Laguna Treatment Plant Disinfection System Update
Mike Prinz -Deputy Director Regional Water Reuse Operations
2 3
4 5
8 New Hypo New Trailer
9 10
11 12
13 14
136 Concrete pours, including up to 23’ high walls, 3’ thick 7,039 CY of 7302 projected CY of concrete poured.
39,250 of 40,337 projected CY of excavation
(3,501 of 3,598 projected truckloads)
2.97 million lbs. of rebar placed (of projected 3.08 million lbs) 173,879 Labor hours
20-30(+) contractor staff on site on any given day
over $100,000/business day burn rate for contractor only By the Numbers (January 17, ’25)
15 2023 2024 2025
To Date: $54.8 M
(Including $3.2 M CCOs)
Construction Payments