COUNCIL AGENDA REPORT
TO: Mayor and City Council
FROM: Brett Fulgoni, Director of Public Works
DATE: January 21, 2025
SUBJECT: Adoption of a Resolution Approving an Award of Bid for Citywide Wharf Fire Hydrant Replacement Project, Bid No. 2024-12
Description:
The City Council will consider approving the award of Bid No. 2024 -12 to Main Line Engineering for the construction of the Citywide Wharf Fire Hydrant Replacement Project.
This project consists of removing 17 substandard fire hydrants and installing 6 new fire hydrants at 4 different City locations.
Environmental Notice: The Project qualifies for a Class 1 Categorical Exemption pursuant to Section 15301 – Existing facilities (operation, repair, maintenance, leasing, etc.) of the California Environmental Quality Act State Guidelines because the sc ope of work to be conducted is an existing public facility with negligible expansion of the existing uses.
RECOMMENDATION:
Adopt a Resolution awarding a bid to Main Line Engineering, in the amount of $208,500, for the construction of the Citywide Wharf Fire Hydrant Replacement Project, Bid No. 2024-12.
BACKGROUND:
Under the direction of the City of Santa Maria Utilities Department, the project was designed internally by Utility Staff. This project will consist of removing 17 substandard fire hydrants and installing 6 new fire hydrants at 4 different City locations. All hydrant removals have been coordinated with the Fire Department. Except for existing pavement and crosswalk improvements that may be removed or damaged during fire hydrant and waterline upgrade work, no other new subsurface or surface improvements will be constructed, and no grade changes are anticipated. All work will be within the City's road right-of-way.
2 DISCUSSION:
The project was extensively advertised for bids. The City received five bids, which was opened on November 26, 2024. A summary of the bids submitted are as follows:
Bidder Bid Amount
Main Line Engineering $208,500.00
AAAA Engineering Contracting, Inc. $212,660.00
The J.F. Will Company Inc. $269,731.44
RCH Construction $325,532.44
Joseph Construction and Consulting Inc
dba Joseph Engineering
$459,471.42
A detailed tabulation of the bids received is attached (Attachment B). Signed proposals and bid bond forms are available for viewing in the office of the Director of Public Works located at 110 South Pine Street, Suite 221, Santa Maria, CA 93458.
The lowest responsive, responsible bid was submitted by Main Line Engineering, in the amount of $208,500.
Main Line Engineering, from Lompoc, CA has performe d and successfully completed similar work for many cities throughout Southern California and on the Central Coast. In addition, they have submitted references for their work history. City staff has checked the firm’s references and are comfortable with the ability of the contractor to perform the work successfully. Therefore, the recommended action is to award the bid to Main Line Engineering in the amount of $208,500.
Alternative(s)
The alternative to the recommended action would be to reject all bids.
Fiscal Considerations
Sufficient funds for this project have been budgeted in Fiscal Year 2024/2025 from the account titled “Wharf Hydrant Replacement Project.”
Available Budget Account Amount
002-011-080-53-22 $ 355,625.26
Estimated Expenditures Amount
Award
Contingency (10%)
$ 208,500.00
$ 20,850.00
Inspection, Testing, Staff Time $ 30,000.00
Total $ 259,350.00
3 Impact to the Community
The community will benefit from the Wharf Fire Hydrant Project as it will replace substandard infrastructure with current standard detail waterlines and fire hydrants.