Santa Rosa EV Masterplan
Santa Rosa City Council
NV5.COM | Delivering Solutions — Improving Lives
PROJECT BACKGROUND
GOALS
• A roadmap to compliance with State
Advanced Clean Fleet Regulations
• Strategy for continuity of fleet
operations, city services
• Evaluate EV charging options during
grid outage
• Provide policy recommendations to
expand EV charger access
NV5.COM | Delivering Solutions — Improving Lives
CITY OF SANTA ROSA FLEET VEHICLES
3 4
10 17
50 129
170
0 2 04 06 08 0 1 0 0 1 2 0 1 4 0 1 6 0 1 8 0
Housing and Community Service
Information Technology
Transit
Planning and Economic Development
Recreation
Public Works
Water
Vehicles by Department
Light Duty Medium Duty Heavy Duty Non Road Construction Note: Public Safety vehicles and Buses not included
NV5.COM | Delivering Solutions — Improving Lives
PURCHASE SCHEDULE ASSUMPTIONS
• Vehicles are replaced at the end of their
planned service life
• Overdue replacements are spread over the
first 4 years of the transition
• EVs are purchased if a feasible AND suitable
model is available
• Cap of $10M annually, not adjusted for
inflation
Replacements Costs
• EV cost reference current market prices
• EVs that are not commercially available are assumed to be 2.5x the price of their fossil fuel counterparts in 2025 • Costs projected to the future based on International
Council on Clean Transportation studies (graph below)
2027 Onward2025-2026ACF
100%50%EV %
Source: ICCT
4 NV5.COM | Delivering Solutions — Improving Lives
ACF COMPLIANCE REALIZATION CHALLENGES
Mismatch between vehicles that CARB
considers available as an EV and those that
Santa Rosa may consider suitable as an EV.
1 CARB Exempt Vehicles List
5 Santa Rosa considers ¾, 1,
1.5-ton EV pickups not
available in 2025 since they
aren’t commercially sold
CARB granted categorical exemption
to very few vehicle types
Class 1, Off-Road, Construction Vehicles
Class 2B-8 Vehicles
CARB considers those EVs
available because EV van
chassis can be upfit with
pickup truck body styles.
1 NV5.COM | Delivering Solutions — Improving Lives
ACF COMPLIANCE IN CURRENT PLAN
• ACF compliance is expected to be achievable from 2027. • Overcompliance (2028) count towards future compliance (2029) 203020292028202720262025Purchases of ACF-regulated vehicles 100%50%ZEV Purchase Requirement
(Current)ACF Purchase
Rules 100%50%ZEV Purchase Requirement
(Post 2027 Update)
100%17%78%53%10%8%Percent Electric Purchases
Non-Exempt 24231843Electric Purchases
010973535Fossil Fuel Purchases
6 NV5.COM | Delivering Solutions — Improving Lives
RESULTS – EV ADOPTION TREND
10%
17%
28%
40% 41%
49%
56% 58% 62% 66%
80%
87% 90%
96% 99% 100%
0 50
100
150
200
250
300
350
400
2025 2028 2031 2034 2037 2040
EV Fleet Composition from 2025 to 2040
EVs ICE
7 NV5.COM | Delivering Solutions — Improving Lives
FUEL TRANSITION
$0
$200,000
$400,000
$600,000
$800,000
$1,000,000
Annual Fuel Cost
Electricity Gasoline Diesel Propane Baseline
- 53%
0 20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
180,000
200,000 Fuel (GGE)
Annual Fuel Consumption
(Gasoline Gallon Equivalent)
Electricity Gasoline Diesel Propane Baseline Total
8 - 63%
NV5.COM | Delivering Solutions — Improving Lives
RESULTS – ALL-IN EV ADOPTION COST
Not IncludedIncluded
Incentives
Inflation Reduction
Act
($2.4 million)
PG&E EV Fleet
($0.5 million)
Communities in
Charge
($0.4 million)
Incentives from
BAAQMD, Sonoma
Clean Power, HVIP
Nominal Cost Increase of $38 million
EV Purchase: $28 million
EV Chargers: $10 million 9
$0
$3,000,000
$6,000,000
$9,000,000
$12,000,000
$15,000,000
$18,000,000
Annual All-In Cost of Baseline vs Transition Scenarios
EV Charging Infrastructure Incremental Cost
EV Purchase Incremental Cost
Business as Usual
NV5.COM | Delivering Solutions — Improving Lives
RESILIENCY STUDY OVERVIEW
• 6 backup EV charging locations
• 2 configurations reviewed
- Solar panels + stationary battery
storage + generator
- Generator Only
10 EV charging site with backup power
EV charging site without backup power
NV5.COM | Delivering Solutions — Improving Lives
RESULTS – EV CHARGER INSTALLATIONS
11 Conceptual layout at MSC North
13 77
48 23
38 12
21 36
2 0
10 20
30 40
50 60
70 80
90 2027 2030 2035
Chargers Added by Phase
L3 - 60kW
L3 - 30kW
L2 - 16.6kW
L1 - 1kW
Concepts developed for 8 total sites:
MSC North, MSC South, UFO, Finley Park, City Hall, Laguna Treatment Plant, Brown Farm, Station 4
NV5.COM | Delivering Solutions — Improving Lives
BACKUP EV CHARGING OPTIONS
Solar + Battery +
Generators all 6 sites
Generators all 6
sites
($14.6 million)($2.6 million)Capital Cost
($11.8 million)($3.4 million)25-Year Net Present
Value
27.646Annual GHG Emission
(metric tons)
• Department staff provided assumptions on operational needs during power outages.
• Assumptions:
• Three 1-day outages per year
• One 7-day outage per 4-years
Conceptual layout at Sonoma Ave WTP
Battery Generator
Solar
EV Chargers
NV5.COM | Delivering Solutions — Improving Lives
POLICY STUDY OVERVIEW
• Planning and Economic Development (PED) seeks recommendations on encouraging private-led EV charger deployment in the public right of way. • Santa Rosa’sGeneral Plan 2050 and GHG Reduction Strategy include objectives and measures for increased public EV charging.
• NV5 and Santa Rosa interviewed:
- EV charger companies (It’s Electric, Voltpost)
- City of Santa Rosa (Planning, Parking)
- City of San Francisco (SF DPW, SF Environment, SFMTA) - City of Alameda
It’s Electric EV Charging Station
NV5.COM | Delivering Solutions — Improving Lives
POLICY STUDY OVERVIEW - RECOMMENDATIONS
1. Impact/Development Fees
- Develop Capital Investment Plan for a city-wide
deployment of EV chargers
- Collect development fees to fund the program
- Determine priority locations (charging deserts)
2. Facilitate Private Agreements for EV
Charger Providers
- Establish permitting pathways for private
companies to partner with property owners to
install EV chargers on curbside
- Update regulations to allow installations
3. Develop a Public EV Charging Task Force
EV charger map from PlugShare
NV5.COM | Delivering Solutions — Improving Lives
MAIN FINDINGS OF FLEET ELECTRIFICATION STUDY
1. Fleet Electrification costs $38 million from 2025 to 2040 over business as usual.
2. Near-term compliance with ACF is difficult due to vehicle availability and cost.
3. City should pursue all exemptions allowable under ACF, and update fleet electrification plan to match future ACF amendments.
4. City should standardize a charge management platform and EV charger.
5. City fleet should leverage CityBus EV chargers for near-term charging flexibility.
6. Conventionally fueled internal combustion generators are currently the most cost- effective option to provide EV charging resiliency to the City.
7. City should explore detailed feasibility, regulatory requirements, and costs of installing generators at EV charging depots.
NV5.COM | Delivering Solutions — Improving Lives
RECOMMENDATION
It is recommended by the Board of Public
Utilities, Santa Rosa Water, and the
Transportation and Public Works
Department that the Council, by motion,
review and accept the Fleet Electrification
Master Plan
NV5.COM | Delivering Solutions — Improving Lives
QUESTIONS