SPECIAL CITY COUNCIL MEETING MINUTES
Monday, January 22, 2024

CALL TO ORDER
The meeting was called to order by Mayor Sobieski at 6:00 p.m., with the meeting conducted via in-person and Zoom.

Councilmember Blaustein
Councilmember Hoffman
councilmember Kellmar
lice Mayor Cor
Mayor Sobieski

BUSINESS ITEMS

1.A. Receive and File the Parametric Insurance Presentation and Provide Direction to Staff Regarding City Interest
Chris Zapata, City Manager, Bridget Carle, Senior Vice President, Public Sector Practice, Guy Carpenter, and Joseph Becker, Senior Vice President, Guy Carpenter made a presentation and responded to questions posed by the City Council.

The City Council directed staff to provide a running total of staff time, a cost breakdown, and for Guy Carpenter to review all reports if they have not done so.

PUBLIC HEARING ITEMS

2.A. Appeal of a Planning Commission Decision Approving Design Review with Heightened Design Review and Encroachment Permit 2023-00013 for 426 Pine Street (APN: 065-054-11)
Members of the City Council announced their ex parte communications.

Brandon Phipps, Community & Economic Development Director, and Kristin Teiche, Principal Planner, made a presentation and responded to questions posed by the City Council.

David Grann, Applicant and Owner/Owner/Principal Designer/Project Manager of G Family Construction, Lam Ngyuen, BIM Designer/Draftsman made a presentation and responded to questions posed by the City Council.

Appellant Conrad Gann, Michael Rex, Sam Chase, and Elizabeth made a presentation and responded to questions posed by the City Council. 1 of 2
Stuart Rabinowitsh, Alice Merrill, Lorraine Cline, Ray Swanson, Jeffrey Conan, and Lori provided public comments.

Jake Beyer, Applicant, and David Grann, Applicant and Owner/Owner/Principal Designer/Project Manager of G Family Construction, made a rebuttal and responded to questions posed by the City Council.

Vice Mayor Cox moved, seconded by Councilmember Hoffman, to continue the hearing to a date uncertain to allow the applicant an opportunity to address the design review and heighten design review findings council as a body indicated were not able to and revise the designs to remove the decks as discussed with the proviso that it is a permanent removal, and applicant will not return in the future to seek approval of adding a deck by the following 4-1 vote:

AYES:

Councilmember Blaustein
ABSTAIN:

Mayor Sobieski

2.B. Adopt a Resolution Authorizing staff to issue a Request for Proposals for the 2024 Building Facility Assessment Study.

Sandra Bushmaker provided public comment.

The City Council continued the item.

ADJOURNMENT
Mayor Sobieski adjourned the meeting at 10:03 p.m.