COUNCIL AGENDA REPORT
TO: Mayor and City Council
FROM: Brett Fulgoni, Director of Public Works
DATE: November 17, 2026
SUBJECT: Adoption of a Resolution Approving Amendment No. 2 to Professional Services Agreement K-PW-2023-052 with Finance DTA for the Growth Mitigation Fee Nexus Study Update Report
Description:
The City Council will consider adopting a Resolution approving Amendment No. 2 to the Professional Services Agreement with Finance DTA to complete additional revisions to the Growth Mitigation Fee Nexus Study, increasing the agreement by $31,144 for a revised total not-to-exceed amount of $131,024 and extending the agreement term.
Environmental Notice: The activity is not a “Project” as defined under Section 15378 of the California Environmental Quality Act State Guidelines; therefore, pursuant to State Guidelines Section 15060(c)(3), no environmental review is required.
RECOMMENDATION:
1. Adopt a Resolution approving Amendment No. 2 to Professional Services Agreement K-PW-2023-052 with Finance DTA for the Growth Mitigation Fee Nexus Study update, increasing the agreement amount by $31,144 for a revised total not-to-exceed amount of $131,024 and extending the agreement term through June 30, 2027; and
2. Authorize the City Manager or designee to execute Amendment No. 2 to the agreement.
BACKGROUND:
The City retained Finance DTA (DTA) under Professional Services Agreement K-PW-2023-052, dated January 15, 2024, following a formal request for proposals process. The original agreement authorized $68,890 to update the City’s Growth Mitigation Fee Nexus Study.
On February 18, 2025, the City Council adopted Resolution No. 2025-28 approving second-quarter amendments to the Fiscal Year 2024-25 budget. Section 4 increased Growth Mitigation Fund appropriations by $150,000 for the Growth Mitigation Program Update.
On October 21, 2025, the City Council adopted Resolution No. 2025-182 approving Amendment No. 1 to the DTA agreement. That amendment added $30,990, increasing 2 the total agreement amount to $99,880, and extended the term through December 31, 2025. The additional services addressed further analysis and public engagement, including evaluation of fees using identified capital improvement project lists.
The City has continued refining the facilities inventory, project costs, and fee methodology. On November 4, 2026, the City provided updated information to DTA for incorporation into the study. DTA subsequently submitted a proposal dated November 9, 2026, identifying the additional work necessary to revise the fee calculations and prepare updated draft and final reports.
DISCUSSION:
Amendment No. 2 will authorize DTA to incorporate the City’s November 4, 2026 facilities inventory and related information into the Growth Mitigation Fee Nexus Study. The updated analysis will use a plan-based methodology for all fee categories except Parks and Recreation. Parks and Recreation will use a standards-based methodology that funds park improvements only.
The additional services include:
Reviewing the facilities and capital improvements needed to serve new development, including the City’s updated facilities inventory and associated cost estimates.
Reviewing and refining cost information, applying inflation adjustments where necessary, and evaluating the relationship between facility costs, mitigation fee revenue, and other funding sources.
Recalculating recommended fees and documenting the methodology supporting each fee category.
Preparing a revised draft report, including updated Appendices A and B, for City staff review.
Incorporating City staff comments and preparing the final report for subsequent City Council consideration.
The proposal addresses City Administration Facilities, Police Facilities, Fire Facilities, Library Facilities, Transportation, Utilities Administration, Parks and Recreation Facilities, Storm Drain Facilities, the Consolidated Corporation Yard, Water Facilities, and Sewer Facilities.
DTA proposes to perform the additional work on an hourly basis, with professional services not to exceed $29,944 and expenses not to exceed $1,200, for a total amendment amount of $31,144. The proposal includes up to two virtual meetings with City staff. Additional meetings, in-person attendance, and other services outside the identified scope may require separate authorization and additional funding. 3 The amendment will establish an agreement expiration date of June 30, 2027 to allow completion of the revised scope and City review.
Approval will allow DTA to complete the additional analysis needed to present the updated study to the City Council. Adoption of the study and any changes to the City’s growth mitigation fees will be considered through a separate Council action.
Alternative(s)
The City Council may decline the amendment or direct staff to revise the scope and return with a modified proposal. Either alternative would delay completion of the updated study.
The Council could also direct staff to procure another consultant; however, a new consultant would need to review the existing work and become familiar with the City’s facilities inventory and fee calculations, potentially increasing both cost and completion time.
Fiscal Considerations
Amendment No. 2 will increase the agreement by $31,144, consisting of $29,944 for professional services and up to $1,200 for expenses. The revised total agreement amount will be $131,024.
The contract amounts are:
Original agreement: $68,890
Amendment No. 1: $30,990
Proposed Amendment No. 2: $31,144
Revised total agreement amount: $131,024
On February 18, 2025, the City Council adopted Resolution No. 2025-28, which increased Growth Mitigation Fund appropriations by $150,000 for the Growth Mitigation Program Update. The revised DTA agreement amount of $131,024 is $18,976 below that appropriation.
Funding for the amendment is proposed to come from previously appropriated Growth Mitigation Program Update funds. No additional appropriation is requested with this action. Before execution, the Director of Finance will confirm that sufficient appropriated funds remain available, including any necessary carryforward of the project appropriation.
Compensation will be based on actual services performed and expenses incurred, subject to the agreement’s payment provisions and not-to-exceed amount. 4 Impact on the Community
The updated study will provide the analytical basis for allocating an appropriate share of growth-related capital facility costs to new development. Incorporating the City’s revised facilities inventory, cost information, and fee methodology will help the Council evaluate future fee levels and support planning for the public infrastructure needed as the community grows.
ATTACHMENT(S)
A. Resolution
B. Amendment No. 2 to Professional Services Agreement K-PW-2023-052 C. City of Santa Maria DIF Update 11-9-26
D. Original Contract, K-PW-2023-052