To: Mayor and City Council
From: Anuj Gupta, Director of Transportation, Department of Transportation, Transit Planning & Performance
Subject: Authorization to enter into a Sixth Modification of Agreement #3571 with Trapeze Software Group, Inc., for Scheduling Support Services for the Department of Transportation
Recommended Action
Staff recommends that the City Council:
1. Adopt a finding of Categorical Exemption pursuant to Section 15061(b)(3) (Common Sense Exemption) of the California Environmental Quality Act (CEQA) Guidelines; and
2. Authorize the City Manager to execute a sixth modification to Agreement #3571 (CCS) in an amount not to exceed $75,000 with Trapeze Software Group, Inc. for scheduling support services for the Department of Transportation and to extend the term through December 31, 2027. This will result in a seven-year amended agreement with a new total amount not to exceed $595,600, with future year funding contingent on budget approval.
Summary
Big Blue Bus (BBB), a division of the Santa Monica Department of Transportation (DOT), operates 173 transit buses across 58 square miles of greater Los Angeles, providing more than 10 million rides annually. DOT’s Transit Planning and Performance Division is responsible for planning and scheduling Big Blue Bus service. Three times a year, the division develops a service plan with updated operating schedules and service changes informed by customer feedback, historical operational data, and the City Council-approved Service, Design, Performance and Evaluation Guidelines.
To operationalize each service plan, the division relies on scheduling support services, currently provided by Trapeze Software Group (Trapeze), to create work runs for 2 of 4
operators and related materials (such as run guides, paddles, and bid sheets) using DOT-licensed Trapeze vehicle and operator scheduling software. To maintain stability in operationalizing service plans while DOT continues to advance procurement of a comprehensive vehicle and operator scheduling software system, staff recommends a sixth modification to Trapeze’s agreement for scheduling support services that would extend the contract term through December 31, 2027. This sixth modification would also add $75,000 to the contract, bringing the total not-to-exceed amount to $595,600.
Discussion
Background
On June 9, 2020, the City issued a Request for Proposals (RFP), “Transit Scheduling – Immediate Need,” for transit scheduling support services and received three proposals.
The division required this support to operationalize service planning starting with the September 2020 service change. Following Procurement’s review and approval, the City awarded the contract to Trapeze, and Agreement #3571 (CCS) was executed on August 11, 2020. Trapeze, working with DOT planning staff, configures work runs and related materials based on information provided by DOT staff. Through five modifications to the agreement, Trapeze has continued support through the December 2026 service change.
Need for the Modification
A sixth modification to Trapeze’s scheduling support agreement is needed while DOT completes two related procurements, which have to occur in sequence.
First, DOT is conducting a competitive procurement for a comprehensive vehicle and operator scheduling software system (RFP #471), which was issued on April 16, 2026, and is now underway. Staff anticipates recommending an award to Council in early spring 2027 and the selected system is expected to be implemented before the end of 2027.
Second, upon completion of the award of the scheduling software system, DOT will release a competitive solicitation for scheduling support services (the same services being extended under this staff report). The scope of the scheduling support services procurement is dependent on the software system to be selected, as bidders typically have expertise in specific software systems. Staff anticipates recommending an award to Council in fall 2027. Following Council approval, contract execution and the City’s 3 of 4
vendor information security assessment must be completed before the new contractor can begin work, anticipated with the April 2028 service change.
This modification will allow scheduling support services to continue without interruption until the new scheduling support contract is in place. The recommended modification will support three additional BBB service changes, tentatively scheduled for April 2027, August 2027 and December 2027.
Scope and Pricing
This contract modification is an exception to competitive bidding pursuant to SMMC Section 2.24.250(l), temporary procurement to allow for a competitive solicitation process under ECB #538, approved by Procurement on November 5, 2026.
The extension would provide services on a Time and Materials basis, with the City billed only for hours actually worked. Trapeze’s proposed Statement of Work (SOW) includes up to 385 hours (63 project management hours and 322 scheduling support hours), which is consistent with this calendar year’s usage of about 380 hours. Rates would increase 5% over current 2026 rates:
Role 2026 Rate (offsite) 2027 Rate (offsite)
Project Manager $256.25 $269.06
Technical Product
Specialist
$243.75 $255.94
Trapeze has completed each service change on schedule and within budget.
Environmental Review
This contract modification is categorically exempt from CEQA pursuant to Section 15061(b)(3) (Common Sense Exemption) of the CEQA Guidelines which states that CEQA does not apply “where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment.” The modification will allow the City to continue to provide service to Big Blue Bus customers.
Therefore, it can be seen with certainty that the agreement would not result in adverse physical impacts on the environment, and as such, is exempt from CEQA.
Past Council Actions
Meeting Date Description
7/27/2021
(attachment A)
Execute a second modification to Contract 3571 with
Trapeze Software Group, to increase the contract amount by $280,000 (NTE $371,600) and extend the term by two
4 of 4
years, through December 2023
11/11/2024
(attachment B)
Execute a fourth modification to Contract 3571 with Trapeze Software Group, to increase the contract amount by
$149,000 (NTE $520,600) and extend the term by one year, through December 2025
The first, third and fifth modifications extended the contract term, and/or added funding within approval authority, and therefore did not require Council action.
Financial Impacts and Budget Actions
Staff seeks authority to approve available funding from the Big Blue Bus Fund to increase the amount of the contract with Trapeze Software Group for scheduling support services.
Contract Modification Request
Agreement #
Current
Authorized
Amount
FY 2026-27
Modified
Request
Amount
Future Years
Amount Dept Account #
Total Revised
Contract
Amount
3571 $520,600 $25,000 $50,000 60600016.552013 $595,600
Future year funding is contingent on Council budget approval.
Prepared By: Jessica Saks, Administrative Analyst
Approved Forwarded to Council
Attachments:
A. Contract 3571_Original Agreement
B. Contract 3571_1st Modification
C. Contract 3571_2nd Modification
D. Contract 3571_3rd Modification
E. Contract 3571_4th Modification
F. Contract 3571_5th Modification
G. Oaks Initiative
H. FY26-27 Living Wage
I. Levine Act Disclosure Form