Mitigation Monitoring and Reporting Program
R
oseland Creek Community Park
Master Plan Project
Se
ptember 2024
Exhibit B

1 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
Air Quality
Construction dust

Standard Measures: The City would implement the
following best management practices as recommend
by BAAQMD for all projects during construction to
reduce dust impacts:

• All exposed surfaces (e.g., parking areas, staging
areas, soil piles, graded areas, and unpaved access
roads) shall be watered two times per day.
• All haul trucks transporting soil, sand, or other
loose material off-site shall be covered.
• All visible mud or dirt track-out onto adjacent
public roads shall be removed using wet power
vacuum street sweepers at least once per day. The
use of dry power sweeping is prohibited.
• All vehicle speeds on unpaved roads shall be
limited to 15 mph.
• All roadways, driveways, and sidewalks to be
paved shall be completed as soon as possible.

Building pads shall be laid as soon as possible
after grading unless seeding or soil binders are
used.

The City and
contractors shall be
responsible for
implementing this
standard measure
during all phases of
construction.

This standard
measure shall be
printed on all
construction
documents,
contracts, and
project plans and
shall be reviewed
and approved by
the Director of
Recreation and
Parks prior to the
issuance of
grading and
building permits.

Director of
Recreation and
Parks or designee

2 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation

• Idling times shall be minimized either by shutting
equipment off when not in use or reducing the
maximum idling time to five minutes (as required
by the California airborne toxics control measure
Title 13, Section 2485 of California Code of
Regulations [CCR]). Clear signage shall be
provided for construction workers at all access
points.
• All construction equipment shall be maintained
and properly tuned in accordance with
manufacturer's specifications. All equipment shall
be checked by a certified mechanic and
determined to be running in proper condition prior
to operation.
• Post a publicly visible sign with the telephone
number and person to contact at the Lead Agency
regarding dust complaints. This person shall
respond and take corrective action within 48
hours. The Air District's phone number shall also
be visible to ensure compliance with applicable
regulations.

3 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project
Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
Biological Resources
Replacement of trees Standard Measures: As a condition of approval for tree removal permits, replacement trees shall be
planted in accordance with the following criteria
from the Ordinance:
• F
or each six inches or fraction thereof of the
diameter of a tree which was approved for
re
moval, two trees of the same genus and species
as the removed tree (or another species, if
a
pproved by the City), each of a minimum 15-
gallon container size, shall be planted on the
project site, provided however, that an increased
num
ber of smaller size trees of the same genus
and species may be planted if approved by the
City, or a fewer number of such trees of a large
r
s
ize if approved by the City.
• If t
he development site is inadequate in size to
acco
mmodate the replacement trees, the trees
shall be planted on public property with the
approval of the Director of the City’s Recreati
on
a
nd Parks Department. Upon the request of the
developer and the approval of the Director, the
City may accept an in-lieu payment of $1

00.00 The City would
ensure the standard
measures are
implemented prior
to issuance of
grading permits.

All measures shall
be printed on all
construction
documents and
reviewed and
approved by the
Director of
Recreation and
Parks or designee
prior to any tree
removal and the
issuance of
grading and
building permits.

Director of
Recreation and
Parks or designee
4 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project
Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
per 15-gallon replacement tree on condition that
all such payments shall be used for tree-related
educational projects and/or planting programs of
the City.

T
he following relevant tree protection measures during
construction are required as a condition of approval, as excerpted from Section 17-24.050 of the Tree
Ordinance:
• Be
fore the start of any clearing, excavation,
c
onstruction or other work on the site, every
prot
ected tree shall be securely fenced off at the
“protected perimeter,” which shall be either the
drip line or other limit as may be established by
the City. Such fences shall remain continuously i
n
pl
ace for the duration of all work undertaken in
c
onnection with the development. The area so
fe
nced off shall not be used as a storage area or
al
tered or disturbed except as may be permitted
under this subsection.
• If the proposed development, including any site
work for the development, will encroach upon the
protected perimeter of a protected tree, special
5 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project
Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
measures shall be utilized, as approved by the
Director, to allow the roots to obtain oxygen,
water, and nutrients as needed. Any excavation,
cutting, filling, or compaction of the existing
ground surface within the protected perimeter, if
authorized at all by the Director, shall be
minimized and subject to such conditions as may
be imposed by the Director. No significant change
in existing ground level shall be made within the
drip line of a protected tree. No burning or use of
equipment with an open flame shall occur near or
within the protected perimeter. All brush, earth
and other debris shall be removed in a manner
which prevents injury to the protected tree.
• No oil, gas, chemicals or other substances that
may be harmful to trees shall be stored or dumped
w
ithin the protected perimeter of any protected
t
ree, or at any other location on the site from
which such substances might enter the perimeter
of a
protected tree. No construction materials shall
be stored within the protected perimeter of a
protected tree.
• Underground trenching for utilities shall avoid
m
ajor support and absorbing tree roots of

6 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
protected trees. If avoidance is impractical,
tunnels shall be made below the roots. Trenches
shall be consolidated to service as many units as
possible. Trenching within the drip line of
protected trees shall be avoided to the greatest
extent possible and shall only be done under the
on-site directions of a Certified Arborist.
• No concrete or asphalt paving shall be placed
within the dripline of protected trees [selected for
preservation]. No artificial irrigation shall occur
within the root zone of oaks.
• No compaction of the soil within the root zone of
protected trees [selected for preservation] shall
occur.

The Tree Ordinance also allows the Director to impose
additional conditions for work encroaching on the
protected perimeter of a protected tree. Where
construction activities overlap with heritage tree
dripline the following protection measures will be
required as conditions of approval:

• A Tree Protection Zone (TPZ) equal to the
dripline radius plus 10 feet shall be the standard

7 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
TPZ for heritage trees selected for preservation in
which ground disturbance shall be limited to the
maximum extent feasible.
• Where possible, temporary protective fencing
shall be installed around the TPZ of each tree
designated for preservation prior to
commencement of any construction activity
conducted within 25 feet of the TPZ, of a tree
designated for preservation.
• Many existing trees in the project area selected for
preservation are situated too close to project
improvements (e.g., trail alignments), where
fencing around the TPZ is infeasible. In those
cases, high visibility temporary fencing shall be
wrapped around the tree trunk to signify the tree is
to be saved and to alert machine operators to
avoid damaging the tree. Extreme caution shall be
taken to avoid mechanical injury to tree trunks,
scaffold branches and root flares. As soon as
required work is complete within the TPZ,
temporary protective fencing shall be installed
around the TPZ and shall remain in place as long
as ground disturbance activities are taking place.

8 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
• The fence shall consist of highly visible material
(e.g., orange safety fencing) to prevent inadvertent
encroachment by heavy machinery. Heavy
equipment use, excavation, fill, grading,
trenching, drainage changes or other soil
disturbance shall be limited within the TPZ.

Material storage, vehicle parking, and trash
disposal shall not occur within the TPZ.
• Grading and soil compacting shall be restricted
within the TPZ to the maximum extent feasible. If
any significant roots (2-inch diameter or greater)
are uncovered within the TPZ they shall be kept
moist at all times with use of damp burlap fabric,
and buried as soon as feasible.
• Grading and/or trail construction within the TPZ
of heritage trees shall be monitored periodically
by a Certified Arborist. All necessary tree work
should be performed by an ISA-Certified Arborist
or comparable tree specialist. Improper pruning
can be harmful to health and structure of trees. No
tree pruning will be permitted unless approved by
a Certified Arborist. Any pruning of existing trees
shall be performed by a licensed tree care
professional and shall comply with the ANSI

9 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
A300 standards and International Society of
Arboriculture (ISA) Best Management Practices
for Tree Pruning. All tree pruning tools must be
cleaned prior to and after use. All branches being
removed shall be cut to, but not beyond, the
branch collar. All pruning shall be done in a way
that maintains the balance and structure of the
tree.
• Site drainage should be designed to create positive
drainage away from the trunk of preserved trees,
and to prevent ponding within the TPZ.

Supplemental irrigation of 1 to 2 inches monthly,
may be necessary within the TPZ of preserved
trees during construction within the dry season.

Impact BIO-1a:

Demolition of the
footbridge and tree
removal on the project
site could potentially
impact special-status bat
species that may use
them as a roost, and
could result in the direct
MM BIO-1a.1: A qualified biologist shall conduct a
roost assessment survey of trees and structures located within the project site prior to removal. The survey
will assess use of the features for roosting as well as potential presence of bats. To prove absence, one to
two nocturnal surveys with appropriate night vision
equipment must be conducted during those times when
bats would be occupying a roost (i.e., during the
maternity season). If the biologist finds no evidence of, The City will
ensure
implementation of
MM BIO-1a.1
occurs prior to
issuance of grading
permits and during
construction.

A final report
documenting the
survey effort and
any protection
measures
implemented by
the project shall be
submitted to the
Director of
Director of
Recreation and
Parks or designee

10 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
removal, abandonment,
or destruction of the
maternity roost.
or potential to support bat roosting, no further
measures are recommended as long as removal occurs
within seven days of the survey. If evidence of bat
roosting is present, additional measures described
below shall be implemented:

• If evidence of bat roosting is discovered during the
pre-construction roost assessment and demolition
is planned March 1 through April 14, or September
1 through October 14 (outside the winter
hibernation, and bat maternity roosting season), a
qualified biologist should implement passive
exclusion measures to prevent bats from re-
entering the structures. After sufficient time to
allow bats to escape and a follow-up survey to
determine if bats have vacated the roost,
demolition may continue and impacts to special-
status bat species will be avoided. For tree removal
that occurs during this time, trees should be felled
in a two-step method as follows:
o Remove limbs of trees first and leave them
unprocessed on the site for at least 24 hours.
o After the 24 hour period passes, the remainder
of the tree can be felled and debris can be
processed.

Recreation and
Parks or designee
prior to the start of
any grading and
demolition activity
or tree removal.

11 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
• If a pre-construction roost assessment discovers
evidence of bat roosting in structures or trees
during the maternity roosting season (April 15
through August 31) or winter hibernation season
(October 15 to February 28), and determines
maternity roosting bats or hibernating bats are
present, demolition of maternity roost or
hibernation structures will be avoided during the
maternity roosting and hibernation seasons or until
a qualified biologist determines the roost has been
vacated. Any trees removed during this time shall
follow the two-step method of removal described
above.

Impact BIO-1b:

Construction activities
associated with the
project could potentially
impact Northwestern
Pond Turtle (NPT)
adjacent to Roseland
Creek.

MM BIO-1b.1: To avoid impacting NPT, a pre-
construction survey shall determine if the species or its nests are present within work impact areas within 300
feet of Roseland Creek. The pre-construction survey
shall be completed within 48 hours prior to
commencement of work to locate any NPT nests or
individual turtles. If no NPT are located, the work may proceed without further actions. If NPT or active NPT
nests are found within the work area, they shall be
avoided by 50 feet and be allowed to leave on their
own accord. If NPT is in a work area that cannot be
The City will
ensure
implementation of
MM BIO-1b.1
occurs prior to
issuance of grading
permits and during
construction.

A final report
documenting the
survey effort and
any protection
measures
implemented by
the project shall be
submitted to the
Director of
Recreation and
Parks or designee
Director of
Recreation and
Parks or designee

12 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
avoided and/or does not leave the area, CDFW shall be
consulted to determine the procedure for relocation.

Any active NPT nest shall be avoided by 15 feet and if
it cannot be avoided, CDFW shall be consulted to
determine next steps. If NPT is listed under the Federal endangered species act, and cannot be avoided, CDFW
and USFWS shall be consulted to determine next
steps, as no “take” can occur without USFWS
authorization.

prior to the start of
any grading
activity.

Impact BIO-1c:

Construction activities
associated with the
project could potentially
impact California Tiger
Salamander (CTS)
occurring on the site and

1.37 acres of upland
dispersal habitat.

MM BIO-1c.1: The project shall implement the
following avoidance and mitigation measures
contained in the Santa Rosa Plan Conservation
Strategy:

• No ground disturbing activities shall be conducted
during the wet season (October 15 through June
15) when CTS migrate to and from breeding
habitats.
• The City or the project biologist shall consult the
72-hour weather forecast from the National
Weather Service (NWS) prior to the start of
ground disturbing activities. Ground disturbing
activities shall not begin unless a no precipitation
The City will
ensure
implementation of
MM BIO-1c.1 to
MM BIO-1c.2
occurs prior to
issuance of grading
permits and during
construction.

Work restrictions
shall be reflected
on all plans.

Mitigation credits,
if needed/required,
shall be purchased
prior to the
initiation of
grading activity on
the site.

Director of
Recreation and
Parks or designee

13 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
forecast is obtained and necessary erosion control
measures are implemented.
• Prior to the commencement of ground disturbing
activities, the site shall be inspected for burrows or
other refugia that could support CTS. If none are
detected, work can proceed without further
measures. If burrows or other refugia with
potential to support CTS are detected and cannot
be avoided, the project shall consult with CDFW to
determine if any additional measures, including an
incidental take permit, may be required.
• To substantiate that no CTS are present and/or
affected by the project, a qualified biological
monitor will be present during initial ground
disturbance. The biological monitor will conduct a
training session for all construction workers before
work is started on the project. If any CTS are
encountered during ground disturbing activities, all
work will stop and not commence until
authorization to commence work has been given
by CDFW and USFWS. Such authorization may
come in the form of take permits, if required.

14 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
• Access routes and number and size of staging and
work areas will be limited to the minimum
necessary.
• All foods and food-related trash items will be
enclosed in sealed trash containers at the end of
each day, and removed completely from the site
once every three days.
• No pets will be allowed anywhere in the project
site during construction.
• All equipment will be maintained such that there
will be no leaks of automotive fluids such as
gasoline, oils, or solvents.
• Hazardous materials such as fuels, oils, solvents,
etc., will be stored in sealable containers in a
designated location that is at least 200 feet from
Roseland Creek. All fueling and maintenance of
vehicles and other equipment and staging areas
will occur at least 200 feet from Roseland Creek.

MM BIO-1c.2: If it is determined that an incidental
take permit is needed because a reasonable
expectation of take has been found and cannot be
avoided, mitigation for impacts to CTS may be
determined to be necessary. In this case, CTS habitat

15 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
that is permanently and adversely impacted by the
project would be mitigated in accordance with the
ratios described in the Santa Rosa Plain Conservation
Strategy. The applicable ratio for mitigation in this
area is one to one. This ratio would be applied to the
net loss of suitable CTS habitat that results from the
project. The square footage of developed areas on-site
that would be removed (resulting in temporary
impacts of approximately 1.88 acres), and restored to
their natural state, may be used to offset novel
impacts that result from the project. A maximum of

1.37 acres of permanent impacts are expected to result
from the project, however, final mitigation ratio and
acreage requirements shall be finalized in consultation with CDFW and/or the USFWS. Permanent loss of
CTS habitat shall be mitigated at a one to one ratio.

Impact BIO-4:

Construction activities
and tree removal
associated with the
proposed project could
result in the loss of fertile
eggs, nesting raptors or
other migratory birds,
MM BIO-4.1: Construction shall be scheduled to
avoid the nesting season to the extent feasible. The
nesting season for most birds, including most raptors
in the San Francisco Bay area, extends from February
1 through September 1.

MM BIO-4.2: If it is not possible to schedule
demolition and construction between September and
The City shall
ensure measures
MM BIO-4.1
through MM BIO-

4.2 are
implemented prior
to issuance of
grading permits.

The biologist shall
complete (if
construction
occurs during
breeding season) a
survey and submit
the results of the
survey to the City
and CDFW, as
Director of
Recreation and
Parks or designee

16 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
and bat maternity roosts.

Nest abandonment could
also occur.

January, pre-construction surveys for nesting birds
shall be completed by a qualified ornithologist no
more than seven (7) days prior to the start of work to
ensure that no nests will be disturbed during project
implementation. During this survey, the ornithologist
will inspect all trees and other possible nesting habitats immediately adjacent to the construction areas for
nests. If an active nest is found sufficiently close to work areas to be disturbed by construction, the
ornithologist, in consultation with CDFW, will
determine the extent of a construction-free buffer zone to be established around the nest, typically 50 to 250
feet with the lesser distance for smaller passerine birds and the greater distance for raptors, to ensure that
raptor or migratory bird nests will not be disturbed
during project construction. Project activities may
resume within the buffer zone only after the young
have fledged the nest or the nest otherwise becomes
inactive. If disturbance does not commence within 7
days of the completed nesting survey, the survey
should be repeated to ensure that active nesting has not begun since the previous survey.

necessary, for
review and
approval.

17 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
Cultural Resources
Impact CUL-3:

Construction activities
associated with the
proposed project could
result in the disturbance
of subsurface prehistoric
and/or historic resources,
including a 19th century
cemetery.

MM CUL-3.1: No prehistoric or historical
archaeological sites were found within the study area
but a 19th century cemetery is reported to be within the study area. Therefore, any ground disturbing activities in the northeast part of the parcel at 1400 Burbank
Avenue (APN 125-331-001) shall be monitored by a
professional archaeologist and/or a tribal monitor from culturally affiliated Tribe(s). Implementation of the
following mitigation measures will reduce potential
impacts to prehistoric and historic resources to less
than significant levels.

• If cultural resources are discovered during the
project construction (inadvertent discoveries), all
work in the area of the find shall cease and a
qualified archaeologist and representatives of the
culturally affiliated tribe(s) shall be retained by the project sponsor to investigate the find and make
recommendations as to treatment and mitigation of
any impacts to those resources. A qualified
archaeological monitor will be present and will
have the authority to stop and redirect grading
activities, in consultation with any designated
tribal monitors, to evaluate the significance of any
The City and
contractors shall be
responsible for
implementing the
mitigation
measures during all
phases of
construction.

All measures shall
be printed on all
construction
documents,
contracts, and
project plans and
shall be reviewed
and approved by
the Director of
Recreation and
Parks or designee
prior to the
initiation of
construction
activities.

Director of
Recreation and
Parks or designee

18 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
archaeological resources discovered on the
property.
• If human remains are encountered, consistent with
California Health and Safety Code Section 7050.5,
no further disturbance shall occur until the Sonoma
County Coroner has made the necessary findings
as to origin of the remains. Further, consistent with
California Public Resources Code Section
5097.98(b), human remains shall be left in place
and free from disturbance until a final decision as
to the treatment and disposition has been made.
• If the Sonoma County Coroner determines the
remains to be Native American, the Native
American Heritage Commission shall be contacted
within twenty-four (24) hours. The Native
American Heritage Commission shall immediately
identify the “most likely descendant(s)” and notify
them of the discovery. The “most likely
descendant(s)” shall make recommendations
within forty-eight (48) hours, and engage in
consultations with the landowner concerning the
treatment of the remains, as provided in Public
Resources Code Section 5097.98.

19 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
Hazards and Hazardous Materials
Impact HAZ-2: The
presence of lead in soils
adjacent to previous
structures on the site and
a reported refuse dump
on the northwest side of
Roseland Creek
containing glass
containers and household
debris including
automobile parts could
present a material threat
of a potential release of
hazardous substances.

MM HAZ-2.1: Any debris or soil containing lead-
based paint or coatings or known to contain elevated
lead concentrations would be disposed of at landfills
that meet acceptance criteria for the waste being
disposed.

Soil sampling and analytical testing shall be performed on that portion of the site identified as the “refuse
dump” in the report entitled Phase I Environmental
Site Assessment, Roseland Creek Community Park,
1400 Burbank Avenue, APN 125-331-001, Santa
Rosa, California, prepared by Econ, dated February 19,
2010. If hazardous materials are detected at levels that exceed regulatory thresholds, the extent of the
contamination shall be identified, and
recommendations for a Health and Safety Plan (HSP),
Soil Management Plan (SMP), and methods for a
cleanup shall be implemented, as applicable. This
work shall be performed under the oversight of a
regulatory agency such as the Sonoma County
Department of Environmental Health and Safety or the
Department of Toxic Substances Control.

The City shall
ensure measure
MM HAZ-2.1 is
implemented prior
to issuance of
grading permits.

The contractor
shall perform
surveys prior to
grading and
provide the results
to the City for
review and
approval.

Director of
Recreation and
Parks or designee

20 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
Noise
Impact NOI-1: The
project would construct a
proposed park adjacent to
noise sensitive,
residential and
educational uses which
could result in temporary
disturbances during
construction.

MM NOI – 1.1: The City’s contractor will develop a
construction noise mitigation plan to ensure noise
levels would be reduced to 80 dBA L
eq at sensitive
receptors. The construction noise mitigation plan may
incorporate, but would not be limited to, the following best management practices:
• Maximize the physical separation between noise
generators and noise receptors. Such separation
includes, but is not limited to, the following
measures:
o Locate stationary equipment to minimize noise
impacts on the community;
o Minimize backing movements of equipment;
• Construct temporary noise barriers, where feasible,
to screen noise-generating equipment. Temporary
noise barrier fences would provide a five dBA
noise reduction where the noise barrier interrupts
the line-of-sight between the noise source and
receptor when constructed in a manner that
eliminates any cracks or gaps.
• Use quiet construction equipment whenever
possible and properly maintained and muffled
internal combustion engine-driven construction
equipment;
The City shall
ensure
implementation of
MM NOI-1.1
occurs during all
phases of
construction.

Copies of the
advance notice of
construction
activity shall be
provided to the City
prior to issuance of
a grading permit.

The Director of
Recreation and
Parks or designee
shall designate a
“disturbance
coordinator” for
construction
activities and
notify local
residents regarding
the proposed
construction
schedule.

Director of
Recreation and
Parks or designee

21 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
• Impact equipment (e.g., jack hammers and
pavement breakers) shall be hydraulically or
electrically powered wherever possible to avoid
noise associated with compressed air exhaust from
pneumatically-powered tools.
• Compressed air exhaust silencers shall be used on
other equipment.
• Prohibit unnecessary idling of internal combustion
engines.
• Limit construction hours from 7:00 am to 7:00 pm
Mondays through Saturdays, and 10:00 am to 6:00
pm on Sundays and holidays.
• The Director of Recreation and Parks shall
designate a “disturbance coordinator” for
construction activities. The coordinator would be
responsible for responding to any local complaints
regarding construction noise and vibration. The
coordinator would determine the cause of the noise
or vibration complaint and would implement
reasonable measures to correct the problem.
• The construction contractor shall send advance
notice in conjunction with the City of Santa Rosa
Recreation and Parks Department to neighborhood
residents within 300 feet of the project site as well

22 MITIGATION MONITORING AND REPORTING PROGRAM
Roseland Creek Community Park Master Plan Project

Impacts Mitigation and/or Standard Measure(s)
Timeframe and
Responsibility for
Implementation
Method of
Compliance
Oversight of
Implementation
as the Roseland Elementary School and Roseland
Accelerated Middle School administrators
regarding the construction schedule and including
the telephone number for the disturbance
coordinator at the construction site.

Source: Roseland Creek Community Park Final Environmental Impact Report. September 2024.