RESOLUTION NO.

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SANTA MARIA, CALIFORNIA, AWARDING A BID TO R. BAKER INC., IN THE AMOUNT OF $1,500,584 FOR THE CONSTRUCTION OF THE CHURCH STREET SEWER LINE PROJECT, BID NO. 2024-07

WHEREAS, the City of Santa Maria formally advertised Church Street Sewer Line Project, Bid No. 2024-07 (“Project”); and

WHEREAS, the Notice Inviting Bids was published and posted in compliance with applicable sections of the Public Contract Code; and

WHEREAS, the bids were publicly opened on October 31, 2024; and

WHEREAS, R. Baker Inc., was determined to be the lowest responsive, responsible bidder who included all required documentation, bid bonds, and signatures; and

WHEREAS, project qualifies for a Class 1 Categorical Exemption pursuant to Section 15301.

NOW, THEREFORE, IT IS HEREBY RESOLVED by the City Council of the City of Santa Maria, California, as follows:

1. The Mayor is hereby authorized and directed to execute, for and on behalf of the City of Santa Maria, an Agreement with R. Baker Inc., for the construction of the Church Street Sewer Line Project, Bid No. 2024-07; and

2. The award of the bid is conditional upon execution of the Agreement by the successful bidder in the form and terms set forth therein by the City; and

3. The City Manager, or designee, is hereby authorized and directed to designate funds from the following identified REAP Grant Funds account for the approved project in the amount of $1,700,642.40; and

4. The City Manager, or designee, is hereby authorized to approve Contract Change Orders so long as expenditures do not exceed funding approved for the project; and

5. The Chief Deputy City Clerk is hereby authorized to make minor changes herein to address clerical errors, so long as substantial conformance of the intent of this document is maintained. In doing so, the Chief Deputy City Clerk shall consult with the City Manager and City Attorney concerning any changes deemed necessary.

2 PASSED AND ADOPTED at a regular meeting of the City Council of the City of Santa Maria held this 19th day of November 2024.

ATTEST:

Chief Deputy City Clerk

Mayor

APPROVED AS TO FORM:
_______________________________
City Attorney
APPROVED AS TO CONTENT:
_______________________________
Department Director
_______________________________
City Manager