110 SOUTH PINE STREET, SUITE #221 ● SANTA MARIA, CALIFORNIA 93458 ● 805-925-0951 Ext. 2225

CITY OF SANTA MARIA

PUBLIC WORKS DEPARTMENT
Engineering Division
Attachment B
DEPARTMENT OF PUBLIC WORKS November 17, 2026
Marjie Kirn
Executive Director
Santa Barbara County Association of Governments (SBCAG) 260 N. San Antonio Road, Suite B
Santa Barbara, CA 93110
SUBJECT: CITY OF SANTA MARIA MEASURE A NAMED PROJECT –
REQUEST TO TRANSFER TO US 101 / SR 135 (BROADWAY)

INTERCHANGE PROJECT
The City of Santa Maria requests that SBCAG amend the Measure A Investment Plan and related implementing documents to reallocate all remaining and future Measure A revenues associated with the Highway 101 / McCoy Lane Interchange allocation, less amounts already expended or otherwise unavailable, to Highway 101 / SR 135 (Broadway) Interchange Project.

On November 17, 2026, the Santa Maria City Council adopted Resolution No. [RESOLUTION NUMBER], authorizing the City Manager or designee to submit this request. The Council Agenda Report and resolution are enclosed.

The Measure A Investment Plan identifies the Highway 101 / McCoy Lane Interchange as a North County named project and assigns $10 million in 2010 dollars to the project.

The proposed interchange would connect McCoy Lane to Highway 101 with northbound and southbound on- and off-ramps to improve access for Santa Maria residents and businesses.

SBCAG's 2025 Measure A Strategic Plan estimates the McCoy project cost at approximately $65.7 million and schedules construction for 2032-2035. The plan identifies approximately $14.009 million in total Measure A funding in 2040 dollars, including approximately $80,000 in actual SBCAG administrative costs and $13.929 million forecast for future project costs. We request that SBCAG confirm the amount available for reallocation based on actual expenditures, commitments, and revenue forecasts.

The City proposes to transfer the remaining and future Measure A revenues associated with the McCoy Lane Interchange allocation to the Highway 101 / SR 135 (Broadway) Interchange Project, an existing North County named project within the Measure A Investment Plan. The project would reconstruct the existing interchange to improve traffic operations and safety, provide new access to Highway 101 from the east, and improve pedestrian and bicycle facilities, including connections to the Santa Maria River Trail. SBCAG’s 2025 Measure A Strategic Plan identifies an estimated project 110 SOUTH PINE STREET, SUITE #221 ● SANTA MARIA, CALIFORNIA 93458 ● 805-925-0951 Ext. 2225

CITY OF SANTA MARIA

PUBLIC WORKS DEPARTMENT
Engineering Division
Attachment B
cost of approximately $75.1 million, including approximately $14.0 million in Measure A funding currently allocated without the proposed transfer, with construction scheduled for 2029–2031. Redirecting the McCoy allocation would strengthen the funding available for this established regional priority, reduce reliance on future funding sources, and support delivery of improvements serving Santa Maria and the broader North County transportation network.

We request that SBCAG amend the Measure A Investment Plan allocations for the existing Highway 101 / McCoy Lane Interchange and US 101 / SR 135 (Broadway) Interchange projects to reflect this transfer, with corresponding changes to the Measure A Strategic Plan and Program of Projects. City staff will coordinate with SBCAG on the transferable amount and funding schedule, consistent with the City Council’s authorization.

The City understands that approval of the amendment would remove the transferred funding from the McCoy Lane Interchange allocation. Any future delivery of McCoy Interchange would require restoration or replacement of that funding. The receiving project will remain subject to applicable environmental review, design, right-of-way, permitting, and other project approvals.

Please initiate consideration of this request by the North County Subregional Planning Committee and the SBCAG Board of Directors through the applicable Measure A amendment process. We recognize that the final allocation and timing of funds remain subject to SBCAG approval and available Measure A revenues.

Thank you for considering this request. Please contact Brett Fulgoni, Director of Public Works, at [email protected] or (805)925-0951 x 2225 with any questions.

BRETT FULGONI
Director of Public Works