Attachment A

Page 1 of 3 ends

RESOLUTION NO.

A RESOLUTION OF THE CITY COUNCIL

OF THE CITY OF SANTA MARIA, CALIFORNIA
ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2026-27
FUNDED BY SENATE BILL 1, THE ROAD REPAIR AND
ACCOUNTABILITY ACT OF 2017

WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and signed into law by the Governor in April 2017 to address the significant multimodal transportation funding shortfalls statewide; and

WHEREAS, SB-1 includes accountability and transparency provisions to ensure that residents of the City are made aware of the projects proposed for funding in the community and which projects have been completed each fiscal year; and

WHEREAS, the City must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and location of each proposed project, a proposed sc hedule for the project’s completion, and the estimated useful life of the improvement; and

WHEREAS, the City is projected to receive $3,148,391 in RMRA funding in Fiscal Year 2026-27 from SB-1; and

WHEREAS, this is the tenth year in which the City is receiving SB 1 funding, which enables the City to continue essential road maintenance and rehabilitation projects, safety improvements, the repair and replacement of aging bridges, and increases in access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and

WHEREAS, City staff uses the Pavement Management Program to develop the SB- 1 project list to ensure revenues are used on the highest-priority and cost-effective projects that also reflect community priorities for transportation investment; and

WHEREAS, the funding from SB-1 will help the City maintain and rehabilitate various roadways throughout the City this year and support the inclusion of active transportation infrastructure; and

WHEREAS, the 2023 California Statewide Local Streets and Roads Needs Assessment found that the City’s streets and roads are in a lower “At-Risk” condition and this revenue will improve the overall quality of the road system, with the goal of bringing the network into “Good” condition over the next decade; and

Attachment A
WHEREAS, the SB 1 project list and overall investment in local streets and roads infrastructure, focusing on basic maintenance , safety, complete streets, and the use of advanced technology, materials, and practices, will have significant positive co -benefits statewide.

NOW THEREFORE, IT IS HEREBY RESOLVED by the City Council of the City of Santa Maria, California, as follows:

SECTION 1. The foregoing recitals are true and correct.

SECTION 2. The budget for Fiscal Year 2026-27 will incorporate funding for the following proposed project to be funded in part or in full with Fiscal Year 2026-27 Road Maintenance and Rehabilitation Account revenues:

1) Enhanced Asphalt Maintenance Project.

Description:

This project will include enhanced asphalt maintenance on one or more of the roadways listed below within the City of Santa Maria, as prioritized by the City’s Pavement Management Program. The work will consist of selective digouts, grinding, and partial or full-width overlay treatments on arterial and collector streets. Additionally, the project will include the installation or replacement of striping and pavement markings, as needed.

Project limits, specific roadway segments, and treatment types may be adjusted based on field conditions, bid results, and available funding, while maintaining consistency with the overall intent of preserving and improving the City’s roadway network.

Locations:

South College Drive: Main Street to Stowell
South Miller Street: Main Street to Stowell
Donovan Road: Suey Crossing to Carlotti
Donovan Road: College to Blosser
Taylor: Railroad to Blosser.

Southside Parkway: Bradley to College.

McCoy: Broadway to Miller
A Street: Fairway to Betteravia

Cost and Funding:

Preliminary Engineer's Estimate: $ 3,359,223
SB-1 (FY 26/27): $ 3,148,391
Attachment A

Page 3 of 3 ends

Gas Tax: $ 210,832

Estimated Start Date: September 2026
Estimated Completion Date: June 2027

Estimated Useful Life: 10-15 years

SECTION 3. The Chief Deputy City Clerk is hereby authorized to make minor changes herein to address clerical errors, so long as substantial conformance of the intent of this document is maintained. In doing so, the Chief Deputy City Clerk shall consult with the City Manager and City Attorney concerning any changes deemed necessary.

PASSED AND ADOPTED at a regular meeting of the City Council of the City of Santa Maria held this 5th day of May 2026.

ATTEST:

Chief Deputy City Clerk

Mayor

APPROVED AS TO FORM:
_______________________________
City Attorney
APPROVED AS TO CONTENT:

_______________________________
Department Director
_______________________________
City Manager

← All documents from this meeting