Project Bid Summary
Project Name: LOW IMPACT DEVELOPMENT AT MUNICIPAL SERVICES CENTER NORTH (MSCN) Contract No: C02391
Bid Opening: 3/3/2025
Business Name Total Bid Amount % Over/Under Estimate
Engineer's Estimate $453,058.50
CORCUS CONSTRUCTION, INC $567,912.00 25.35% OVER
GHILOTTI BROS, INC $879,000.00 94.01% OVER
ATTACHMENT 2
Project Name: LOW IMPACT DEVELOPMENT AT MUNICIPAL SERVICES CENTER NORTH (MSCN) Contract No: C02391
Bid Opening: 3/3/2025
CORCUS CONSTRUCTION, INC GHILOTTI BROS, INC
Line Number Description Unit Quantity Estim ated Price Estimated Total Price Total Price Total 1 1 TEMPORARY RAILING TYPE K (K RAIL) LS 1 $18,000.00 $18,000.00 $15,000.00 $15,000.00 $138,885.00 $138,885.00 2 2 WATER POLLUTION CONTROL LS 1 $6,000. 00 $6,000.00 $8,500.00 $8, 500.00 $71,900.00 $71,900.00 3 3 MODIFY SD INLETS EA 2 $5,000.00 $10,000.00 $3,500.00 $7,000.00 $2,000.00 $4,000.00 4 4 REMOVE ASPHALT, BASE, AND SUBGRADE SF 6,000 $20.00 $120,000.00 $6.50 $39,000.00 $36.00 $216,000.00 5 5 IRRIGATION LS 1 $53, 845.00 $53,845.00 $55,000.00 $55, 000.00 $60,000.00 $60,000.00 6 6 PLANT ESTABLISHMENT LS 1 $9,770.00 $9, 770.00 $27,000.00 $27,000. 00 $6,300.00 $6,300.00 7 7 BIORETENTION AREA SF 4,367 $30. 00 $131,010.00 $71.00 $310, 057.00 $59.00 $257,653.00 8 8 6" PERFORATED PIPE - PVC LF 97 $25. 00 $2,425.00 $220.00 $21, 340.00 $16.00 $1,552.00 9 9 HOT MIX ASPHALT TON 70 $300.00 $21, 000.00 $110.00 $7,700.00 $367.00 $25,690.00 10 10 CURB AND GUTTER WITH RETAINING CURB LF 283 $255.00 $72,165.00 $210.00 $59,430.00 $300.00 $84,900.00 11 11 FLEXIBLE DELINEATORS EA 14 $75.00 $1,050.00 $185.00 $2, 590.00 $225.00 $3,150.00 12 12 STRIPING (4" WHITE THERMOPLASTIC STRIPE LF 1,220 $5.00 $6,100.00 $10.00 $12,200.00 $4.00 $4,880.00 13 13 PAVEMENT MARKING (TYPE I ARROW) SF 84 $5.00 $420.00 $20.00 $1,680.00 $15.00 $1,260.00 14 14 REFLECTIVE WHITE PAINT ON CURB LF 283 $4.50 $1,273.50 $5.00 $1,415.00 $10.00 $2,830.00 $453,058.50 $567,912.00 $879,000.00