Attachment 1_Water Funding Sheet (added 3/10/22)

Budget Review Subcommittee
March 15, 2022

Document
Attachment 1_Water Funding Sheet (added 3/10/22)
Meeting
March 15, 2022
Body
Budget Review Subcommittee
Original file
225 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

3/8/2022 2022-23 WATER DEPARTMENT CIP WORKSHEET - WATER CAPITAL FUND 1614 1 See Carryover 2021-22 2021-22 IFAS REQUEST
Line Note IFAS Funding From Budget Mid-Year ITD Y.T.D. Current Projected YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 5 YEAR No. PID [n] Key Project Title Type 2020-21 Request Revisions Expenditures Expenditures Encumbered Available 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL 1 Public Assistance (PA) Projects
2 2208 [1] 55769 Potable water pumps and Reservoirs - Cat F CONT $582,488 $0 $0 $1,188,52 1 $116,009 $88,233 $378,245 $1,400,000 $0 $0 $0 $0 $1,400,000 3 2316 55796 Reservoir 5 Recoating CO $1,398,106 $0 $0 $4,785 $2,89 1 $0 $1,395,215 $0 $0 $0 $0 $0 $0 4 2222 [1] 55766 Replace Water Services - Tubbs Fire (Inside Advisory Area CO $9,397 $0 $420,000 $3,443,189 $415,675 $6,099 $7,623 $0 $0 $0 $0 $0 $0 5 N/A 55792 Glass Fire Emergency Response - Water CO $2,044 $0 $0 $23,120 $165 $0 $1,880 $0 $0 $0 $0 $0 $0 6 N/A 55791 Water Quality Investigation - Glass Fire CO $1,889 $0 $0 $38,11 1 $0 $0 $1,889 $0 $0 $0 $0 $0 $0 7 2207 [1] 55771 Water Dept Metering - Citywide - Cat F CO $552,399 $0 ($543,123) $817,121 $8,646 $0 $629 $0 $0 $0 $0 $0 $0 8 PA Project Totals $2,546,323 $0 ($123,123) $5,514,848 $543,386 $94,333 $1,785,481 $1,400,000 $0 $0 $0 $0 $1,400,000 9 10
11 Hazard Mitigation Program (HMGP) Projects
12 2256 [2] 55772 Water Facility Generator Replacements - HMG CO $1,664,819 $2,970,000 $3,000,000 $626,994 $193,505 $700,700 $6,740,614 $0 $0 $0 $0 $0 $0 13 HMGP Project Totals $1,664,819 $2,970,000 $3,000,000 $626,994 $193,505 $700,700 $6,740,614 $0 $0 $0 $0 $0 $0 14 15
16 Master Planning/Studies/Miscellaneous
17 509 55574 Water Project Contingency CONT $3,173,354 $1,000,000 ($3,344,741) $0 $0 $0 $1,571,683 $742,700 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $6,742,700 18 242 55420 Water Supply Planning CONT $107,422 $200,000 $0 $2,508,395 $108,463 $69,268 $129,69 1 $550,000 $150,000 $150,000 $150,000 $150,000 $1,150,000 19 2402 55498 Local Water Repairs - On Call Contracts CONT $201,146 $0 $271,192 $1,432,687 $428,832 $96,84 1 ($53,336) $291,000 $291,000 $291,000 $291,000 $291,000 $1,455,000 20 2362 55795 Water Tank Condition Assessment 202 1 CONT $180,000 $0 $0 $2,344 $2,344 $0 $177,656 $250,000 $0 $250,000 $0 $0 $500,000 21 1641 55511 Pre-Design, Planning, Budget, GIS Support - Water CONT $70,442 $60,000 $0 $1,822,807 $106,085 $15,540 $8,817 $190,000 $190,000 $190,000 $19 0,000 $36,389 $796,389 22 2174 55730 SC TPW Coordination - Various Locations CONT $74,475 $0 $0 $323,525 $0 $0 $74,475 $75,000 $0 $0 $0 $0 $75,000 23 292 55505 Warranty Punch List - Water CONT $9,819 $0 $0 $365,366 $30,338 $0 ($20,519) $25,000 $28,81 1 $69,000 $25,000 $30,000 $177,81 1 24 247 55527 Water Peak Reduction CONT $634,687 $0 $0 $5,703,935 $214,95 1 $0 $419,736 $0 $0 $300,000 $0 $0 $300,000 25 2291 55777 Water On-Call Engineering Services CONT $83,402 $0 $8,000 $61,016 $8,317 $74,109 $8,975 $0 $0 $200,000 $250,000 $0 $450,000 26 244 55495 Water Conservation Indoor Water Use Efficiency CONT $285,369 $0 $0 $1,721,085 $44,986 $25,746 $214,636 $0 $0 $0 $50,000 $0 $50,000 27 1765 55675 AMI/AMR Feasibility Study & Implementation CO $1,286,340 $0 $0 $7,637,714 $76,054 $1,196,534 $13,752 $0 $0 $0 $0 $0 $0 28 64 5537 1 Water Master Plan CO $375,168 $100,000 $0 $782,832 $0 $372,108 $103,06 1 $0 $0 $0 $0 $0 $0 29 2314 55784 Strategic Asset Management Plan - Water CO $2,016 $0 $0 $4,984 $0 $0 $2,016 $0 $0 $0 $0 $0 $0 30 2358 55793 Design-Build Water CO $35,587 $0 $60,000 $55,546 $31,133 $38,623 $25,83 1 $0 $0 $0 $0 $0 $0 31 2057 55740 Computer Maintenance Management System Replacement CO $338,273 $0 $0 $1,793,090 $115,816 $62,088 $160,370 $0 $0 $0 $0 $0 $0 32 2315 55785 Catastrophic Reserve Study - Water CO $22 $0 $0 $6,978 $0 $2 $20 $0 $0 $0 $0 $0 $0 33 1148 55562 Drought Response CO $112,745 $0 $50,000 $398,497 $85,756 $1,793 $75,196 $0 $0 $0 $0 $0 $0 34 2238 55774 Water System Reliability Study CO $218,729 $0 $0 $403,988 $12,717 $188,125 $17,887 $0 $0 $0 $0 $0 $0 35 Master Planning/Studies/Miscellaneous Totals $7,188,995 $1,360,000 ($2,955,549) $25,024,789 $1,265,792 $2,140,775 $2,929,948 $2,123,700 $2,159,811 $2,950,000 $2,456,000 $2,007,389 $11, 696,900 36 37
38 Water Mains and Services
39 2154 55623 WMR Sherwood Forest Neighborhood, Phase I CONT $0 $600,000 $0 $1,870 $1,870 $0 $598,130 $1,600,000 $0 $800,000 $4,150,000 $0 $6,550, 000 40 2210 55762 WMR Sonoma Ave and Montgomery Drive RCF NEW $0 $0 $0 $0 $0 $0 $0 $500,000 $1,300,000 $0 $0 $0 $1,800,000 41 2323 55788 WMR Terra Linda and Buena Vista NEW $0 $0 $0 $0 $0 $0 $0 $400,000 $1,000,000 $0 $0 $0 $1,400,000 42 166 5567 1 WSR Meyers Drive NEW $0 $0 $0 $0 $0 $0 $0 $70,000 $370,000 $0 $0 $0 $440,000 43 1903 55716 WMR Streamside to Elaine CONT $240,094 $0 $270,000 $23,350 $8,445 $0 $501,650 $70,000 $0 $0 $0 $0 $70,000 44 1999 55731 Cobblestone Dr Zone R2-R4 Water Main Connection CONT $870,362 $0 $0 $506,754 $52,117 $164,803 $653,442 $40,000 $0 $0 $0 $0 $40,000 45 472 55720 WMR Corby Ave - Barham to Baker NEW $0 $0 $0 $0 $0 $0 $0 $0 $400,000 $1,650,000 $0 $0 $2,050,000 46 477 55680 WMR Raegan Way and California Ave NEW $0 $0 $0 $0 $0 $0 $0 $0 $400,000 $1,500,000 $0 $0 $1,900,000 47 204 55586 WSR Salem Ave NEW $0 $0 $0 $0 $0 $0 $0 $0 $200,000 $650,000 $0 $0 $850,000 48 1904 55717 WMR Elaine Dr to Melita Rd CONT $9,874 $140,000 $0 $8,177 $7,870 $0 $142,003 $0 $100,000 $0 $0 $0 $100,000 49 2153 55754 WMR Corby Ave - Inglewood to Earle NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $950,000 $1,000,000 $0 $1,950,000 50 592 55594 WMR Carrington St NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $788,705 $2,250,000 $0 $3,038,705 51 240 55387 WMR Wright St - Silva to Carr NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $700,000 $750,000 $0 $1,450,000 52 2040 55734 WMR Palomino Dr and Sunny Manor Way NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $600,000 $1,000,000 $0 $1,600,000 53 2152 55760 WMR Corby Ave Colgan to Barham CONT $800,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,464,766 $1,500,000 $2,964,766 54 2211 55763 WMR Chanate Rd in Vicinity of RCF NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $750,000 $4,500,000 $5,250,000 55 234 55645 WMR College Ave - E to 4th NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $500,000 $1,600,000 $2,100,000 56 2410 55806 Oakmont Dr. WMR - Riven Rock to R12B NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $400,000 $2,679,000 $3,079,000 57 612 55592 WMR Apple Valley Lane NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $200,000 $700,000 $900,000 58 184 55630 WMR Grace Ave Area (Finlaw/James)- Phase 4 NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,000,000 $2,000,000 - P R O J E C T E D -
3/8/2022 2022-23 WATER DEPARTMENT CIP WORKSHEET - WATER CAPITAL FUND 1614 2 See Carryover 2021-22 2021-22 IFAS REQUEST
Line Note IFAS Funding From Budget Mid-Year ITD Y.T.D. Current Projected YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 5 YEAR No. PID [n] Key Project Title Type 2020-21 Request Revisions Expenditures Expenditures Encumbered Available 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL - P R O J E C T E D -
59 186 55625 WMR Grace and El Camino - Phase5 NEW $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $900,000 $900,000 60 2269 [1] 55787 Water Consolidation Project CONT $991,503 $0 $0 $20,110 $1,593 $0 $989,910 $0 $0 $0 $0 $0 $0 61 727 55696 WSR Stony Point Rd CO $15,886 $0 $0 $1,228,333 $0 $10,455 $5,43 1 $0 $0 $0 $0 $0 $0 62 158 55714 WMR Chanate at Mendocino CO $598,069 $0 $850,000 $1,238,972 $413,039 $911,544 $123,487 $0 $0 $0 $0 $0 $0 63 189 55633 WMR Lewrosa Way & Slater St CO $2,112,820 $0 ($512,911) $1,192,498 $1,015,318 $469,989 $114,602 $0 $0 $0 $0 $0 $0 64 2290 55783 WMR Rock Springs and Matanzas CO $3,889,995 $0 $0 $351,817 $131,81 1 $165,780 $3,592,403 $0 $0 $0 $0 $0 $0 65 2041 55800 WMR between 10th and Healdsburg CO $0 $0 $323,000 $5,386 $5,386 $0 $757,614 $0 $0 $0 $0 $0 $0 66 2263 55804 Calistoga Rd Water Main and Service Replacement CO $0 $0 $0 $0 $0 $0 $40,000 $0 $0 $0 $0 $0 $0 67 203 55628 WMR Albany/Malano/Clement CO $955,330 $1,300,000 $0 $80,264 $75,594 $120,339 $732,397 $0 $0 $0 $0 $0 $0 68 308 55694 WMR East Haven Dr - 4th to Eleanor- Phase 3 CO $153,693 $0 $0 $1,557,375 $1,068 $65,466 $7,159 $0 $0 $0 $0 $0 $0 69 1568 55669 WMR Augustan, El Camino, Grosse - Phase 2 CANC $5,94 1 $0 $0 $1,213,306 $0 $2,265 $3,676 $0 $0 $0 $0 $0 $0 70 1675 5564 1 WMR Montgomery - Mission to Jackson CO $436,633 $0 $0 $1,397,877 $51,119 $167,688 $7,826 $0 $0 $0 $0 $0 $0 71 1684 5568 1 WMR East Haven and Eleanor - Phase 6 CO $182,095 $1,520,000 $322,000 $77,459 $57,553 $37,977 $1,928,564 $0 $0 $0 $0 $0 $0 72 327 55736 WMR Terra Linda/Buena Vista/Miraloma CO $1,554,32 1 $1,400,000 ($2,566,551) $175,269 $29,590 $20,430 $1,664,749 $0 $0 $0 $0 $0 $0 73 661 55713 WSR Pacific Ave CO $1,117,185 $0 $0 $2,440,537 $967,722 $108,69 1 $40,772 $0 $0 $0 $0 $0 $0 74 Water Mains and Services Totals $13,933,801 $4,960,000 ($1,314,463) $11,519,353 $2,820,095 $2,245,428 $11,903,815 $2,680,000 $3,770,000 $7,638,705 $12,464,766 $13,879,000 $40,432,471 75 76
77 Groundwater Program
78 80 55523 Groundwater Supply Development CONT $3,132,265 $0 ($2,765,000) $11,169,382 $35,764 $143,365 $188,136 $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 79 2361 55794 EGW Bennett Valley Golf Course CONT $500,000 $0 $0 $15,920 $15,920 $912 $483,168 $1,000,000 $1,000,000 $1,000,000 $0 $0 $3,000,000 80 2121 55758 Leete Well Rehab ilitation CONT $399,743 $500,000 $0 $56,196 $51,055 $359,392 $489,296 $500,000 $0 $0 $0 $0 $500,000 81 1997 55725 Carley & Peters Emergency Well Upgrades CONT $2,645,896 $0 ($530,000) $130,018 $63,860 $905,44 1 $1,146,595 $0 $1,200,000 $0 $0 $0 $1,200,000 82 2142 55747 Farmers Lane Treatment Plant Rehabilitation Phase 2 CONT $506,08 1 $0 $0 $295,034 $1,114 $164,147 $340,820 $0 $0 $500,000 $0 $0 $500,000 83 1839 5569 1 Farmers Lane Well and Treatment Plant Rehabilitation CO $317,597 $0 $0 $4,017,403 $0 $0 $317,597 $0 $0 $0 $0 $0 $0 84 2079 55745 Farmers Lane Well Pump Replacements CO $214,494 $0 ($205,000) $594,701 $2,911 $1,176 $5,408 $0 $0 $0 $0 $0 $0 85 1965 55710 Emergency Groundwater Well - A Place to Play CO $23,685 $0 $0 $122,469 $21,155 $2,647 ($117) $0 $0 $0 $0 $0 $0 86 1965 55709 Emergency Well Pump Station - A Place to Play CO $1,597,707 $0 $3,500,000 $1,845,684 $328,978 $3,014,638 $1,754,090 $0 $0 $0 $0 $0 $ 0 87 2083 55742 EGW Speers Well CO $1,322,725 $0 $0 $321,128 $53 $175,78 1 $1,146,891 $0 $0 $0 $0 $0 $0 88 2237 55773 EGW Hwy 12 CO $61,767 $0 $0 $138,233 $0 $0 $61,767 $0 $0 $0 $0 $0 $0 89 2083 5574 1 EGW Oakmont Well CO $933,715 $0 ($550,000) $55,138 $53 $175,78 1 $207,881 $0 $0 $0 $0 $0 $0 90 2398 55802 Freeway Well Abandonment CO $0 $0 $550,000 $0 $0 $0 $550,000 $0 $0 $0 $0 $0 $0 91 2204 5575 1 EGW Freeway Well CO $192,905 $0 $0 $902,072 $6,14 1 $13,661 $173,103 $0 $0 $0 $0 $0 $0 92 Groundwater Totals $11,848,580 $500,000 $0 $19,663,379 $527,005 $4,956,940 $6,864,635 $1,600,000 $2,300,000 $1,600,000 $100,000 $100,000 $5,700,000 93 94
95 Reservoirs
96 2212 55764 Seismic and Water Quality Upgrades - Reservoirs 9A, R16, R17 CONT $2,049,84 1 $4,000,000 $0 $384,335 $134,176 $780,949 $5,134,716 $5,500,000 $2,500,000 $0 $0 $0 $8,000,000 97 491 55606 R9C Analysis and Decommission CANC $105,470 $0 $0 $742,25 1 $0 $74,600 $5,870 $0 $0 $0 $0 $0 $0 98 568 55618 Seismic Upgrade - R3, R7, R12B CANC $453 $0 $0 $6,458,295 $496 $0 ($43) $0 $0 $0 $0 $0 $0 99 1801 55677 Road Access Stabilization Repairs for R7 CO $218,04 1 $0 $0 $2,989,112 $38,314 $215,973 ($36,245) $0 $0 $0 $0 $0 $0 100 1572 55647 R11 Permanent Electrical Power CO $90,247 $0 $0 $49,753 $0 $0 $90,247 $0 $0 $0 $0 $0 $0 101 2305 5578 1 Water Tanks Tree Removal CO $96,937 $0 $400,000 $34,809 $21,746 $0 $475,19 1 $0 $0 $0 $0 $0 $0 102 Reservoir Totals $2,560,990 $4,000,000 $400,000 $10,658,555 $194,732 $1,071,522 $5,669,736 $5,500,000 $2,500,000 $0 $0 $0 $8,000,000 103
104
105 Pump Stations and Facilities
106 2045 55732 Water Pump Station 10 High Flow Retrofit CONT $16,08 1 $0 $0 $8,919 $0 $0 $16,08 1 $900,000 $2,000,000 $0 $0 $0 $2,900,000 107 1986 55663 S14 Pump Station Upgrades - High Fire Severity Zone CONT $7,587 $0 $0 $109,413 $0 $0 $7,587 $0 $1,400,000 $0 $0 $0 $1,400,000 108 2351 55805 Fiber Optic Installation: Various Pump Stations and Reservoirs NEW $0 $0 $0 $0 $0 $0 $0 $0 $500,000 $0 $500,000 $0 $1,000,000 109 1713 55702 S13 Pump Station Upgrades - High Fire Severity Zone CONT $7,510 $0 $0 $86,490 $0 $0 $7,510 $0 $0 $1,650,000 $0 $0 $1,650,000 110 1907 55705 Booster Pump for Westerly Zone 9 CONT $0 $0 $0 $29,999 $0 $0 $0 $0 $0 $1,230,000 $0 $0 $1,230,000 111 2052 55678 WaterPLCReplBoosterStation CO $748,697 $0 $1,000,000 $458,075 $73,806 $132,036 $1,542,855 $0 $0 $0 $0 $0 $0 112 2052 55789 Radio Controller Upgrades CO $1,800,000 $0 ($1,000,000) $5,166 $5,166 $0 $794,834 $0 $0 $0 $0 $0 $0 113 2377 55799 Fiber Optic Installation – S7 to R7 CO $5,000 $0 $0 $579 $579 $0 $4,42 1 $0 $0 $0 $0 $0 $0 114 2150 55748 Station 3 Power Filter Installation and Stn 2 Gen Replacement CO $148,874 $0 $0 $611,180 $55 $18,354 $5,466 $0 $0 $0 $0 $0 $0 115 2327 55790 Fiber Optic Installation – S12 to R12 A CO $49,990 $0 $0 $63,990 $57,087 $90 ($7,187) $0 $0 $0 $0 $0 $0 116 2313 55782 Station 6&7 Soil & Groundwater Investigation CO $34,080 $0 $0 $37,630 $21,709 $0 $12,370 $0 $0 $0 $0 $0 $0 117 2374 55798 Station 4 Evaluation and Rehabilitation CO $0 $0 $270,000 $17,032 $17,032 $235,22 1 $17,747 $0 $0 $0 $0 $0 $0 118 2061 55761 Water Pump Station 1 Retaining Wall CO $394,245 $0 $0 $102,060 $46,305 $97,985 $249,956 $0 $0 $0 $0 $0 $0 119 1994 55735 Station 15 Upgrades CO $173,909 $0 $0 $1,236,574 $11,436 $168,312 ($5,839) $0 $0 $0 $0 $0 $0 120 Pump Station and Facility Totals $3,385,974 $0 $270,000 $2,767,106 $233,176 $651,997 $2,645,801 $900,000 $3,900,000 $2,880,000 $500,000 $0 $8,180,000 3/8/2022 2022-23 WATER DEPARTMENT CIP WORKSHEET - WATER CAPITAL FUND 1614 3 See Carryover 2021-22 2021-22 IFAS REQUEST
Line Note IFAS Funding From Budget Mid-Year ITD Y.T.D. Current Projected YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 5 YEAR No. PID [n] Key Project Title Type 2020-21 Request Revisions Expenditures Expenditures Encumbered Available 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL - P R O J E C T E D -
121 Grand Totals - Cash Funding $43,129,481 $13,790,000 $75,775,025 $5,777,691 $11,861,696 $38,540,030 $14,203,700 $14,629,811 $15,068,705 $15,520,766 $15,986,389 $75,409 ,371 Funding Type: Notes:

CANC = Project is expected to be completed by end of current fiscal year [1] This project is anticipated to be reimbursed at 100% with Prop 84 grant funding CO = Carryover project with no additional funding
CONT = Continue project with additional funding
NEW = New project with initial funding within five year plan Assumptions:
3% construction cost inflation per year