Attachment A
RESOLUTION NO.
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF SANTA MARIA, CALIFORNIA
AUTHORIZING THE APPROPRIATION OF ADDITIONAL FUNDING
IN THE AMOUNT OF $301,335.99 FOR THE PINE STREET
SEWER UPGRADES PROJECT, FORMAL BID NO. 2025-05
WHEREAS, on October 21, 2025, the City Council awarded the Pine Street Sewer Upgrades Project, Formal Bid No. 2025-05, to J.F. Will Inc. in the amount of $783,720.47 for construction of a new 460-foot-long, 12-inch diameter gravity sewer in Pine Street between Boone Street and Jones Street; and
WHEREAS, during construction, unforeseen field conditions, including the discovery of unknown utilities, excessive road cave-ins, and an extended project schedule, resulted in additional project costs; and
WHEREAS, construction has been completed, and all invoices from the contractor and project consultants have been submitted, resulting in total project expenditures of $1,675,693.96; and
WHEREAS, the previously approved project funding of $1,374,357.97, in addition to the requested additional funding of $301,335.99, will bring the total available project funding to $1,675,693.96; and
WHEREAS, the additional funding will be appropriated from the Wastewater Enterprise Fund (SC7445|CC0260|FD640) and will be fully funded through sewer rates; and
NOW, THEREFORE, IT IS HEREBY RESOLVED by the City Council of the City of Santa Maria, California, as follows:
SECTION 1. Approves appropriation of additional funding in the amount of $301,335.99 for the Pine Street Sewer Upgrades Project, Formal Bid No. 2025-05, for Fiscal Year 2025-26 in the Wastewater Enterprise Fund (SC7445|CC0260|FD640).
SECTION 2. Authorizes the City Manager or designee to execute any necessary project amendments and future change orders, provided such amendments or change orders are within the scope of the project and consistent with the adopted project budget.
SECTION 3. Authorize the City Manager or designee to execute necessary project amendments to the agreement not to exceed the contingency amount.
Attachment A
SECTION 4. Authorize the Chief Deputy City Clerk to make minor changes herein to address clerical errors, so long as substantial conformance of the intent of this document is maintained. In doing so, the Chief Deputy City Clerk shall consult with the City Manager and City Attorney concerning any changes deemed necessary.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of Santa Maria, California, held this 17th day of November 2026.
ATTEST:
Chief Deputy City Clerk
Mayor
APPROVED AS TO FORM:
_______________________________
City Attorney
APPROVED AS TO CONTENT:
_______________________________
Department Director
_______________________________
City Manager