Cities Index.
agenda-report Award RFP #SP2745 to and Authorize the City Manager to enter into an Agreement with Landscape Structures Inc. for Design-Build services for the Virginia Avenue Park Playground Replacement for the Public Works Department

Santa Monica City Council
November 17, 2026

Document
agenda-report Award RFP #SP2745 to and Authorize the City Manager to enter into an Agreement with Landscape Structures Inc. for Design-Build services for the Virginia Avenue Park Playground Replacement for the Public Works Department
Meeting
November 17, 2026
Body
Santa Monica City Council
Original file
567 KB
Text extracted from the city's file for reading and search. Open the original on santamonicacityca.iqm2.com. That file is the official record.

City Council
Report
City Council Meeting: November 17, 2026
Agenda Item: 4.A
1 of 7
To: Mayor and City Council
From: Christopher Dishlip, Director of Public Works, Architecture Services Division Subject: Award RFP #SP2745 to and Authorize the City Manager to enter into an Agreement with Landscape Structures Inc. for Design-Build services for the Virginia Avenue Park Playground Replacement for the Public Works Department
Recommended Action
Staff recommends that the City Council:

1. Adopt a finding of Categorical Exemption pursuant to Sections 15301 (Existing Facilities) and 15302 (Replacement or Reconstruction) of the California Environmental Quality Act (CEQA) Guidelines;

2. Award RFP# SP2745 to Landscape Structures Inc. for design-build construction services for the Virginia Avenue Park Playground Replacement for the Public Works Department; and

3. Authorize the City Manager to execute an agreement with Landscape Structures Inc. in a total amount not to exceed $2,399,834 (including a $200,000 contingency), with future year funding contingent on Council budget approval.

Summary
Santa Monica’s Parks and Recreation system includes aging facilities and equipment that require regular reinvestment and repair to maintain accessible open spaces.

Following an assessment of the system’s current physical conditions and needs, and incorporating community and stakeholder input, the removal and replacement of the existing Virginia Avenue Park playground with an inclusive (universally accessible) and sustainable playground was identified as a priority project.

Staff recommends awarding RFP # SP2745 to Landscape Structures, Inc. and further recommends that Council authorize the City Manager to execute a design-build 2 of 7
agreement for the design, purchase of equipment, and installation of an inclusive playground at Virginia Avenue Park in an amount not to exceed $2,399,834 (including $200,000 contingency). Staff anticipates up to 18 months for the design and construction phases of the project, with design beginning in early 2027 and construction completion anticipated in late summer 2028.

Discussion
Parks and recreational activities are central to the quality of life in Santa Monica.

Community members consistently express their appreciation for the City’s diverse parks and recreation system, and ongoing investment in cherished parks and recreation assets is necessary to maintain the system’s functionality. In the 2025 Parks and Recreation Vision Plan, Appendix B: Existing Amenity and Component Action Matrix, staff recommends the replacement of the Virginia Avenue Park playground equipment and surface materials, as these amenities are considered high-volume use and are essential to the recreational function of the park.

Play embraces Santa Monica’s culture of fitness, and playgrounds should be accessible and inviting for all. Without reconstruction, our playgrounds would eventually reach a condition that would require them to be closed to the public. Virginia Avenue Park playground reconstruction was identified by staff as a top priority due to its aging equipment and limited accessibility. Virginia Avenue Park was originally developed in 1976 as a 5.8-acre park. Renovation and expansion of the park were completed in 2005, and it reopened as the first LEED-certified park in the United States. Now at 9.5 acres, in size, the park includes two children’s playgrounds, two basketball courts, a splash pad, picnic areas with BBQs, walking paths, grass play areas, and two on-site surface parking lots including an overflow parking area that doubles as green space and a campus of community buildings with a robust set of programs that serve youth, families and seniors from the surrounding neighborhood. In 2014, the Pico Branch Library and Annex building were added to the campus. This active and full-service neighborhood park hosts a weekly Farmers’ Market and numerous festivals and events. 3 of 7
The playground was last renovated in 2005, and the 20-plus-year-old play equipment needs replacement. See Figure 1 below for the project location and context.

Figure 1 - Virginia Avenue Park Playground Location
This project is necessary to ensure the playground at Virginia Avenue Park remains available to the public and that the recreational space is not diminished. The proposed project would include the following improvements, design considerations, and activities:
• Replacement of the existing play equipment with inclusive play equipment, with a goal of minimizing the use of plastic and/or petrochemical-based elements in all proposed materials.
• Replacement of the existing sand, concrete, and rubber surfacing with new playground-approved sand, concrete, and surfacing materials, with natural and/or food-grade materials prioritized over plastic and/or petrochemical-based elements.
• Improved ADA access between the existing park and the new playground. 4 of 7
• Pedestrian amenities, including shade structures, fencing, seating, signage, and plantings.
• Exploring ways to integrate nature as a play element that complements the formal structures (i.e. adjacent sensory plants, boulders, interesting focal specimen trees, etc.).
• Community engagement, including, but not limited to, input on elements such as playground equipment and surface materials; theme and color palette; trees and shade; inclusivity and sustainability.
• A tree strategy that retains as many trees as possible, transplants trees only if required and appropriate, with no trees slated for removal.

Staff recommends that the City enter into a design-build agreement with Landscape Structures, Inc. for the design, purchase, and installation of an inclusive and sustainable playground at Virginia Avenue Park.

Vendor Selection
Bidder Recommendation
Best Qualified Firm Landscape Structures Inc.

Evaluation Criteria Experience/Technical Competence; Ability to Meet Project Work Plan/Timeliness; Quality Control; Cost of Services, Cost Control; Stability/References;
Flexibility/Creativity/Responsiveness; Value Add/Breadth of Service.

Municipal Code SMMC 2.24.100(b)
RFPs Received
Landscape Structures Inc. Curious Creative
RFP Data
Posted On Posted On Advertise In
(City Charter & SMMC)
Vendors
Downloaded
Date Publicly
Opened
08/14/2026 City's Online
Bidding Site Santa Monica Daily Press 149 09/16/2026
Best Bidder Justification
The City received two proposals through OpenGov for the Virginia Avenue Park 5 of 7
Playground Replacement Project—Landscape Structures, Inc. and Curious Creative.

The evaluation committee consisted of four staff members from the Public Works Department. The proposal submitted by Curious Creative was deemed non-responsive because the Request for Proposals (RFP) required a Design-Build team, and Curious Creative submitted a design-only team that did not include a Design-Build approach.

Curious Creative received a score of 27.75 out of 100.

Staff recommends awarding RFP # SP2745 to Landscape Structures, Inc. as the best qualified firm. Their proposal demonstrates the capacity, experience, creativity, and technical expertise to design and construct an inclusive, and sustainable playground that meets the City’s standards. The firm is known for reliability, high-quality play equipment, on-time delivery, and staying on budget. Their materials and design approach align with the City’s goals for accessibility, durability, safety, sustainability, and long-term maintenance. Their team plans to lead a focused, inclusive and interactive community engagement process throughout project development.

Environmental Review
The project is categorically exempt pursuant to CEQA Guidelines Sections 15301 (Existing Facilities) and 15302 (Replacement or Reconstruction). Section 15301 provides an exemption (Class 1) for the operation, repair, maintenance, or minor alteration of existing public or private structures or facilities, involving negligible or no expansion of use. Section 15302 (Class 2) provides an exemption for the replacement or reconstruction of existing structures and facilities where the new structure will be located on the same site as the structure replaced and will have substantially the same purpose and capacity as the structure replaced. The project would reconstruct the existing playground at Virginia Avenue Park. In addition, none of the exceptions specified in Section 15300.2 of the CEQA Guidelines apply that would preclude the use of this CEQA exemption, the project site is not located in a sensitive environment, the project will not have a significant effect on the environment, the project would not damage scenic resources, the project would not be located on a hazardous waste site, and the project would not cause a change to a historical resource. Therefore, this project is a Class 1 and Class 2 project exempt from CEQA.

Past Council Actions
6 of 7
Meeting Date Description
4/23/2024
(Attachment A)
Approval of the Proposed FY 2024-25 Annual Action Plan
Allocating Federal Community Development Block Grant (CDBG) and HOME Investment Partnerships Act Program (HOME)
Entitlement Grant Funds
5/28/2024
(Attachment B)
Fiscal Year 2024-25 Proposed Budget and Fiscal Year 2024-26 Biennial Capital Improvement Program Budget
6/24/2025
(Attachment C)
Approval of the Proposed 2025-29 Five-Year Consolidated Plan and the 2025-26 Annual Action Plan Allocating Federal
Community Development Block Grant (CDBG) and HOME
Investment Partnerships Act Program (HOME) Funds
6/23/2026
(Attachment D)
Adoption of the Second Year of the FY 2025-27 Biennial Budget / Adoption of the First Year and Approval of the Second Year of the FY 2026-28 Biennial Capital Improvement Program Budget
4/28/2026
(Attachment E)
Public Hearing and Approval of the Proposed 2026-27 Annual Action Plan Allocating Federal Community Development Block (CDBG) and HOME Investment Partnerships Act Program
(HOME) Funds
Financial Impacts and Budget Actions
Staff seeks authority to approve available funding from the Special Revenue Source Fund, funded by the Park and Recreation Development Impact Fee resources, and CDBG Fund to award a lump sum design-build contract with Landscape Structures, Inc. to perform all design and construction services, provide all material, the equipment, tools and labor, permits, licenses, and taxes, and all other items necessary to complete the work described in the Request for Proposals.

Agreement Request
Funding
Source
FY 2026-
27 Requested
Amount
Future Years
Amount
Department/CIP
Account #
Total Contract
Amount
CDBG
Fund $500,000 $707,834 C1908980.689000 $1,207,834
Special
Revenue
Fund
$1,000,000 $192,000 C1008980.689000 $1,192,000
Total $1,500,000 $899,834  Total $2,399,834
Future year funding is contingent on Council budget approval. 7 of 7
Prepared By: Heidi Creighton, Senior Design Manager
Approved Forwarded to Council
Attachments:

A. April 23, 2024 Staff Report (web link)
B. May 28, 2024 Staff Report (web link)
C. June 24, 2025 Staff Report (web link)
D. June 23, 2026 Staff Report (web link)
E. April 28, 2026 Staff Report (web link)
F. Levine_Act_Disclosure_Form
G. OAKS_INITIATIVE_FORM

← All documents from this meeting