SEVENTH MODIFICATION OF AGREEMENT NUMBER 8153 (CCS)
This Seventh Modification of Agreement Number 8153 (CCS) is made effective this _1...

Jure - 2009, by and between the City of Santa Monica ("City"), a municipal corporation, and Continental Automotive Systems US, Inc. ("Continental"), a Delaware corporation (collectively referred to as "the parties").

WHEREAS the City and Continental entered into Agreement Number 8153 (CCS) ("Original Agreement) on May 30, 2003, for an Advance Fleet Maintenance System.

WHEREAS the parties entered into a First Modification dated on or about June 1, 2004 ("First Modification) to authorize assignment of the Original Agreement from Siemens Transportation Systems to Siemens VDO Automotive Corporation.

WHEREAS the parties entered into a Second Modification dated on or about June 17, 2004 ("Second Modification") to increase the amount of compensation.

WHEREAS the parties entered into a Third Modification dated on or about March 21, 2005 ("Third Modification) to delete certain services and reduce the contract price.

WHEREAS the parties entered into a Fourth Modification dated March 2, 2006 ("Fourth Modification") to delete certain services and reduce the contract price.

WHEREAS the parties entered into a Fifth Modification dated August 11, 2006 ("Fifth Modification") to extend the term and amend the deliverables.

WHEREAS the parties entered into a Sixth Modification dated December 8, 2008 ("Sixth Modification) to memorialize the name change from Siemens VDO Automotive Corporation to Continental Automotive Systems US, Inc.

WHEREAS the Original Agreement, Second Modification, Third Modification, Fourth Modification, Fifth Modification and Sixth Modification are collectively referred to herein as "Agreement"; WHEREAS the City and Continental desire to modify the Agreement to further amend the contract to accurately reflect the agreement of the parties;
NOW THEREFORE, in consideration of the mutual promises herein, the parties agree as follows:

AGREEMENT
A. The contract end date of the Agreement shall be extended to June 30, 2009, exclusive of warranty and maintenance. A copy of the Project Schedule is attached hereto as Exhibit "A" and incorporated herein by this reference. The parties agree this Project Schedule is predicated upon Continental, City of Santa Monica and Big Blue Bus allocating the required resources, assets and facilities as needed and agreed in the attached Project Schedule by and between the parties. The parties acknowledge that any delay in providing the required resources, assets and facilities as referenced in the Project Schedule may cause additional delays to this Project Schedule; B. The parties' Agreement, Deliverables List and Compliance Matrices state Continental will provide Mobile Supervisor. Mobile Supervisor has since been upgraded to Mobile Dispatch. The parties agree the Agreement, Deliverables List and Compliance Matrices shall be amended such that all references to "Mobile Supervisor" are hereafter substituted with "Mobile Dispatch". The Deliverables List has been further modified to list all equipment required to facilitate this change. The City shall be responsible for any ongoing costs associated with this upgrade.

C. Pursuant to the December 29, 2006 Response to System Deployment Specifications, a copy of which is attached hereto as Exhibit "B" and incorporated herein by this reference, it is agreed by the Parties that: (i) the farebox interface functionality shall be delivered and tested during the warranty period, warranty period defined as one (1) year after Final System Acceptance, (i) if the farebox interface

Page 1 of 20 ends

functionality is not delivered and accepted within the one (1) year warranty period, warranty shall continue until such time as the farebox interface functionality is delivered and passes its Acceptance Test Procedure, and (iii) the delay in the delivery of the farebox interface functionality shall not delay or prohibit Final System Acceptance;
D. The Deliverables List reflecting all changes listed herein is attached hereto and incorporated herein as Exhibit "C". All prior Deliverables Lists are deleted and replaced by the attached Exhibit "C".

Changes to the Deliverables List include those named above and also include the following:
a. The delivery of TMDataMart software as provided on page 5 of Attachment C of this Seventh Modification and one (1) TDataMart server (HP Proliant DL380) as provided on page 5 of Attachment C of this Seventh Modification in exchange for deleting the following reports as detailed in RFP Addendum III dated 10-29-01, Section 7.1.3, Reports: Markup Sheet-Pick List, Bus Assignment Sheets, and Public Timetable with Map; b. The reduced number of mobile installations pursuant to the Fourth Modification to the Contract.

E. The parties agree that Continental shall add the performance of Vehicle Acceptance Testing on the fifty-two (52) New Flyer Industries vehicles received by the City from New Flyer Industries on or about April 30, 2005. The Vehicle Acceptance Test shall consist of the Vehicle Acceptance Test procedure previously agreed to and performed by the Parties for the testing of all the vehicles pursuant to Agreement Number 8153. The Parties expressly agree that the fifty-two (52) New Flyer Industries vehicles are outside the scope of Agreement Number 8153 and that the performance of the Vehicle Acceptance Test by Continental on said vehicles shall not be construed as incorporating these fifty- two (52) New Flyer Industries vehicles into Agreement Number 8153 for any purposes or benefits whatsoever including, but not limited to, warranty, maintenance, or materials used in repair of said vehicles. In exchange for performing the Vehicle Acceptance Testing described herein, Continental shall be released from the requirement to provide the interface to the Run Dash Route signs on all City/Big Blue Bus coaches.

F. The parties agree that Continental shall credit the City the sum of Seventy Dollars U.S. ($70.00) each to have the handset cords modified on the one hundred fifty eight (158) vehicles in this Agreement and Continental further agrees to credit the City the sum of Seventy Dollars U.S. ($70.00) each to have the handset cords modified on the fifty two (52) NFl vehicles listed in Paragraph E above, upon written permission from NFl for such modification. The Parties expressly agree that the fifty-two (52) New Flyer Industries vehicles are outside the scope of Agreement Number 8153 and that the used in repair of said vehicles. All of these vehicles currently have a four foot (4) long handset cord which the City desires to be shortened for safety reasons. The four foot (4) long handset cords shall be modified to a length that has yet to be determined by the City. In exchange for providing the City a credit for performing the handset cord modifications described herein, Continental shall be released from the requirement to provide the Street Index by Route Report as set forth in Section 7.1.3 of the Technical Specifications. The change in the total contract value is detailed in Paragraphs R and S of this Seventh Modification.
mant to Content on hero 0 Are are are a man a che
maximum amount of liquidated damages recoverable under this Contract ($97,500.00). With this settlement, the parties agree to delete the liquidated damages provision from Agreement Number 8153 at Section 7.12.2 and acknowledge that no liquidated damages are recoverable under Agreement Number 8153 from this date forward. This settlement will have no negative impact on either party with regard to their obligations under Agreement Number 8153. The change in the total contract value is detailed in Paragraphs R and S of this Seventh Modification.

Page 2 of 20 ends

H. The installation of six (6) TMOnStreet signs shall be removed from the Agreement. The Agreement shall now reflect installation of fourteen (14) TMOnStreet signs. The remaining six (6) TMOnStreet signs shall be spares. The change in the total contract value is detailed in Paragraphs R and S of this Seventh Modification.

The billing milestones shall be amended as shown in Paragraph K per the June 25, 2007 letter from Al Dave, attached hereto as Exhibit "D" and incorporated by this reference. And as shown in Attachment "D", the credit applied to Agreement 8153 pursuant to the Fourth Modification to Agreement Number 8153, dated March 2, 2006, and set forth as Billing Milestone 27.1, shall be applied to Billing Milestones 24, 25, 26, 27, 28, 29, and 29.1. The alteration of these Billing Milestones shall fulfill Continental's credit obligation as previously set forth in Billing Milestone 27.1. Further, pursuant to the June 25, 2007 letter from Al Dave, upon execution of this Amendment, (1) the City shall make full payment on Milestone 25 and fifty percent (50%) payment of Milestone 26; (2) the remaining fifty percent (50%) of Milestone 26 shall be made upon resolution of the NABI bus issues; (3) full payment of Milestone 24 shall be made upon resolution of the Thomas bus issues; (4) full payment of Milestone 27 shall be made upon resolution of the New Flyer issues; and (5) Milestones 29 and 29.1 shall be paid when the TransitMaster™ equipment is installed and functional in the remaining non-revenue vehicles. The issues to be resolved regarding Milestones 24, 27, and fifty percent (50%) of Milestone 26 are as set forth in Attachment E, Billing Milestone Completion Activities. The approval of the • Completion Activities shall not be unreasonably withheld.

J. The four (4) vehicle annunciation kits for the MCI buses shall be deleted. Therefore a total of one hundred fifty four (154) annunciation kits shall be provided and installed, exclusive of spares. The change in the total contract value is detailed in Paragraphs R and S of this Seventh Modification.

K. The four (4) Automatic Passenger Counter kits (APC) for the MCI buses shall be deleted. Therefore a total of one hundred fifty four (154) APC shall be provided and installed. The change in the total contract value is detailed in Paragraphs R and S of this Seventh Modification.

L. The three hundred (300) Vehicle Operator Quick Reference Decals shall be deleted. The change in the total contract value is detailed in Paragraphs R and S of this Seventh Modification.

M. The installation of the TransitMaster™ equipment for Vehicle Number 75 shall be deleted. and the TransitMaster equipment for Vehicle Number 75 shall be added to the spares pool. The change in the total contract value is detailed in Paragraphs R and S of this Seventh Modification.

N. There has been damage to the City's property as shown in the City's invoices numbered 2503A. The change in the total contract value is detailed in Paragraphs R and S of this Seventh Modification.

O. Regarding the deletion of the pricing for the GPRS modem upgrade, the change in the total contract value of -$785, is detailed in Paragraphs R and S of this Seventh Modification.

P. It is agreed by and between the parties that the Mini Fleet Test shall be incorporated into the Final System Acceptance Test.

Q. For clarification purposes only to the Deliverables List, the following changes are agreed:

I. The number of Adtran 8 port Ethernet routers/hubs shall total four (4); II. The number of IVR Gateway Server - Proliant DL 380R03 shall total one (1); Ill. Loquendo software shall be provided as part of the Ontira software suite; IV. The Ontira Hardware package shall also include a quantity of one (1) Mediaform 1000 IVR, which consists of four (4) fxo modules with a total of sixteen (16) ports; V. A quantity of one (1) survey tool kit shall be provided and installed; and VI. The number of Mobile supervisor installation kits and installation of those kits shall total six (6). Mobile supervisor installation kits consist of an IVLU, a laptop computer, mounting hardware, cables, and quantity of two (2) Motorola MCS 2000 radios.

Page 3 of 20 ends

R. Section 5.1 of the Original Agreement and Section 1 of the Second, Third, and Fourth Modifications of Agreement are hereby deleted and replaced with the following:

5.1 Total Contract Amount. City agrees to pay Vendor, and Vendor agrees to accept from City, the sum $5,901,248.25, which includes taxes and fees at the rate in effect as of the date of this Seventh Modification, for the System in the following amounts and in accordance with the following performance milestones set forth in Section 5.1.1 below.

Total after Fourth Mod Total after Fifth Total after Changes New Total Third Fourth Modification CO#5 Per Seventh Per Seventh
Modification Modification Modification Modification
$1,491,963.00 $1,491,963.00 0 $1,491,963.00 $1,491,963.00 $3,222,149.02 ($412,447.00) $2,809,702.02 ($17,225.81) $2,792,476.21 -17,312.00 $2,775,164.21 $1,218,233.42 $45,948.00 $1,264, 181.42 $1,264,181.42 -14,700.00 $1,249,481.42 $0.00 NA $0.00 $0.00
$508,156.46 ($40,286.93) $467,869.53 0 $467,869.53 $467,869.53 $0.00 $0.00
$0.00 $0.00
$0.00 $0.00 $0.00 -97,500.00 ($97,500.00)
($360,100.00)
($360,100.00) ($360,100.00) -1,139.65 ($361,239.65)
$6,080,401.90 ($406,785.93) $5,673,615.97 ($17,225.81) $5,656,390.16 -130,651.65 $5,525,738.51 $407,693.23 ($31,126.34) $376,566.89
$376,566.89 (1,057.16) $375,509.74
$6,488,095.13 ($437,912.27) $6,050,182.86 ($17,225.81) $6,032,957.05 -131,708.81 $5,901,248.25 S. Section 5.1.1 of Agreement Number 8153 entitled "Billing Milestones" is modified to provide for the changes set forth in Paragraph H above. Therefore, Section 5.1.1 of Agreement Number 8153 is hereby deleted and replaced with the following:

Milestone Description MS Billing $
1 Notice to Proceed 310,710.56
2 Vehicle - Survey - (By Vehicle Type: Bus, 186,426.33
Supvs, PS)
3 Site Surveys Complete 124,284.22
4 Approval of Project Plan 186,426.33
5 Fingerprint Logon Design Approval 186,426.33
6 Fingerprint Logon Equipment Delivered to 186,426.33
ILG for FAT
7 Dispatch Center Survey Approval 124,284.22
8 Site Design Approval 186,426.33
Dispatch Equipment Delivered to ILG for 248,568.45
FAT
10 OnStreet Signage Delivered to ILG for FAT 186,426.33 Computer Network Design Approval 124,284.22
12 ATP Approval 186,426.33
Cutover Plan Approval - Brick Building 124,284.22
14 Network Equipment Delivered to ILG for FAT 310,710.56 15 Vehicle - Mechanical Design Approval - (By 186,426.33 Vehicle Type: Bus, Supvs, PS)
16 Dispatch Center Equipment Approval 186,426.33
FAT Approval 186,426.33

Page 4 of 20 ends

18 OnStreet Signage Installed 186,426.33

18.1 OnStreet Signage Installed-CO#7 -2,143.00
19 Prototype Installation - 12 186,426.33
20 Network Equipment Approval 186,426.33

20.1 Contract Mod 1 Addition 77,398.32
GeoCode Routes Complete 186,426.33
Final Prototype Design Approval 186,426.33

22.1 Damage to Property Credit Memo - CO #5 -17,225.81
Damage to Property Credit Memo - CO #7 - 1,139.65
23 Training and Documentation Complete 248,568.45
24 Vehicle Installation - 10 186,426.33

24.1 Contract Mod 7 - Application of Vehicle -53,826.50 Removal Credit (10%)
CO #7 Reduction of 4 Annunciator -3,779.00
Systems
CO #7 Reduction of 4 APC -9,591.00
CO #7 Descope 300 Vehicle Operator -600.00
Quick Reference Decals
CO #7 Delete installation on Vehicle #75 -414.00
25 Vehicle Installation - 60 186,426.33

25.1 Contract Mod 6 - Application of Vehicle -107,653.00 Removal Credit (20%)
26 Vehicle Installation - 60 186,426.33

26.1 Contract Mod 7 - Application of Vehicle -107,653.00 Removal Credit (20%)
27 Vehicle Installation - 60 186,426.33

27.1 Contract Modification 4 (Vehicle Reduction - -538,264.93 52)

27.2 Contract Modification 7 - 27.1 Applied 538,265.00
Across Multiple Milestones to reflect CO 6

27.3 Contract Mod 7 - Application of Vehicle -107,653.00 Removal Credit (20%)
Vehicle Installation Approval 186,426.33

28.1 Contract Mod 7 - Application of Vehicle -80,739.75 Removal Credit (15%)
29 Vehicle Installation - 32 186,426.33

29.1 Contract Modification 4. Vehicle Additions-3 85,531:00

29.2 Contract Mod 7 - Application of Vehicle -80,739.75 Removal Credit (15% of BM 29 Only)

29.3 Contract Modification 7 - Credit for -14,700.00
handset cord length modification and de-
scope Street Index by Route Report
ATP Acceptance 186,426.33

30.1 Liquidated Damages -97,500.00
31 Final System Acceptance 497,137.00

31.1 Contract Mod 3. Antenna Site lease refund -30,000.00

31.2 Contract Mod 3. Antenna site lease credit -71,068.58

Page 5 of 20 ends

31.3 Contract Mod 3. T1 cost refund -110,139.00

31.4 Contract Mod 4. Radio Frequency Change 45,948.00

31.5 Contract Mod 7. GPRS Modem Upgrade -785.00
refund

0.00 Total (W/Out Tax) 5,525,738.51
T. Except as expressly set forth in this Seventh Modification, all other terms and conditions of the Original Agreement, First Modification, Second Modification, Third Modification, Fourth Modification, Fifth Modification, and Sixth Modification shall be and remain in full force and effect.

IN WITNESS WHEREOF, the parties hereto have duly executed this Seventh Modification on the day and year first above written.

CONTINENTAL AUTOMOTIVE SYSTEMS US, INC.

By: By:

Dand Brandom For: Mail
(Signature) (Signature)
Title: General Manager Title: Controller

CITY OF SANTA MONICA
a municipal corporation
Print Name:

Print Name:
-ATTEST:~
sane lo prement
City Clerk
Print Name:

Page 6 of 20 ends

EXHIBIT "A"
Project Schedule
(14 Pages)
Follows this page

Page 7 of 20 ends

Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Duration Start Finish Predecessors Successors Big Blue Bus AFMS Project Otr 1 QK.1
1544 days Mon 6/9/03 Wed 7/1/09
Preliminary Project Functions 183 days Mon 6/9/03 Wed 2/25/04 Notice To Proceed '° days Mon 6/9/03 Mon 6/9/03!
Hold kickoff Meeting Conti Man 6/9/03 Mon 6/9/03
Create Project Plan Conti. 21 days: -Tue 6/10/03! *Tue 7/8703 Submit Pian to BBB for Review Conti 2 days. Wed 7/9/03 Thu 7M0/03 Make Required Changes to Project Schedue "Conti 2 days: Mon 2/3/071 Tue 2/10/04 Conti Submit Project Schedule for Approval Conti Tue 2M0/04Г "Tue 2/10/04 2110 BBB - Schedule Approval 11 days Wed 2/11/04 Wed 272504" AFMS Project Change Orders 1341 days Tue 1/27/04 Fri 5/1/09 11 7 Change Order # 2 Voting" 96 days Tue 15704 Wed 6/9/04 12 v Slemens to Develop and Submit Change Order to BBB Conti 14 days Tue 1727704g Fr 2713704" BBB: Fully Executed Change Order From BBB 7 B9B 82 days: Mon 2/16/04 Wed 6/9/04

14. V Change Order # 3 Lease Resolution 215 days Mon 6/7/04 Tue 4/5/05 15 / Development of Change Order # 3* Cont.BB8". 53 days Von 67/04 Thu 8/19/04 167 BBB Develops, Formalizes, and Submits CO 3 Contract Documentation BBB: 124 days Fr 8/20/04! Tue 2/15/05 Siemens Signs and Retums Chänge Order #3 Documentation Conti "Bdays Wed 2/16/05 Fil 27257051 *BBB Signs and Retums Co#s BBST 30 days Mon 2/28/05 'Tue 4/5/05 Change Order 4 Vehicle Reduction 254 days Fri 7/30/04 Mon 7/25/05 Development of inital iteration of Change Order #4 Cons.3BB" 109 days! FA 7/30/04 Tue 1/4/05 Siemens submits next revision to CO # 4 Conti 1.day | Wed 175/05 Wed 1/5/05 22 BBB Develops, Formalizes, and Submits CO#4 Contract Documentation 60 days Thu 116/05 FH325I05 21 Slemens response and schedule adjustments to Change Order # 4" Conti 10 days Mon 3/28/05 Ex 408/05 Siemens Signs and Retums Change Order 14 Documentation 2i daysT Thu 5/12/05 EH 6/10/05 Signs and Retum 30 days Mon 6713/051 on 725/05
Change order is Schedule Exiension'.- T0 days; Mon 72/061 F тi5470в Change Order i7 Contract Cleanup and Schodule Update 558 days Mon 2/26/071 * 371/09 Santa Monica BBB Review and Submit to S00 177 days! Mon 2126/071 7üe 10/20/07 Development of initial iteration of Change Order # 7 Cont BBB 100 days Tue 10/307071 Mon 3/17/08 Conti, BBB Cond submits nox 100017 "Conti" 31 days 1 Fri 5/9/08 31SS+10 davs BBB Develous Formalizes and Stoms CO7 Contact Documentation *22 days! *Wed 5/44708 Fri 6713/08 305S+10 days 32ss+5 days Contl BBB i Cons response and schodule adjustments to Change Örder # 7 •Cond 14 days Mon 6/30/081 FA 7M8/08 3155+5 days Cond Signs and Retums Change Order # Documentation™ Conti i5 days! Mon 3/30/051 Fr 4/97/09 Conti
BBB Signs and Retums CO#6 88B 64 dave: "Mon 978709 Man 128/08 25 33 3BB Signs and Returns CO#T 6аB 10 days 33,34 592.591,593 Trapaze Subsystems 1502 days Mon 6/9/03 Fri 514/09
Contracts Signed & Notico to Proceed 65 days; Mon 6/9/03

EX Implementation 1121 days Tuo 9/30/03 Fri 511/09
EX-Operational Review 102 days Tue 9/30/03 63,51
Operational Review Meetings with BBB BBB Trapeze 1 day: Tue 930/03: Te 930/03 44,41 Customized Components 18 days Wed 1M404 F 20/04
Prepare Technical Specifications for Paddle Report BBB, Trapeze" a Wed 1/14/04 LBBB,Trapeze
Continental Proprietary Information
Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Duration Start Finish Predecessors Successors 2008
Prepare specification for customized run gulde BB8.Trapeze 1 day Fri 2/8/04 Frl 2/6/04 BBB,Trapeze Cost Routines 3 days Wed 10/1/03 Mon 10/6/03
Roview & Documeni Custom Costing Rules (Union Contract and Past Pracices" BBB 3 days! Wed 10/1/03 Fi 10/3/03 İ BB provides documentation of Bick, Run and Roster numbering rules 3 days Wed 10/1/03 Fri 10/3/03:

Review and Document of Custom Rules ö days Mon 10/8/03 Mon 10/6/03 Update Implementation Plans & Operational Review 5 days* Wed 10/22/03 Tue 10/28/03 1 BBB Review of Final Operational Review, implementation Pian and Project Plan Doc: 8 days Thu 2/12/04 Man 2i23704' Milestone - Acceptance of Imptementation Plan, Operatonal Review and Project Piar BBB 2 days: Tue 2/24/04 'Wed 2725/04 Data Development 794 days Wed 11/26/03 Tue 1/16/070
Data conversion sta ö days Wed 11726703* Wed 11/26/03
Data Load at Trapeze • *FI1212/03 'Frl 12/12/03
BBB GIS Dela converted at Trapeze 5 days Wed 11/26/03 Thu 12/4/03 B88 Porforms Data Entry for Vehide Go-Live Data Mode 30 days. Mon 1/3/05 Fri 2/11/05 Slemens Supplies TransitMaster Merge SW for Go-Live Merge (PATCH) Cont: Prl 2/18/05 Pr 2/18/051 Siemens /BB8 Complete TransitMaster. Data Merge for Go-Live" 0.5 days" Mon 2/21/051 Mon 2721/05 BBS Validates Accuracy of Schedule Data Merged into TraneltMaster" 28 days -Tue 5/31/05 "Fa 7/805 Siemens Validatos FX Data Ready for Trapexe Info Agent Cont 14 days Mon 2/74/05 Thu 3/3/05 Siemens Validatos PX Data Ready for Trapeze into Web ™ *Conb. 14 days Mon 2/14/05 The 373705 Slemens Validates PX Dala Ready for Ontira IVR 14 dayst Mon 0/25/06 Thu 10/12/051 413 Milestone - B8B Map and Data available for Installation''' 60 days F 10/12/06 Tue 1/16/07 18 Customization and Report Development 1404 days F10/22/03 Frl 5/1/09 Costing Routine™ 173.7 days Pr 1716/04 Mon 9/20/04
Costing routne development and revisions 108 days E746/041 Milestone - BBB Acceptance of Costing Routine BBB 14 days Mon 62404 Mon 9/20/04 Customized Reports 7204 days Thu 10/23/03 Fri 8/1/09
Package 1 Report Customizations. 229 days Thu 10/23/03 Frl 9/17/04 Paddie reports developed and tested 164 days Thu 10/23/031 Wed 6/16/044 Paddle reports tested by customer B8B Thu 517/04° FT 6018/04 Driver Paddie accepted 888 6i days F B18/04 Fr 917/047
Customized nin guide developed and tested 59 days Thu 5/13/04 Customized run guide tested by oustomet BBB 2 days!
Run guide accented 88B 8à days Fris si17704
1318 days! Thu 2/26/04 Fri 5M/09T
Cont Validates Remaining Report Requirements with Trapeze "884 days Mon 1/10/05: EN 6/20/08T Trapeze to Provide (Conti to provide per CO #7) 1165 days Mon 1014104 Headways 665 daysi Mon 1074/04 Wed 51607
79 TEH Provide Mileage data by route by block by day 233 days 98,80 Conti Review Mileage Report & Provide Foodback B9B 3 days Mon 4/20/09 EN 4/24/09 Complete Final Modifications to Mileage Report Mon 4/27709 Operator block schedule 488 days T Thu 6/9/05 Wed 5/16/073 7655120 Operators route guides 528 dan wed 4M2/05
Bus stop list by route 528 days: Wed 4193/05 Wed 5/16/07 Continontal Proprietary informaton Pase 2
Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Duration Predecessors 2000 2008 528 days: Wed 4/13/55 Wed 5/16/071
Trapeze(103%] 528 days "Wed 4/13705 Wed 5/16/07 (103%)
Trapeze(103%) 528 days Wed 4/13/051 Wed 5/16/07
6o days Mon 5/12/08 Tue B/5/08
miles e* Trapeze(106%),Conti 58 days Mon 5/12/08 Fr B/1/08 [106%1,Conti Trapeze 60 days Mon 5/12/08 Tue Biste
190 days Wed S/17/06 Thu 2/15/07
Trapeze(102%] 150 days Wed 7/i2/08 Thu 2/15/07
of mop colors Trapeze 190 days Wed 5/17/08 Thu 2715707' Not Avalable 421 days Thu 2/26/04 Fri 10/14/05
i21 days! Thu 2/26/04 Fri 10/14/05 |
150 days Thu 3/17/05 Fri 10/14/051
150 days Thu 3/17/05 Fn 10/14/05
Miles BBB. 1 day Mon 4/20/09 Mon 4/20/09 BBB
installation 3 days Mon 11/24/03* Wed 11/26/03
Hardware Trapeze 1 day: Mon 11/24/03 Mon 11/24/03
Trapeze S Trapoze" Wed 11726/03
Milestone Trapaze 0, days! Wed 11726/03 Wed 11/26/03
Troking & Data Development™ 138 days Mon 12/1/03 Wed 6/18/04 BB9 Training 1: Ancilary Data, Route Definition, & Trip Büliding BBB.Trapeze 5 days Mon 12/1703". Fr 12/6/03 Milestone - Roule Dotiniton Training Complote " BB8,Trapeze* 0 days Fa 12/5/03T FA 12/5/031 BBB Data Development (Ancillary Data, Route Definition, & Thip Building) BBB 17 days Man 12/8/03 Fri 1/2/04 BBB Training 2: Manual Blocking, Deadheads, Manual Runcutting & Travels B88 Trapeze* 5 days Mon 1/5/04 Fri 1/9/04 12,108,109 BBB Data Development (Manuaf Blocking, Deadheads, Manual Runcutting & Travel? BBBT 5 days Mon 1/12/04 = 716/04 115 BBB Training 3: "Automatic Blocking and Automatic Runcuting BBB.Trapeze 5 days Mon 1/19/04 *Fr1230 8BB 4: User training for route tracing, pottom trading, and schedule system notes 8BB.Trapezo 5 days! Mon 3/8/04 Er 3/1204 BBB date development (route trading, pattem trading, and schedule syslem notes) 45 dave Mon 3/15/04" Wed 6/16/041 Miesione - Automatic Blocking, Runcutting & Rostoring Trahing Complete FA 3/18/04 FA 3/5/041 BB8 Training: Report Generation and Tropeze System Administration Trapeze, B38 "2 days: "Thu 1715/04: * 1716/04 Milestone - Report Generation and Trapeze System Admin Training Complete Trapeze,BBB Fr10/0t Fri 1/16/04 113 115 V Consulting 980 day Mon 1174704 *Fri 8/20/08
" Efficiently Üsing Run-Cutting BBB,Trapeze,Conti 5 days? Mon 111/041 Fri 11/5i04 Five remaining consulting days - Push to end of Project BB8. Trapeze Cons: Wed 1/20/09 Milestone Consuluna Complete... 3BB Trpozo,Conti" 6 days #M 829/08 System Functional.... 584 days
Parallel Operations - System Test MISSED BBB.Trapeze: '20 days 747/041* Milestone - BBB Acceptance of System Test MISSED *BBB *1 day Mon 621704 Mon 6/21/04" Milestone - Component Closeout for FX REPLACES MISSED ACCEPYANCE BBB Trapeze, Conti 0 days *Thu 10/12/06: Thu 10/12/06 58.59.60,61 Trapeze FX-MON Interface to TransitMaster 343 days Thu 3/25/04 Mon 7/25/05 Operational Revion 038 Trapeze Cont Wed 422/04 Wor 421/04 Software Installation 1 day Non 7/49/04 Mon 7/19/04 126FS+13 mons System Administration Training Trapeze 2 days F: 72205 Mon 7/25/05 125FS+13 mons Continental Proprietary Information Page 3
Frl 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Duration Start Finish Predecessors Successors 2000 at 1 Qtr1
Data development (data cleanup for AVL purposes) Trapeze,B8B 115 days: Thu 3/25/04! Fri 9/3/04 : 28FS+11 mons Trapeze FX-MON to TransitMaster Interface Validaton Conti• "i day Thu 7/14/05 "Thu 7/14/05 127FS+11mons 129 7 VR Real-ime Interface Trapeze INFO-MON 1189 days Wed 4/21/04 Tue 12/16/08 Operational Review*' Öntra Ned 4/21/04 Wed 4/21/04
Siemens develops initial interface rgmts to source system Cont 60 days Thu 422704" FA7/16/04] Siemens develops interface code between TransitMaster and iNFO-MON 138 days Tue 4/19/05 ! Tue 1171/05 Conti and BBB validates fully functioning interface "96 days Thu 7/31/08 Tue 12/16/09 Conti,BBB Ontra ViR implementation 1431 days Wed 11/12/03
'''"SITE EVALUATION & SYSTEM SPECIFICATION" 83 days "Wed 11/12/03 Fr 3112704 Travel to Site - Evaluation 0 days Wed 11/12/03 Wed 11/12/03* S.... 1 day! Wed 11/12/03 142,138,139, 140,141
Review telephone requirements Wed 11/12/03
Review facilitos and network requirements Thu 11/13703
Finalize hardware installaton pian Thu 11/13/031
Review, implementation schedule Thu 11/13/03
Finalize Systom implementation Specificaton (SIS 10 days! Fr 11714/03 37. 138 139 140, 141 "Siemens Sign-Off SIS Conti 5 days Mon 3/8/04 7A2
"PROCURE VR HAROWARE/SOFTWARE 42 days Tue 12/9/03
Siemens procure IVR Server (VXL Gateway), ship to Onfra™ 15 days t Fr 12712/03 143 Ontra procure Media Server, VoiceGenle Hardware/software 9 days Two 12/9/03 43 Hardware Purchases - Logic Cards " 0 days 146
Ontra installs VXML platform and iVR Application software on server 10 days The 127704 Development of Flow Chart 1014 days Fl 130/04
Ontra provides sample how chart" i day Fr 1/30/04
BBB provides exsting flowchart of ACO Tue 2710/04
Ontra Develops Initial Flowchart ..... 8 deys Wed 2/11/04 150, 131 § does Mon 9/18/06
BaB sions off final VR fowchort 1 day Mon 9125/06 1531+10 mons.243.310.308 888 Sumbits. Undate Flowchart for Ontira Review 888 200 days 156,18289,312SS 10 days
Onóra Voice Genle "Gateway 5 days Mon 246/04
BBB - Secure City Aporoval 5 days Mon 246/04
INSTALLATION IVR SYSTEM 48 days Wed 51404
Öntro ships Media Server to Simmens 3 days Wed 2404
Siemens integrates media server into computer rack 1 day:

B86 provides VR IP address for servor connection BB฿ 5 days Mon 279/04 Slemens contracts with Subcontractor to make cable puit 5 daysi Mon 2/18/04 Subcontractor to pull s0 cable pas.. Thu 2/10/041
BBB provides and terminates 16 Analog fines from PBX i day T 2126/04 BBB makes croasconnects from PBX to new cable pairs 3 days Siemens delivers computor rack with media server to BBB 102460 15859.171 170.172 175.174 1 day Mcn 3/1/04: i9.170.171.172 173.174
Continental Prondetary Informaton Paco 4
Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Duration Start Finish Predecessors Successors Otr Ot 1 Oir 1
Ontira to rack mount VR server in BBB provided cabinet Onfica 5 days Mon 3/1/04: FRi 315/041 167,168 Ontra makes crossconnects from new cable pairs to RJ14 panel Ontira 5 days Mon 3/1/04 Fri.3/5/04: 168,167 Siemens instatis Media Server rack in BBB Computer Room Conti : 5 days Mon 3/1/04 Fri 3/5/04 167.168 Siemens connects Media Server and IVR Server via B3B provided switch Conti 5 days Mon 3/1/04: Fri 3/5/04 167.168 BBS provides VPN and SSH for remote access support BBB 3 days Wed 3/3/04! Fri 3/5/04 167.168 Ontira test platform, LAN connectivity and telephone service 27 days Thu 3/4/04- Fil 4/9764 167,168 Trapeze INFO-IVR to Ontira interface implementaton 4 days Wed 5/12/04 Мол 5/17/04 Procure/setup hardware Conti Wed 5/12/04! Wed 5/12/04
Trapeze INFO-IVR Sottware instaltation Trapeze" 3 days Thu 5/13/04 Mon 5/17/04 Replace IP Gear Gateway and install AudioCades Mer 16 port analog FO Önürai 22 days Thu 6/12/097 Mon 7/14/08! 170 integrate with Claco VOiP Network Ontra 43 days Tue 4/29/08 Fri 6/27/08 ! i opine 180 BUSLINE CUSTOMIZATION 575 days Fri 3/30/07 * The 6/30/092 181 / BBB provides other info content, eg. Fanes, service. BBB(0%] '''3 days Wed 4/23/08 Pr 4/25/08 T BBB10%) BBB Submits Fareset. Service changes to Ondira BBB: 200 days #n 3/30/07? Thu 1/3/081 BBB 183/ Ontire changes Faresets, Services and provides update to BBB 10 days Fr 174/08! Thu 1/17/08 " 182" Ontira 184 Ontina customizes voiceXL acripts Englich & Spanish Ontira.BBB(25%1" 100 days Wed 4716/08 Fri 875/08 18,Ontira, BB8125%1 Ontra Tests IVR and Performs QA™ 5 doys Mon 9/8/09T *Fri 8/127081 Resolution of defects detected during OA Si days" Wed 12/16/08! #n 2127709:

Recove Integration issuas with B8B telephony environment Tue 10728/08:1 Fri 3127109| Flowchart Sign-off O days Fa 417/09 = 4/17/091
FX-Fix Producton Flags' 888 0 days Fri 497/09 Fi 4117/097 191 AVL. Test Data Avaliable Continental, Trapeze 224/09 Er 494/09 Transfors Tasue Resolved Ontima: 10 days Mon 5/4/09 FA 5715/091 System Online and Testable Ontira. •O deys
Factory Testing § days!* Tue 5/26/09 Mon 6/1/09
Provide 8B8 Recording Talent Phrases Ontin. daya Frl 4/3/09 Fr 4/3/09 Spanish Recordings 21 daye Mon 4:20/09 Mon 5/18/09
Translate System into Spanish BB8! 5 days Mon 4/20/09 FA 424/09 Export Spanish Phrases. Ontira. 1 day Mon 4127/09 Mon 4/27/091 Complete Spanish Recordings BBB! 15 days Tuo 4/28/09 Mon S718/09 Complete All Recordines 15 days Mon 4/20/09"
200 E Follow up Training Ontira, BBB: i day Mon 6/8/09 Mon 68m9 201 Re-Work Contingency
202 Customer Acceptanco Tosting 5 days: Mon Bieros Pr 8/12/09 Re-Work Contingency "3 days Mon 6/15/09 Wed 6/17/09
O days Wed 6/17/09 Wed 644709
System Acceptance BBB 9 days "Thu 6/18/09t Tue 6/30/09| Continental Proprietary Information Pace's
Fri 4117/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Duration Start Finish Predece [2000 Transit Data Load 9 days Wed 4/23/08 Mon 5/5/08
Siemens provides updated city geocode data 1 day Wed 4/23/08 Wed 4123/081 213,217,218 Siemens provides geocoded neighborhood data Conti 4 days Thu 4/24/08 Tue 4120/08 Siemens provides gecooded landmark net Conti 5 days Wed 4/23/08 Tue 4/29/08 217,218 Ontra gets recent stops and schedules from INFO server Ontira 3 days! Wed 4/23708 Fr 4/25/08 216,217,218 B8B validates stops and schedule list BBB 3 days Mon 4/28/08 Wed 4/30/081 215 * 217,218 Öndra inserts data into XTIS IVR database 2 days Thu 5/1/08 - Fri 5/2/08 212,214,215.216 1,88 Öntira inserts data Into TiS Schedule Cache Ondira: "3 days Thu 5/1/08 Mon 5/5/08 1*212 214215216 Validato Annotations 74 days " Mon 7/21/08 Fri 10/31/08% Add and Update Unerances Tó days" Fri 7i25/08 M Fri 10/31/08 BBB validates street names BBB 70 days: Fri 7/25/08 Fri 16/31/091 "BeB validates street types BB8 TÖ days: #i 125/08 Fri 10/31/08 *BBB valtdates street prefixes (orientations) B88T 70 days Fr 7/25/08 Fr 10/31/08 B88* 7ô days: Fri 725/08 710151709
BBB vaedates landmark names BBB 70 days F6 72508 Fi 10/31708 BB8 validates routes and directions ВBB! 70 days FA 725/08 FA 10/31108 Ontra incorporates utterance changes Ôntira 1 day Wed 4723/08 Ist Round Recordings 1 day Wed 4/23/081 Wed 4/23/08
BBB Provide English Voice Files 88B 1 day Wed 4/23/08 Wed 4/23/08 'Ontra Approve English Voice Files Öntira 1 day Wed 4123708 BBB Provide Spanish Volce Fles 1 day Wed 4/23/08" Wed 423708 Öntira Approve Spanish Voice Files 1 day Wed 4/23/68 Wed 4/23/08 2nd Round Recordinos ™ 10 days Mon 5/12/08 Fri 5/23/08
Onöra integrates voiceXML with Trapeze Interface Ontra Cont 10 do m Mon 5/12/08 = 522708 SPEECH CREATION NOTE RECOROING WiTransliMester DUP *2 days Wad 4123/08 Thu 4/24/08 Ontra provides IVR prompt phrases to bo recorded 2 days Wed 452708 = 45408 TRAINING 2 days F12008 Wed 4/30/08
TransitMaster Systoms 1544 days Mon 6/903: Wed 7/1/09
(SDS) TransitMaster System Desin/Deptoyment Specifications 661 days Mon 6/7/04 Mon 1/15/07 Submit Initial Version of SOS Volumes Cont i day- Mon 6/7/04 Mon 677/04 Develop and Submit SEns Conti 125 daws Wed 4/6/05 'Fri 9730/05 Cont 2 days!
36 dayst
77 days Wed 830/05
888-SDS Volumes Final Agproval BOR 15 deys: Mon 12/18/06 Network / Radio / Dispatch Center Engineering 225 A 1 Tue 6/10/031 Mon 4/26/04 Complete Network Survene.

Complete Network Design & Drawings 36 days Tue7/45/03 Ta 972/03 Review Network Design with BBB BBB "7 day Wed 9/10/03 Wed 9/10/03 Obtain Design Approval o days Wed 9/10/03 Wed 9/10/03
Decatch Center Desion Document Mon 4126/041 Mon 4/28/04 Vehicle Prototype Engineering 66 days Mon 6/16/03 Mon 9/15/03 Continental Proprietary Inforialon Paos 6
Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Rosource Names Duration Start Finish Predecessors 12000 Otr
261 Complete Vehicle Surveys Conti 9 days Mon 6/16/03 Thu 6/26/031 262 v Complete Preliminary Vehicle Designs & Drawings "Cont! 'S0 days Fri 6/27/03 Thu 914/03 Review Preliminäry Vehicle Designs with BBB " i day Wed 8/10/03 Wed 9/10/03 | BBE 264 J Complete Modifications to Vehicle Designs 2 days Thu 9/11/03: Fri 9/12/03 265 / "Obtain Preliminary Vehicle Design Approval" 1 day Mon 9/15/03 Mon 8/15/03 identify Equip Installation by ID# for Non-Rov Vonices 1 day Mon 9/15/03 Mon 9/15/03 OnStreet Customer Information Signs 1368 days Tue 1/20/04: Wed 6/3/09.3 dontity OnStreet Locations (14) 19 days Tue 1/20/047 Frl 2/13/041 Complete Site Surveys (updaled to Indicated 2nd survey) 50 days Mon 2/16/04 Provide BBB with Sample OnStreet Mounting Designs Drawings Sonti 30 days Mon 4/26/04 Mon 6/7/04 g 271 Delivery of OnStreet Signs for FAT Canti! 1 day Thu 3/4/04 Thu 3/4/04:

Slemens to Provide Throughput Analysis of OnStreet Signs 1"day* Wed 6/29/05 Wed 6/29/05 Siemens to provide updated recommendation for OnStreet Implementation Conti 10 days Wed 8/31/05 Wed 9/14/057 274/ BBB allows access to the sites for subcontractor site review B8B 341 days Mon 11/27/06 Tue 3/25/08 275 7 Siemens constructs initial drawings and submits to BBB for city review 297 days Thu 3/1/07 Fri 4/18/08 City Reviews inlial "drawings"" 34 days Mon 4/21/08 Frt 6/6/08 277. 3 Cond submits final drawings to suboontractor for eng stamp 1 day Mon 6/9/08 Mon 6/9708 276/ Conti obtains Eng Stamp. 6 days FA 7/19/08 Er 7725/08 279 279 Conti resubmits drawings to city 1 day Mon 7/28/08 Mon 7/28/08 280 280 City revlows drawings and provides approval to Conti 5 days Too 729/08 Mon B4708 281V Permits Obbined 9 days Tue 8/5/08 f Fri B/15/08
282 Quallty and Select Construction Contractors) 20 ca 7ue9/27/551 Mon 1024/05 283 Ship OnStreet Signage to property 30 days Mon 9/4/06 284/ BBB - Siemens Preinstuf! Revlow 1 day FA 222/08 Mon 225708 28578 Final Wiring and Installation of OnStreet Signage (14) 276 days Тие 245/08 446,447 Installation @ UCLA (2) 145/08 Wed 4M6/08
2877 installaton Rimpau (4) 254 days
286/ Procure Mounts and Brackets 25 days Fr 5721087 290FF 291 289 TEr Verify OnStreet Network in Workine Proporty Conti 15 days Mon 3/23/08 Fr 4/10/09 290FF Wire & Test Signs" B8B 10 dave Mon 4/13/09 EN 424/09 288FF 259FF 201FS+5 days. 291 E Install Signs at Rimpau Conti, Fluoresco, 38B 3 deys Mon 5/4/09 Wed 5/6/08 289,290FS+5 days Conti.Fluoresco, BBB Tost Rimpau Schedule Adherence Cont: 388 2 dame Thu 570e! "E 5/8/09 301FS+2 days cbntl.BBB 293 installation @ Downtown Transit Mall (8) 205 days Mon 7128108 Fri 5122/09 Complete February Shakeup™ 1 day 289
205/ Procure Mounting Hardware & Enclosures 45 days Mon 7/28/08 Ten 920/08 278: 296552978+10 days 1.BBB Wire and Tost Sians 45 days Mon 3/9/091 295S$
297e install Signs at DT Transit Mati Locations Fluoresco 54 đays Tue 3/10/09 295FS+10 days 306 Complete Shelter Design Mods Based on RF Test Results 19 days Tue 310/09 Fri 4/3/09 209.3001 299 Obtain Design Approval from city of Santa Monica 5 days Procure Materials for Antenna Mounts 20 days Fa 6/1/09
301 m Shetter 1: 200 Block of Broadway between 2nd and 3rd street Fluoresco, BBB.Conti Mon 5/18/09 Mon 5/48/09 oresco, BBB.Conti 302 Sheiter 2: 300 Block of Broadway Between 3rd and 4th street, in front of Fluorosco.BB5 Conti Tue 5/19/09 Tue 5/19/09 303FS+1 day horesco, BBB.Conti the Active Fitness Store on Broadway
Continental Proprietary Information
Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Duration Finish Predecessors Successors 2000 303 Qr 1
Shefter 3: 300 Black of Santa Monica Between 3rd and 4th street, shelter Fluoresco, 888 Conti 1 day Thu 5/21/09 Thu 5/21/09: 302FS+1 day 304 doresco, BBB,Conti faces South and is front of the Jamba Juice
304 Shelter 4: 400 Block of Santa Monica Between 4th and Sin streets Fluoresco,BB8,Conti 1. day Fri 5/22/09 Fri 6/22/09 'BOs oresco,BBB,Conti ÖnStreet Sign Subsystem Testing Cont.B88 2 days' Tue 5/26109 Wed Si27/097 304° 306,564FS+1 day OnStreet Sign Application Instalation Approval and Sign off" 5 days Thu 5/28/09* Wed 6/3/09 305,297 584 Transit aster and Ontira Studio Speech Recordings 801 days: Wed 3/10/04 Thu 5/3/07 BBB - Identify and Submit Ontra and Transitiaster Recordings Words List 888 5 days; Tue 6/29/04 Tuo 7/6/04 154,323 BBB - Recording Studio Selection BB8 13 days Wed 3/10/04: Frl 3/26/04 310 BBB - Studio Recording Sessions TranslMaster & Ontira English/ Spanish Coni B8B? 16 days Tue 6/29/04 Wed 7/21/04 309,154 BB8 - convert wave file format for TransitMaster and Onüra Use BB8 2 days Thu 7/22/04 Fri 7/23/04 310! 888 - Review Wave Flles for Updatos ***** BB8* 25 days "Pr 3/30/07 Thu 5/3/07 TransitMaster Map Data 102 days Thu 9/11/03 Fri 2/8/04
BBB - Provide Applicable Map Data BBB 60 days *Thu 9711403 Frl 12/5/031 Convert Map Data to TM Format™ 25 days Mon 1/5/04 Fri 2/6/04 TranaltMaster Route and Schedule Data 150 days Wed 3/24/04: Fri 10/22/041 '''Install equipment in 2 survey vehicles™ '2 days! *Thu 6/3/04 Fr 6/4/04 BBB Schedule data preparaton at stop love for route surveys "62 days Wed 3/24/04 Fr 6/18/04 " TransitMaster Route Surveys 30 days! Mon 9/13/04 Fo 10/22/04 318,367 Complete schedute data proparation for Septomber shakeup 25 days • Fri 6/4/04 Fri 710704 Cedar Rapids Factory Acceptance Tesung 119 days 'Tue 10/28/05 #r 4/16/04 -EAT Database Preparation 82 days Tue 10/28/03 Wed 2/25/04 Submit Database Preparation Document to B8B 11120/09 Thu 1120/03 33B complete and send database preparation document. B8B "82 days Tue 10/28/03 Wed 2/25104 Order/Buld Vehicle BusIno Ecument Conti 30 days Mon 2/16/04 Setup intecraton Lab for the FAT *
-* SetupStage Network Equipmont 5 days FA 3/26/04
Setup/Stage Radio Equipment' 5 days Mon 3/22/04
Setup/Stage Oispatch Equipment Mon 3722/04 Fri 3/28/04
Instali TransitMaster 17.1 Software on BBB Computers 110313 1 day Mon 2/22/04 Mon 322/04
Tue 3/23/04 Tue 3123/04 68 8
FAT Dry Run Testing 3 days Wed 3124/04 = 326/04
BBB- advise Scimens who will attend FAT in Codar Rapids 371204 Er 3i12/04 Slemens to Conduct FAT 6 days Mon 4/5/04 Fr 40/04
BSB. Submit FAT Summary Results to Slemens § days Mon 4/12/041 Fr 4/16/04 TransMaster Fixed Site Network Radio 7 Dispatch Systems 307,8 days Mon 6/9/03 Fri 8/20/04 Order Fixed Site Equipment 63 days! Mon 12/15/03 Mon 3/15/04 151.8 days Tue 1/20/04 Fri 820/04
Accoss Point Installation" Conti Mon 12804 Wed 1128/02
Obtain Access Point Antonna Permits 124,3 days: Tue 1/20/04 F820/04 1 day Mon 5/10/04 Mon 5/10/04
Containe PiX remall Conti 1 day Tue 5/11/04 Tue 5/11/04 343 7 DGPS Installation 3 days Te 5141/04 Thu 5/13/04
347/ DGPS Installaton Conti 3 days Fe 514704
Contental Proprietary Information Pogo a
Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Duration Start
Predecessors Successors
Otr 1
TransitMaster Network 12 days Mon 5/3/04 Tue 5/18/04
'Ship Network Equipment to BBB Conti • 5 days Mon 5/3/04 Fri 5/7/04 " Install Network Equipment at BBB Conti 5 days Mon 5/10/04 Fri 5/14/04 BBB Acceptance of Network installation 2 days Mon 5/17/04 Tue 5/18/04 TransitMaster Radio 240 days Mon 6/9/03 Fri SM 4/04
Validate Radio Tower Site Environmentals Conti,BBB 12 days "Mon 1126/041 Tue 2/10/04 Conti '5 days Mon 5/3/04 Fri 517/04 352
Install Redio Equipment al BiB Conti s days! Man 5/10/04 Fri 5/14/04:

BBB Acceptance of Radio Installation 2 days Mon 8/9/03 | Tue 6/10/03 TransitMaster Dispat ....... 68.2 daya Tue 2/24104 Fri 528/04 Dispatch Center Design Decision - Joint Cont,BBB: ö days Mon 3/29/04 Fr 4204 358 Determine 7 Finalize / Order / Deliver Fumiture B88 49 days Tue 2/24/041 Frl 5/28/04 57 "Ship Diepatch Equipment to BBB Conti 5 days Mon 5/5/04 Frl 5/7/04 358* "instali Dispatch Equipment at BBB Cont: 5 days! Mon 5/10/04 Frt 5/14/04 159 install and configure BBB ovned Badger alarm workstation BB8.Conti" 1 day Mon 5/17/041 Mon 5/17/04 BBB Acceptance of Dispatch Installation BBB 2 days Tue 5/18/04: Wed 5/19/041 TransitMaster Vehicle and Dispatch Systoms 1345 days Wed 5/90/04* Mon 6/22/09 Vehice Prototypes installation 73 days Wed 3/10/04 Mon 6/21/04 Post Survey MDT Mount Fli Check Conti 1 day Wed 3/10/02 Wed 3/10/04 *BBS - Approval of MOT Mount for NABl, Thomas, Now Flyer, MCI BBB 1 day! T3104 Thu 3/11/041 :Vehicle Equipment Production at Siemens Faciity 5 days? Mon 5H004 Fri 5/14/04 Ship Equipment from Siomons Warehouse to Installer 5 days Mon S/17/04 Fri 5121/04 Rocolive Vehicle Eouipment at installer Cont *T day Mon 522004 Mon 5124/04 368,317,319 Install Prototypes Equipment in Vehices Conti 16 days Tue 5/25/04 Tue 6/15/04 Edit (Red Line) Engineering Doca & Drawings 2 days Wed G716/04 Thu 6/17/04 370 372 *BBS - Prototype Installation Approval ВвВ: 2 days! Fr 6/18/04 Mon 6121/04 Revenue Vehicles Installotion 747 days: Fri 6/18/04 Mon 5128/07 Croate Final BOM (Bill of Materials) Conti: 2 days! Fn 619/04 Mon 6121/04 375 г Vehicle Equipment Producson at Slemens Conti 58 da Mon e121704 374/ Stage, Kit & Ship Equipment # 748/04
375 / instait Vehicle Equipment 3X Per Day Conti T Mon 81204 21028702 BBB-ATP Vehide Equipment 3X Per Day B887 Mon 5128/07
Non-Revenue Vehicle Insolation does not indude CO"E 4 vehicles) 1092 days Mon 2/14/05 Fri 5/28/09 378/ 'Drawing Approval... BBB Mon Mans Mon 2/14/051
379 5 7 Drawing Release to Producen 2 days Tue 2/15/05 Wed 2116705:

Equipment and Kit Production Cons 75 days Thu 297/05 50705| 381/ Equipment and Kit Shipment to Santa Monica™ "4 days! Mon 5/30/05 382 / Deinstall second radio from Tal 1 day Mon 10/31/05 Mo 10/5105 BBB - ATP Vehicle Equipment (Including Last Police Car) 496 days 3761 384v Nor-Revenue Vehicle install (from CO # 4) 374 days Mon 740705t Mon 12/2407 Complation of Drawines 7 days Mon 7/10/06 Tue 7/48/05
Drawings Released to Producion and Parts Ordered 25 days Wed 7/19/06 Tue 822/05 Continental Proprietary Information Pace 9.

Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Rescurce Names Duration Start Finish Predecessors 12000 Cables Built and Shipped to BB8 5 days Wed 8/23/06 Tue 8/29/06 386 388 Equipment installation and Testing 5 days Wed 8/30/06 Tue 9/5/06 B88 - ATP Vehicle Equipment 50 days Tue 10/16/07 Mon 12/24/07:

Farebox System Single Point of Login 802 days Thu 6/10/04 Fri 8/3/07 Vehicle Systems Final ATP for Installation Approval 1005 days Wed 7/6/05 Mon 6/22/09 Resolve Vehicle Issues Conti 75 days* Tue 5/29/07! Mon 9/10/071 376 403SS Provide Document Regarding Contractually Disputed items 150 days The 5129/07 Mon 12/24/07 404 Final Revenue Vehicie Installadon Approval and Signiff'** BBB 5 days Tue 6/16/09 - Mön 6/22/091 595.405 Final Non-Revenue Vehicle Installation Approval and Signoff *7 days Mon 8i4/081 Tư812/08 Transister-ve / 79 days Wed 7/8/05 Tue 10/25/05
TransitMaster Software Release 23.1 Software Development and Deployment 946 daya Wed 12/8/04 Mon 8/18/081 *Fingerprint login application development and testing 260 days: Wed 12/8/04 Fri 12/9/05 411./ Trapeze INFO-MON to TransitMaster development and testing 260 days Wed 12/8/04: Fri 12/0/05 412 / **Morge Process Testng 150 days Fri 1/18/08 Mon 8/18/08 Reloase 192 installation *6 days: 'Sun 9/17/06 Fr 9/22/06 | 410,411FS+1 mon Realtime feature testng 1 day"* Men 925/08 "Mon $/2s/06" Fingerprint locin functional testing 2 days Man 92s06 026106 413 Fingörprint login training and data loading Cont.888 30 days Wed 9/27/06 415.413 208 days Mon 3/31/08 Fri 1/30/09
Load TM 23.1 on Test Server 5 days! Mon 351/08 Frl 414/08 alTM 23.1 Test Server at BBB 23 daya* Mon 477708 Wed 5/7/08 418 Evaluate TM 23.1 in Tost Environment B88 10 days Mon 10/26/08 FA 10/31/08 419 Obtein Initial Go Ahead for T 231 Launch 5 days t Mon 10/20/08 Fr 10/24/08 4205$ Verify Bud and Applicaton Fixes Conti 5 days Mon 10/27/08 Fa 10/31/08 42055+6 days Solo Sauna Reports in Test Environment Cond 3881 Mon 10127/081 EN 1031/09 42033+5 days Tum Up TM 23.1 in Production Environment "Conti 7 days!* Fet 11/44/081 Mon 11/24/59 421,422.4237 205 assssi day Obtain TM 23.1 Signoff Cont 888 | 10 days
Tan Master BBB Training 1397 days Mon 6/9/03 Mon 11/24/08 Create a Training Ptan Conti Mon 3/1/04 Mon 3/9/04
Submit Training Plant wal 5 days Mon 3/1/04 Fil 3/5704
BBS Review Preilminary Training Pian 5 days Mon 4/12/04 # 416704 Make Edits to the Training Plan Cond: Thu 5220104 Tue 6104 Submit Final Training Plan Cont: Wed 62104
BB8. Amoval for Final Training Plan 888: 5 days:

Shod a Semens Busino Training Simulator 5 days:

Pra Fixed Rome Vehicle Operator Trainer Training 10000
Mon 8/23/041
Provide Non-Revenue Vehicle Operator Trainer Training Tue 8/24/04 Tue 824/04 Provide Route Management Training Wed 8/25/04:

Provide Fixed Route Workstation Operations Training 1 (Group A) Мол 9143/04 1 1o 9/12/04 Provide Fixed Route Workstation Operations Training i (Group B) Te 9794/04 rovide Configuration Management Training We oriend Wed Era stor Studio Training Thu 9/16/04 Thu 9/16/04
Continental Proprietary Information Peoe 10
Frl 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name
Resource Names Duration Start Successors
Provide System Administration Training (2 Days) Qin 1
Conti 2 days Wed 10/13/04 Thu 10/14/04
Provide Dispatch Refresh Training (3 days) Conti 3 days Mon 8/29/05 Wed 8/31/05 Provide Fixed Rolo Workstation Operations Training i (Grous A) (1 day) Cont 1 day Wed 10/26/0s Wed 10/26/05:

Provide Fixed Route Workstation Operations Training 1 (Group B) (1 day) Cont 1 day Thu 10/27/05 Thu 10/27/05 Provide Fixed Site Equipment Maintenance Training (iday) Conti 1 day Wed 6/1/05 Wed 6/1/05 *Provide Traveler Information Training (112 day) Conti 0.5 days Mon 11/6/06 Mon 11/8/061 Provide Customer Service Training (112 day) Conti: 0.5 days Mon 11/B/06 Mon 11/8/06% Provide Vehice Equipment Maintenance Training (3 days) Conti 3 days Mon 4/11/05 Wed 4/13/05! Dispatch Refresher Training - Catch-Up (112 day) Conti ö.5 days Mon 9/26/05 Mon 9/26/05 408S$ Provide Reports Training (1 day) Conti 1 day Mon 12/11/06 Mon 12/11/06 401FS-22 days Provide Fixed Route Workstation Operations Training IT (2 day) Cont 5 days: Mon 3/13706 Fri 3717/06 7:8- Provide Fixed Route Workstation Operations Training Til (5 day) Conti 1 day Mon 9/18/06 Mon 0/98/06 Provide Advanced Route Training (1/2 day) Conti: ö.5 days Mon 12/11/06 Mon 12/11/06 *491FS-22 days Provide Advanced Configuration Management Traning (172 day) Conti 0.5 days Mon 12/11/061 Mon 12/11/06 491FS-22 days Provide Follow-on Training (4 - 5 days) - To occur after TM 23.1 is deployed Conti 5 days Man 11/17/08 Fri 11/21/08 424SS+1 day Provide Fingerprint Logon Training (2 days) 2 days Mon 6/9/03 Tue 6/10/031 BB8. Training Signori 1 day: Man 11/24/06™ Mon 11/24/08 Cutover Plan For Move (Old Admin Bidg Cutovor) 138 days; Wed 919704: Tue 3/15/05 459- Review As-Built infrastructure Design 20 days Wad 9m/04 Wed 9128/04 Jointy Develop System Cutover Pian Cont 8BB 6 days = 7050704 FA 11/5/04 Submit Cutover Plan for Approval Man 178/04 Mon 11/8/041 162 / Cutover Plan Reviow and Plan Adjustments Cont B83 80 days Thu 3/3/05 Cutover Plan Final Approval BBB 10 days En 374/05 Tue 3/15/05 465,579 Dispatch and Radio Cutover to Old Admin Bullding 6 days" Wed 3/16/05 Tue 3/22/05 Teet Ti Lines at Old Admin Bullding™ 1 day Wed 3/16/05 Wed 3/16/05 467 Conduct Radio Sysiom Tests'" Tue 3/2205 T222/05
Conduct TransitMaster Dispatch Equipment Tests 1 day Tue 3/22/05 468 EMS Proud System Acceptanco Test Plan 522 days Mon 1122/07 Thu 2/5/09 469 "Develop initial Draft of the ATP' Cont 50 davs Mon 1/22/07 5 2720707 470./ Conti i day** Mon 42/07
471/ BiBB Review and Submit Adjustments to Siemens BBB! 20 days 472 Cont SYS ATP Adjustments and Submit to 8BB Conti 122 days 473 / BBB- Sys ATP Approval 988 30 days: Thu 2/5/09
Whoo/Chair Modifications™ 177 days Thu 8/7/08 Pr 4124709" 4751 Desic Cyde Counter Integration Solution 177 days! 'thu B77/08 476 1 Deploy Prototype Sclutions (Nabl, Thomas; Novas) 46 devs! "Thu 877/08 F10M0/08 477 Procure Materials Conti Mon 10r13/08 * 10508
478 | 5 Install Wheelchair Cyde Count Soluton 100 d1 T174081 F: 41709 479 Obtain Signoff from BBB & Update Vehicle ATP Conti BBB! 5 days 1420/09 5454709 480 Passenger Counter Validator ..... 243 days Tue 6r2408$ "Mon 6/15/09 481 Petem Hardware Validation 106 days "Tue 6/24/08 Thu 11/20/08 Validate Hardwaro Validation 2 davei 112409
Continental Proprietary Information Paoe 11
Fri 4/17:09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Duration Start Finish Predece: [2008 483 Otr 1
Perform Third Party Valldation BBB 39 days Mon 4/13/09 Frl 6/5/09 484 Perform Phase 1 Testing (First bus set) 10 daya Mon 4/13709'* Fri 4/24/09 485 Perform Phase 2 Testing (First bus set) 9 days Tue 5/26/09 Fri 8/5/09 86FF+5 days 486 Perform DB Validation Cont,BB3 9 days Tue 6/2/09 48SFF+5 days BB8
Obtain BBB Sübsystem Acceptance BBB i day Mon 6/15/09 Mon 6/15/09 - '486.425" AFMS Pioject Systems Acceptance 72 days Mon 3/23/09 Wed 7/1/09 499 1 Perform System ATP Test Cons.BBB 65 days Mon 3123/09 Mon 6/22/09 490SS+5 days Punch List Resolution 80 days Mon 3/30/09 Von 6122/09! * 489SS+5 days System ATP Sian OH 888 5 days Tuö 8/23/09" on 61201097 490 ! days,589,118,596,492 Commence Warranty Period Conil O days Wed 7/1/09 Wed 7/1/09 iNFO-Agent Implementation 1123 days Wed 4121/04 Thu 9/11/08 /Operational Review**.'. 33 days Wed 4/21/04 Mon 6/7/04 1 day Wed 4/21/04 Wed 4121/64
Review Systom and Current Operation i day! Thu 4/22/04 Thu 4122/04 Update Implementaton Plans and Oporatonal Review 1 day: # 423/04 # 42304 BB8 Review of Final Öperatonal Review, implementation Plan and Project Plan Documer™ BBR 1 day -M 64/04 Fri B/4/04! 'Milestone - Acceptanco of implementation Pian, Operatonal Review and Project Pian Dor!" Mon 6r7i04 Mon 6/7/04 Data. Devolopment 3 days Thu 6/24/04
Seccode initial Computerized Data Tue 6222/04
Data Load Suparvision Wed G/23/04 Wed 6723/041
303 Milestono - BBB Data avallable TBрA02i The 624/04
504* Customnizations Development (Placohcider) 345 days Fri 7/1/05 Wed 11/8/08 Customizations* "day Frt 771705 Fr 7/1/051
Milestone - Customtzations completed 1 day Tue 7/5/051 Tue 7/6/053 in-house Customization Tosting 1 day Mon 11/6/061 Mon 11/606 888 i dayt "Tue 117706* To 11/7706
Milestone - BB8 Approves Customizations Wed 1178/06 Wed 1178/06 5105 Software and Database instalfaton ¡ day* Mon 9/12/05 Database and Trapeze Software Installation Mon 9/12/05 Mon 9/12/05 Training & Data Development 281.15 days Wad 9i405 Mon 10/23/06 BeB Training 9 days Wed 9714/05 Mon 9/26/05
514 // Sustem Administraton Training Wed 9/14/05 Wad 97i4/05 Training: System Parameter Training (Parameters, Security, Transfer Creation) BBB. Trapeze" TU 9/45/05 Wod 9121/05 516 V 8BB Report Writer Training i'days:
517 07 Milestone - System Parameter, BBB Training Complete i•Mon 9/26/05 Mon 5728/05 518 BBB Data Development 281.15 days Wed 9/14/05: Mon 10/23/06 Plea Tronsters on Bus Sions • 3 days Wed 8/14/05 Fri 9/16/05 Transfer Dato Develooment B9B 3 deys Wed 9114/05
521 Wed 9/44/05 FA 9416/05
522 / Pattern Destination Signs 3 days:
523/ Milestone - Data Development Complete TraDeze BeB" 20 days Wed 9/17/05 Mon 10723/06 Trap
System Fun.. Tue 9127705" Thu 9/11/08
Continental Proprietary Information Page 12
Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Duration Start Finish Predecessors Successors 2000.

Go live support BBB,Trapeze Tue 9/27/05 Tue 9/27/05 512 52695,542 526 Parallel Operations - 30-Day Agent App System Test 22 days Tue 9/27/05 Wed 10/26/05 327 Milestone - BBB Acceptance of System Test "1 day Thu 10/27/05 Thu 10/27/05 $34,528 BBB Operational with Info-Agent 1 day Fri 10/28/05 Fri 10/28/05 'Trapeze Fixes 459 days Mon 11/27/06 Wed 9/10/08 534,412 Correction of Items by Trapeze 15 days Mon 11/27106 En 12/16/06 Installation and Testing in Test Environment Trapeze 55 days Man 2/5/07 Fr 4120/07 Testing of Trapeze Version" 22 days Tue 8/5/08 Thu 9/4/08 531,559 installation of new Trapeze version (live) Trapeze " 4 days Fr 9/5/08: Wed 8/10/08 Milestone - Component Closeout 1 day Thu 9/11/08"1 Thu 9/11/08 527,529 BBB,Cont INFO-Web Implementation 1145 days Wed 4/21/04 Mon 10/13/08* Operaticnal Review 33 days Wed 4121/04 Mon 6/7/04
537/ BBE - Operational Review Meetings with BB$ 3 days Wed 4721/043 Fr 4123/041 538 i Update implementation Plans and Operational Review 1 day Mon 4/26/64T Mon 4/26/047 539 M 8BB - Review of Final Operatonal Roview, Implementation Plan and Project Plan Docum 5 days FF 5/28/54" Fr 874704", $40 J Milestone - Acceptance of Implementation Plan, Operational Revlow and Project Plan Dot 88B 1 day Mon 6/7/04 1 Mon 6/7/04 541- Software Installation" 737 days Wed 9i28/05 Mon B/18/08 542 / Software Install 736 days Wed 9r28/051 in 8715/08 543 V Milestone - installaton of Tropeze Software (Binaries/Map/Date) Trapeze 1. day. Mon 8/18/08* Mon 8/18/08 548.542 S4S 551 541/ Training & Data Development 1 day Fr 9/30/05 Fri 9/30/05 BBB Training: System Administrator Training: 1 day! Er 9130/05 Fi 930/051 546 7 Milestone - System Administrator Training Complete 0 davs A 930/05 F93005 0/30 547/ System integration 350 daws Mon 10/17/05 Fri 3/9/07 5487 City web deloper review of webpages 8B8 50 бву» 1 171707 a 2007 549,543 549/ Hook into Wob Design, Work with ISP (Web Consulting) 10 days Tr 10728/05 551 550 System Functional 3a days Thu 9/19/08f Mon 10/13/08 351/ Parallel Operations - 30 Day Web App Svstem Test 22 days Thu 9/11/08 T FR 10/10/08 5527 / Milestone - BBB Acceptance of INFO-WEB and Component Closeout" BBS, Trapeze, Conti" 1 day Mon 10/13/08 Mon 10/13/08 Tranere Conti 553 INFO-MON implementation (Derok & Andrew) 349 dave Mon 1128/087 Tus 0116/09 554 7 Instati INFO-MON Server Hardware BBB.Cont: 1 day: Mon 1/28/081 Mon 1/28/08 5557 instali iNFÖ-MON on BBB test site Trapeze 1 day To 1/20108 Tue 1129/08 556 Confaure Siemons Server B88.Cont 1 day: T299/08
557 J Data Stream From BBB 088 Cont Ô days Tie 2119/08 + 290708 55811 DATessing ........ 170 days:

Install sofiware, configure and test on BBB production server BBB,Trapeze, Conti ¡ day" Tue 12/16/08 560 System Admin Training w/ Trapeze 1 day: Wed 12M7/0฿ Wed 12/17/08 561 "User Training" BBB.Trapeze 2 days! Thu 12/18/08 Fr 12/99/08 Acceptance Testina 888 Mon 1002108
Remedate and Tort BBB.Trapeze 4 days To 12231081 Mon 1/5/09 Man BAEMO 30558160y
Go-Lve Support for Info Web (Ön Site) Trapeze 2 days Tue 8/16/09 AFMS Project Billing Milestones 1542 days Mon 6/9/03 Mon 6/29/0g Continental Proprietary Information Pace 13
Fri 4/17/09
Santa Monica BBB AFMS Project Schedule
Fri 4/17/09
Task Name Resource Names Durallon Start Finish Predec 2008 1 Notice to Proceed 1 day. Mon 6/9/03 Mon 6/9/03 Conti
2 Vehicle - Survey - (By Vehicle Type: Bus. BBB.Cond 1 day Mon 6/9/03 " Mon 6/5/03 3 Site Surveys Complete BB8,Conti T day Mon 6/9/03 Mon 6/9/03:
570 4 Approval of Project Pian BB8. Conti i day Wed 2/18/04 Wed 2/18/04! 5 Fingerprint Logon Desigh Approval #BB,Conti 1 day Thu 4/8/04 'The 4/8704". 6 Fingerprint Logon Equip Dellvered to iLG for FAT 1 day Mon 3/29/04* Mon 3/29/04! * Dispatch Center Survey Approval BB8.Cont" i day Mon 4/$/04: Mon 4/5/047 & Site Design Approval ... BB8 Conti: 1 day "Mon 6/9/03 Mon 6/9/03 9 Dispatch Equipment Delivered to ILG for FAT 3B8,Conti 1 day Mon 3/29/04 g Mon 3/29/04 326 TO Onstreet Signage Delivered to iLGfor FAT Fri 3i5/04 Fri 3/5/04 | f1 Computer Network Design Approval BB8.Cond 1 day Man 6/9/03 Mon 6/9/03 12 ATP Approval BBB,Cons" 0 days Fil 4/17/09 F Fri 4/17/09 417 13 Cutover Plan Approval - Brick Building 888.Cont 1 day Wed 3/16/05: Wed 3/16/05 14 Network Equipment Dellvered to ILG for FAT BB8,Cont" i day Mon 3/29/04 Mon. 3/29/04 15 Vehicle - Mechanical Design Approval - (By Vehicle Type: Bus, Supvs, PS) BB8.Conti 1 day i Tue 6/22/047 Tue 6/22/04 LIll 16 Despatch Center Equipment Approval BB8,Cont 1 day Thu 5/20704 Thu 5/20/041 17 FAT Approval BBB Cont 1 day Fri 4/23/04 Fr 4/23/04
18 OnStreet Signage Instated BBB.Conti O days Wed e2/09 695 19 Prototype Installaton - 12' 888 Conti 1 day Tue 6/22/04. ввв, 20 Network Equipment Approval B88 Cont 1 day Wed 5/18/041 Wed 3115/04 BBB,Cont 51 GooCode Routes Come B88 Cod Fi 10/29/047 So 10/29/04: BBB,Cont TRA 22 Final Prototype Design Approval 1 day To 6n00 To 622/02 BBB.Contl 589 25 Training and Documentation Completo B9B:Cont Ô days? Mon 820709 Man 629/081 24 Vehide Installation - 10" BBB.Cont O days
25 Vehico installation - 60 BB8,Cont 0 davs "En 5/1/09 * 5/1709 | 26 Vehide installation - 60" 0 days Fd 5/1/09 Fil 5/1/09 27 Vehide Instaltation - 60 ADJUST TO CO #4* 889 Cont O days F 5/1709 •Fil 579/09 28 Vehice Instalfation Approval 888 Conti o days Mon 6/22/09: Mon 6/22/09 29 Vohide Installatlon-35 BB8 Co Ö days Mon 6/22/00 Man 6/22/09 *30 ATP Acceptance Mon 82009
31 Final System Acceptance O days Man 6129/09
Continental Proprielary Informafen Pace 14
EXHIBIT "B"
December 29, 2006
Response to System Deployment Specifications
(2 Pages)
December 29, 2005
Mir, Jason Wibben
Project Manager
Siemens VDO Corporation
5285 Rockwell Drive N,E.

Cedar Rapids, IA 52402
Re: Contract No. 8153 for Advanced Fleet Management System Subject: Response to System Deployment Specifications - Final Changes Dear Mr. Wibben,
The City of Santa Monica (City") has rovlewed Slemens VDO Corporation (Siemens" Jetter entitleci *System Deployment Specifications - Final Changes" dated December 8, 2006.

The City underslands that Siemens is not able to conduct the section of the Vehice Acceptance Test Procedure ("ATP*) related to the farebox interface at this time due to the interface functionality still being in development. It is also understood that this functionality will be delivered during the warranty period of the contract and that the City will remain in the warranty phase for a perlod of one year from Final System Acceptance or until such time as the functionality Is delivered.

Testing of the remalning sections of the Vehicle ATP can be undertaken at this time. Completion of the lesling of the farebox interface portion of the ATP will be accomplished once the functionality is delivered.

The ATP remalns the one outstanding appendix to the System Design Specification ("SDS") to be delivered. As this veraion of the ATP is acceptable to both the City and Slemens, thle version of the document will be incorporated into the SDS thereby completing the content of the SDS. The City will now conduct one further review of the SDS prior to accepting the submission.

Sincerely,
Golin Probert
Transit Systems Analyst
CC: Stephanle Negritt
Joe Stitcher
Jory Wolf

Page 8 of 20 ends

Big Shue Bus
1660 Seventh Street
Santa Monica, Califomia 90404-2521

FIRST GLASS
Nir. Jason Wibuen
Siemens VDO Corporation
5265 Rockwell Drive N.E.

Cedar Rapids, IA 52402
DEd02tO1A-eS cÖas halsstadedlnskbdallonbddnet-Mmaldr
EXHIBIT "C"
Deliverables List
(7 pages)
Deliverables List

CITY OF SANTA MONICA
Deliverables List
AMENDED (Change Order #7)
Description Quantities
FIXED NETWORK:

Fixed Network - Computer & Network Hardware
Cisco 2651
Domain Controller - Proliant DL380R03
Domain Controller
Transitivaster™* Database Server - Proliant ML570T01
TransitMaster™ Database Server
Dispatch Workstation - Dual Capable - Dell Precision 350 Dell Flat Screen 21* Monitors
Application Server - Proliant DL3B0R03
Application Server
Differential Station (DGPS)
Operation Workstation - Dell Precision 350
HP Laser Printers
Cisco 2950 12 Switch
Compag Server Rack w/ KVM & LCD Monitor
Omni Card Swipe UNA
Siemens ID Mouse Pro
Temporary Furniture - Chair, Desk & Installation
Permanent Furniture - Chair, Desk & Installation
Cisco 26004 Port Etheret Module NM-4E
Radio Consoles
TMDataMart Server - Proliant DL380
TMDataMart Server - Proliant DL380 at at us to
TMIDCenter Server - Proliant DL$20
TMIDCenter Server - Proliant DL320 1
TiMobileDispatch Server - Proliant DL360
TMiMobileDispatch Server - Proliant DL360 * 79
Adtran 8 port Ethernet
Fixed Network - Software
1 154
Rapeze rApicior Sofiare ludes 80 Hours For Custom Reports 2 1 Trapeze INFO Was Stilare und and
1 Jeritas Backup Sottware - Executive Full Versior
/eritas Backup Software - Executive Client Versio
Continental Automofive Systems US, Inc, PROPRIETARY and COMPETITION Sensilive Information 1 of 7 2/16/2069

Page 10 of 20 ends

Deliverables List

CITY OF SANTA MONICA
Deliverables List
AMENDED (Change Order #7)
Description Quantities
/eritas Backup Software - Executive SQL Server Ager
/aritas Backup Software - Executive Open File Agen
TransitMaster Services (Software Sulte);
MDMA - Responsible for all communications between mobile vehicles and the Dispatch.

Coordinates vehicia polling, siot assignments, message queuing by priority, and reassembling multi- packet messages.

TRouter - Roules all internal message tralc pecullar to an agency.

MCG/MAR - Multi Channel Controller/ Multi Agency Router. This application is a dual purpose application and is the heart of the communications suite. The MCG Is responsible for managing loading of all Redo Network Controllers (RNC's) in the system and MCalc - Manages real time data and service requests that do not require user intervention.

TMDGPS - Receives GPS time from the GPS Base Station for distribution to all machines running the TMDGPS service,
DGPSTime - Receives GPS time and updates system time on the hast computer.

TSummary - Summarizes the daily database and performs online anelyticel processing necessary for report generation.

TWorkAssignments - Manages routing of vehicle messages to the assigned dispatcher and ensures that a vehicie will always be assigned to a dispatcher.

TMHostLogon - NT Based service to validate user security rights for the TransitMaster suite of applicallons.

FTManager - FT Manager is a GUl based application to manage scheduled upload and download of data files belween FTP server and the vehicle feel.

TransitMaster Applications (Software Sulte Continued);
TMBusops - TMBusOps is a centralized control application that provides the dispatcher with voice communications control and current vehicie status for all vehicles assigned to a dispatcher.

TMAv! Map - ThAv Map is the sister applications to TMBusOps. TMAvi Map provides the - dispatcher with a graphical-representation of a vehicle's current-location and status.

TMP layback - Provides the ability to graphically replay a given vehicle's aclivities across a selected time period.

TMReports - Provides a user friendly interface for generation of standard reports included standard with the TransitMaster software suite.

TMRouteManager - RouteManager is a data collection and merge application used to create and modify vehicte route files.

MAnnunciator Studio - Provides the ability to record audio annunciations, create graphics and text messages for overhead signs, and interface with Route Manager for the creation of vehicle route files.

Continental Automotive Systems US, Inc. PROPRIETARY and COMPETTON Senaltive Information 2 of 7 2/16/2009

Page 11 of 20 ends

Deliverables List

CITY OF SANTA MONICA
Deliverables List
AMENDED (Change Order #7)
Description Quantities
TMSurvey Tool - ATM Application used to record the GPS latitude and longitude of bus stops and TSurvey Tool also measures distances between bus stops.

Configuration - Central configuration applicalion for the TransitMaster suite of applications.

Transfer - Provides a tabular listing of time points with scheduled time, driver, vehicle, and schedule adherence.

TMPlanter - Uility for vehicle and driver assignment to a route and schedule.

TMincident Reports - A database component of TM BusOps used by dispatchers or maintenance ersonnel to record accidents, maintenance items, ete
Maintenance - Maintenance application to display real time mechanical alarms received fron active vehicles and sef vehicle stalus.

MClientMonitor- Troubleshooting and diagnostics fool for the TransitMaster sulte of applications.

TDMA ServiceViewer - Configuration applet for the MDMA service.

TMEventMonitar - Displays and logs events specific to the TransitMaster suite of applications.

TMService Control - Application to start and stop TrensitMaster services.

TransitMaster Drivers (Software Suite Continued):

Modem Drivers - Interface between the TransitMaster modem and the TDMA service.

TransitMaster Control Panel Applications (Software Suite Continued); TMLogger Control Applet - Configures the TMLogger service.

TMDgps Control Applet - Configures the local DGPSTime Service.

TWebwatch • Realtime Internet Route Information 1
TMArrival - Departure - Realtime public route information display software (Site license) Customized Yard Four Quadrant Map Data
Calatel Camera System Interface
Slemens ID Center Software
S/emens Biometrics ID Center User License (250)
TMDataMart
TM Mobile Dispatch 1
Trapeze Hardware
INFO Server - Proliant DL380R03
INFO Server
Web Server - Proliant DL380R03 1
Web Server 1
Database Server - Proliant ML570T01
Database Server
Rack Parts
Ontira Hardware
IVR Server - Prollant DL3BOROS
IVR Server 1
Continental Automotive Systems US, Inc. PROPRIETARY and COMPETTION Sensitive Information. 3 of T 2/16/2009

Page 12 of 20 ends

Deliverables List

CITY OF SANTA MONICA
Deliverables List
AMENDED (Change Order #7)
Description Quantities
Wireless Local Area Network (WLAN) Infrastructure
WLAN Access Point
WLAN Antenna :

Inatallation Kits

FIXED RADIO
Fixed Radio - Radio Base Stations

RNC UPS
Repeater Racks
Cisco 0766M 4 Port Hub
T Band UHF Base Antenna - Tessco 78031
UHF Multicupler - Tessco 55147
UHF 3 Channel Combiner TXRX
Badger Remote Alarm
TNT Software for Badger Remote Alarm System
UHF Qusntar
Data Quantar
SNMPc Enterprise Network Management Software
Fixed Radio - Radio Network Controller (RNC)
Siemens Radio Network Controller (RNC)
{includes 17" Display, RF and
Network Interfaces, CD ROM, Keyboard, Mouse)
Coaxial Cables
Standard 17" Monitor
Industrial PC NNNAN
Keyboard / Mouse
Siemens Internal Modem (601-1677-002).

Voting Comparators

SPETRA TAC COMPARATOR

TONE KEY MODULE

TONE PRIORITY MODULE NO NO NA
Signal Quailty Module
Emergency Power Kit
Handset, Receiver Test
Monitoring Cable Kit
Command Console Interface
Continental Aufomotive Systems US, Inc, PROPRIETARY and COMPETITION Sensitive Information 4 of 7 2/18/2009

Page 13 of 20 ends

Deliverables List

CITY OF SANTA MONICA
Deliverables List
AMENDED (Change Order #7)
Description Quantities
Manual, SpecTraTac Comparator
Battery Tray for 2 batteries
Console Interface Cable for CommandSTAR Lite
Console Interface I/O Module for CommandSTAR Lite
Local Antenna System
Antenna DB636C
Andrew LDF-6 7/8" Holiax Cable § -
6 Top per 12 Halax
7/8" Ground Kits
NM Connectors for Superflex 1
NM R-Angle Connectors for 1/2" Supertiex 1
PolyPhaser Protector 1
Misc antenna mounting hardware
RX Multicoupler - 4-channel Minimum w/amp. 1
Misc RF cabling 1
Rack Mount Surge Suppression, 1 for bases, 1 for voters 2 Quantar Receivers - Voting Receivers only.

Quanter Receiver
UHF Frequency Band 450-512 MHZ
Conventional Operation
Battery Revert power supply with charger
7' Open Heavy Duty Rack for equipment
On Board Data Storage
Sandisc 128Mb Compact Flash Card. 158
Survey Tool Kit, including Panasonic Toughbook Lap Top Computer (An interface cable and a software application that will be loaded onto a laptop) 12 Surveys Including Labor Included VEHICLE SYSTEM:

Vehlcle - Radio
Mobile Vehicle: - Motorola MSC2000 UHF T Band Model Il, Dash Mount - Fixed Moble Vehicle: - Motorola MSC2000 UHF T Band Model Il, Remote Mount - Maintenance Mobile Vehicle: - Motorola MSC2000 UHF T Band Madel Il, Remote Mount - Supervisor Per Colin this should be 12 radios for 6 vehicles. One radio is used to monitor voice, and one for date.

Mobile Vehicle: - Motorola MSC2000 UHF T Band Model II, Remote Mount - Admin Continental Autonotive Systems US, Inc. PROPRIETARY and COMPETMON Sonsiltve information 5 of 7 2/162009

Page 14 of 20 ends

Deliverables List

CITY OF SANTA MONICA
Deliverables List
AMENDED (Change Order #7)
Description Quantities
Mobile Vehicle: - Motorola MSC2000 UHF T Band Model II, Remote Mount - Police Mobile Vehicle - Motorola MSC 2000 UHF T Band Model It, Remote Mount - Pool (Same as an Admin IVLU and MDT) 1
Vehicle - Portable Radio
Moble Vehicle: - Portable - Motorola XTS 3500 20
Moblie Vehicle: - Portable - Charger - Single Unit 20
Vehicle - Mobile Data Terminal • (MDT)
Mobile Vehicle: MDT - Fixed 158
Mobile Vehicle: MDT - Maintenance 5
Mobile Vehicle: MDT - Supervisor
Mobile Vehicle: MDT - Admin
Mobile Vehlale: MDT - Police
Mobile Vehicle: MDT - Pool
Vehicle - Integrated Vehicle Logia Unit System {IVLUS)
Moblle Vehicle: - Fixed
Mobile Vehicle: - Maintenance
Mobile Vehicle: - Supervisor
Mobile Vehicle: - Admin
Mobile Vehicle: - Police
Mobile Vehicle: - Pool
Vehicle - Base Installation Kits
Mobile Vehicle: Fixed
Mobile Vehicle: Maintenance
Mobile Vehicle: Supervisor
Mobile Vehicle: Admin
Mobile Vehicle: Police
Mobile Vehicle: Pool
Vehicle - Annunciation w/K#
Annunciation Kit 154
Vehicle - Laptop
Panasonic Laptop with modem and mount 7
Dispatch - Headsets
Headset 10
chicle - Passenger Counte
assenger Counte 154
OnStreet™
Continental Automotive Systems US, Inc, PROPRIETARY and COMPETITION Sensitis information 6 of T 2/18/2009

Page 15 of 20 ends

Deliverables List

CITY OF SANTA MONICA
Deliverables List
AMENDED (Change Order #7)
Description Quantities
Beatronic Message Boars
2 Line 20 Char
OnStreet ™ Software Site License
Spares
Mobile Vehicle: MCS2000 UHF T Band Model If, Dash Mount Mobile Vehicle: MSC2000 UHF T Band Model II, Remote Mount Mobile Vehicle: MDT 30
Mobile Vehicle: IVLUS
30 Passenger Counters 25
Panasonic Laptop with modem and mount t
Annunciation Kit 20

DOCUMENTATION
Vehicte Operator Guide (2 per vehicle)
Vehicle Operator Quick Reference Deca
Dispetchers Manual, User Guide
Systems Administration Manual (SAM)
Mobile Equipment Maintenance Manual
Fixed Site Maintenance Manual
Training Plan Document
Project Installation Plan

TRAINING
Bus (formerly termed "vehicle") in a Box (BIAB Training Kit) 2 Maintenance - Hardware & Software 5 years
Continental Automotive Systems US, ha. PROPRIETARY and COMPETION Sensive information 2/16/2009

Page 16 of 20 ends

EXHIBIT "D"
June 25, 2007 Letter from Al Dave
(3 Pages)
City of
Santa Monien
June 25, 2007
Dan Spinks
Director of Project Management
Siemens VDO Corporation
. 5265 Rockwell Drive N.E.

Cedar Rapids, IA 52402
Reference: Contract No. 8153
Subject: Contract Billing Milestones
Dear Mr. Spinks,
The City of Santa Monica (City) has reviewed Siemens proposed modification to the payment amounts related to the vehicle installation milestones due to the credit owed the City as a result of change order #4.

The City finds the proposal, attached here as Exhibit A, acceptable. Please incorporate these changes into change order #6. Once the change order has been processed by both parties, the City will be in a position fo make payment on completed work.

Per our conversation of May 22, 2007, as part of the management meeting held at the Cily, the City will make full payment on milestone #26 and a 50% payment of milestone #26, Both milestones are titled "Vehicle Installation - 60." The City will make the remaining 50% payment for milestone #26 when issues related to the NABI buses are resolved. Similarly, full payment will be made on milestone #24 when issues related to the Thomas buses are resolved and milestone #27 for the 1987 New Flyer bus issues.

Page 17 of 20 ends

A follow up item from the management meeting was a review by the Project Managers of the deliverables and the associated quantities. While that review has been completed, the City has not received any information related to any adjustments that are to be made to the contract. In the event the City is owed a monetary credit, the City reserves the right to review the methodology for determining the amount and for deciding to which payment milestone the credit should be applied.

This information should be forwarded to the City as soon as possible so as to avoid delay in the processing of Change Order #6.

Sincerely,
Sofiware Systems Officer.

Page 18 of 20 ends

Exhibit A
City of Santa Monica
Billing Milestone Credit
To Be Percentage of Billing Milestone
Total Credit Amount
Invoiced BM 27.1 Credit Amount After
Amount Date Appilled Applied Credit
186,428 Jun-07 10% 53,826.50 132,600
188.426 Jun-07 20% 107,653.00 78,773
186,426 Jun-07 20% 107,653.00 78,773
186.426 Jun-07 15% 80,730.75 105,687

86.351 Jun-07 0% 85,351
186,426 Juf-07 20% 107,653.00 76,773
186,426 Sep-07 15% 80,739.75 105,686
186,426 Mar-07 0% 186,426
- 1,390,335001 100% 538,265.00| 852,070

Page 19 of 20 ends

EXHIBIT "E"
Billing Milestone Completion Activities
Vehicle ATP Items List for Billing Milestone Completion Issue Resolved
land Tested/
Approved by Milestone
Vehicle Type ssue Description City Affected
ransitmastart Syster does not shutoff with th
Nabi Yes 26
napier peer avichot clear when the rear door
Nabl pens, as required No 26
leadsigns are not connected to the
Thomas ransitMaster™ system. Yes 24
Wheelchair fit discreet is being trigger based or
the power switch, not on deployment.
24

Page 20 of 20 ends