City of Santa Maria
Bid Results for Project CELL 1 PHASE II LINER EXTENSION PROJECT (2024‐03) Issued on 04/15/2024
Bid Due on May 21, 2024  2:00 PM (PDT)
GENERAL CONDITIONS ‐ BID SCHEDULE ITEMS A, B, & C
Item Code Description Unit of
Measure Quantity Unit  Price Total Unit  Price Total Unit  Price Total A1 MOBILIZATION  AND BONDING LS 1 $360,000.00 $360,000.00 $845,890.00 $845,890.00 $1,500,000.00 $1,500,000.00 A2 BONDING  AND INSURANCE LS 1 $150,000.00 $150,000.00 $172,000.00 $172,000.00 $150,000.00 $150,000.00 B1 TEMPORARY  FIELD FACILITY FOR CQA AND CM PERSONNEL LS 1 $25,000.00 $25,000.00 $46,903.00 $46,903.00 $50,000.00 $50,000.00 B2 CONSTRUCTION SUPPORT TASKS ‐ SWPPP COMPLIANCE WITH CGP AND IGP ‐ CONSTRUCTION ACTIVITIES STORMWATER MANAGEMENT PLAN (CASMP) ‐ INTERIM EROSION CONTROL AND BMP'S LS 1 $85,000.00 $85,000.00 $157,544.00 $157,544.00 $150,000.00 $150,000.00 B3 SANTA  MARIA RIVER MINING PERMIT AND SUPPORT LS 1 $80,000.00 $80,000.00 $28,962.00 $28,962.00 $50,000.00 $50,000.00 C1 SUBMITTALS  AND PROGRESS SCHEDULE LS 1 $105,000.00 $105,000.00 $70,413.00 $70,413.00 $30,000.00 $30,000.00 Subtotal: $805,000.00 Subtotal: $1,321,712.00 Subtotal: $1,930,000.00 CLEAR, GRUB, AND DEMOLITION ‐ BID SCHEDULE ITEMS D
Item Code Description Unit of
Measure Quantity Unit  Price Total Unit  Price Total Unit  Price Total D1 CLEARING,  GRUBBING, DEMOLITION AND SALVAGE AC 50 $2,400.00 $120,000.00 $3,947.00 $197,350.00 $3,500.00 $175,000.00 D2 REMOVAL AND SALVAGE UPPER 8" OF BASE PAD MATERIAL,  STOCKPILED, AND REINSTALLED @ 90% RELATIVE COMPACTION TO GRADES PER PLAN SF 69000 $1.00 $69,000.00 $0.32 $22,080.00 $1.00 $69,000.00 D3 REFUSE REMOVAL TO EFFECTUATE THE EXISTING CELL 1 LINER JOIN OR FOR LFG PIPING, TRANSPORT TO, AND DISPOSAL AT WORKING FACE CY 10000 $7.25 $72,500.00 $15.35 $153,500.00 $9.50 $95,000.00 Subtotal: $261,500.00 Subtotal: $372,930.00 Subtotal: $339,000.00 Raminha Construction, Inc. Wood  Bros Inc. Sukut  Construction, LLC Raminha Construction, Inc. Wood  Bros Inc. Sukut  Construction, LLC Attachment A
EARTHWORK ‐ BID SCHEDULE ITEMS E
Item Code Description Unit of
Measure Quantity Unit  Price Total Unit  Price Total Unit  Price Total E1 NHIS  FINAL COVER EXCAVATION/REMOVAL TO TOP DECK STOCKPILE CY 30000 $4.80 $144,000.00 $3.46 $103,800.00 $3.75 $112,500.00 E2 NHIS  EXCAVATION TO NHIS FILL TO CONTOURS PER PLAN CY 45000 $3.60 $162,000.00 $7.13 $320,850.00 $4.45 $200,250.00 E3 NHIS  EXCAVATION TO NHIS DAILY COVER STOCKPILE CY 15000 $3.60 $54,000.00 $3.83 $57,450.00 $3.50 $52,500.00 E4 NHIS  EXCAVATION TO NHIS STOCKPILE 1 CY 215000 $6.40 $1,376,000.00 $3.47 $746,050.00 $4.25 $913,750.00 E5 UNCLASSIFIED  EXCAVATION TO ENGINEERED FILL TO CONTOURS PER PLAN CY 50000 $8.00 $400,000.00 $7.36 $368,000.00 $10.00 $500,000.00 E6 UNCLASSIFIED  EXCAVATION TO NHIS CLOSURE TOP DECK REGRADING FILL TO CONTOURS PER PLAN CY 85000 $8.00 $680,000.00 $7.30 $620,500.00 $12.45 $1,058,250.00 E7 EXTRA PROCESSING FOR NHIS FINAL SLOPE ‐ SCREENED FILL MATERIAL PLACEMENT WITHIN 12‐INCHES OF GEOSYNTHETIC MATERIALS (NHIS SLOPE AREAS) ‐ DELETABLE CY 5000 $6.00 $30,000.00 $12.65 $63,250.00 $7.35 $36,750.00 E8 REMOVAL  OF OVERSIZE MATERIAL IN EXCESS OF 10‐PERCENT (BY VOLUME) FROM UNCLASSIFIED FILL CY 5500 $5.00 $27,500.00 $12.70 $69,850.00 $3.60 $19,800.00 E9 SUBGRADE  PREPARATION / VENEER FILL SF 715000 $0.20 $143,000.00 $0.54 $386,100.00 $0.32 $228,800.00 E10 FINAL CLOSURE SOIL ‐ SLOPE AND DECK (PER DETAILS 1/D5 AND 2/D5) ‐ INCLUDES ADDITONAL 10% VOLUME CY 21200 $18.00 $381,600.00 $15.04 $318,848.00 $8.50 $180,200.00 E11 FINAL  COVER SLOPE TRANSITION (PER DETAIL 5/D5) CY 1050 $15.00 $15,750.00 $33.30 $34,965.00 $19.20 $20,160.00 E12 TOP  DECK BERM OR BENCH BERM (PER DETAIL 3/D5) LF 4100 $6.00 $24,600.00 $5.31 $21,771.00 $4.25 $17,425.00 Subtotal: $3,438,450.00 Subtotal: $3,111,434.00 Subtotal: $3,340,385.00 Raminha Construction, Inc. Wood  Bros Inc. Sukut  Construction, LLC LEACHATE COLLECTION AND REMOVAL SYSTEM (LCRS) ‐ BID SCHEDULE ITEMS F Item Code Description Unit of
Measure Quantity Unit  Price Total Unit  Price Total Unit  Price Total F1 6 ‐INCH LCRS SLOTTED HEADER/LATERAL (PER DETAIL 5/D2) LF 3250 $17.00 $55,250.00 $24.30 $78,975.00 $14.60 $47,450.00 F2 6 ‐INCH LCRS SOLID SLOPE RISER (PER DETAIL 6/D2) LF 120 $42.00 $5,040.00 $50.80 $6,096.00 $35.90 $4,308.00 F3 6 ‐INCH LCRS PIPE JUNCTION (PER DETAIL 4/D2) EA 6 $850.00 $5,100.00 $1,066.00 $6,396.00 $767.00 $4,602.00 F4 6 ‐INCH SLOTTED AND SOLID SUMP FLUSH PIPE (PER DETAIL 2/D4) LF 140 $44.00 $6,160.00 $44.20 $6,188.00 $20.00 $2,800.00 F5 3 ‐INCH SDR‐17 SOLID HDPE INSIDE 6‐INCH SDR‐17 SOLID HDPE LCRS OUTFALL PIPE LF 650 $42.00 $27,300.00 $47.50 $30,875.00 $38.00 $24,700.00 F6 10 ‐INCH SOLID LCRS SUMP COLLECTION PIPE (PER DETAIL 2/D4) LF 120 $77.00 $9,240.00 $61.20 $7,344.00 $48.00 $5,760.00 F7 4 ‐INCH LFG SLOTTED EVACUATION PIPE (PER DETAIL 5/D2) LF 1600 $17.00 $27,200.00 $12.16 $19,456.00 $11.00 $17,600.00 F8 4 ‐INCH LFG SOLID SLOPE RISER (PER DETAIL 6/D2) LF 300 $17.00 $5,100.00 $19.30 $5,790.00 $12.70 $3,810.00 F9 LFG  SLOPE RISER TERMINATION (PER DETAIL 7/D2) EA 3 $3,000.00 $9,000.00 $1,686.00 $5,058.00 $1,040.00 $3,120.00 F10 LCRS  SLOPE RISER TERMINATION/SUPPORT (PER DETAIL 7/D2) EA 3 $4,000.00 $12,000.00 $4,506.00 $13,518.00 $4,025.00 $12,075.00 F11 18 ‐INCH LYSIMETER SUMP RISER PIPE WITH CONTROLLED LOW STRENGTH MATERIAL  (PER DETAIL 1/D4) LF 90 $240.00 $21,600.00 $136.00 $12,240.00 $211.00 $18,990.00 F12 18 ‐INCH LCRS SUMP RISER PIPE WITH CONTROLLED LOW STRENGTH MATERIAL  (PER DETAIL 2/D4) LF 140 $250.00 $35,000.00 $86.80 $12,152.00 $268.00 $37,520.00 F13 6 ‐INCH SDR‐17 SOLID LCRS CUT‐OFF JUNCTION WITH PIPE PIG (DETAILS 2/D6 AND 3/D6) EA 3 $4,200.00 $12,600.00 $1,840.00 $5,520.00 $1,160.00 $3,480.00 F14 6 ‐INCH SDR‐17 SLOTTED LCRS CUT‐OFF PIPE (DETAIL 1/D6) LF 20 $65.00 $1,300.00 $282.40 $5,648.00 $40.00 $800.00 F15 6 ‐INCH SDR‐17 SOLID LCRS CUT‐OFF RISER LF 340 $35.00 $11,900.00 $21.40 $7,276.00 $12.75 $4,335.00 F16 3 ‐INCH LCRS OUTFALL BUTTERFLY VALVE EA 2 $2,100.00 $4,200.00 $3,571.00 $7,142.00 $1,995.00 $3,990.00 F17 LCRS  GRAVEL ‐ BASE LINER (PER DETAIL 1/D1) SF 575000 $2.50 $1,437,500.00 $4.39 $2,524,250.00 $3.20 $1,840,000.00 F18 LYSIMETER  AND LCRS SUMP GRAVEL (PER DETAILS 1/D4 AND 2/D4) SF 3500 $30.00 $105,000.00 $43.79 $153,265.00 $22.50 $78,750.00 F19 WRAPPED  GRAVEL (PER DETAIL 8/D2) LF 20 $230.00 $4,600.00 $226.90 $4,538.00 $67.25 $1,345.00 F20 LCRS SUMP PUMP, PIPING, OUTFALL PIPE CONNECTION, CONTROL PANEL, AND POWER TO CONTROL PANEL (PER DETAILS 2/D4 AND 6/D8) WITH ELECRTICAL ENGINEER'S PLAN LS 1 $65,000.00 $65,000.00 $28,668.00 $28,668.00 $44,150.00 $44,150.00 F21 LCRS  CONTAINMENT STORAGE FACILITY EXPANSION (PER DETAIL 1/D9) LS 1 $625,000.00 $625,000.00 $434,080.00 $434,080.00 $369,000.00 $369,000.00 F22 LCRS CONTAINMENT STORAGE FACILITY NEW COMPONENT PIPING UPGRADE TO HDPE MATERIAL ‐ (DELETABLE) LS 1 $20,000.00 $20,000.00 $87,456.00 $87,456.00 $1,150.00 $1,150.00 F23 LCRS CONTAINMENT STORAGE FACILITY COMPONENT PVC TO HDPE MATERIAL REPLACEMENTS ‐ (DELETABLE) LS 1 $20,000.00 $20,000.00 $87,456.00 $87,456.00 $38,000.00 $38,000.00 Subtotal: $2,525,090.00 Subtotal: $3,549,387.00 Subtotal: $2,567,735.00 Raminha Construction, Inc. Wood  Bros Inc. Sukut  Construction, LLC GEOSYNTHETICS / GROUNDWATER PROTECTION SYSTEM ‐ BID SCHEDULE ITEMS G, H, I, J, P, & K Item Code Description Unit of
Measure Quantity Unit  Price Total Unit  Price Total Unit  Price Total G1 LFG  COLLECTION GEOCOMPOSITE ‐ BASE LINER (PER DETAIL 1/D1) SF 575000 $1.00 $575,000.00 $1.05 $603,750.00 $0.95 $546,250.00 G2 DRAINAGE  GEOCOMPOSITE ‐ FINAL CLOSURE SLOPE (PER DETAIL 4/D5) SF 110000 $1.00 $110,000.00 $1.05 $115,500.00 $1.04 $114,400.00 H1 8  OUNCE GEOTEXTILE ‐ BASE LINER (PER DETAIL 1/D1) SF 575000 $0.40 $230,000.00 $0.39 $224,250.00 $0.26 $149,500.00 H2 12  OUNCE GEOTEXTILE ‐ BASE LINER (PER DETAIL 1/D1) SF 575000 $0.50 $287,500.00 $0.45 $258,750.00 $0.37 $212,750.00 H3 16  OUNCE GEOTEXTILE ‐ SLOPE LINER (PER DETAIL 2/D1) SF 160000 $0.60 $96,000.00 $0.56 $89,600.00 $0.51 $81,600.00 I1 20 ‐MIL GEOMEMBRANE ‐ NHIS STOCKPILE 1 BASE LINER (PER DETAIL 4/D6) SF 255000 $0.60 $153,000.00 $0.61 $155,550.00 $0.62 $158,100.00 I2 60 ‐MIL GEOMEMBRANE ‐ BASE LINER (PER DETAIL 1/D1) SF 575000 $0.75 $431,250.00 $0.73 $419,750.00 $0.75 $431,250.00 I3 60 ‐MIL GEOMEMBRANE ‐ SLOPE LINER (PER DETAIL 2/D1) SF 160000 $0.75 $120,000.00 $1.02 $163,200.00 $0.81 $129,600.00 I4 80 ‐MIL GEOMEMBRANE ‐ BASE LINER (PER DETAIL 1/D1) SF 575000 $0.90 $517,500.00 $0.87 $500,250.00 $0.88 $506,000.00 I5 80 ‐MIL GEOMEMBRANE ‐ SLOPE LINER (PER DETAIL 2/D1) SF 160000 $0.90 $144,000.00 $0.87 $139,200.00 $0.98 $156,800.00 I6 80‐MIL GEOMEMBRANE ‐ CUT OFF LINER FLAP AND ANCHOR TRENCH (PER DETAILS 1/D6, 2/D6, AND 3/D6) SF 25000 $1.35 $33,750.00 $1.29 $32,250.00 $1.54 $38,500.00 I7 SLOPE  TO BASE LINER TRANSITION (PER DETAIL 3/D1) LF 2850 $23.00 $65,550.00 $21.50 $61,275.00 $41.78 $119,073.00 I8 CELL  1 PHASE II LINER TO CELL 1 EXTENSION LINER JOIN (PER DETAILS 4/D1 AND 6/D1) LF 800 $44.00 $35,200.00 $21.50 $17,200.00 $60.20 $48,160.00 I9 SLOPE  LINER JOIN (PER DETAIL 7/D1) LF 70 $63.00 $4,410.00 $21.50 $1,505.00 $56.00 $3,920.00 I10 NORTHERN  TOP BENCH ANCHOR TRENCH (PER DETAIL 5/D1 ) LF 1150 $43.00 $49,450.00 $14.10 $16,215.00 $37.00 $42,550.00 I11 WESTERN  TOP BENCH ANCHOR TRENCH (PER DETAIL 1/D5 ) LF 550 $40.00 $22,000.00 $19.40 $10,670.00 $37.00 $20,350.00 I12 SOUTHERN  TOP BENCH ANCHOR TRENCH (PER DETAIL 2/D5 ) LF 1100 $95.00 $104,500.00 $14.79 $16,269.00 $52.72 $57,992.00 I13 NHIS  STOCKPILE 1 PERIMETER ANCHOR TRENCH (PER DETAIL 4/D6) LF 2050 $17.00 $34,850.00 $38.60 $79,130.00 $37.90 $77,695.00 J1 GEOSYNTHETIC  CLAY LINER ‐ BASE LINER (PER DETAIL 1/D1) SF 575000 $1.15 $661,250.00 $1.15 $661,250.00 $1.06 $609,500.00 J2 GEOSYNTHETIC  CLAY LINER ‐ SLOPE LINER (PER DETAIL 2/D1) SF 160000 $1.15 $184,000.00 $1.16 $185,600.00 $1.21 $193,600.00 J3 GEOSYNTHETIC  CLAY LINER ‐ FINAL CLOSURE DECK AND SLOPE (PER DETAILS 1/D5 AND 4/D5) SF 120000 $1.15 $138,000.00 $1.15 $138,000.00 $1.21 $145,200.00 P1 PROTECTIVE  PLASTIC COVER AND HDPE GEOTEXTILE BALLAST SYSTEM (WIND DEFENDER) SF 305000 $1.10 $335,500.00 $1.22 $372,100.00 $0.87 $265,350.00 K1 PROTECTIVE  COVER SOIL ‐ BASE LINER (PER DETAIL 1/D1) SF 575000 $1.15 $661,250.00 $0.81 $465,750.00 $1.54 $885,500.00 K2 PROTECTIVE  COVER SOIL ‐ SLOPE AND BENCH LINER (PER DETAIL 2/D1) SF 195000 $1.50 $292,500.00 $0.80 $156,000.00 $1.40 $273,000.00 K3 PROTECTIVE  COVER SOIL ‐ CUT OFF BERM WITH ORANGE SAFETY FENCE (PER DETAIL 2/D1) CY 4500 $22.00 $99,000.00 $11.10 $49,950.00 $18.85 $84,825.00 Subtotal: $5,385,460.00 Subtotal: $4,932,964.00 Subtotal: $5,351,465.00 Raminha Construction, Inc. Wood  Bros Inc. Sukut  Construction, LLC LANDFILL GAS SYSTEM ‐ BID SCHEDULE ITEMS L
Item Code Description Unit of
Measure Quantity Unit  Price Total Unit  Price Total Unit  Price Total L1 INSTALLATION  OF NEW LFG TEMPORARY HEADER PIPE (AS NEEDED) LS 1 $115,000.00 $115,000.00 $25,587.00 $25,587.00 $175,000.00 $175,000.00 L2 LFG  WELL ADJUSTMENTS (RAISE OR LOWER) TO FINAL GRADE (PER DETAIL 6/D7) EA 15 $1,350.00 $20,250.00 $1,977.00 $29,655.00 $1,400.00 $21,000.00 L3 EXTEND LFG WELLHEAD ASSEMBLY ABOVE FINAL COVER GRADE AND JOIN TO HEADER/LATERAL (PER DETAIL 1/D7) EA 15 $1,350.00 $20,250.00 $2,060.00 $30,900.00 $975.00 $14,625.00 L4 REINSTALL LFG WELLHEAD AS REMOTE WELLHEAD RISER AND JOIN TO HEADER/LATERAL  (PER DETAIL 5/D7) EA 13 $3,200.00 $41,600.00 $3,629.00 $47,177.00 $2,800.00 $36,400.00 L5 INSTALL  NEW IN‐LINE LFG REMOTE WELLHEAD AND JOIN TO HEADER/LATERAL (PER DETAIL 5/D7) EA 6 $2,800.00 $16,800.00 $13,325.00 $79,950.00 $3,125.00 $18,750.00 L6 INSTALL  SALVAGED LFG 6‐INCH SOLID HDPE LATERAL ABOVE GRADE (PER DETAIL 2/D7) LF 3000 $20.00 $60,000.00 $7.80 $23,400.00 $13.50 $40,500.00 L7 INSTALL  SALVAGED LFG 6‐INCH SOLID HDPE LATERAL BELOW GRADE (PER DETAIL 2/D8) LF 3800 $30.00 $114,000.00 $20.44 $77,672.00 $19.75 $75,050.00 L8 INSTALL  SALVAGED LFG 18‐INCH SOLID HDPE HEADER ABOVE GRADE (PER DETAIL 2/D7) LF 2600 $40.00 $104,000.00 $11.07 $28,782.00 $44.00 $114,400.00 L9 INSTALL  SALVAGED LFG 18‐INCH SOLID HDPE HEADER BELOW GRADE (PER DETAIL 2/D8) LF 100 $105.00 $10,500.00 $90.66 $9,066.00 $34.00 $3,400.00 L10 INSTALL NEW LFG 6‐INCH SOLID HDPE LATERAL ABOVE GRADE (PER DETAIL 2/D7) ‐ COST OF MATERIAL ONLY (DELETABLE) LF 750 $26.00 $19,500.00 $7.80 $5,850.00 $6.00 $4,500.00 L11 INSTALL  NEW LFG 8‐INCH SOLID HDPE HEADER HEADER ABOVE GRADE (PER DETAIL 2/D7) LF 1700 $32.00 $54,400.00 $31.01 $52,717.00 $27.00 $45,900.00 L12 INSTALL  NEW LFG 12‐INCH SOLID HDPE HEADER ABOVE GRADE (PER DETAIL 2/D7) LF 2600 $58.00 $150,800.00 $40.16 $104,416.00 $46.00 $119,600.00 L13 INSTALL  NEW LFG 12‐INCH SOLID HDPE HEADER BELOW GRADE (PER DETAIL 2/D8) LF 150 $98.00 $14,700.00 $87.90 $13,185.00 $49.50 $7,425.00 L14 INSTALL  NEW LFG 18‐INCH SOLID HDPE HEADER ABOVE GRADE (PER DETAIL 2/D7) LF 750 $96.00 $72,000.00 $37.60 $28,200.00 $89.50 $67,125.00 L15 INSTALL  NEW 6‐INCH LFG HEADER BUTTERFLY VALVE EA 2 $2,800.00 $5,600.00 $3,435.00 $6,870.00 $2,000.00 $4,000.00 L16 INSTALL  NEW 8‐INCH LFG HEADER BUTTERFLY VALVE EA 2 $3,500.00 $7,000.00 $3,879.00 $7,758.00 $2,450.00 $4,900.00 L17 INSTALL  NEW 12‐INCH LFG HEADER BUTTERFLY VALVE EA 8 $4,900.00 $39,200.00 $4,464.00 $35,712.00 $4,750.00 $38,000.00 L18 INSTALL  NEW 18‐INCH LFG HEADER BUTTERFLY VALVE EA 2 $12,000.00 $24,000.00 $10,785.00 $21,570.00 $10,750.00 $21,500.00 L19 INSTALL  NEW LFG 6‐INCH SLOTTED HDPE GEOCOMPOSITE COLLECTOR PIPE/TRENCH (PER DETAIL 4/D8) LF 3300 $40.00 $132,000.00 $51.59 $170,247.00 $36.00 $118,800.00 L20 INSTALL  NEW LFG 6‐INCH SOLID HDPE GEOCOMPOSITE RISER PIPE BELOW GRADE (PER DETAIL 5/D8) LF 800 $55.00 $44,000.00 $44.87 $35,896.00 $31.75 $25,400.00 L21 INSTALL  NEW LFG GEOCOMPOSITE COLLECTION WELLHEAD AND JOIN TO HEADER (PER DETAIL 5/D8) EA 4 $2,500.00 $10,000.00 $3,179.00 $12,716.00 $1,550.00 $6,200.00 L22 INSTALL LANDFILL GAS CONDENSATE SUMP WITH AIR SUPPLY AND CONDENSATE RETURN LINES (PER DETAIL 1/D8) EA 1 $42,000.00 $42,000.00 $29,004.00 $29,004.00 $50,500.00 $50,500.00 Subtotal: $1,117,600.00 Subtotal: $876,330.00 Subtotal: $1,012,975.00 Raminha Construction, Inc. Wood  Bros Inc. Sukut  Construction, LLC MISCELLANEOUS CIVIL IMPROVEMENTS ‐ BID SCHEDULE ITEMS M Item Code Description Unit of
Measure Quantity Unit  Price Total Unit  Price Total Unit  Price Total M1 INSTALL 6‐INCHES OF CRUSHED MISCELLANEOUS BASE (CMB) OVER 8 0Z/SY GEOTEXTILE (PER DETAIL 3/D2) SF 65000 $0.50 $32,500.00 $1.71 $111,150.00 $2.40 $156,000.00 M2 INSTALL  12‐INCHES OF CRUSHED MISCELLANEOUS BASE (CMB) ACCESS ROAD (PER DETAIL 2/D2) SF 11000 $1.00 $11,000.00 $3.44 $37,840.00 $1.78 $19,580.00 M3 CONSTRUCT  CONCRETE TRAPEZOIDAL CHANNEL ‐ B=50", D=2.0', Z=1 (PER DETAIL 3/D3) LF 1000 $200.00 $200,000.00 $184.90 $184,900.00 $209.00 $209,000.00 M4 CONSTRUCT  DRIVEABLE CONCRETE CHANNEL CROSSING ‐ B=50", D=1.0', Z=5 (PER DETAIL 3/D3) LF 65 $275.00 $17,875.00 $257.00 $16,705.00 $287.00 $18,655.00 M5 CONSTRUCT  CONCRETE CUT‐OFF WALL (PER DETAIL 6/D3) LF 40 $110.00 $4,400.00 $103.40 $4,136.00 $99.00 $3,960.00 M6 CONSTRUCT  SPLASH WALL (PER DETAIL 4/D3 ) LF 40 $94.00 $3,760.00 $86.20 $3,448.00 $66.00 $2,640.00 M7 CONSTRUCT  DRIVEABLE CONCRETE TRANSITION TO TRAPEZOIDAL CHANNEL (PER DETAIL 7/D6) SF 65 $21.00 $1,365.00 $20.00 $1,300.00 $755.00 $49,075.00 M8 RECONSTRUCT  HDPE FLARED INLET TO DOWN DRAIN (PER DETAIL 2/D3) EA 5 $2,800.00 $14,000.00 $2,041.00 $10,205.00 $1,275.00 $6,375.00 M9 INSTALL  18‐INCH HDPE CORRUGATED SMOOTH INTERIOR WALL PIPE (PER DETAILS 1/D3 AND 3/13 ) LF 120 $125.00 $15,000.00 $162.90 $19,548.00 $165.00 $19,800.00 M10 INSTALL CORRUGATED METAL PIPE (CMP) FOR THE LFG ROAD CROSSING ENCASEMENT (PER DETAIL 4/D7) SIZED PER PLAN LF 140 $110.00 $15,400.00 $106.30 $14,882.00 $112.00 $15,680.00 M11 INSTALL  STEEL CHANNEL BRIDGE CROSSING (PER DETAIL 6/D6) EA 1 $13,000.00 $13,000.00 $47,216.00 $47,216.00 $29,000.00 $29,000.00 M12 CONSTRUCT  LANDFILL GAS PIPE CHANNEL CROSSING (PER DETAIL 8/D6) EA 1 $4,000.00 $4,000.00 $22,146.00 $22,146.00 $17,100.00 $17,100.00 M13 ADJUST CONTACT WATER DISCHARGE PIPES TO PROPOSED FINISHED GRADE AND DRAIN AT 1‐PERCENT MINIMUM LF 4500 $5.00 $22,500.00 $17.42 $78,390.00 $10.25 $46,125.00 Subtotal: $354,800.00 Subtotal: $551,866.00 Subtotal: $592,990.00 Raminha Construction, Inc. Wood  Bros Inc. Sukut  Construction, LLC FINAL EROSION CONTROL ‐ BID SCHEDULE ITEMS N
Item Code Description Unit of
Measure Quantity Unit  Price Total Unit  Price Total Unit  Price Total N1 HYDROSEEDING  DECK AND SLOPE AC 30 $5,800.00 $174,000.00 $6,397.00 $191,910.00 $6,600.00 $198,000.00 N2 FIBER  ROLLS (PER DETAILS 2/EC1 AND 3/EC1) LF 18000 $4.00 $72,000.00 $3.41 $61,380.00 $3.50 $63,000.00 N3 INSTALL  GRAVEL BAG CHEVRON (PER DETAIL 1/EC1) EA 22 $350.00 $7,700.00 $296.00 $6,512.00 $305.00 $6,710.00 N4 INSTALLATION  OF 2 TO 3 INCH THICK MULCH ON SLOPES AND DECK AC 27 $17,000.00 $459,000.00 $13,653.00 $368,631.00 $14,000.00 $378,000.00 Subtotal: $712,700.00 Subtotal: $628,433.00 Subtotal: $645,710.00 SURVEYING ‐ BID SCHEDULE ITEMS O
Item Code Description Unit of
Measure Quantity Unit  Price Total Unit  Price Total Unit  Price Total O1 CONSTRUCTION  AND ASBUILT SURVEYING LS 1 $150,000.00 $150,000.00 $105,404.00 $105,404.00 $108,000.00 $108,000.00 Q1 ALLOCATION  FOR SUPPLEMENTAL SUPPORT (DELETABLE ITEM) T&M 1 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 Q2 ALLOCATION  FOR UNSUITABLE MATERIAL REMOVAL WITHIN THE NHIS AREA (DELETABLE ITEM) T&M 1 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 $25,000.00 Q3 ALLOCATION  FOR DIESEL FUEL PRICE ADJUSTMENT (DELETABLE ITEM) T&M 1 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 Q4 ALLOCATION  FOR GEOSYNTHETICS AND HDPE PIPE RESIN PRICE ADJUSTMENT (DELETABLE ITEM) T&M 1 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 Subtotal: $225,000.00 Subtotal: $225,000.00 Subtotal: $225,000.00 Total: $14,975,600.00 Total: $15,675,460.00 Total: $16,113,260.00 Raminha Construction, Inc. Wood  Bros Inc. Sukut  Construction, LLC Raminha Construction, Inc. Wood  Bros Inc. Sukut  Construction, LLC