CityBus route to
100% Local Renewable Powered
Operations
Climate Action Subcommittee
August 10, 2022
Presenters:

Yuri Koslen – Transit Planner
Shawn Sosa – Administrative Analyst
Transportation and Public Works – Transit
Framework of the
Zero-Emission
Rollout Plan
1 Where we are:

WE KNOW OUR
DIRECTION.

WE KNOW THE
BENEFITS.

WE HAVE DONE
ENOUGH
PLANNING.

WE HAVE FUNDING
TO GET STARTED.

WE ARE STARTING
TO BUILD.
2 Our direction: Phases
Phase 1
• First funded
Grant
• Sonoma Clean
Power Study
• PG&E EV Fleet
Program
• First 9 battery
electric buses
(BEB) and 5 dual-
port chargers
Phase 2
• Additional
• 5-10 BEB’s
• 5 dual-port
chargers
Resiliency Phase
• Understand City-
wide vehicle
electrification
• Micro-grid
• Solar
• Battery
Storage
• Generator
Final Phases
• BEBs and
chargers to
complete 100%
3 Our direction
• City Climate Action Plan from 2012
• Municipal Climate Action Plan
• Replace diesel powered buses with GHG
reducing vehicles
• Use low-carbon fuel
• FTA Sustainable Transit for a Healthy Planet Challenge • City participating along with 171 other transit
agencies
• City’s Climate Action Plan shows plan to reduce
GHG emissions
• Next steps
• Healthy Planet Challenge will require transit
agency to develop measurable greenhouse
gas (GHG) emission targets
• Sign on by March 2023
4 Our direction: State Requirement
• California Air Resources Board (CARB) passed
Innovative Clean Transit (ICT) Rule in 2018
• Requires conversion to zero-emission fleet
• ICT timeline for small agencies:
• 2023: Submit Council approved Zero-Emission Bus (ZEB) Rollout Plan
• 2026: Each bus purchase must contain 25% or more ZEB
• Potentially including paratransit
(dependent on bus manufacture testing approvals)
• 2029: Each bus purchase is 100% ZEB
• 2040: Full ZEB Fleet
5 Benefits
• Reduce GHG emissions
• On-road emissions largest source
in Sonoma County
• Encouraging increased ridership
into the future as a low carbon
transportation choice
• Potential Life Cycle cost savings
• Continued opportunities to
qualify for grant funding
6 Planning
• Partnership with Sonoma Clean Power (SCP) and
regional operators
• Study focused on short term deployment
• Transit yard vs. Transit Mall charging
• Charging Equipment and management
solutions
• Types of buses
• Resiliency
• Solar
• Back up generator
• Energy Storage
7 FTA 5307
$1,698,855
8%
FTA 5339
$9,043,139
41%
AHSC
$800,000
4%
HVIP
$552,000
3%
LCTOP
$706,928
3%
LPP
$551,000
2%
PG&E
$206,000
1%
TDA
$5,470,408
25%
TFCA
$447,670
2%
TIRCP
$2,524,000
11%
INDIVIDUAL PROGRAM AMOUNTSFunding: Bus Replacement
(approx. $22M total committed)
Federal
$10,741,994
49%
State
$11,052,006
50%

FUNDING SOURCE
Allocation
$5,470,408
25%
Discretionary
(Competitive)
$11,701,951
53%
Formula
$4,621,641
21%
PG&E
$206,000
1%

TYPE OF AWARD
Continuing to pursue eligible funding to offset use of
our matching capital reserve (HVIP , etc.)
8 Funding: Infrastructure (approx. $2.6M total committed) PG&E
$150,000
6%
TDA
$756,000
28%
TIRCP
$1,744,000
66%

PROGRAM AMOUNTS
Phase 1a

PG&E TTM &
3 Charger Install
$906,000
34%
Phase 1b
(+2 Chargers)
$245,000
9%
Phase 2
Upgrade PG&E TTM
5 Charger Install
$1,499,000
57%

PROJECT PHASE AMOUNTS
Continuing to pursue eligible funding to offset use of
our matching capital reserve (EnergIIZE, etc.)
9 We are starting
to build.
• The Power: City Evergreen
• The Chargers:
• PG&E EV Fleet
• Behind the meter
• To the meter
• The Buses
• Oakmont/Paratransit
• Fixed Route
• The new BEB
10 The Power :
100% Local
Renewable
• The Source – The EverGreen program
• City of Santa Rosa operates on EverGreen power
• Geothermal power at the Geyser Fields and solar
• An energy portfolio provided by Sonoma Clean Power (SCP) • Sonoma County is uniquely positioned to more significantly reduce our transportation related emissions
• BEB’s have zero tail pipe emissions. Emissions depend solely on how electricity is produced
11 Starting to Build: Charging Infrastructure
• April 2019 - Council Study Session and Approval for PG&E EV Fleet Program
• Covers the $140,000 infrastructure cost “to the meter” • Plus “behind the meter” incentive rebates to City of up to $206,000
• City commits to:
• Purchase 9 BEBs and 5 dual-port chargers by 2024
• Operate this infrastructure for a minimum of ten
years
• May 2020 - Council approved EV Fleet Contract with PG&E • January 2021 - Council Authorized Design-Build Procurement • April 2021 – Council approved contract with Cupertino Electric
12 PG&E pays for, constructs, owns, and
maintains all infrastructure “to the
meter”
City pays for, constructs, owns, and
maintains infrastructure “behind the
meter”
13 14
15 16
17 Overall preliminary design18
19 2014 *
2014 *
2014 *
2014
2014
2014
2015
2020
2020
2020
2020
Funded for gas vehicle replacements
*Pending award
2010
Current Cutaway Fleet
Use of capital reserve
5310
$293,277
29%
TDA
$206,723
21%
Unknown:
-Funding Source
-Vehicle Availability
-Vehicle Cost (est.)
$500,000
50%

PROJECT FUNDING AMOUNT
(ASSUMING ELECTRIC)
5310
$293,277
59%
TDA
$206,723
41%

PROJECT FUNDING AMOUNT
(ASSUMING GAS VEHICLE)
20 The Buses
21 2002
2002
2002
2002
2013
2013
2013
2013
2013
2013
2002
2016
2016
2016
2016
2018
2018
2018
2018
Current Fixed Route Fleet
2008
2008
2008
2011
2011
2011
2011
2011
2011
2011
Funded for replacement
22 2013
2013
2013
2013
2013
2013
2002
2016
2016
2016
2016
2018
2018
2018
2018
Fixed Route Fleet in Jan 2023
2008
2008
2008
2011
2011
2011
2011
2011
2011
2011
2022
2022
2022
2022
23 2013
2013
2013
2013
2013
2013
2016
2016
2016
2016
2018
2018
2018
2018
Fixed Route Fleet in Jan 2024
2011
2011
2011
2011
2011
2011
2022
2022
2022
2022
2023
2023
2023
2023
2023
2011
24 2013
2013
2013
2013
2013
2013
2016
2016
2016
2016
2018
2018
2018
2018
Fixed Route Fleet Projected 2026
2022
2022
2022
2022
2023
2023
2023
2023
2023
2026
2026
2026
2026
2026
2026
?
2026
25 The New BEB
26 27
The New Look
28 • August 23: Council consideration of 5 bus purchase • Late 2022/Early 2023
• Phase 1 Charger Infrastructure (install 2 additional chargers) • Oakmont & Paratransit vehicle purchase (gas vs. electric?) • Early 2023: CARB ICT Zero Emission Bus Rollout Plan
• March 2023: FTA Sustainable Transit for a Healthy Planet Challenge – Phase 2 • Would require CityBus to set GHG targets
• 2024-2025
• Purchase funded bus replacements (#10-15)
• Design/Construct funded phase 2 bus charging infrastructure • Ongoing / future
• Resiliency planning: overall City-wide electrification needs • Regional transit collaboration: en-route charging at Transit Mall, etc. • Future technologies
• Telematics (real-time bus energy management)
• Charger management software (depot charging enhanced management) Next Steps
29 • August 23: Council consideration of 5 bus purchase • Late 2022/Early 2023
• Phase 1 Charger Infrastructure (install 2 additional chargers) • Oakmont & Paratransit vehicle purchase (gas vs. electric?) • Early 2023: CARB ICT Zero Emission Bus Rollout Plan
• March 2023: FTA Sustainable Transit for a Healthy Planet Challenge – Phase 2 • Would require CityBus to set GHG targets
• 2024-2025
• Purchase funded bus replacements (#10-15)
• Design/Construct funded phase 2 bus charging infrastructure • Ongoing / future
• Resiliency planning: overall City-wide electrification needs • Regional transit collaboration: en-route charging at Transit Mall, etc. • Future technologies
• Telematics (real-time bus energy management)
• Charger management software (depot charging enhanced management) Next Steps --- QUESTIONS??