City of Santa Maria
Bid Results for Project FIRE ADMINSTRATION BUILDING RE‐ROOFING PROJECT (2023‐20) Issued on 11/22/2023
Bid Due on February 15, 2024 2:00 PM (PST)
BID SCHEDULE
Item Num Item Code Description Quantity Unit of Measure Unit Price Line Total Unit Price Line Total Unit Price Line Total 1 C1 Mobilization and Demobilization 1L S $3,000.00 $3,000.00 $15,000.00 $15,000.00 $7,000.00 $7,000.00 2 C2 Removal and Disposal of Existing (E) Asbestos Shingle Roof 1L S $58,430.00 $58,430.00 $77,974.00 $77,974.00 $58,430.00 $58,430.00 3 C3 Installation of New Shingle Roof System (appox. 56 sq.) 1L S $146,220.00 $146,220.00 $156,121.00 $156,121.00 $201,708.00 $201,708.00 4C 4 R e ‐Install Roof Gutters and Downspouts 1L S $5,000.00 $5,000.00 $7,035.00 $7,035.00 $2,730.00 $2,730.00 5 C5 Replacement of Deteriorated (E) Roof Decking (Allowance) 100 SF $3.50 $350.00 $12.00 $1,200.00 $8.00 $800.00 6 C6 Replacement of Deteriorated (E) Fascia Boards (Allowance) 100 LF $50.00 $5,000.00 $20.00 $2,000.00 $12.00 $1,200.00 7 C7 Refurbish (E) Roof Vents and Flue Stacks 1L S $0.00 $0.00 $5,000.00 $5,000.00 $1,250.00 $1,250.00 Total $218,000.00 $264,330.00 $273,118.00
GN Roofing Chapman Coast Roof Co., Inc. BEST CONTRACTING SERVICES, INC.
Attachment A