3,314

10.4 Traffic Management Plan 14 $3,313.92 14 $3,314

10.5 Design Scoping Index 6 $1,615.54 6 $1,616

10.6 PSR/PDS Surveys Needs Questionnaire 10 $2,262.79 10 $2,263

10.7 Order of Magnitude Capital Cost Estimate Sheets 50 $8,854.01 50 $8,854

10.8 Milestone Schedule 10 $2,614.89 10 $2,615
Total Task 10 124 $26,944.90 124 $26,945

11.0 Draft and Final PSR-PDS (WBS 100.25)

11.1 Draft and Final PSR-PDS 530 $99,648.19 530 $99,648 Total Task 11 530 $99,648.19 530 $99,648
TOTAL DIRECT LABOR HOURS 2,244 $442,395.24 203 $39,085.00 120 $21,800.00 243 $37,205.00 2,810 $540,485.26 TOTAL OTHER DIRECT COST $7,500.00 $910.00 $200.00 $950.00 $9,560.00 TOTAL PROJECT COST $449,895.24 $39,995.00 $22,000.00 $38,155.00 $550,045.24

US 101 / Main St (SR 166)
City of Santa Maria
Dewberry
Prime
EXHIBIT “B”

Loaded Rate:

PIC, Dennis
Haglan

PM, F. Jose Silva

Project Engineer,
Miguel Ramirez

ENGINEER V, To
Be Determined

ENGINEER I, To
Be Determined

Bridge Lead,
Matthew Burgard

ENGINEER V, To
Be Determined

ENGINEER II, To
Be Determined

DESIGNER IV, To
Be Determined

Bridge QA/QC,
Kevin Ross

Roadway QA/QC,
Nathan Donnelly
Environmental Lead,
Jeff Bray

PROFESSIONAL
VIII, To Be
Determined

PROFESSIONAL
VI, To Be
Determined

PROFESSIONAL I,
To Be Determined

TASK HOURS

ESCALATION

TASK COSTS
$360 $306 $232 $202 $123 $232 $202 $143 $182 $306 $261 $286 $261 $212 $108 Task # Task Name

1.0 Project Management, Stakeholder Coordination and Meetings (WBS 100.05) 1.1 Coordination/Meetings/Administration 1 60 40 20 20 20 161 $3,013.06 $42,528.58

1.2 Quality Managemet Plan & Compliance 1 24 24 8 24 81 $1,675.93 $23,655.30 Total Task 1 2 84 64 20 20 20 8 24 242 $4,688.99 $66,183.88

2.0 Base Map (WBS 150.05)

2.1 Base Mapping/Data Reasearch and Collection 2 8 20 40 40 110 $936.97 $19,676.39 Total Task 2 2 8 20 40 40 110 $936.97 $19,676.39

3.0 Geometry Development and Refinement (WBS 150.10)

3.1 Initial Geometry Development 8 60 140 180 180 24 592 $5,298.32 $111,264.82

3.2 Structures Concept Development

3.2.1 Background Research & Review 2 2 2 6 $87.99 $1,241.94

3.2.2 Field/Site Review 4 5 8 8 8 33 $349.88 $7,347.58

3.2.3 PSR-PDS Concepts and Cost Estimates 40 80 140 260 $3,466.92 $48,934.67 Total Task 3 12 65 140 180 50 90 150 180 24 891 $9,203.11 $168,789.01

4.0 Traffic Engineering Performance Assessment (TEPA) (WBS 150.15)

4.1 Data Collection

4.2 Travel Demand Modeling

4.3 Alternatives Development, Analysis and Refinement

4.4 Traffic Engineering Performance Assessment (TEPA)
Total Task 4

5.0 Preliminary Environmental Analysis Report (PEAR) (WBS 150.20)

5.1 Preliminary Environmental Analysis Report (PEAR)

5.1.1 Research/Record Searches 2 4 4 12 22 $188.38 $3,955.99

5.1.2 Recon Site Visit 1 1 12 14 $92.46 $1,941.75

5.1.3 Phase I ISA 1 2 20 50 73 $523.72 $10,998.07

5.1.4 Draft/Final Document Prep 2 8 6 30 46 $435.00 $7,625.02 Total Task 5 6 15 30 104 155 $1,239.56 $24,520.82

6.0 Storm Water Data Report (PID Phase) (WBS 150.25)

6.1 Storm Water Data Report (PID Phase) 1 2 8 40 51 $585.96 $10,271.28 Total Task 6 1 2 8 40 51 $585.96 $10,271.28

7.0 Preliminary Drainage, Floodplain and Water Quality Study (WBS 150.15)

7.1 Preliminary Drainage, Floodplain and Water Quality Study 1 4 8 40 53 $614.01 $10,762.88 Total Task 7 1 4 8 40 53 $614.01 $10,762.88

8.0 Utility Research and Verification (WBS 150.05)

8.1 Utility Research and Verification 1 4 10 20 35 $286.02 $6,006.48 Total Task 8 1 4 10 20 35 $286.02 $6,006.48

9.0 Right of Way Reqiurements and Right of Way Data Sheets (WBS 150.15)

9.1 Right of Way Reqiurements and Right of Way Data Sheets 1 4 24 24 53 $547.18 $9,591.41 Total Task 9 1 4 24 24 53 $547.18 $9,591.41

10.0 Other Supporting Documentation (WBS 100.05)

10.1 Risk Register 2 4 6 $117.32 $1,655.92

10.2 Division of Engineering PSR/PDS Scoping Checklist 2 4 8 14 $157.81 $3,313.92

10.3 Transportation Planning Scoping Information Sheet 2 4 8 14 $157.81 $3,313.92

10.4 Traffic Management Plan 2 4 8 14 $157.81 $3,313.92

10.5 Design Scoping Index 2 4 6 $76.93 $1,615.54

10.6 PSR/PDS Surveys Needs Questionnaire 1 1 8 10 $107.75 $2,262.79

10.7 Order of Magnitude Capital Cost Estimate Sheets 1 1 24 24 50 $505.11 $8,854.01

10.8 Milestone Schedule 2 8 10 $149.18 $2,614.89 Total Task 10 14 30 56 24 124 $1,429.70 $26,944.90

11.0 Draft and Final PSR-PDS (WBS 100.25)

11.1 Draft and Final PSR-PDS 8 24 120 140 30 24 24 160 530 $5,684.79 $99,648.19 Total Task 11 8 24 120 140 30 24 24 160 530 $5,684.79 $99,648.19 TOTAL DIRECT LABOR HOURS 2 124 205 386 428 100 134 194 460 8 48 6 15 30 104 2244 $25,216.29 $442,395.26 OTHER DIRECT COSTS (see attached sheet) $7,500.00
TOTAL PROJECT COST $449,895.26

US 101 / Main St (SR 166)
City of Santa Maria
Fehr & Peers
Traffic
EXHIBIT “B”
.

.

Principal
Transportation
Engineer,
Project
Transportation
Engineer,
Project
Transportation
Engineer,
GIS and Document
Specialist,

TASK HOURS

TASK COSTS
$330.00 $230.00 $165.00 $135.00

Task # Task Name

4.0 Traffic Engineering Performance Assessment (TEPA) (WBS 150.15)

4.1 Data Collection 1 3 5 1 10 $1,980.00

4.2 Travel Demand Modeling 2 4 31 3 40 $7,100.00

4.3 Alternatives Development, Analysis and Refinement 5 42 65 4 116 $22,575.00

4.4 Traffic Engineering Performance Assessment (TEPA) 2 19 8 8 37 $7,430.00 Total Task 4 10 68 109 16 203 $39,085.00
TOTAL DIRECT LABOR HOURS 10 68 109 16 203 $39,085.00
OTHER DIRECT COSTS (see attached sheet) $910.00
ANTICIPATED SALARY INCREASE (see attached sheet)

TOTAL PROJECT COST

$39,995.00

US 101 / Main St (SR 166)
City of Santa Maria
Hamnew Jewell
Right-of-Way
EXHIBIT “B”
.

.

, Lillian Jewell

Senior Associate,
TBD

Associate II, TBD

Associate I, TBD

Transaction
Coordinator, TBD

Appraiser, TBD

Clerical Support, TBD

TASK HOURS

TASK COSTS
$262.00 $120.00 $150.00

Task # Task Name

9.0 Right of Way Reqiurements and Right of Way Data Sheets (WBS 150.15)

9.1 Right of Way Reqiurements and Right of Way Data Sheets 50 60 10 120 $21,800.00 Total Task 9 50 60 10 120 $21,800.00
TOTAL DIRECT LABOR HOURS 50 60 10 120 $21,800.00
OTHER DIRECT COSTS (see attached sheet) $200.00

TOTAL PROJECT COST

$22,000.00

US 101 / Main St (SR 166)
City of Santa Maria

HDR - WRECO
Hydraulics/Stormwater
EXHIBIT “B”
.

.

Supervising E ngineer,

Senior Civil
Engineer I,

Senior Civil
Engineer II,

Senior Civil
Designer (A),

Senior Civil
Designer (B),

Civil Coordinator,

Staff Civil EIT I,

Technical Editor,

Project
Accountant,

Project
Coordinator,

TASK HOURS

TASK COSTS
$275.00 $180.00 $260.00 $180.00 $180.00 $115.00 $125.00 $110.00 $105.00 $105.00 Task # Task Name

6.0 Storm Water Data Report (PID Phase) (WBS 150.25)

6.1 Storm Water Data Report (PID Phase) 1 4 8 24 8 40 4 89 $13,435.00 Total Task 6 1 4 8 24 8 40 4 89 $13,435.00

7.0 Preliminary Drainage, Floodplain and Water Quality Study (WBS 150.15)

7.1 Preliminary Drainage, Floodplain and Water Quality Study 16 8 4 12 20 36 44 4 6 4 154 $23,770.00 Total Task 7 16 8 4 12 20 36 44 4 6 4 154 $23,770.00
TOTA L DIRECT LA BOR HOURS 17 8 8 20 44 44 84 8 6 4 243 $37,205.00 OTHER DIRECT COSTS (see attached sheet) $950.00
TOTAL PROJECT COST $38,155.00

SCHEDULE OF FEES (7/1/22 - 6/30/23)
EXHIBIT “B”

OTHER DIRECT COSTS

DESCRIPTION OF ITEM COST
Personal Vehicle Mileage see note 1
Overnight Mail Service Actual

NOTES:

1. Pre-approv ed travel and per-diem costs will
be reimbursed in conformance with the current
Department of Transportation Travel and
Expense Guide for Consultants. No charge will
be invoiced for employee relocation cost.

2. Classifications identified with ** are subject
to prevailing wage.

3. Rates subject to an annual escalation of 5%.

NAME OR CLASSIFICA TION

2022

BILLING
RATE

CLASSIFICATION

BILLING RATE
RANGE
PRINCIPAL $360 $ 325 - $ 395
ENGINEER IX $306 $ 284 - $ 328
ENGINEER VIII $276 $ 257 - $ 296
ENGINEER VII $261 $ 248 - $ 276
ENGINEER VI $232 $ 215 - $ 249
ENGINEER V $202 $ 188 - $ 217
ENGINEER IV $178 $ 165 - $ 191
ENGINEER III $163 $ 153 - $ 173
ENGINEER II $143 $ 125 - $ 161
ENGINEER I $123 $ 112 - $ 135
TECHNICAL VI $178 $ 150 - $ 205
TECHNICAL V $158 $ 146 - $ 170
TECHNICAL IV $143 $ 131 - $ 156
TECHNICAL III $128 $ 119 - $ 138
TECHNICAL II $108 $ 100 - $ 118
TECHNICAL I $94 $ 82 - $ 106
CADD TECHNICIAN V $178 $ 150 - $ 205
CADD TECHNICIAN IV $148 $ 138 - $ 158
CADD TECHNICIAN III $128 $ 119 - $ 138
CADD TECHNICIAN II $108 $ 97 - $ 120
CADD TECHNICIAN I $89 $ 78 - $ 100
DESIGNER VI $227 $ 214 - $ 240
DESIGNER V $207 $ 198 - $ 217
DESIGNER IV $182 $ 163 - $ 202
DESIGNER III $163 $ 153 - $ 173
DESIGNER II $143 $ 131 $ 156
DESIGNER I $118 $ 105 - $ 132
PROFESSION AL VII $232 $ 215 - $ 249
PROFESSION AL VI $212 $ 205 - $ 220
PROFESSION AL V $197 $ 187 - $ 208
PROFESSION AL IV $178 $ 168 - $ 188
PROFESSION AL III $153 $ 136 - $ 170
PROFESSION AL II $128 $ 119 - $ 138
PROFESSION AL I $108 $ 97 - $ 120
CONSTRUCTION PROFESSIONAL VII $325 $ 305 - $ 345
CONSTRUCTION PROFESSIONAL VI $285 $ 266 - $ 305
CONSTRUCTION PROFESSIONAL V $251 $ 231 - $ 271
CONSTRUCTION PROFESSIONAL IV $216 $ 200 - $ 234
CONSTRUCTION PROFESSIONAL III $197 $ 184 - $ 210
CONSTRUCTION PROFESSIONAL II $162 $ 139 - $ 186
CONSTRUCTION PROFESSIONAL I $138 $ 127 - $ 149
INSPECTOR VII ** $236 $ 223 - $ 250
INSPECTOR VI ** $207 $ 188 - $ 226
INSPECTOR V ** $177 $ 166 - $ 189
INSPECTOR IV ** $162 $ 152 - $ 173
INSPECTOR III ** $143 $ 132 - $ 154
INSPECTOR II ** $118 $ 104 - $ 133
INSPECTOR I ** $93 $ 81 - $ 107
ADMIN PROFESSI ON AL V $173 $ 161 - $ 185
ADMIN PROFESSI ON AL IV $158 $ 146 - $ 170
ADMIN PROFESSIONAL III $123 $ 106 - $ 141
ADMIN ASSISTANT II $99 $ 86 - $ 112
ADMIN ASSISTANT I $84 $ 74 - $ 94
GEOGRAPHER/GI S IX $291 $ 278 - $ 305
GEOGRAPHER/GIS VIII $252 $ 225 - $ 278
GEOGRAPHER/GIS VII $217 $ 206 - $ 229
GEOGRAPHER/GIS VI $192 $ 177 - $ 208
GEOGRAPHER/GIS V $173 $ 164 - $ 182
GEOGRAPHER/GIS IV $153 $ 142 - $ 164
GEOGRAPHER/GIS III $128 $ 113 - $ 144
GEOGRAPHER/GIS II $113 $ 104 - $ 123
GEOGRAPHER/GIS I $99 $ 92 - $ 106
ARCHITECT IX $252 $ 240 - $ 264
ARCHITECT VIII $227 $ 214 - $ 240
ARCHITECT VII $207 $ 198 - $ 217
ARCHITECT VI $187 $ 179 - $ 197
ARCHITECT V $168 $ 154 - $ 182
ARCHITECT IV $148 $ 141 - $ 156
ARCHITECT III $133 $ 123 - $ 144
ARCHITECT II $118 $ 111 - $ 126
ARCHITECT I $103 $ 94 - $ 112

EXHIBIT “C”

INSURANCE

INSURANCE REQUIREMENTS
Provider shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Provider, his/her agents, representatives, or employees. If the Provider maintains broader coverage and/or higher limits than the minimums shown above, the City requires and shall be entitled to the broader coverage and/or higher limits maintained by the Provider.

A. Minimum Scope of Insurance
Coverage shall be at least as broad as:

1. Insurance Services Office Commercial General Liability coverage (occurrence form CG 0001), including products and completed operations, property damage, bodily injury and personal & advertising injury.

2. Insurance Services Office Business Auto Coverage Form Number CA 00 01 covering any auto (Code 1), or if Provider has no owned autos, covering hired (Code 8) and non-owned autos (Code 9).

3. Workers' Compensation insurance as required by the State of California and Employer's Liability Insurance.

4. Errors and Omissions liability insurance appropriate to the Provider's profession. Architects' and engineers' coverage is to be endorsed to include contractual liability.

5. Cyber Liability Insurance, Coverage shall be sufficiently broad to respond to the duties and obligations as is undertaken by Vendor in this agreement and shall include, but not be limited to, claims involving infringement of intellectual property, including but not limited to infringement o f copyright, trademark, trade dress, invasion of privacy violations, information theft, damage to or destruction of electronic information, release of private information, alteration of electronic information, extortion and network security. The policy shall provide coverage for breach response costs as well as regulatory fines and penalties as well as credit EXHIBIT “C”
Atty. Rev. 2021

monitoring expenses with limits sufficient to respond to these obligations.

B. Minimum Limits of Insurance
Provider shall maintain limits no less than:

1. General Liability - $2,000,000 per occurrence for bodily injury, personal injury and property damage. If Commercial General Liability Insurance or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to this project/location (ISO CG 25 03 or 25 04) or the general aggregate limit shall be twice the required occurrence limit.

2. Automobile Liability - $1,000,000 per accident for bodily injury and property damage.

3. Workers’ Compensation: Statutory limits.

4. Employer's Liability - $1,000,000 per accident for bodily injury or disease.

5. Errors and Omissions Liability - $1,000,000 per occurrence or claim, $2,000,000 aggregate.

6. Cyber Liability- $2,000,000 per occurrence or claim, $2,000,000 aggregate.

C. Self-insured Retentions
Self-insured retentions must be declared to and approved by the City.

The City may require the Provider to purchase coverage with a lower retention or provide proof of ability to pay losses and related investigations, claim administration and defense expenses within the retention.

D. Other Insurance Provisions
The commercial general liability and automobile liability policies are to contain, or be endorsed to contain, the following provisions:

1. The City, its officers, officials, employees and volunteers are to be covered as additional insureds on the CGL policy with respect to liability arising out of work or operations performed by or on behalf of the Provider including materials, parts or EXHIBIT “C”
Atty. Rev. 2021

equipment furnished in connection with such work or
operations. General liability coverage can be provided in the form or an endorsement to the Provider’s insurance (at least as broad as ISO Form CG 20 10 11 85 or both CG 20 10, CG 20 26, CG 20 33, or CG 20 38 and CG 20 37 forms if later revisions are used).

2. For any claims related to this project, the Provider's insurance coverage shall be primary insurance coverage at least as broad as ISO CG 20 01 04 13 as respects the City, its officers, officials, employees and volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees or volunteers shall be excess of the Provider's insurance and shall not contribute with it.

3. Each insurance policy required by this clause shall be endorsed to state that coverage shall not be canceled or reduced, except with notice stating the title of this contract to the City. All notices provided pursuant to this Agreement shall be given to the City representative listed for notice in this agreement and shall specify the title of this Agreement. Notice may be given by overnight mail, facsimile with confirmation of receipt, or certified mail with return-receipt requested.

4. Provider hereby grants to City a waiver of any right to subrogation which any insurer of said Provider may acquire against the City by virtue of the payment of any loss under such insurance. Provider agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation, but this provision applies regardless of whether or not the City has received a waiver of subrogation endorsement from the insurer.

5. If any of the required policies provide claims-made coverage:
a. The Retroactive Date must be shown, and must be
before the date of the contract or the beginning of contract work. b. Insurance must be maintained and evidence of
insurance must be provided for at least five (5) years after completion of the contract of work.
c. If coverage is canceled or non-renewed, and not
replaced with another claims-made policy form with a
Retroactive Date prior to the contract effective date, the Provider must purchase “extended reporting” coverage for a minimum of five (5) years after completion of work.

E. Acceptability of Insurers
EXHIBIT “C”
Atty. Rev. 2021

Insurance is to be placed with insurers with a current A.M. Best's rating of no less than A:VII, unless otherwise acceptable to the City.

F. Verification of Coverage
Provider shall furnish the City with original certificates and amendatory endorsements of the applicable policy language effecting coverage required by this clause. All certificates and endorsements are to be received and approved by the City before work commences. However, failure to obtain the required documents prior to the work beginning shall not waive the Provider’s obligation to provide them. The City reserves the right to require complete, certified copies of all required insurance policies, including endorsements effecting the coverage required by these specifications at any time.

G. Special Risks or Circumstances
The City reserves the right to modify these requirements, including limits, based on the nature of the risk,
coverage, or other special circumstances.
prior experience, insurer,
EXHIBIT “C”
Atty. Rev. 2021

← All documents from this meeting