MTC, November 2022 TDA Article 3 Model Resolution Page 1 Resolution No. _____ page _1__ of _2__
Exhibit A-2
TDA Article 3 Project Application Form

1. Agency City of Santa Rosa

2. Primary Contact Torina Wilson

3. Mailing Address 69 Stony Circle, Santa Rosa, CA 95401

4. Email Address [email protected] 5. Phone Number 707-543-3910

6. Secondary Contact (in
the event primary is
not available)
Rob Sprinkle

7. Mailing address (if
different) N/A☐

8. Email Address [email protected] 9. Phone Number 707-543-3817

10. Send allocation
instructions to (if
different from above):

11. Project Title N Dutton Avenue Road Diet and Pedestrian Improvements

12. Amount requested $200,000 13. Fiscal Year of
Claim
2024/25

14. Description of Overall Project:

15. Project Scope Proposed for Funding: (Project level environmental, preliminary planning, and ROW

16. P roject Location: A map of the project location is attached or a link to a online map of the project location is provided below: Map is provided below.

Project Relation to Regional Policies (for information only) Road diet project on N Dutton Avenue from College Avenue to W Third Street in order to improve bicycle and pedestrian facilities. Reducing the number of travel lanes in each direction from two to one, installing a Class IIb bicycle lane in each direction, preserving existing parking, and sidewalk improvements where necessary. In some areas along the corridor, vertical delineators will be installed in the bicycle lane buffer.

Construction
N Dutton Avenue from College Avenue to W Third Street. N Dutton is an arterial in the city, and it located in the vicinity of a Highway 101 on-ramp at College Avenue and to a Highway 12 on-ramp at Dutton Avenue.

November 2022 TDA Article 3 Model Resolution Page 2

17. Is the project in an Equity Priority Community? Yes☐ No☒

18. Is this project in a Priority Development Area or a Transit-Oriented Community? Yes☐ No☒

19. Project Budget and Schedule

Project Eligibility
A. Has the project been reviewed by the Bicycle and Pedestrian Advisory Committee? Yes☒ No☐ If “YES,” identify the date and provide a copy or link to the agenda.

If "NO," provide an explanation).

B. Has the project been approved by the claimant's governing body? Yes☐ No☒ If "NO," provide expected date:__4/9/2024________________

C. Has this project previously received TDA Article 3 funding? Yes☐ No☒ (If "YES," provide an explanation on a separate page)

D. For "bikeways," does the project meet Caltrans minimum safety design criteria Yes☒ No☐ pursuant to Chapter 1000 of the California Highway Design Manual?

E. 1. Is the project categorically exempt from CEQA, pursuant to CCR Section 15301(c), Yes☒ No☐ Existing Facility?

2. If “NO” above, is the project is exempt from CEQA for another reason? Yes☐ No☐ Cite the basis for the exemption. __________________________ N/A☐ If the project is not exempt, please check “NO,” and provide environmental documentation, as appropriate.

F. Estimated Completion Date of project (month and year): _____10/2027_______

G. Have provisions been made by the claimant to maintain the project or facility, or has Yes☒ No☐ the claimant arranged for such maintenance by another agency? (If an agency other than the Claimant is to maintain the facility, please identify below and provide the agreement.

H. Is a Complete Streets Checklist required for this project ? Yes☐ No☒ If the amount requested is over $250,000 or if the total project phase or construction phase is over $250,000, a Complete Streets checklist is likely required. Please attach the Complete Streets checklist or record of review, as applicable. More information and the form may be found here: https://mtc.ca.gov/planning/transportation/complete-streets Project Phase TDA 3 Other Funds Tot al Cost Estimated Completion (month/year)
Bike/Ped Plan
ENV
PA&ED
PS&E
ROW
CON 200,000
Total Cost 200,000

TDA Article 3 Claim Applications Appendix A Page 1