Attachment B

AGREEMENT FOR SERVICES
This Agreement is made on November 3, 2026, by and between Nichols Consulting Engineers, Chtd. (NCE), a Nevada Corporation (“Contractor”) and the City of Santa Maria, a California Municipal Corporation and charter city (“City”), in Santa Maria, California, based on the following recitals:

WHEREAS, City has determined it is in the public interest to proceed with the work hereinafter described as "Project"; and
WHEREAS, City does not have available employees to perform the services for the Project; and
WHEREAS, City has requested the Contractor to provide manpower to complete the Project; and
WHEREAS, Contractor is registered or licensed in California to perform desired services for the Project.

NOW, THEREFORE, IT IS AGREED:

1. Recitals true. The above recitals are true.

2. General.

2.01. Term and Termination. The term of this contract is one year, beginning on the date first written above. This contract may be extended by mutual consent of the parties, consistent with the terms identified in the Request for Proposals. This contract may be terminated for breach of its terms or conditions, or because of discovery of any act which violates local, state or federal law. Termination is effective 14 days after deposit of notice as specified in this Agreement.

2.02. Services to be Performed. Contractor shall determine the method, details and means of providing professional engineering services for final design and preparation of Plans, Specifications, and Estimate (PS&E) and associated services for the ATP Cycle 7 Railroad Avenue/Depot Street Corridor Improvements project. More specifically, Contractor agrees to perform the specific services listed in Exhibit A.

2.03 City’s Duties. City’s duties under this Agreement are to cooperate with Contractor in the performance of the contract and timely pay invoices.

2.04. Payment. Payment terms under this Agreement are listed in Exhibit B.

2.05. Insurance. Contractor shall provide insurance as listed in Exhibit C.

2.06. Prevailing wage. Where applicable, Contractor shall follow the prevailing wage requirements listed in Exhibit D and applicable law.

2.07. Exhibits. Exhibits “A, B, C, and D are attached and incorporated.

3. Contractor’s Obligations.

3.01. Minimum Amount of Service. Contractor shall devote sufficient time to perform services under this agreement efficiently and effectively. Contractor may represent, perform services for and be employed by additional individuals or entities, in Contractor’s sole discretion, as long as the performance of these extra-contractual services does not interfere with or present a conflict with City's business.

3.02. Tools and Equipment. Except as otherwise stated in this Agreement, Contractor will supply all tools and equipment necessary to perform this Agreement.

Attachment B

3.03. Status. Contractor (including its employees) is an independent contractor.

No employer/employee relationship exists between Contractor and the City. Contractor's assigned personnel shall not be entitled to any benefits payable to employees of the City. The City is not required to make any deductions or withholdings from the compensation payable to Contractor under this agreement.

3.04. Indemnification. To the fullest extent permitted by law, the Contractor shall indemnify, defend (with independent counsel approved by the City) and hold harmless the City, and its directors, officers, and employees from and against all liabilities (including without limitation all claims, losses, damages, penalties, fines, and judgments, associated investigation and administrative expenses, and defense costs, including but not limited to reasonable attorneys’ fees, court costs and costs of alternative dispute resolution) regardless of nature or type that arise out of, pertain to, or relate to the negligence, reckless, or willful misconduct of the Contractor or the acts or omissions of an employee, agent or subcontractor of the Contractor. The provisions of this paragraph survive completion of the services or the termination of this contract. The provisions of this Section are not limited by the provisions of the Section relating to insurance.

4. Miscellaneous

4.01. Notices. All communication relating to the day-to-day activities of this Agreement shall be exchanged between a designated representative of the CITY and a representative of CONTRACTOR, listed below. All notices shall be addressed as follows unless a written change is filed with the City:

To City: To Contractor:

Zoe Glick, P.E. Jim Bui, P.E.

Senior Civil Engineer Project Manager
City of Santa Maria, Public Works Nichols Consulting Engineers, Chtd. 110 S. Pine Street, Suite 221 2300 E. Katella Avenue, Suite 125 Santa Maria, CA 93458 Anaheim, CA 92806
If the designated Representative or address of either party changes during the term of this agreement, a written notice shall be given to the other party prior to the effective date of change. Any written notices required under this agreement shall be effective five (5) days after deposit into United States mail, postage prepaid, addressed to the designated Representative, or upon confirmation of receipt of delivery if another notification process is used.

4.02. Compliance With Laws, etc. Contractor shall comply with all laws, including but not limited to the rules and policies of the City, in performing this agreement.

4.03. Integration. This agreement constitutes the entire agreement of the parties with respect to the subject matter. All modifications, amendments, or waivers of the terms of this agreement must be in writing and signed by the appropriate representatives of the parties.

4.04. Interpretation. This agreement shall be interpreted in accordance with the laws of the State of California.

4.05. Jurisdiction. Jurisdiction and venue of all disputes over the terms of this agreement shall be in the County of Northern Santa Barbara, State of California.

4.06. Warranty of authority. Each person signing this agreement on behalf of a party warrants that he or she has authority to do so.

4.07. No Waiver. Failure to enforce with respect to a default shall not be construed as a waiver.

4.08. Severability. The provisions of this agreement are severable. If any part Attachment B
of this agreement is held invalid by a court of competent jurisdiction, the remainder of the agreement shall remain in full force and effect unless amended or modified by mutual written consent of the parties.

4.09. Submittals. In addition to any other submittals required by this agreement, Contractor shall submit copies of its current business license and current certificate of workers compensation coverage to the City before beginning work on this project.

4.10 Prevailing Wage. Prevailing Wage. If applicable, Contractor and all subcontractors are required to pay the general prevailing wage rates of per diem wages and overtime and holiday wages determined by the Director of the Department of Industrial Relations under Section 1720 et seq. of the California Labor Code. The Director's determination is on file and open to inspection at www.dir.ca.gov and is referred to and made a part hereof; the wage rates therein ascertained, determined and specified are referred to and made a part hereof as though fully set forth herein. Further requirements are attached as Exhibit D.

IN WITNESS WHEREOF, this agreement is executed by the parties on the date first written above.

NICHOLS CONSULTING ENGINEERS,
CHTD. (NCE)
___________________________
Margot Yapp
President
CITY OF SANTA MARIA, a Municipal Corporation
Brett Fulgoni
Public Works Director
ATTEST:

Donna G. Schwartz
Chief Deputy City Clerk
APPROVED AS TO FORM:
_______________________________
Risk Manager
_______________________________
City Attorney
Attachment B

EXHIBIT A

SCOPE OF SERVICES
Task 1: Project Management and Meetings
NCE’s Project Manager (PM) will serve as the City’s single point of contact and will have primary responsibility for coordinating the efforts of the project team. Specific project management tasks to be conducted by the PM include monthly budgeting, invoicing, scheduling, and general project administration. The PM will arrange a kick-off meeting with the City to initiate the work. The objectives of the kick-off meeting will be:
 Review the scope of work.
 Establish paths of communication.
 Review project schedule and critical milestones.
 Review project requirements, including design objectives, budget, constraints, and criteria. The City’s requirements will be further defined during the meeting.  Request the pertinent ATP Grant Application and environmental approvals.  Review City Standard Design Criteria and latest City-adopted formats.  Request background information and as-builts.
 Obtain electronic file of the City’s cover sheet template, title block, and CAD Standards.

At the kick-off meeting, key deliverables and the project schedule will be reviewed and adjusted to meet the City’s needs.

The following meetings are included in the scope: kick-off/preliminary meeting (1 hour) and monthly virtual progress meetings. The purpose of these meetings will be to confirm project limits, identify and resolve design issues that may surface, present design alternatives and recommendations, and continue coordination with project stakeholders, as necessary.

Deliverables: Kick-Off meeting and monthly progress meeting agendas and minutes.

Task 2: Existing Conditions Verification and Technical Support NCE will review available basemap information for the corridor provided by the City, including topographic survey information, utility information, drainage information, and traffic as-builts. We’ll also review the City’s ATP Grant Application and Environmental Commitments for data needs. This information combined with the City’s concept plans included in the RFP will be the basis for evaluating the site constraints and required design data.

NCE’s staff will walk or drive the corridor as appropriate, focusing on the discrete intersection improvements and note possible data gaps, the need for supplemental topographic surveying, or other technical studies. At this time, special attention will be given to the 4 intersections with “direct” storm Attachment B
drain impacts, and 4 intersections with likely traffic signal conflicts. For specific areas of concern, we will also take photographs of the potential issues and brief measurements to help quantify the issue.

We will prepare a brief technical memorandum with our observations and submit to the City for their review and input. If needed, based on the City’s preliminary review, we may also conduct up to one (1) follow-up site meeting with City staff to clarify the site issues and finalize the approach for the 30% design phase.

Deliverables: Field review summary and existing conditions constraints memo.

Task 3: PS&E – 30% Design Submittal
Task 3.A Basemap Preparation
Task 3A.1 Topographic Survey
NCE’s project surveyor will conduct a topographic surveying effort with the effort divided into discrete intersection surveys and a separate longitudinal corridor mapping effort. The mapping will be compiled at an agreed-upon scale (1” = 40’ or similar) with a 1-foot contour interval and horizontally tied to the California State Plane coordinate system (NAD83) based upon the current Santa Barbara County adjustment and vertically tied to the Santa Barbara County benchmark network (NAVD88).

The intersection surveys will include top of curb, flowline, gutters, manholes (rim and invert elevations), utility boxes and vaults, striping and other markings, driveways, sidewalks, fences, walls, gates, tree and tree wells, street furniture, light and utility poles, traffic signals, and signs. The intersection will include 10’ grid spacing, including visible grade breaks. Medians will be included if they exist at the intersection. Limits covered by the intersection topo will extend 50 feet beyond the curb returns and up to the right of way lines. A TIN surface will be provided for each intersection.

For the remaining corridor, topographic information will be taken at cross sections with 250’ intervals on the straight sections of the roadway (at least one per block) and will extend from back of sidewalk to back of sidewalk. Where the road curves, cross sections will be taken at the beginning of the curve and end of curve. Curb, gutter, sidewalk, striping, and grade breaks will be included in the cross sections. It will be combined with planimetric aerial mapping to create a composite corridor basemap.

Approximately 90 - 110 cross sections will be taken but may be adjusted to meet City accuracy goals for the Class IV bikeway.

Survey work will be performed under the direct supervision of a Professional Land Surveyor Licensed in the State of California. Work will be conducted in accordance with standard acceptable surveying practices.

Deliverables: CAD Basemap (DWG format), Aerial Ortho-Imagery (GeoTIFF or similar).

Task 3A.2 Underground Utility Locating and Potholing (Optional) At up to four (4) intersections, NCE’s project surveyor will collect detailed storm drain invert elevation information for manholes and catch basins. This investigation will include non-destructive underground Attachment B
utility locating such as ground penetrating radar combined with surveying the invert elevations of storm drain facilities. The utility locating will collect utility location data including possible utility type, approximate alignment, and approximate depth with markings painted on the pavement.

If needed for utility relocation and conflict checking, NCE’s utility locating sub-consultant can also direct the collection of various utility potholes in the pavement to determine actual utility depths. This effort assumes only up to one (1) day of field effort to collect the utility potholes, which may include 4-6 test locations depending on the proximity of test sites. NCE will execute a no-fee encroachment permit with the City for performing utility potholing. Our utility locator will pre-mark locations and clear locations with DigAlert. Holes will be backfilled with excavated materials and capped with Asphalt Concrete cold patch.

Deliverables: Supplemental utility surveying data added to Basemap (DWG format), Utility Locating/Pothole Report (PDF).

Task 3A.3 ROW Mapping
If the City has not yet conducted ROW Mapping to identify ROW constraints, NCE’s project surveyor will collect ROW mapping information at intersections to confirm available ROW for bulb-outs and intersection improvements. Using recorded maps for the area around the corridor, the project surveyor will search for and collect survey monuments to be able to plot the recorded boundary. We will also gather grant deed descriptions of the right of way where available. In the area of the Santa Maria Valley Railroad crossing, Main Street crossing, and the Flood Control Channel Crossing, we will perform a more detailed boundary survey for your use in engaging with those entities in obtaining as-needed encroachment permits and temporary construction easements.

As the remainder of the corridor outside of the intersections has worked primarily within the roadway pavement, it is assumed that the City already has sufficient ROW for those improvements. Therefore, only a high-level, Geographic Information Systems (GIS) based ROW boundary will be prepared.

Alternatively, as an optional task, the ROW for the larger corridor may also be mapped to the same standards as those of the intersections. A preliminary search of recorded maps for the entire corridor resulted in approximately 60 maps to search for monumentation.

Task 3.B Utility “A” Letter
Working with other agencies, we have observed that utility letters receive more prompt attention when distributed by a City. Therefore, NCE will utilize a City-provided utility contact list and prepare a Utility “A Letter” on City letterhead for City distribution to both notify the utilities of impending intersection concrete/utility work and request available utility mapping information. NCE will track the progress of inbound and outbound responses in a utility tracking matrix.

Deliverables: Utility Tracking Matrix (Excel/PDF).

Task 3.C 30% Plans and Estimate
Attachment B
NCE will utilize the basemap, compiled background information, and results of our site verification to develop 30% conceptual plans. The importance of the concept plans will be to better understand possible conflicts between the proposed bulb-outs with the existing drainage conditions and traffic signal systems. Also, bikeway barrier elements can be evaluated for long-term maintenance and access needs like street sweeping.

Large bulb-outs may require the installation of underdrains or trench drains to intercept drainage, as the widened sidewalks may create negative drainage areas flowing backwards towards the existing sidewalk. In some instances, more sizeable bulb-outs like several of the 20’ bulb-outs along the project may trigger significant grading issues requiring full reconstruction of the intersection pavement. In those instances, the design will evaluate the tradeoffs and costs between pavement reconstruction versus installing intermediate storm drain catch basins or manholes to connect to the larger storm drain systems. However, NCE understands that intersection re-grading and new storm drain facilities are a last resort and the City would first prefer reducing the size of the bulb-outs to be compatible with existing drainage features. Therefore, NCE’s proposal assumes a limited effort of reducing the size of the bulb-outs, which will in turn reduce the anticipated design effort in subsequent design phases.

Once the conceptual bulb-outs footprints are better understood, a preliminary review of impacted traffic signal systems can be performed, and the approach to relocating or adjusting various pedestrian pushbuttons and signal heads can be evaluated. NCE will also attempt to minimize the amount of pedestrian pushbutton impacts with the reduced bulb-out sizes.

Deliverables: 30% Engineering Plans and Estimate of Probable Construction Cost (PDF).

Task 4: PS&E – 60% Design Submittal
The 60% draft PS&E will incorporate the various data collection efforts compiled as part of previous tasks, including available as-built information from the City. The 65% intersection improvements will incorporate typical design elements, including Public Right-of-Way Accessibility Guidelines-compliant curb ramp layouts, bulb-outs layouts, concrete flatwork, curb and gutter, and required Hot Mix Asphalt conforms. Based on the assumption that the bulb-out sizes will be effectively reduced, we anticipate only a minimal amount of roadway re-grading design and need for HMA conforms. The bikeway improvements will include lane dimensions, required tapers, and bikeway barrier information. Surface visible utility structures within the project footprint will be identified on the Plans for either adjustment or protection as appropriate. Where large bulb-outs require substantial relocation or reconstruction of the adjacent storm drain system, dedicated utility relocation plans may be developed to ensure improvements do not impact other crossing underground utilities. However, we assume that the need for this storm drain system relocation or reconstruction work will be extremely limited due to the successful reduction in size of the bulb-out footprints during the 30% design. Impacted traffic signals and push buttons will be shown for relocation or adjustment as needed. Traffic signal modifications will be included to relocate traffic signals and pedestrian pushbuttons conflicting with the proposed curb ramps and striping.

Attachment B
We generally assume signal modification plans can be prepared as a streamlined plan set. However, at Stowell Street the new crosswalk will require new traffic signal equipment and a more in-depth design, and at Alvin Avenue, the large bulb-out may require more extensive relocation such as relocation of the traffic signal mast-arm.

The Plans will be prepared in AutoCAD format on 24” x 36” sheets, utilizing the City Title Block and CAD Template as agreed upon during Task 1 and drawn at a scale of 1” = 20’. Striping and signage plans will be prepared at a scale of 1” = 40’.

Anticipated 65% Street Improvement Plan List (62 total):
 (1) – Cover Page
 (1) – Notes, Legends, and Abbreviations
 (1) – Construction Details
 (11) – Improvement Plans (Plan/Plan)
 (11) – Striping and Signage Plans (Plan/Plan)
 (4) – Storm Drain Relocation Plan (Intersection)
 (4) – Traffic Signal Modification Plan (Intersection)  (29) – Curb Ramp Details [25 for bulb-outs, 4 for other locations] The Engineer’s Estimate of Probable Construction Cost will be prepared in Microsoft Excel format using a Bid Item format and will be based on recent construction cost data available to NCE for projects of this type.

NCE assumes the City will provide boilerplate specifications suitable for the development of the roadway rehabilitation project in Microsoft Word format. NCE will provide revisions to the Special Provisions related to the specifications for materials or construction related to our bid items using Caltrans Specifications. NCE assumes the City will develop the “front-end” specifications, including the overall bid book.

Deliverables: 60% Engineering Plans (PDF), Cost Estimate (PDF), and Technical Specifications (MS Word).

Task 5: PS&E – 90% Design Submittal
The 60% PS&E will be revised to incorporate design review comments received from the City. NCE will meet with the City to review these comments, from which the Draft 90% PS&E will be prepared. NCE will further refine the design to a 90% level of design at this stage. This will include fine-tuning of grading and improvement plans for the bulb-outs, adjusting the traffic signal plans, and making adjustments to the storm drain design as needed. The draft 90% PS&E will then be packaged and submitted similarly to the 65% PS&E, unless directed otherwise.

Attachment B
Deliverables: 90% Engineering Plans (PDF), Cost Estimate (PDF), and Technical Specifications (MS Word), Comment Resolution Matrix.

Task 6: Final PS&E and Advertisement Package
Task 6.A Final PS&E
The 90% PS&E will be prepared to incorporate final design review comments received from the City.

NCE will meet with the City to review these comments, from which the Final PS&E will be prepared.

The Final PS&E will be prepared and sent to the City in a bid-ready format.

Deliverables: Final Engineering Plans (PDF), Cost Estimate (PDF), and Technical Specifications (MS Word), Comment Resolution Matrix.

Task 6.B Caltrans Encroachment Permit Support (Optional) As an optional task, NCE can provide the City with as-needed encroachment permit application support led for a City-led encroachment permit application related to improvements adjacent to Main Street (SR-166). Support may include modifications to electrical plans to Caltrans standards, including plan view, removal plan, conductor schedule, equipment schedule, and notes for modifications to signal equipment and detection. We have included a limited number of hours in our scope and only anticipate the need to develop 1-2 electrical modification sheets and minor turning template exhibits. However, this task will be billed on a time and materials basis for the work requested by the City. We will be able to refine the scope in more detail with the City after receiving initial review comments from Caltrans regarding the proposed project elements and elimination of the dedicated northbound right-turn pocket.

Deliverables: As-needed design support.

Task 7: Construction Phase Design Support (OPTIONAL)
NCE may provide construction phase support services to the City as an optional task, including design services during bidding and construction. During the bidding period, this may include responding to one round of written contractors’ inquiries from a question and answer (Q&A) phase, providing revisions to the bid documents due to clarifications from the Q&A phase, and preparing up to 1 Bid Document Addendum.

We assume the construction project will be professionally managed by the City’s Construction Manager (CM), including the required inspection staff. Once the project has been awarded to a Contractor, NCE anticipates attendance at the construction kick-off meeting, responding to contractor requests for information (assume up to three [3] Request for Information [RFI]), and providing recommendations for necessary changes to the construction documents due to unforeseen field conditions. Construction support will also include material submittal review for conformance with the NCE-developed Technical Provisions.

Attachment B
The limited number of hours to provide construction phase design support in the Fee Estimate is an estimate only. The actual cost will be dependent on the City and Contractor and will be billed on a time and materials basis.

Deliverables: As-needed bidding Q&A responses and bid document addenda (up to one [1]); As-needed RFI responses (up to three [3]) and submittal review during construction.

Task 8: Record Drawings/As-Built Support (OPTIONAL)
NCE may provide records drawings and as-built support as an optional task. We assume the City’s CM will provide legible, consolidated as-built plan redlines for NCE to develop into a digital as-built of the project Plans. NCE will submit an electronic copy of the as-builts to the City in PDF format. We assume a limited number of hours to prepare as-built drawings. The actual cost will be dependent on the City and Contractor and will be billed on a time and materials basis.

Deliverables: Digital as-built of the Plans (PDF) and CAD E-Transmittal.

Attachment B

EXHIBIT B

PAYMENT
I. Progress Authorization
Written authorization to proceed from the City authorizes Contractor to incur costs up to the total not-to-exceed amount of SEVEN HUNDRED NINETY THOUSAND TWO HUNDRED THIRTY DOLLARS AND ZERO CENTS ($790,230) for all services under this Agreement, including the optional services identified below. No work shall commence until the City issues a written Notice to Proceed.

Compensation shall be based on NCE’s cost proposal dated June 19, 2026, revised September 11, 2026, attached hereto and incorporated into this Exhibit “B.” Task Description Budget
1 Project Management and Meetings $32,900
2 Existing Conditions Verification and Technical Support $24,070 3 PS&E – 30% Design Submittal, including optional underground utility locating and potholing $239,040
4 PS&E – 60% Design Submittal $231,590
5 PS&E – 90% Design Submittal $116,600
6 Final PS&E and Advertisement Package, including optional Caltrans encroachment permit support $109,750
7 Construction Phase Design Support (Optional) $26,015
8 Record Drawings/As-Built Support (Optional) $10,265
Total Not-to-Exceed Amount $790,230
The total includes $668,370 for base services and $121,860 for optional services. Optional services consist of:
 Underground utility locating and potholing: $45,130.
 Caltrans encroachment permit support: $40,450.
 Bidding and construction-phase design support: $26,015.  Record drawings/as-built support: $10,265.

Optional services shall be performed only as needed and directed in writing by the City.

Inclusion of an optional service in the budget does not require the City to authorize its use.

Contractor shall bill only for services performed and authorized costs incurred.

II. Invoice procedure.

A. Payment shall be monthly based on the billable charges.

B. The Contractor shall present the bill for charges from the previous month.

Attachment B
C. The Contractor's bill shall be substantiated by appropriate documentation, and include an itemized listing of personnel, subcontractors, and other direct costs incurred.

D. City may withhold payment for disputed work. Payment of fees shall not constitute an acceptance of work.

Rates shall be billed according to Contractor’s attached fee schedule, up to the not-to-exceed amount. Work Authorized by Change Order/Amendment shall be billed at on a time and materials basis according to the attached fee schedule, unless another payment method is agreed to in writing by the City prior to initiation of work.

III. Maximum billable amounts
Under no circumstance shall the total of all payments to the Consultant exceed ninety percent (90%) of the maximum not-to-exceed cost, prior to acceptance by the City of all items to be completed as noted within Exhibit "A".

IV. IV. Consultant Fee Schedule (continued on next page) Attachment B
Attachment B
Attachment B
Attachment B
Attachment B

Attachment B

EXHIBIT C

INSURANCE REQUIREMENTS
Consultant shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Consultant, his/her agents, representatives, or employees. If the Consultant maintains broader coverage and/or higher limits than the minimums shown above, the City requires and shall be entitled to the broader coverage and/or higher limits maintained by the Consultant.

A. Minimum Scope of Insurance
Coverage shall be at least as broad as:

1. Insurance Services Office Commercial General Liability coverage (occurrence form CG 0001), including products and completed operations, property damage, bodily injury and personal & advertising injury.

2. Insurance Services Office Business Auto Coverage Form Number CA 00 01 covering any auto (Code 1), or if Consultant has no owned autos, covering hired (Code 8) and non-owned autos (Code 9).

3. Workers' Compensation insurance as required by the State of California and Employer's Liability Insurance.

4. Errors and Omissions liability insurance appropriate to the Consultant's profession.

Architects' and engineers' coverage is to be endorsed to include contractual liability.

5. Cyber Liability Insurance, Coverage shall be sufficiently broad to respond to the duties and obligations as is undertaken by Vendor in this agreement and shall include, but not be limited to, claims involving infringement of intellectual property, including but not limited to infringement of copyright, trademark, trade dress, invasion of privacy violations, information theft, damage to or destruction of electronic information, release of private information, alteration of electronic information, extortion and network security. The policy shall provide coverage for breach response costs as well as regulatory fines and penalties as well as credit monitoring expenses with limits sufficient to respond to these obligations.

B. Minimum Limits of Insurance
Consultant shall maintain limits no less than:

1. General Liability - $2,000,000 per occurrence for bodily injury, personal injury and property damage. If Commercial General Liability Insurance or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to this project/location (ISO CG 25 03 or 25 04) or the general aggregate limit shall be twice the required occurrence limit.

2. Automobile Liability - $1,000,000 per accident for bodily injury and property damage.

3. Workers’ Compensation: Statutory limits.

4. Employer's Liability - $1,000,000 per accident for bodily injury or disease.

5. Errors and Omissions Liability - $1,000,000 per occurrence or claim, $2,000,000 aggregate.

Attachment B

6. Cyber Liability- $2,000,000 per occurrence or claim, $2,000,000 aggregate.

C. Self-insured Retentions
Self-insured retentions must be declared to and approved by the City. The City may require the Consultant to purchase coverage with a lower retention or provide proof of ability to pay losses and related investigations, claim administration and defense expenses within the retention.

D. Other Insurance Provisions
The liability policies are to contain, or be endorsed to contain, the following provisions:

1. The City, its officers, officials, employees and volunteers are to be covered as additional insureds on the CGL policy with respect to liability arising out of work or operations performed by or on behalf of the Consultant including materials, parts or equipment furnished in connection with such work or operations. General liability coverage can be provided in the form or an endorsement to the Consultant’s insurance (at least as broad as ISO Form CG 20 10 11 85 or both CG 20 10, CG 20 26, CG 20 33, or CG 20 38 and CG 20 37 forms if later revisions are used).

2. For any claims related to this project, the Consultant's insurance coverage shall be primary insurance coverage at least as broad as ISO CG 20 01 04 13 as respects the City, its officers, officials, employees and volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees or volunteers shall be excess of the Consultant's insurance and shall not contribute with it.

3. Each insurance policy required by this clause shall be endorsed to state that coverage shall not be canceled or reduced, except with notice stating the title of this contract to the City. All notices provided pursuant to this Agreement shall be given to the City representative listed for notice in this agreement and shall specify the title of this Agreement. Notice may be given by overnight mail, facsimile with confirmation of receipt, or certified mail with return-receipt requested.

4. Consultant hereby grants to City a waiver of any right to subrogation which any insurer of said Consultant may acquire against the City by virtue of the payment of any loss under such insurance. Consultant agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation, but this provision applies regardless of whether or not the City has received a waiver of subrogation endorsement from the insurer.

5. If any of the required policies provide claims-made coverage:
a. The Retroactive Date must be shown and must be before the date of the contract or the beginning of contract work.
b. Insurance must be maintained and evidence of insurance must be provided for at least five (5) years after completion of the contract of work. c. If coverage is canceled or non-renewed, and not replaced with another claims-made policy form with a Retroactive Date prior to the contract effective date, the Consultant must purchase “extended reporting” coverage for a minimum of five (5) years after completion of work.

E. Acceptability of Insurers
Insurance is to be placed with insurers with a current A.M. Best's rating of no less than A:VII, unless otherwise acceptable to the City.

F. Verification of Coverage
Attachment B
Consultant shall furnish the City with original certificates and amendatory endorsements of the applicable policy language effecting coverage required by this clause. All certificates and endorsements are to be received and approved by the City before work commences.

However, failure to obtain the required documents prior to the work beginning shall not waive the Consultant’s obligation to provide them. The City reserves the right to require complete, certified copies of all required insurance policies, including endorsements effecting the coverage required by these specifications at any time.

G. Special Risks or Circumstances
The City reserves the right to modify these requirements, including limits, based on the nature of the risk, prior experience, insurer, coverage, or other special circumstances.

Attachment B

EXHIBIT D

PREVAILING WAGE REQUIREMENTS FOR MAINTENANCE WORK, DESIGN AND PRECONSTRUCTION

PHASES OF CONSTRUCTION, AND INSTALLATIONS
The terms of this Exhibit apply to all Public Works projects for over $1,000.

For purposes of this Exhibit, “Public Works” includes any project of a type defined in California Labor Code section 1720 when paid for in whole or in part by public funds. These projects include: construction, alteration, demolition, installation, or repair work done under contract.

For purposes of this definition, "construction" includes work performed during the design, site assessment, feasibility study, and other preconstruction phases of construction, including, but not limited to, inspection and land surveying work, regardless of whether any further construction work is conducted, and work performed during the postconstruction phases of construction, including, but not limited to, all cleanup work at the jobsite. For purposes of this definition, "installation" includes, but is not limited to, the assembly and disassembly of freestanding and affixed modular office systems.

Pursuant to California Labor Code sections 1720 and 1771, construction, alteration, demolition, installation, repair and maintenance work performed under this Agreement is subject to State prevailing wage laws. State prevailing wage laws require certain provisions be included in all contracts for public works. The CONTRACTOR and any subcontractors shall comply with all applicable State prevailing wage laws, whether included in this agreement or inadvertently omitted, including but not limited to the requirements listed below:

1. Compliance with Prevailing Wage Requirements. Pursuant to California Labor Code sections 1720 through 1861, the CONTRACTOR and all subcontractors shall ensure that all workers who perform work under this Agreement are paid not less than the prevailing rate of per diem wages as determined by the Director of the California Department of Industrial Relations (DIR). This includes work performed during the design, site assessment, feasibility study, and other preconstruction phases of construction, including but not limited to inspection and land surveying work, regardless of whether any further construction work is conducted, and work performed during the post-construction phases of construction, including but not limited to all cleanup work at the jobsite.

1.1. Copies of such prevailing rate of per diem wages are on file at the City Public Works Department and are available for inspection to any interested party on request.

Copies of the prevailing rate of per diem wages also may be found at http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm. The CONTRACTOR and all subcontractors shall post a copy of the prevailing rate of per diem wages determination at each job site and shall make them available to any interested party upon request.

1.2. The wage rates determined by the DIR refer to expiration dates. If the published wage rate does not refer to a predetermined wage rate to be paid after the expiration date, then the published rate of wage shall be in effect for the life of this Agreement. If the published wage rate refers to a predetermined wage rate to become effective upon expiration of the published wage rate and the predetermined wage rate is on file with the DIR, such predetermined wage rate shall become effective on the date following the expiration date and shall apply to this Agreement in the same manner as if it had been published in said publication. If the predetermined wage rate refers to one or more Attachment B
additional expiration dates with additional predetermined wage rates, which expiration dates occur during the life of this Agreement, each successive predetermined wage rate shall apply to this Agreement on the date following the expiration date of the previous wage rate.

If the last of such predetermined wage rates expires during the life of this Agreement, such wage rate shall apply to the balance of the Agreement.

2.Penalties for Violations. The CONTRACTOR and all subcontractors shall comply with California Labor Code section 1775 in the event a worker is paid less than the prevailing wage rate for the work or craft in which the worker is employed. This shall be in addition to any other applicable penalties allowed under California Labor Code sections 1720 through 1861.

3. Payroll Records. The CONTRACTOR and all subcontractors shall comply with California Labor Code section 1776, which generally requires keeping accurate payroll records, verifying and certifying payroll records, and making them available for inspection.

The CONTRACTOR shall require all subcontractors to also comply with section 1776. The CONTRACTOR and all subcontractors shall furnish records specified in section 1776 on a monthly basis, both to the City and directly to the Labor Commissioner in the manner required by California Labor Code section 1771.4. The CONTRACTOR shall ensure its subcontractors prepare and submit payroll records to the City and the DIR as required by this section. The City may require the CONTRACTOR and its subcontractors to prepare and submit records specified in section 1776 to the City and the Labor Commissioner on a weekly basis, at no additional cost to the City.

4. Apprentices. The CONTRACTOR and all subcontractors shall comply with California Labor Code sections 1777.5, 1777.6 and 1777.7 concerning the employment and wages of apprentices. The CONTRACTOR is responsible for compliance with this section for all apprenticeable occupations pursuant to California Labor Code section 1777.5(n).

5. Working Hours. The CONTRACTOR and all subcontractors shall comply with California Labor Code sections 1810 through 1815, including but not limited to: (i) restrict working hours on public works contracts to eight hours a day and forty hours a week, unless all hours worked in excess of 8 hours per day are compensated at not less than 1½ times the basic rate of pay; and (ii) specify penalties to be imposed on CONTRACTORs and subcontractors of $25 per worker per day for each day the worker works more than 8 hours per day and 40 hours per week in violation of California Labor Code sections 1810 through 1815.

6. Required Provisions for Subcontracts. The CONTRACTOR shall include, at a minimum, a copy of the following provisions in any contract they enter into with a subcontractor: California Labor Code sections 1771, 1771.1, 1775, 1776, 1777.5, 1810, 1813, 1815, 1860 and 1861.

7. Labor Code Section 1861 Certification. In accordance with California Labor Code section 3700, the CONTRACTOR is required to secure the payment of compensation of its employees. By signing the Agreement, to which this is an exhibit, the CONTRACTOR certifies that:
“I am aware of the provisions of Section 3700 of the California Labor Code which require every employer to be insured against liability for workers’ compensation or to Attachment B
undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this Agreement.”

8. Compliance Monitoring and Enforcement. This project is subject to compliance monitoring and enforcement by the DIR. The City must withhold contract payments from the CONTRACTOR as directed by the DIR, pursuant to California Labor Code section 1727.

9. CONTRACTOR and Subcontractor Registration Requirements. The CONTRACTOR and all subcontractors shall not engage in the performance of any contract for public work, unless currently registered and qualified to perform public work pursuant to California Labor Code section 1725.5 CONTRACTOR certifies that the CONTRACTOR has verified that all CONTRACTOR and all subcontractors (if any approved by City) used on this project are registered with the DIR in compliance with California Labor Code sections 1771.1 and 1725.5. The CONTRACTOR shall provide proof of registration for themselves and all listed subcontractors to the City at the time of signature of contract and immediately upon any changes or City’s request.

10.Stop Order. Where a CONTRACTOR or subcontractor engages in the performance of any public work contract without having been registered in violation of California Labor Code sections 1725.5 or 1771.1, the Labor Commissioner must issue and serve a stop order prohibiting the use of the unregistered CONTRACTOR or subcontractor on ALL public works until the unregistered CONTRACTOR or subcontractor is registered. Failure to observe a stop order is a misdemeanor.