Staff Briefing:
2017 Tubbs Fire
Recovery Projects
Update
Joe Schiavone
Acting Director, Transportation and Public Works
Grant Bailey
Acting Deputy Director, Engineering Services
01 August 23, 2022
 20 of 29 FEMA Public Assistance projects are complete  4 completed since February 2022
 2 of 3 FEMA Hazard Mitigation Grant projects are complete  8 projects in final closeout
 2 projects in construction
 Six Fire Damaged Parks
 Fire Damaged Roadway Landscaping
 Fire Station No. 5 Design Build Entity under contract Jan 2023  Reimbursements to date = $17.8 million
02 Fire Recovery Project
Statistics
Utilities (FEMA Obligated Amount: $14.2M)
• Sewer Lift Stations:
• Skyfarm
• Hansford
• Stagecoach
• Contaminated Water Supply System
• Storm Drain System Repairs
03 Completed Projects
Infrastructure (FEMA Obligated Amount: $18.3M)
• Signs, Poles & Electrical Conduit Replacement
• Pedestrian Bridges
• Battery Backup Retrofit

Projects in
Design/Construction
04 7 Pending Projects
Design

1. Rebuild Fire Station 5

2. Fire Damaged Roadway Resiliency Improvement

3. Arterial and Collector Roadway Repairs - FHWA

4. Hopper Ave Corridor Fire Recovery Improvements
Construction

1. Backup Generators – Water and Wastewater Facilities

2. 6 Fire Damaged Parks Recovery

3. Fire Damaged Roadway Landscaping Repair

Fire Station 5
Resiliency and Relocation
05 APR
2022
Property
acquisition and
environmental
clearance
completed
JULY
2022
Design-Build
RFQ phase
complete
NOV
2022
Design-Build
RFP phase
targeting
completion
Contract
Award
Anticipated
Construction
Begins
Construction
Complete
Notice to
ProceedJAN
2023
MAR
2023
SUMMER
2023
SPRING
2025
Fire Damaged
Roadway Resiliency
Improvements
• Resurface 36 miles of residential
streets impacted by the debris
removal mission
• Grant funding clearance: Summer
2022
• Approx $13.5M in CDBG-DR/INF
• Design build RFP: Summer 2022
• Contract award: Fall 2022
• Construction: Spring 2023 – Spring
2024
06 2017 Fire Damaged
Roadway Repairs -
FHWA
• Address roadway damages on:
• Fountaingrove Parkway
• Hopper Ave
• Bicentennial Way
• Funded through FHWA Emergency Response
program
• $4.75M Project
• ~60% Federal match
• Caltrans approval to proceed with construction
anticipated October 2022
• Award Project January 2023
• Construction Complete May 2023
07 Hopper Ave Corridor
Fire Recovery
Improvements
• Restore Hopper Ave between Hwy 101 S
on ramp and Coffey Lane
• Project funded by PGE Settlement Funds
• July 2022: Public Engagement and
Preliminary Design contract awarded
• September 2022: 1st Community scoping
meeting
• Winter 2023 – Summer 2024:

Design/Build Delivery
• Summer 2024: Project Complete
08 Backup Generators –
Water and Wastewater
Facilities
• Replace Backup Generators at
water and wastewater facilities
to ensure a more reliable fuel
option
• Project Funding: FEMA HMGP
• Contract award: August 2022
• Construction: Fall 2022 – Fall
2023
09 Fire Damaged
Roadway Landscaping
Repair
• Replace roadside and median
landscaping, irrigation and
associated electrical services
along Fountaingrove Parkway
and in Coffey Park
• Funded by FEMA Public
Assistance and PGE Settlement
Funds
• Construction schedule: August
2022 – August 2023
10 Six Fire Damaged
Parks – Recovery
• Restoration of:
▪ Fir Ridge Park
▪ Francis Nielsen Park
▪ Nagasawa Park
▪ Rincon Ridge Parks
▪ Rincon Ridge Open Space
▪ Parker Hill Open Space
• Funded by FEMA Public Assistance
and PGE Settlement Funds
• Construction began June 2022
• Completion in January 2023
11 Financial Update
• Project Funding
12 FEMA
• $32.5M obligated
• $17.8M reimbursed
Community
Development Block
Grant
• $33M awarded
(obligation
pending)

FHWA - ER
• $4.75M awarded
PGE Settlement Funds
• $20M dedicated by
Council
• Project Closeout
• 8 Projects in closeout with FEMA
Questions?
13