City Council
Report
City Council Meeting: November 17, 2026
Agenda Item: 4.D
1 of 5
To: Mayor and City Council
From: Christopher Dishlip, Director of Public Works, Engineering Services Division Subject: Approval of First Modification to Agreement #6006 with P2S LP for the Pier South Beach Electrical Service Project
Recommended Action
Staff recommends that the City Council:
1. Adopt a finding of categorical exemption pursuant to Section 15303 (Class 3, New Construction or Conversion of Small Structures) of the California Environmental Quality Act (CEQA) Guidelines; and
2. Authorize the City Manager to execute a first modification to Agreement #6006 in the amount of $305,000 with P2S LP for additional construction management services for the SP2791 Pier South Beach Electrical Service Project for the Public Works Department. This will result in an amended agreement with a new total amount not to exceed $400,000, with future year’s funding contingent on Council budget approval.
Summary
The Los Angeles region is expected to host numerous high-profile sporting, cultural, and entertainment events in the coming years, creating opportunities for Santa Monica to host large gatherings, festivals, fan experiences, and broadcast operations at the Pier and surrounding beach areas. The current reliance on temporary generators for event power creates additional logistical challenges and limits the flexibility to accommodate future events and activations. The Pier South Beach Electrical Service Project (Project) would provide a permanent marine-rated electrical system to support event operations and other future activities in the area. The Project would reduce reliance on temporary generators, improve the reliability of event power, and provide long-term electrical infrastructure to support continued use of the Pier and beach for large-scale events. 2 of 5
The City executed Agreement No. 6006 with P2S LP in an amount not to exceed $95,000 to provide construction management and preliminary design services for Phase 1 of the Project. The original solicitation included services for both Phases 1 and 2, and P2S LP submitted a proposal of approximately $170,000, plus a $30,000 contingency, for a total of $200,000. The City initially authorized $95,000 to expedite the start of design services. Staff recommends authorizing a first modification to Agreement No. 6006 in the amount of $305,000 with P2S LP for additional services for Phases 2 and 3 of the Project. Phase 2 services were included in the original solicitation and proposal, while Phase 3 would address additional electrical infrastructure needs identified following the City's recent agreement for Austria House and anticipated partnerships with other country houses in the south beach parking lots. Phase 2 of the project would complete the design and advance the electrical service south of the Santa Monica Pier into construction, Phase 3 would complete preliminary design and siting for additional electrical service(s) near Beach Parking Lot 4 South. The modification would result in a new total amount not to exceed $400,000.
Discussion
The goal of this Project is to build two or more electrical services for events and activation south of the Pier as soon as feasible. The Project would provide a permanent marine-rated electrical system to support event operations and other future activities in the area. On January 9, 2025, the City issued Request for Qualifications, RFQ #SP1982 (2025) for Construction Management Services for various construction projects and established a prequalified list of 19 firms. On March 26, 2026, the City issued RFP #SP2791 through OpenGov to the 19 prequalified firms for Construction Management Services, including electrical design, for the Pier South Beach Electrical Service Project.
The original RFP included services for both Phases 1 and 2 of the Project. One proposal was received from P2S LP. Based on the firm's experience and technical competence, proposed project team, references, and cost, P2S LP (P2S) was selected as the best qualified firm. P2S submitted a proposal of approximately $170,000, plus a $30,000 contingency, for a total estimated cost of $200,000 for the originally contemplated work.
3 of 5
On July 15, 2026, the City executed Agreement No. 6006 with P2S in an amount not to exceed $95,000 for Construction Management Services for Phase 1 of the Project. The scope of Phase 1 included evaluating the anticipated electrical demand, reviewing the existing electrical infrastructure serving the Pier, developing conceptual electrical planning, providing a preliminary constructability review, and conducting preliminary coordination with Southern California Edison (SCE) for the new electrical service requirements and a connection feed point. Although the original solicitation and the P2S proposal included both Phases 1 and 2, the City initially authorized only Phase 1 services, within the City Manager's approval authority, to expedite the start of design and advance the Project without delaying implementation while seeking City Council authorization for the remaining services.
Staff recommends authorizing a first modification to Agreement No. 6006 for Phase 2 of the construction management services and Phase 3 additional electrical infrastructure planning and design services. The additional services are needed to advance the project from preliminary design into final design and construction. The Phase 2 services were included in the original competitive solicitation and the P2S proposal. Since that time, City Council has directed staff to execute an agreement for Austria House and anticipates partnerships for up to four activations in the south beach parking lots. These developments have increased the anticipated electrical demand and the need for additional permanent electrical services beyond what was initially contemplated. As a result, staff recommends expanding the scope and budget to provide design and construction management services to evaluate and accommodate these additional electrical infrastructure needs, if possible.
The modification would complete the Phase 2 design, construction, provide subsurface investigation, geotechnical evaluation, civil and electrical engineering design, extended SCE coordination, and pre-construction and construction phase support services.
Phase 3 would complete preliminary design and siting for additional electrical service(s) near Beach Parking Lot 4 South and evaluate other feasible locations for electrical services to support upcoming activations. These Phase 3 additional services would 4 of 5
build upon the electrical infrastructure planning and design work already underway and would allow the City to coordinate electrical service requirements with SCE under a single consultant agreement. Continuing with P2S would maintain continuity of design, avoid duplicating preliminary work, and support the timely delivery of the electrical infrastructure needed for upcoming events and country house operations.
The modification would result in a new total amount not to exceed $400,000 including $305,000 for Phase 2 services and Phase 3 expanded electrical infrastructure planning and design services.
.
Environmental Review
This project is categorically exempt from CEQA pursuant to Section 15303 of the CEQA Guidelines. Section 15303 exempts Class 3 (New Construction or Conversion of Small Structures) projects from CEQA, which include electrical and other utility extensions of reasonable length. The project would install a new electrical service and switchgear system at the Pier South Beach area to support future events and other activities, and it has been determined that the project would fall within the Class 3 categorical exemption. Furthermore, none of the exceptions to categorical exemptions set forth in the CEQA Guidelines, Section 15300.2 would preclude the use of this exemption.
Financial Impacts and Budget Actions
Staff seeks authority to approve available funding from the General Fund to increase the amount of agreement with P2S LP for construction management services.
Agreement Modification Request
Agreement
#
Current
Authorized
Amount
FY 2026-27
Request
Amount
CIP Account # Total Revised
Contract Amount
6006 $95,000.00 $305,000 C0109310.689000 $400,000
Future year funding is contingent on Council budget approval. 5 of 5
Prepared By: Matthew Hoffman, Civil Engineering Associate Approved Forwarded to Council
Attachments:
A. X - Levine_Act_Disclosure_Form_P2S_LP
B. X - Oaks_Initiative_Disclosure_Form_P2S_LP_revised 05.19.2026 C. 00 EXECUTED_CT6006_SP2791_-_PSA_-