COUNCIL AGENDA REPORT
TO: Mayor and City Council
FROM: Brett Fulgoni, Director of Public Works
DATE: November 17, 2026
SUBJECT: Adoption of a Resolution Authorizing and Appropriating Additional Funding for the Pine Street Sewer Upgrades Project, Formal Bid No. 2025-05
Description:
The City Council will consider adopting a Resolution authorizing the appropriation of additional funding in the amount of $301,335.99 for the Pine Street Sewer Upgrades Project, Bid No. 2025-05.
Environmental Notice: The activity is not a “Project” as defined under Section 15378 of the California Environmental Quality Act State Guidelines; therefore, pursuant to State Guidelines Section 15060(c)(3) no environmental review is required.
RECOMMENDATION:
1. Adopt a Resolution authorizing the appropriation of additional funding in the amount of $301,335.99 for the Pine Street Sewer Upgrades Project, Bid No. 2025- 05;
2. Approve the additional funding for Fiscal Year 2025-26 in the Wastewater Enterprise Fund (SC7445|CC0260|FD640); and
3. Authorize the City Manager or designee to execute any future amendments or change orders, provided such amendments are within the scope of the project and consistent with the adopted project budget.
BACKGROUND:
On October 21, 2025, the City Council awarded the Pine Street Sewer Upgrades Project, Bid No. 2025-05, to J.F. Will Inc. for $783,720.47, for the construction of a new 460-foot-long, 12-inch diameter gravity sewer in Pine Street between Boone Street and Jones Street. On May 5, 2026, City Council authorized additional funding for the Pine Street Sewer Upgrades Project to complete construction. However, the previous authorized funds were quickly depleted because of issues encountered during construction.
DISCUSSION:
Underground construction for the Pine Street Sewer Upgrades Project has been completed. Additional funding is now necessary to compensate the contractors and project consultants for all work completed. The increased costs are attributable to change 2 orders authorized for additional work required due to unforeseen field conditions, including the discovery of unknown utilities, excessive road cave-ins, and an extended project schedule.
Previously City Council funded the project as detailed below:
Funding Description Amount
CMEP 2022-23 $75,000
CMEP 2023-24 $450,000
Resolution 2025-179 $556,138.97
Resolution 2026-70 $293,219.00
Total Available Budget: $1,374,357.97
Now that construction is done and all invoices from JF Will and the project consultants have been submitted, staff has determined that an additional $301,335.99 is needed to cover all the expenditures. Expenses for the project are as detailed in the table below:
Description Amount
JF Will – Construction $1,281,622.11
Cannon – Inspection Services $182,964.12
Earth Systems – Materials Testing $34,029.50
The Wallace Group –
Designer/Construction Support $90,000.00
Inter Departmental Billing $85,890.63
Misc. Expenses (Printing, Etc.) $1,187.60
Total Project Expenses: $1,675,693.96
Available Budget: $1,374,357.97
Short Fall: $301,335.99
Fiscal Considerations
Staff is requesting an additional appropriation of $301,335.99 from the Wastewater Fund to the project (SC7445|CC0260|FD640|PRJ-00000201). The requested increase will bring the total available project budget to $1,675,693.96. The requested appropriation will be fully funded through existing sewer rates and there is sufficient fund balance available to cover the cost. No General Fund resources are required, and the action remains consistent with the long-term financial planning for the Sewer Fund. 3 Impact on the Community
The community will benefit from the installation of the new gravity sewer in Pine Street between Boone Street and Jones Street, which will increase system capacity and reduce the potential for sewer backups and overflows.