COUNCIL AGENDA REPORT
TO: Mayor and City Council
FROM: Brett Fulgoni, Director of Public Works
DATE: November 3, 2026
SUBJECT: Adoption of a Resolution Approving a Professional Services Agreement with Nichols Consulting Engineers for the Active Transportation Program Cycle 7 Railroad Avenue/Depot Street Corridor Improvements Project
Description:
The City Council will consider adopting a Resolution approving the award of a Professional Services Agreement to Nichols Consulting Engineers for the Active Transportation Program Cycle 7 Railroad Avenue/Depot Street Corridor Improvements project.
Environmental Notice: The Project qualifies for a Statutory Exemption pursuant to Section 15301 - Class 1: Existing facilities pursuant to the California Environmental Quality Act State Guidelines.
RECOMMENDATION:
1. Adopt a Resolution awarding a Professional Services Agreement to Nichols Consulting Engineers for final design and preparation of Plans, Specifications, and Estimate and associated services for the Active Transportation Program Cycle 7 Railroad Avenue/Depot Street Corridor Improvements project in a not-to-exceed amount of $790,230; and
2. Authorize the City Manager or designee to execute the agreement.
BACKGROUND:
The City received Active Transportation Program (ATP) Cycle 7 state grant funding for bicycle and pedestrian improvements along approximately 4.1 miles of the Railroad Avenue/Depot Street corridor. Proposed improvements include Class IV separated bikeways, accessible curb ramps, curb extensions, and enhanced pedestrian crossings, consistent with the City’s adopted ATP.
Consultant services are needed to prepare final construction plans, specifications, and an engineer’s estimate in accordance with City standards and applicable Caltrans requirements. The City has filed a CEQA Notice of Exemption for the project and will lead right-of-way certification and related agency coordination, with technical support from Nichols Consulting Engineers (NCE).
2 DISCUSSION:
The City solicited proposals through PlanetBids using a qualifications-based selection process. Three addenda clarified the submission requirements and project scope, with the final proposal deadline established as June 19, 2026. Following consultant selection, staff negotiated the scope and fee with NCE, resulting in revised proposals dated September 11, 2026.
The proposed Agreement includes surveying, existing conditions verification, utility coordination, and preparation of preliminary through final Plans, Specifications, and Estimate (PS&E). Design will address potential drainage, utility, and traffic signal conflicts while refining curb extensions to minimize impacts to existing infrastructure.
Staff recommends awarding the full not-to-exceed amount of $790,230, including optional utility locating and potholing, Caltrans encroachment permit support, bidding and construction-phase design support, and record drawings. These services will be used as needed and directed by the City.
The Engineering Division will manage the Agreement, update the project schedule with NCE, and coordinate with Caltrans regarding grant milestones and any necessary extension requests.
Alternative(s)
The City Council could decline to award the Agreement and direct staff to revise the scope or issue another Request for Proposals. These alternatives are not recommended because they would delay final design and could affect the City’s ability to meet grant delivery milestones.
Fiscal Considerations
The proposed Agreement has a total not-to-exceed amount of $790,230, consisting of $668,370 for base services and $121,860 for optional services. The optional services include:
Utility locating and potholing: $45,130.
Caltrans encroachment permit support: $40,450.
Bidding and construction-phase design support: $26,015. Record drawings/as-built support: $10,265.
The Agreement will be funded through the ATP CMEP PW-04 project account (FD464 | CC1120 | SC7425), with Measure A Alternative Transportation funds supplementing the project account as necessary. These funds support bicycle and pedestrian transportation improvements.
Impact on the Community
The project will improve accessibility and connectivity for people walking and bicycling along the Railroad Avenue/Depot Street corridor. Proposed improvements will shorten 3 pedestrian crossing distances, improve visibility at crossings, upgrade curb ramps, and provide separated bicycle facilities.
Other Agency Review
The project will require coordination with Caltrans regarding grant administration, applicable project delivery requirements, construction allocation, and improvements affecting Main Street/State Route 166. Utility providers and other affected agencies will be consulted as needed during design.
ATTACHMENT(S)
A. Resolution
B. Agreement