City of Santa Maria and Vernon Construction Group – Sales and Disposition Agreement Summary of Terms
Property Project Description Timing (subject to
meeting milestones)
City Concessions
(subject to meeting
milestones)
Lot 3 – Alvin
Newton
 82 apartments
 Ground floor
commercial, with
minimum 4,500 sq. ft.
for dining/food
establishments
 Firefighters’ memorial
plaza
 Planning entitlements
approved 10/3/23
 Submit building plans
by 7/25/24
 Approval of building
plans by 01/25/25
 Complete
construction 3 years
from building plan
approval (1/25/28)
 50% discount on
Planning and
Building fees
 Up to 100% discount
on selected impact
fees
 Water and sewer
public improvements
(or reimbursement of
infrastructures costs
up to $800,000)
 Use of T own Center
parking structure at
rate of 2 spaces per
apartment
 Purchase price of
$120,000
Lot 2 –
Perlman

 150 affordable
apartments (overall 60
percent AMI), 1
manager’s unit
 Pedestrian connection
from Central Plaza
Park to corner of Main
and Broadway
 Podium parking at 0.5
ratio
 Submit planning
application by
8/16/24
 Submit building plans
by 8/16/25
 Approval of building
plans by 2/16/26
 Complete
construction 3 years
from building plan
approval (2/26/29)
 50% discount on
Planning and
Building fees
 Use of T own Center
parking structure at
rate of 1 space per
apartment
 Purchase price of
$120,000
Lot 1 –
Town
Center West
 285 multi-family units,
with 75 condo units
 20,000 sq. ft. of
commercial uses, with
minimum of 10,000 sq.
ft. for dining/food
 Reconstruction of
Heritage Walk, plazas
and outdoor gathering
areas
 Podium parking serving
residents at a 1.0 ratio
 Submit planning
application by
12/31/2025
 Submit building plans
by 12/31/2026
 Approval of building
plans by 6/30/2027
 Complete
construction 3 years
from building plan
approval (6/30/2030)
 50% discount on
Planning and
Building fees
 Use of T own Center
parking structure
 Purchase price of
$120,000