3/8/2022
City of Santa Rosa
Project Bid Summary
Project Name:
FULTON RD FROM
GUERNEVILLE RD TO PINER
RD - WIDEN TO FOUR LANES
Contract No.: C01178
Client: CITY OF SANTA ROSA Project No.: C01178
Bid Opening: 03/08/2022 2:00 PM Owner: City of Santa Rosa Rank Vendor Number Business Name Total Bid Amount Percent Over Low Bid Percent Over/Under Estimate Engineers Estimate $14,219,207.00
1 N/A
GHILOTTI BROS/FBD
VANGUARD CONSTRUCTION
JV
$15,578,565.00 0.00% 9.56% OVER ESTIMATE
2 V000592 ARGONAUT CONSTRUCTORS $16,807,679.30 7.89% 18.20% OVER ESTIMATE 3 V006204 TEAM GHILOTTI INC $16,997,141.00 9.11% 19.54% OVER ESTIMATE 4 V003440 GHILOTTI CONSTRUCTION
COMPANY, INC $19,530,233.80 25.37% 37.35% OVER ESTIMATE 5 V003710 GRANITE CONSTRUCTION $19,823,672.80 27.25% 39.41% OVER ESTIMATE Project Bid Abstract Summary for Project C01178