Cities Index.
Presentation (added 4/27/22)

Contract Review Subcommittee
April 28, 2022

Document
Presentation (added 4/27/22)
Meeting
April 28, 2022
Body
Contract Review Subcommittee
Original file
377 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

Board of Public Utilities
Contract Review Subcommittee
April 28, 2022
Jason Roberts, PE
Supervising Engineer, Capital Projects Engineering
1 Construction
Contract Award
C00284 – Laguna Treatment Plant
Disinfection Improvements Project
2 • Project Purpose
• Timeline Since Fall of 2021
• Issuance for Bid and Bid
Period Details
• Review of Bids Received
• Identification of Low Bidder
• Impacts and Schedule
• Recommendation
Presentation Outline
Flow
Equalization
To Reuse
3 • Aged and de-rated UV
disinfection system
• New UV system capable of
treating up to 67M gallons
per day
• Hypochlorite facility
replacement
• New effluent diversion
facility and stormwater
pump station
• New trailer for LTP staff
Project Purpose
Flow
Equalization
To Reuse
4 UV Equipment Procurement:
• September 2021 – Best and Final Price
received from De Nora
• Sept – Dec 2021: City staff negotiated with
De Nora a Best and Final Price to include
increased steel prices totaling $288,791.28
• December 1, 2021: Best and Final Offer
letter received from De Nora to include
increased price of steel and new Final Price
of $5,923,491.28 for the UV System
• December 16, 2021: BPU approved a
Second Amended and Restated MOU with
De Nora
• This approval allowed design to be finalized
and bid documents to be prepared
Timeline Since Fall of 2021
De Nora UV Technologies
5 • Invitation for Bids was issued on
January 28, 2022, with a bid open
date of March 29, 2022.
• Engineer’s Estimate: $50M - $60M
• Two Mandatory Pre-Bid meetings
were held.
• Five contract Addenda were issued
• Contract based on MasterFormat
Invitation for Bids and Bid
Period Details

6 • Four bids were received on March 29, 2022.
• Shimmick: $68,109,000
• Overaa: $71,987,000
• Mountain Cascade: $78,720,033
• Ranger Pipelines: $79,181,414
• Design and Construction Management team
verified that Shimmick was responsive and
responsible
• Notice of Intent to Award was issued on April
13, 2022.

Identification of Low Bidder
+
7 • Fiscal Impact
• Funding was appropriated with the fiscal year 2021-22 CIP budget and mid-year appropriations by City Council.
• Environmental Impact
• The proposed improvements are covered under the Amended Incremental Recycled Water Program (IRWP) EIR approved by the Board on November 19, 2020.
• Schedule
• April 28, 2022: Contract Review Subcommittee
• May 5, 2022: BPU Contract Award
• May 2022: Notice to Proceed
• January 2025: Anticipated project completion
Impacts and Schedule
8 It is recommended by the Transportation and Public
Works Department and the Water Department that
the Contract Review Subcommittee recommend to
the full Board of Public Utilities award of
construction contract C00284 – Laguna Treatment
Plant Disinfection Improvements Project to the
lowest responsive bidder, Shimmick Construction
Company, in the amount of $68,109,000, approve a
10% contingency, and authorize a total contract
amount of $74,919,900.

Recommendation
9 Thank You!
Flow
Equalization
To Reuse

← All documents from this meeting