CONTRACT AWARD – SIX FIRE
DAMAGED PARKS - RECOVERY
City Council Meeting
February 22, 2022
Danny Chen, Assistant Engineer
Transportation and Public Works Department
1 BACKGROUND
• Fir Ridge Park
• Nagasawa Community Park
• Francis Nielsen Park
• Rincon Ridge Park
• Rincon Ridge Open Space
• Parker Hill Rd Trail
2 This project will replace park amenities
that were destroyed by the Tubbs Fire
in the following parks and open space
locations:
ANAL YSIS
• The project was advertised on 12/9/2021;
5 of bids were received on 1/11/2022,
ranging from $1,471,254.00 to
$1,821,980.50.
• The low bid was 10.48% under the
Engineer’s estimate.
• Construction is anticipated to begin in
March of 2022 and last 120 working days.
3 RECOMENDATION
• It is recommended by the Transportation and Public
Works Department that the Council, by resolution: 1)
award Contract No. C02248., Six Fire Damaged Parks-
Recovery, in the amount of $1,471,254.00 to the
lowest responsible bidder, Oak Grove Construction Co.,
Inc, of Petaluma, California, approve a 10% contract
contingency, and authorize a total contract amount of
$1,618,379.40; and 2) authorize the appropriation of
$1,675,000.00 from the General Fund reserves for the
Six Fire Damaged Parks – Recovery project, and
increase General Fund federal and state grant revenue
by at total of $1,675,000.
• Questions?
4 LOCATION MAP
5