HOPPER AVE CORRIDOR FIRE
RECOVERY IMPROVEMENTS- PSA
APPROV AL
City Council Meeting
July 26, 2022
Chris Balanesi, Assistant Engineer
Grant Bailey, Supervising Engineer
Transportation & Public Works
1 BACKGROUND
• Hopper Ave Corridor – Coffey to Hwy 101 S
• Residential access to variety of uses
• 2017 Tubbs Fire destroyed homes & City-
maintained landscape
• July 2021 Council Study Session on one-time
monies
• February 2022 CC approved $6M of PG&E
Settlement Funds to project.
2 BACKGROUND
• Project scope not finalized, likely to
include:
• Pavement surface/reconstruction
• Addition of median island
• Vegetation restoration
• Sidewalk rehabilitation & Creek Access
• Bike & pedestrian improvements
3 ANAL YSIS
• Request For Proposals issued 4/12
• 2 proposals received 5/10
• Solicitation, review and selection
completed in accordance with City policy
• Evaluation determined Callander
Associates Landscape Architecture, Inc.
(CALA) most qualified
4 ANAL YSIS
• CALA to provide:
• Public Outreach & Engagement
• Translation & Interpretation
• Preliminary Design/Bridging Docs
• Optional Environmental Review (as
authorized by City only)
5 RECOMMENDATION
It is recommended by the Transportation and
Public Works Department that the Council, by
resolution, approve a Professional Services
Agreement with Callander Associates Landscape
Architecture, Inc. of Gold River, California, for
public outreach and preliminary
engineering/architectural design services
associated with the Hopper Avenue Corridor Fire
Recovery Improvements project, in an amount not
to exceed $466,764.00. 6
LOCATION MAP
7 QUESTIONS?