To: Mayor and City Council
From: Aileen Reynolds, Director, Housing and Human Services Department Subject: Authorization for City Manager to Negotiate and Execute a Housing Trust Funds Bridge Loan to Community Corporation of Santa Monica to Address Cost Overruns for the Property Located at 1342 Berkeley Street Recommended Action:
Staff recommends that the City Council:
1. Adopt a finding of categorical exemption pursuant to Section 15301 (Existing Facilities) and a finding of no possibility of significant effect pursuant to Section 15061(b)(3) (Common Sense Exemption) of the California Environmental Quality Act (CEQA) Guidelines
2. Authorize the City Manager to negotiate and execute a Housing Trust Funds bridge loan to Community Corporation of Santa Monica (CCSM) in an amount not to exceed $450,000 to address cost overruns on the Berkeley Station development, located at 1342 Berkeley Street.
Executive Summary
Berkeley Station, located at 1342 Berkeley Street, is a 100% affordable housing development comprised of 13 one-bedroom apartments and opened in March 2026.
Community Corporation of Santa Monica (CCSM) constructed the development with an $11.3 million Housing Trust Funds loan from the City. In addition, CCSM also obtained grant funding totaling around $1.07 million from the United Way and the California Community Foundation to further support development of the Berkeley Station project.
Following an unresolved billing dispute between CCSM and Howard CDM (HCDM), the general contractor on the project, HCDM filed a foreclosure lawsuit and a mechanic’s lien on title seeking payment for approximately $1.3 million in amounts owed per contract, and another $658,000 in disputed time extension change orders. 2 of 6
Subcontractors who worked on the project have also filed mechanic’s liens on title for the Berkeley Station project.
Given the dispute, the City has met with both CCSM and HCDM. Through those discussion, both CCSM and HCDM have agreed, in concept, on settlement terms, which would include acceptance of a negotiated delay claim of approximately $65,000 that HCDM has agreed to, along with CCSM’s payment of all other amounts owed to HCDM and subcontractors. The settlement also requires HCDM and all subcontractors to agree to release their liens.
However, given funding shortfalls being experienced by CCSM, in order to effectuate the settlement, staff is recommending that the City Council authorize a Housing Trust Funds bridge loan not to exceed $450,000 to facilitate CCSM’s payment under the proposed settlement terms. If approved, the bridge loan would be made subject to issuance of a final Certificate of Occupancy for the Berkeley Station project, including the revised delay claim of approximately $65,000 and funding the operating reserves required for the project under the existing City loan.
Background
Berkeley Station, a 100% affordable housing development comprised of 13 one-bedroom apartments, opened in March 2026. CCSM constructed the development in large part with an $11.3 million Housing Trust Funds loan from the City (City Loan).
Berkeley Station serves households between 30% - 50% of Area Median Income (AMI) and is supported by 13 Project-Based Vouchers (PBVs) from the Santa Monica Housing Authority (SMHA). Eight of the apartments are reserved for young adults aged 18-26 facing housing insecurity.
CCSM drew the last of its City Loan funds in March 2026 to pay its general contractor, HCDM, for construction work completed through the end of January. At the time of payment, work had also been completed in February and March to get the building ready for tenants to move in.
3 of 6
Following the final disbursement of the City Loan, CCSM utilized their remaining external grant funds to complete the payments for the development. However, CCSM halted payments for work completed in February and thereafter amid a dispute with HCDM over change order requests, in which HCDM sought to increase the construction contract amount for time extensions reflecting over six months in delay of project completion.
As a result of the stoppage in payments, HCDM and its subcontractors recorded mechanic’s liens on the property. CCSM paid HCDM in June 2026 with non-City grant funds for work completed through the end of February. However, as of October 7, 2026, there were several mechanic’s liens filed on the property. HCDM filed a foreclosure action in September 2026.
Discussion
Following the dispute between CCSM and HCDM, the City engaged discussions with all parties in an attempt to identify a pathway towards resolving the situation. Through that engagement, the following settlement terms were reached. • The total unpaid balance to HCDM was agreed to be: $1,331,587.20 • The agreed upon delay claim amount would be: $65,113.39 In addition to those amounts, in order to ensure that the Berkeley Station project has the necessary funding for operations, City staff have also identified that funding for capitalized operating reserves (approximately $30,000) and supportive service reserves (approximately $75,000) are also financial obligations that would need to be addressed.
Given the financial factors outlined above, the total funding needed to finish and stabilize the Berkeley Station project are estimated to be $1,501,700.59, as follows:
HCDM Accrued Construction Costs $ 1,331,587.20
HCDM Delay Claim $ 65,113.39
4 of 6
Project Capitalized Operating Reserves $ 30,000.00
Project Supportive Service Reserves $ 75,000.00
TOTAL EST. FUNDING NEEDED $ 1,501,700.59
CCSM will need additional funding to effectuate the terms of the settlement with HCDM and stabilize the project. Currently, CCSM has only $1,071,944.06 remaining for the Berkeley Station project (from grant funds obtained for the project). This leaves a funding shortfall of approximately $430,000, as follows:
Berkeley Station Project Funding Needed $ 1,501,700.59
CCSM Available Cash $ 1,071,944.06
EST. FUNDING GAP $ 429,756.53
If the amount not to exceed $450,000 is approved by the City Council for use towards effectuating the settlement terms in this matter, the following process would be executed to deploy the additional monies:
• Upon receipt of Certificate of Occupancy, the City would fund the gap between CCSM’s non-City funding sources and the total amount owed to HCDM, utilizing a repayable Housing Trust Funds bridge loan.
• The bridge loan would also include amounts budgeted under CCSM’s existing loan and regulatory agreement for operating reserves and supportive services reserves.
• Of note, the reserve amounts would be held by the City in the event they are needed to cover future operating or supportive services expenditures that would not be covered by the property’s cash flow.
Punch list completion and final Certificate of Occupancy There is punch list work left to complete both inside the residences and in exterior areas. A final inspection by the City’s building official is also required to confirm any additional items that would need to be addressed to obtain final Certificate of 5 of 6
Occupancy. HCDM has agreed to complete the punch list items and any other items needed to obtain Certificate of Occupancy at no additional cost.
Environmental Review
Authorization of a bridge loan for the 1342 Berkeley affordable housing development is exempt from CEQA pursuant to Section 15301 (Existing Facilities) and Section 15061(b)(3) (Common Sense Exemption) of the CEQA Guidelines. Section 15301 exempts projects that consist of the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of existing or former use. The bridge loan would provide for the completion of punch list work for the existing residential building (which was completed in March 2026) and would not increase the number of units or expand its residential use. Additionally, authorization of the bridge loan is an administrative action and would have no effect on the environment. Therefore, the bridge loan is also exempt from CEQA pursuant to Section 15061(b)(3) of the CEQA Guidelines, which states that CEQA does not apply, “where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment.” Financial Impacts and Budget Actions
Should Council approve a Housing Trust Funds bridge loan, the amount would not exceed $450,000. Approval of the recommended action and execution of the bridge loan documents will result in a total loan to CCSM for the project as detailed in the table below.
Year Funding Source Housing Trust Funds
2017 Predevelopment Loan $467,735
2023 Additional Loan Amount for
Construction
$8,958,571
2025 Additional Loan Amount for
Construction
$1,893,855.35
6 of 6
2026 Bridge Loan (not to exceed) $450,000
Total Loan to CCSM $11,770,161.35
Prepared By: Ayala Scott, Senior Development Analyst
Approved Forwarded to Council