PART 3 - 100 v04262022

SPECIAL PROVISIONS
Failure to comply with this section will prevent the City from towing vehicles parked in the proposed work area. Work will not proceed if vehicles are parked in the proposed work area.

Full compensation for providing all labor, equipment and materials necessary for the furnishing and placement of construction area signs shall be included in the lump sum paid for construction area signs and no additional compensation shall be allowed, therefore. Compensation for providing all labor, equipment and materials necessary for the removal of construction area signs shall be considered as included in the prices paid for related bid items and no additional compensation shall be allowed. 14-1.10 Maintaining Traffic. In addition to complying with Part III – Section 30 of the Special Provisions, attention is directed to Section 12-1.05, “Maintaining Traffic and Pedestrian Obstructions”, of the General Provisions. Unless otherwise directed by the City, at all times during construction the Contractor shall maintain not less than one lane of traffic on State Route 116, each direction, and not less than one lane of traffic on all intersecting streets where ADA Ramps improvements are proposed.

Maintaining Traffic shall be paid as part of the bid item for Traffic Control. No separate payment will be made, therefore.
14-1.11 Notice to Area Residents. The Contractor shall provide notice to all residents, business owners and tenants affected by the construction relative to the Contractor’s schedule of work including the traffic control provisions during construction. A sample notice shall be provided to the Contractor by the City. If the Contractor desires to modify the notice, the revisions must be submitted to the City for approval at least 10 days prior to beginning work. The Notice to Area Residents and to businesses shall be a door hanger type notice printed on heavy paper or cardboard. The dates of work shall match the work schedule provided to and approved by the City.

If the Contractors schedule shall change to include dates of work beyond the dates indicated in the posted notices, the Contractor shall repost such notices at least 48 hours prior to commencing work on the changed schedule work.
14-1.12 Traffic Control. Comply with Part III – Section 31 of the Special Provisions. All costs associated with traffic control including construction area signs, maintaining traffic, placing no parking signs and notice to area residents and businesses shall be included in the lump sum paid for Traffic Control. The lump sum paid for traffic control shall include all costs associated with the work described herein including all labor, equipment, materials, printing costs and other associated costs with completing the work. Payment for Traffic Control shall be paid as a percentage of work completed. 14-1.13 Existing Highway Facilities. The work performed in connection with various existing highway facilities shall conform to the provisions in Section 15, "Existing Facilities," of the Standard Specifications and these Specifications
Residue from the removal of existing roadway, curb, gutter, sidewalk and ramp improvements shall be disposed of immediately after removal. Residue shall not be allowed to enter the storm drain system. Disposal shall be performed in accordance with Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 111 of 219 ends

PART 3 - 101 v04262022

SPECIAL PROVISIONS
Section 15-1.03B “Removing Concrete” of the Standard Specifications and these Specifications.

Full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved including, but not limited to, removal and disposal of curb, gutter, sidewalk ramps and asphalt and unsuitable material shall be considered as included in the contract unit prices for the various items of work and no additional compensation will be allowed.
14-1.14 Work Within Caltrans R/W. In general the State Route 116 ADA Sidewalk Ramp improvements are located within the limits of the Caltrans State Route 116 R/W.

Improvements have been prepared in conformance with the 2018 Caltrans Standard Plans. Caltrans has reviewed the improvement plans prepared for this project and has issued an Encroachment Permit to the City of Sebastopol (Permit No. 04-17-N-MC0670). A copy of this Encroachment Permit is included in the Appendix of these Contract Documents.

Full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all work for the Contractor’s compliance with the provisions of the Caltrans Encroachment Permit shall be considered as included in the contract prices paid for the various items of work and no additional compensation will be allowed. 14-1.15 Clearing and Grubbing. Clearing and grubbing shall conform to the provisions in Section 17-2, "Clearing and Grubbing," of the Standard Specifications and these Specifications.

All existing vegetation, outside the areas to be cleared and grubbed, shall be protected from the Contractor's operations unless specifically shown on the plans to be removed.

Nothing herein shall be construed as relieving the Contractor of his responsibility for final cleanup of the highway as provided in Section 4-1.13, "Cleanup," of the Standard Specifications.

Compensation for clearing and grubbing shall be included in the various items of work and no separate or additional compensation shall be made therefore. 14-1.16 Watering. Watering shall conform to the provisions in Section 14.4, "Water Usage," of the Standard Specification.

Attention is directed to Section 12-1.14, “Water For Construction And Dust Control”, of the General Provisions.

Full compensation for developing a water supply shall be considered as included in the contract prices paid for the various items of work involved and no additional compensation will be allowed.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 112 of 219 ends

PART 3 - 102 v04262022

SPECIAL PROVISIONS
SECTION 14-2 TECHNICAL SPECIFICATIONS
14-2.01 MOBILIZATION, BONDS & INSURANCE. Mobilization shall consist of preparatory work and operations, including but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to and from the project site; for the establishment of all offices, buildings, construction yards, sanitary facilities, and any other facilities necessary for work on the project; and for all other work and operations which must be performed or costs incurred prior to beginning work on the various contract items on the project site, as well as the related demobilization costs anticipated at the completion of the project. The cost of all bonds and insurance policies, including premiums and incidentals, shall be included in mobilization. Unless otherwise approved by the City, the price bid for Mobilization, Bonds and Insurance shall not exceed 10% of the total contract amount.

No additional compensation will be allowed for additional mobilizations required, including but not limited to, delays caused by the relocation of existing utility facilities shown on the Plans or discovered during construction operations.

The deletion of work or the addition of extra work as provided for herein shall not affect the price paid for Mobilization.

Payment for "Mobilization, Bonds, & Insurance" will be made at the Contract Lump Sum price included in the Bid Schedule. Said price shall constitute full compensation for all such work. Payment for Mobilization will be made as follows:
70% of the bid item for Mobilization will be paid on the first progress payment. 100% of the bid item for Mobilization will be paid on the second progress payment, unless all the Mobilization items listed herein have not been completed, at which point payment will be withheld until all the items are completed.
14-2.02 REMOVE EXISTING ASPHALT PAVEMENT, PAVEMENT BASE ROCK AND SUBBASE MATERIAL. Existing asphalt concrete pavement, base rock and subbase material shall be removed to the limits and to the depth shown on the Plans. Saw cut the existing pavement at the limits of work so that the visible edge of the remaining asphalt form a neat straight line. Asphalt concrete pavement, base rock and subbase material removed shall be properly disposed of offsite by the Contractor. Contractor shall wedge grind a 5-foot conform where shown on the plans.

All costs for removal of existing asphalt concrete pavement (excluding cold plane asphalt concrete pavement), base rock and subbase shall be included in the unit price per Cubic Yard paid for “Roadway Excavation” and shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all the work involved with removing asphalt concrete pavement (excluding cold plane asphalt concrete pavement), base rock and subbase removal and disposal as shown on the Plans, as specified in the Standard Specifications, these Specifications and as directed by the City and no additional compensation shall be allowed.
14-2.03 REMOVE CONCRETE. Existing concrete, including curbs, sidewalks, gutters, curb ramps, and other PCC surface structures as shown on the plans, shall be removed to Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 113 of 219 ends

PART 3 - 103 v04262022

SPECIAL PROVISIONS
the limits shown on the Plans. Saw cut the existing concrete at the limits of work so that the visible edge of the remaining concrete forms a neat straight line. Demolished concrete shall be disposed of at a facility which recycles broken PCC into usable construction materials.

Removal of base and subbase beneath PCC shall be included in PCC removal.

The contract unit price paid per Cubic Yard of Remove Concrete shall include full compensation for furnishing all labor, materials, tools, equipment, incidentals, and for doing all work involved in the demolition and removal of concrete as shown on the Plans, as specified in the Standard Specifications, these Specifications, and as directed by the City and no additional compensation will be made therefore. 14-2.04 CLASS 2 AGGREGATE BASE. Aggregate base shall be Class 2 and shall conform to Section 26, “Aggregate Bases,” of the Standard Specifications, and these Specifications.

Prior to placing the new Aggregate Base, the Contractor shall compact the existing subgrade materials to 95% RC. If soft and yielding sections are present, the Contractor shall excavate the soft sections to firm grade and fill with compacted Aggregate Base.

The cost for excavating the soft material shall be included in the unit price for Aggregate Base, and no additional compensation shall be paid.

Aggregate base shall be produced from commercial quality aggregate consisting of broken stone, crushed gravel, clean, rough-surfaced gravel and sand, or a combination thereof. The grading of the material shall be three-fourth inch (3/4”) maximum.

Spreading and compacting shall be performed by methods that will produce a uniform base when firmly and properly compacted free from pockets of coarse or fine material.

Compact aggregate base material to not less than 95% Relative Compaction per ASTM D1557
Class 2 Aggregate Base shall be placed, where shown on the Plans, under new pavement, curb ramps, curb, gutter, sidewalk, and driveway as specified in these Specifications, and as directed by the City. Place aggregate base material in lifts not greater than 4 inches compacted thickness.

Finished grade tolerances shall conform to the State Standard Specifications.

Furnishing and placement of Class 2 Aggregate Base for curb ramps, curb, gutter, sidewalk, and driveway shall be included in the unit price per Cubic Yard for Portland cement concrete for the associated item, and no additional compensation will be allowed therefore.

The contract unit price paid per Cubic Yard of Class 2 Aggregate Base furnished and placed for pavement reconstruction shall include full compensation for furnishing all labor, materials, tools, equipment, incidentals, and for doing all work involved in excavating, placing, and compacting Class 2 Aggregate Base as shown on the Plans, as specified in the Standard Specifications, these Specifications, and as directed by the City and no additional compensation will be allowed.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 114 of 219 ends

PART 3 - 104 v04262022

SPECIAL PROVISIONS
14-2.05 HOT MIX ASPHALT TYPE A. Hot Mix Asphalt concrete shall be Type A and shall conform to the provisions of Section 39, “Asphalt Concrete,” of the Standard Specifications and these Specifications.

The paving asphalt shall be Performance Grade (PG) 64-16 per Section 92, “Asphalt Binders,” of the Standard Specifications.

The final pavement elevation shall be ± ¼” higher than the adjacent lip of gutter. Where paving a hot mix asphalt section with a total thickness that exceeds that of an adjacent overlay thickness, place the final lift of hot mix asphalt with the same paving operation as the overlay placement.

Emulsion shall be applied to both the vertical edges of the existing pavement or the existing curb and gutter prior to placing new asphalt concrete. Asphaltic emulsions shall conform to Section 94, “Asphaltic Emulsions” of the Standard Specifications and shall be included in the unit bid price for Hot Mix Asphalt, Type A and no additional compensation shall be allowed therefore. If the final lift of pavement is not placed on the same day as the initial pavement course, a tack coat shall be placed on the surface of the initial pavement course prior to placement of the final pavement course.

The contract unit price paid per Ton of Hot Mix Asphalt, Type A shall include full compensation for furnishing all labor, materials, tools, equipment, incidentals, and for doing all work involved in the production, delivery, and placement of Hot Mix Asphalt Type A as shown on the Plans, as specified in the Standard Specifications, these Specifications, and as directed by the City and no additional compensation will be made therefore.
14-2.06 COMPENSATION ADJUSTMENTS FOR PRICE INDEX FLUCTUATIONS. The provisions of this section shall apply only to the following contract item:

A. Hot Mix Asphalt, Type A
The compensation payable for the above listed items will be increased or decreased in conformance with the provisions of this section for paving asphalt price fluctuations exceeding 10 percent (Iu/Ib is greater than 1.10 or less than 0.90) which occur during performance of the work.

The adjustment in compensation will be determined in conformance with the following formulae when the above listed items are included in a monthly estimate:

Total monthly adjustment = AQ
A. For an increase in paving asphalt price index exceeding 10 percent::

A = 0.90 (Iu/Ib-1.10) Ib
B. For a decrease in paving asphalt price index exceeding 10 percent:

A = 0.90 (Iu/Ib-0.90) Ib
C. Where:

1. A = Adjustment in dollars per ton of paving asphalt used to produce asphalt concrete and asphaltic emulsion residue used as paint binder rounded to the nearest $0.01.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 115 of 219 ends

PART 3 - 105 v04262022

SPECIAL PROVISIONS

2. Iu = The California Statewide Paving Asphalt Price Index which is in effect on the first business day of the month within the pay period in which the quantity subject to adjustment was included in the estimate.

3. Ib = The California Statewide Paving Asphalt Price Index for the month in which the bid opening for the project occurred.

4. Q = Quantity in tons of paving asphalt that was used in producing the quantity of asphalt concrete shown on the monthly estimate using the amount of asphalt determined by the Engineer plus the quantity in tons of paving asphalt that would have been used as residue in the asphaltic emulsion (paint binder) shown on the monthly estimate.

The adjustment in compensation will also be subject to the following:

A. The compensation adjustments provided herein will be shown separately on payment estimates. The Contractor shall be liable to the City for decreased compensation adjustments and the City may deduct the amount thereof from moneys due or that may become due the Contractor.

B. Compensation adjustments made under this section will be taken into account in making adjustments in conformance with the provisions in Section 9-1.06 “Changed Quantity Payment Adjustments" of the Standard Specifications.

C. In the event of an overrun of contract time, adjustment in compensation for paving asphalt included in estimates during the overrun period will be determined using the California Statewide Paving Asphalt Price Index in effect on the first business day of the month within the pay period in which the overrun began.

The California Statewide Paving Asphalt Price Index is determined each month on the first business day of the month by the City using the median of posted prices in effect as posted by Chevron, Exxon Mobil, and ConocoPhillips for the Buena Vista and Midway Sunset fields.

In the event that the companies discontinue posting their prices for a field, the City will determine an index from the remaining posted prices. The City reserves the right to include in the index determination the posted prices of additional fields.

The California Statewide Crude Oil Price Index is available on the Division of Construction website at: https://dot.ca.gov/programs/construction/california-statewidecrude-oil-price-index 14-2.07 COLD PLANE ASPHALT CONCRETE PAVEMENT. Cold plane asphalt concrete pavement shall conform to the provisions of Section 39-3.04, “Cold Planing Asphalt Concrete Pavement,” of the Standard Specifications and these Specifications. Pavement shall be planed to the areas and the depth shown on the Project Plans.

Geotechnical borings of the existing pavement found pavement fabric between existing asphalt concrete layers at one location. The Contractor is hereby made aware that pavement fabric may be encountered during cold planning operations.

If permanent asphalt concrete has not been placed to the level of existing pavement before the pavement is to be opened to public traffic, a temporary asphalt concrete taper Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 116 of 219 ends

PART 3 - 106 v04262022

SPECIAL PROVISIONS
shall be constructed. Asphalt concrete for temporary tapers shall be placed to the level of the existing pavement and tapered in five (5) feet to the level of the planed area.

Asphalt concrete for tapers shall be commercial quality and may be spread and compacted by any method that will produce a smooth riding surface. Asphalt concrete tapers shall be completely removed, including removing all loose material from the underlying surface, before placing the permanent surfacing. Full compensation for furnishing asphalt concrete for temporary tapers and for constructing, maintaining, removing, and disposing of the tapers shall be considered as included in the contract price paid per square yard for wedge grinding and no additional compensation will be allowed therefore.

All material planed from the roadway surface, including material deposited in existing gutters or the adjacent traveled way, shall be immediately removed from the surface and disposed of off-site as directed in these Specifications or by the City. The removal crew shall follow within fifty (50) feet of the planer.

All planed material, not used to replace unsuitable material removed from the project area, shall be transported and properly disposed of offsite. Transport and off-loading of material shall be considered incidental and included in the unit price paid for this item.

Following planing operations, no drop-off will be allowed at any time adjacent to driveways or around the edges of manhole rims, drain inlets, vaults, valve boxes, and any other roadway appurtenances that are open to traffic. Where transverse joints are planed in the pavement at conform lines, no drop-off shall remain between the existing pavement and the planed area when the pavement is opened to public traffic.

Cold plane asphalt concrete pavement will be measured by the square yard. The quantity to be paid will be the actual area of pavement cold planed, irrespective of the number of passes required to obtain the specified depth.

The contract unit price paid per Square Yard of Cold Plane Asphalt Concrete shall include full compensation for furnishing all labor, materials, tools, equipment, incidentals and for doing all work involved in cold planning asphalt concrete pavement as shown on the Plans, as specified in the Standard Specifications, these Specifications and as directed by the City and no additional compensation will be allowed, therefore.

When shown on the Project Plans or directed by the City, wedge grinding shall consist of cold planing a 5 to 9 foot wide continuous section of asphalt pavement to the limits shown on the Project Plans. The depth of the planing below the gutter lip shall be 1-¾”.

The pavement overlay grade shall be ¼” higher than the adjacent lip of gutter.

The wedge grinding of asphalt concrete pavement shall be performed by cold planing.

The cold planing machine shall have a cutter head at least five (5) feet wide and shall be operated so as not to produce fumes or smoke. The depth, width, and shape of the cut shall be as shown on the Project Plans, or as directed by the City. The final cut shall result in a uniform surface. The outside lines of the planed area shall be neat and uniform. The road surfacing to remain in place shall not be damaged in any way. The planed road surface shall not be damaged or spalled.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 117 of 219 ends

PART 3 - 107 v04262022

SPECIAL PROVISIONS
Wedge grinding will be measured by the square foot. The quantity to be paid will be the actual area of pavement cold planed, irrespective of the number of passes required to obtain the specified depth.

The contract unit price paid per Square Foot of wedge grind shall include full compensation for furnishing all labor, materials, tools, equipment, incidentals and for doing all work involved in the wedge grind as shown on the Plans, as specified in the Standard Specifications, these Specifications and as directed by the City and no additional compensation will be allowed, therefore.
14-2.08 GEOSYNTHETIC PAVEMENT INTERLAYER (PAVING MAT. A geosyntheic pavement interlayer (paving mat) shall be placed on all cold planed asphalt concrete surfaces prior to placement of hot mix asphalt overlay. Place geosyntheic pavement interlayer (paving mat) per Section 39, “Asphalt Concrete” of the Standard Specifications and per manufacturer’s instructions. Geosyntheic pavement interlayer (paving mat) material shall conform to Section 96, “Geosynthetics” of the Standard Specifications and these Specifications.

Asphalt binder shall be Performance Grade (PG) 64-16 unless otherwise directed by the City.

The contract unit price paid per Square Yard of Geosyntheic Pavement Interlayer (Paving Mat) shall include full compensation for furnishing all labor, materials, tools, equipment, incidentals and for doing all work involved in placing geosyntheic pavement interlayer (paving mat) as shown on the Plans, as specified in the Standard Specifications, these Specifications and as directed by the City and no additional compensation will be allowed, therefore. The payment quantity for geosynthetic pavement interlayer is the area measured from the actual pavement covered, with no additional payment made for overlaps in material. Payment for asphalt binder required for placement shall be included in the unit price paid for geosyntheic pavement interlayer (paving mat).
14-2.09 REPLACE MANHOLE FRAME AND COVER. Manhole frame and cover material and installation shall conform Section 14-2.10 “Adjust Manhole to Grade” of these Specifications, the Sebastopol Standard Construction Drawing, and as directed by the City.

All materials removed during replacement shall become the property of the Contractor and shall be properly disposed of offsite.

The contract unit price paid per Each replace manhole frame and cover shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all work in replacing the manhole frame and cover as specified in the Standard Specifications, these Specifications, the Plans, the Sebastopol Standard Construction Drawings, and as directed by the City and no additional compensation shall be allowed. 14-2.10 ADJUST MANHOLE TO GRADE. Manhole covers shall be set flush with finished paved surface. Finished grade construction shall conform to City of Sebastopol Standard Drawing. Manholes located within the limits of asphalt pavement work shall be carefully referenced prior to the placement of the final asphalt pavement course. When covered Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 118 of 219 ends

PART 3 - 108 v04262022

SPECIAL PROVISIONS
by paving operations, the location of the manhole covers shall be painted on the asphalt surface immediately after paving.

The manhole covers shall be adjusted to grade conventionally. Grade rings are not acceptable. Adjustment of manhole covers shall be accomplished by removing the existing frame and cover, removing the existing concrete encasement, pouring a new concrete encasement, resetting the existing frame and cover and then placing 2” thick asphalt concrete over the concrete encasement.

The manhole opening shall be covered during the entire operation so that no debris can fall into the manhole. Extreme care shall be taken to prevent spilling foreign material into the sanitary sewer system. The City will require the Contractor to immediately remove the manhole cover for inspection to determine if any foreign material has fallen into the manhole.

All materials removed during adjustment, except the existing frame and cover and shall become the property of the Contractor and shall be properly disposed of offsite. If, in the City’s judgment, the existing frames or covers are unsuitable, the existing damaged frame or cover shall be replaced with new frame and cover as appropriate. Unsuitable frames and covers shall become the property of the Contractor and shall be properly disposed of offsite. The cost of replacing unsuitable frames and covers which, in the City’s judgment, were damaged by the Contractor’s operations shall be at the Contractor’s expense.

The contract unit price paid per Each adjust manhole to grade shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all work in adjusting the manhole as specified in the Standard Specifications, these Specifications, the Plans, the Sebastopol Standard Construction Drawing, and as directed by the City and no additional compensation shall be allowed. 14-2.11 ADJUST UTILITY VALVE COVERS TO GRADE. Valve covers shall be adjusted to grade in accordance with City Standard Specifications and Standard Drawing W-2.1, or per utility owner standards. All valves shall be carefully referenced prior to the placement of the final asphalt pavement. When covered by paving operations, the location of the valve covers shall be painted on the asphalt surface immediately after paving.

City owned valve box covers shall be adjusted to grade conventionally. Adjustment of valve covers to finished grade shall be accomplished by removing the existing frame and cover, removing the existing concrete encasement, paving a new concrete encasement, resetting the existing frame and cover and then placing 2” thick asphalt concrete over the concrete encasement.

The valve opening shall be covered during the entire operation so that no debris can fall into the valve opening and damage the valve. Prior to the placement of the new concrete, the Contractor shall demonstrate to the satisfaction of the City, that each water valve is operating properly and has not been damaged by the Contractor’s operations.

At the Contractor’s expense, any water valve damaged during the construction of the pavement reconstruction improvements shall be replaced with a new, City standard, water valve matching the size, type and valve manufacturer and model of the valve replaced.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 119 of 219 ends

PART 3 - 109 v04262022

SPECIAL PROVISIONS
All materials removed during adjusting the utility valve covers to grade shall become the property of the Contactor and shall be properly disposed of offsite. If, in the City’s judgement, existing valve frame or cover are unsuitable and were damaged by the Contractor’s operations, they shall be replaced by the Contractor with a new valve frame and cover at no cost to the City.

The contract unit price per Each adjust utility valve to grade shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all work in adjusting utility valve curves to grade as specified in the City Sebastopol Specifications, these Specifications, the Plans, the Sebastopol Standard Construction Drawing or as directed by the City and no additional compensation will be allowed. 14-2.12 PORTLAND CEMENT CONCRETE (PCC) (VARIOUS ITEMS. Portland cement concrete driveway, sidewalk, curb ramp, curb and gutter, and valley gutter shall be constructed in accordance with Section 73, “Concrete Curbs and Sidewalks”, and Section 90, “Concrete”, of the Standard Specifications and these Specifications. The concrete shall attain a minimum compressive strength of 3000 psi at 28 days unless otherwise shown on the Project plans or standard details, and shall contain not less than six sacks of cement per cubic yard. Maximum slump of the concrete shall be 4 inches, as determined in accordance with ASTM C-143. The City shall provide inspection and testing of the PCC material placed.

Pedestrian ramps shall be constructed in accordance with the requirements of the Americans with Disabilities Act (ADA) Standards and shall be constructed at the locations, the dimensions, grades, and limits shown on the Plans. Thickness of Portland cement concrete shall be nominal 4 inches in sidewalk and curb ramps unless otherwise shown on the plans.

Base material under curb and gutter, valley gutter, driveways, sidewalks and curb ramps shall comply with the provisions of Section 26, “Aggregate Bases” of the State Standard Specifications and shall be a minimum of 4 inches in compacted thickness unless otherwise shown on the Project plans or standard details.

The unit price paid per Cubic Yard for various Portland cement concrete items shall include all work to construct item, complete in place, including but not limited to, saw cutting, excavation, subgrade preparation, the furnishing and placement of Class 2 Aggregate Base to support the item and for furnishing and placing Portland Cement Concrete as shown on the Plans, as specified in these Specifications and as directed by the City and no additional compensation will be allowed. 14-2.13 DETECTABLE WARNING SURFACES. All curb ramps shall include a cast in place prefabricated detectable warning surface as shown on the Plans. Detectable warning surfaces shall conform to Section 73-1.02B, “Detectable Warning Surfaces” of the Standard Specifications.

The unit price paid per Square Foot for Detectable Warning Surface shall include all work to furnish and install item, complete in place, as shown on the Plans, as specified in these Specifications and as directed by the City and no additional compensation will be allowed.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 120 of 219 ends

PART 3 - 110 v04262022

SPECIAL PROVISIONS
14-2.14 DRAINAGE INLETS. Drainage inlets shall comply with the provisions of Section 51, “Concrete Structures,” of the Standard Specifications and the Plans.

Unless otherwise specified on the Plans, drainage inlets may be either cast in place or precast. Contractor shall verify invert elevations, sizes, and locations of existing inlet and outlet pipes at existing drainage inlets prior to ordering precast inlets.

Connect existing drain pipes to new drainage inlets as directed in the Standard Specifications, as shown on the Plans, or as directed by the City.

Unless otherwise shown on the Plans, do not construct gutter depressions at the grate inlets. Gutter slopes are to remain constant entering and exiting the inlet. All grates shall be bicycle proof.

The unit price paid per Each for drainage inlets shall include all work to furnish and/or construct item, complete in place, including all pipe connections and material necessary to connect pipes to inlets, as shown on the Plans, as specified in these Specifications and as directed by the City and no additional compensation will be allowed. Payment for frames, grates, and miscellaneous iron and steel required to construct inlets shall be included in the price paid for drainage inlet.
14-2.15 REMOVE DRAINAGE INLET. Drainage inlet removal shall comply with the provisions of Section 71, “Existing Drainage Facilities,” of the Standard Specifications.

Existing pipe entering and exiting the drainage inlet shall be protected in place.

Drainage inlets shall not be removed more than two (2) days prior to construction or installation of a new drainage inlet. Inlets shall not be removed if rainfall is expected before the new drainage inlet can be constructed/installed.

The unit price paid per Each for remove drainage inlets shall include all work to remove drainage inlet, as shown on the Plans, as specified in these Specifications and as directed by the City and no additional compensation will be allowed. 14-2.16 THERMOPLASTIC TRAFFIC STRIPES AND PAVEMENT MARKINGS. Thermoplastic traffic stripes (traffic lines) and pavement markings shall conform to the provisions in Section 84, "Markings", of the Standard Specifications and these Specifications.

Pavement markers shall conform to the provisions in Section 81, “Miscellaneous Traffic Control Devices,” of the Standard Specifications and these Specifications.

White thermoplastic traffic stripes shall have enhanced wet-night visibility.

Unless otherwise directed by the Engineer, thermoplastic stripe and pavement marking shall not be placed on new asphalt for a minimum of seven (7) days after placement of asphalt.

The unit price paid per Linear Foot for thermoplastic traffic stripes will be measured and paid for by the lineal foot of the striping detail involved without deductions for gaps in the broken traffic stripe. A double thermoplastic traffic stripe consisting of two 6-inch-wide yellow stripes is measured as 1 traffic stripe. If pavement markers are a part of the detail, the pavement markers shall be considered as included in the lineal foot price of the Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 121 of 219 ends

PART 3 - 111 v04262022

SPECIAL PROVISIONS
stripe. No separate measurement or payment will be made for the installation of individual pavement markers.

The unit price paid per Square Foot for thermoplastic pavement markings will be measured and paid for by the square foot per the Standard Specifications.

Full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all the work involved with placing thermoplastic traffic stripes and pavement markings, including pavement markers, as specified in these Specifications, as shown on the Plans and as directed by the City shall be considered as included in the contract price for Thermoplastic Traffic Stripe, of the various kinds and the contract price for Thermoplastic Pavement Markings, and no additional compensation will be allowed. 14-2.17 ROADSIDE SIGN. Sign panel fabrication, mounting, and installation shall conform to Section 82, “Signs and Markers” of the Standard Specifications, these Specifications, and the Plans.

Roadside sign shall be placed as shown on the plans or as directed by the City. All signs shall conform to the California Manual on Uniform Traffic Control Devices (latest edition).

Panel size shall be for conventional road unless otherwise shown on the plans.

Existing roadside signs, at those locations shown on the plans to be removed, shall be removed and disposed of as shown on the plans. Existing roadside signs shall not be removed until replacement signs have been installed, or until the existing signs are no longer required for the direction of public traffic, unless otherwise directed by the Engineer.

Each roadside sign shall be installed at the new location on the same day that the sign is removed from its original location.

Removed signs, sign posts, and other mounting equipment shall become the property of the Contractor unless otherwise directed by the City.

The unit price paid per Each for roadside sign shall include compensation for manufacturing and furnishing all labor, materials, tools, equipment and incidentals involved with installing roadside sign, as specified in these Specifications, as shown on the Plans and as directed by the City. Multiple signs installed on the same post or pole will be counted as one sign.

The unit price paid per Each for remove roadside sign shall include compensation for furnishing all labor, materials, tools, equipment and incidentals involved with removing roadside signs, as specified in these Specifications, as shown on the Plans and as directed by the City. Multiple signs installed on the same post or pole will be counted as one sign.

Payment for resetting a sign shall be considered as included in the unit bid price for other contract items and no additional payment shall be made.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 122 of 219 ends

PART 3 - 112 v04262022

SPECIAL PROVISIONS
14-2.18 TRAFFIC SIGNAL MODIFCATIONS. The Contractor shall comply with Section 86, “General,” Section 87, and “Electrical Systems,” of the Standard Specifications, these Specifications, and as shown on the Plans.

Signal pole welding shall conform to the following:
(a) Welding and Repair Welding
Welding and repair welding for all steel fabrication shall comply with the AWS D1.1/D1.1M, latest edition, Structural Welding Code.

The Contractor shall weld structural steel only to the extent shown in the Plans.

No welding, including tack and temporary welds shall be done in the shop or field unless the location of the welds is shown on the approved shop drawings reviewed and accepted by the Engineer.

Welding procedures shall accompany the shop drawing Working Drawing submittal. The procedures shall specify the type of equipment to be used, electrode selection, preheat requirements, base materials, and joint details.

When the procedures are not prequalified by AWS or AASHTO, evidence of qualification tests shall be submitted.

Welding shall not begin until completion of the shop plan Working Drawing review and approval by the Engineer. These plans shall include procedures for welding, assembly, and any heat-straightening or heat-curving.

Any welded shear connector longer than 8 inches may be made of two shorter shear connectors joined with full-penetration welds.

In shielded metal-arc welding, the Contractor shall use low-hydrogen electrodes.

Preheat and interpass temperatures shall conform to the applicable welding code as specified in this section.

If groove welds (web-to-web or flange-to-flange) have been rejected, they may be repaired no more than twice. If a third failure occurs, the Contractor shall:

1. Trim the members, if the Engineer concurs, at least ½ inch on each side of the weld; or

2. Replace the members at no expense to the Contracting Agency.

By using extension bars and runoff plates, the Contractor shall terminate groove welds in a way that ensures the soundness of each weld to its ends. The bars and plates shall be removed after the weld is finished and cooled. The weld ends shall then be ground smooth and flush with the edges of abutting parts.

The Contractor shall not:

1. Weld with electrogas or electroslag methods unless shown in the Plans or allowed by the Engineer,

2. Weld nor flame cut when the ambient temperature is below 20ºF, or Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 123 of 219 ends

PART 3 - 113 v04262022

SPECIAL PROVISIONS

3. Use coped holes in the web for welding butt splices in the flanges unless the Plans show them
The Contractor shall be paid for the work related to traffic signals and lighting, including but not limited to signal pole modifications, new and relocated pedestrian push buttons, and adjusting pull boxes on a lump sum basis for Traffic Signal Modification. 14-2.19 WATER POLLUTION CONTROL PROGRAM (WPCP. The Contractor shall comply with Section 13, “Water Pollution Control,” of the Standard Specifications, Section 10-

1.02 of these Specifications, and Appendix A – General Guidelines for Construction Activities contained herein.

The Contractor shall be paid for the work of preparing, implementing, inspecting, maintaining, and removing the WPCP on a lump sum basis as indicated in the Bid Schedule. Payment will be based on the percentage of work completed to date. 14-2.20 FINAL CLEAN-UP. Before final inspection of the work, the Contractor shall clean the work area and all ground occupied by him/her in connection with the work, of all rubbish, excess materials (including liquid asphalt), and equipment. The sidewalks and curbs shall be thoroughly swept clean of all dirt, dust, and foreign material. All parts of the work shall be left in neat and presentable condition.

Payment for cleaning of sidewalks and curbs, and clean up in general, shall be considered as included in the unit bid price for other contract items and no additional payment shall be made.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 124 of 219 ends

APPENDIX A

CITY OF SEBASTOPOL
General Guidelines for Construction Activities
Erosion and Sediment Control and
Minimization of Hazardous Materials Contact with Stormwater General

1. The Erosion and Sediment Control Field Manual, Third Edition, June 1999, by the California Regional Water Quality Control Board, San Francisco Bay Region, forms the basis for these requirements, and is incorporated herein in its entirety. A copy of the Field Manual may be obtained from the California Environmental Protection Agency State Water Resources Control Board Water Quality home page, http://www.waterboards.ca.gov/stormwtr/training.html under “Publications Available”.

2. The City shall periodically inspect the Contractor’s work to ensure that work conforms to these erosion control guidelines and requirements.

3. For public projects, the City shall perform erosion control follow-up and maintenance and be responsible for post construction stormwater protection following completion of the project, in accord with the provisions of the Field Manual and the City’s Storm Water Management Plan.

4. The Contractor shall conform to all of the requirements contained in the approved plans and these contract documents and specifications and any other documents referenced herein.

EROSION CONTROL
Contractor shall conform with the requirements contained in Part IV, Specifications, Section 02770, Soil Erosion Control, and these guidelines.

GENERAL PRACTICES TO MINIMIZE HAZARDOUS MATERIALS CONTACT WITH STORM WATER (to be used in conjunction with the Field Manual)

1. Scheduling: The key to keeping potentially hazardous construction materials (PHCM) out of storm water is to perform most of the construction (earthwork and foundation work) during the dry season. All erosion control facilities shall be in place by October 15, or before the first rains - which ever comes first. All PHCMs shall be covered with tarps and elevated off the ground if rain is predicted.

2. Chemical Storage: Chemicals shall be stored in their original containers or in well-labeled, sealed containers in designated areas.

3. Drainage: PHCMs shall not be transported, applied, or washed within areas which drain to the City Storm Drain System.

4. Construction Equipment and Vehicles - Maintenance
a. Maintain all construction equipment to prevent oil or other fluid leaks. b. Use drip pans for any oil or fluid changes that are required for maintenance of equipment.

Keep vehicles and equipment clean. Do not allow excessive build-up of oil and grease. c. Use off-site repair shops as much as possible.
d. Always use secondary containment, such as a drain pans or drop cloths, to catch spills or leaks when removing or changing fluids.
e. Place stockpiled spill cleanup materials where they will be readily accessible. Regularly Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 125 of 219 ends

inspect on-site vehicles and equipment for leaks, and repair immediately. Check incoming vehicles and equipment (including delivery trucks, and employee and subcontractor vehicles) for leaking oil and fluids. Do not allow leaking vehicles or equipment on-site.
f. Segregate and recycle wastes, such as greases, used oil or oil filters, antifreeze, cleaning solutions, automotive batteries, and hydraulic and transmission fluids.

5. Construction Equipment and Vehicles – Fueling
a. Use off site fueling stations as much as possible.
b. If fueling must occur on-site, use designated areas, located away from drainage. Locate on-site fuel storage tanks over a retention area designed to hold the total tank volume. c. Cover the retention area with an impervious material and install it in a manner to ensure that any spills will be contained in the retention area. d. Discourage "topping-off" of fuel tanks, as it frequently leads to fuel spillage. e. Always use secondary containment, such as a drain pans or drop cloths, when fueling to catch spills/leaks.
f. Place stockpiled spill cleanup materials where they will be readily accessible. g. Avoid mobile fueling of mobile construction equipment around the site; transport the equipment to designated fueling areas.

6. Construction equipment and Vehicles – Washing
a. Use off-site commercial washing businesses as much as possible. b. Washing vehicles and equipment outdoors or in areas where wash water flows onto paved surfaces or into drainage pathways can pollute storm water. If you wash a large number of vehicles or pieces of equipment, conduct this work at an off-site commercial facility.
c. Do not permit steam cleaning on-site. Steam cleaning can generate significant pollutant concentrations.

7. Construction Equipment and Vehicles – Storage
a. Locate vehicle and equipment storage, cleaning, and maintenance areas in designated, confined areas. These areas should be located away from significant drainage courses. b. Direct any concentrated storm water run-on/runoff around storage and service areas.

Minimize contact of storm water and run-on/runoff with stored equipment by raising equipment on pallets or other similar devices.

8. Toxic Materials: Through proper material use, waste disposal, and training of employees, the discharge of toxic pollutants can be prevented. Such methods include the following:
a. Dispose of all wastes in accordance with Federal, State, and local regulations. b. Use the entire product before disposing of the container. c. Do not remove the container's original product label prior to disposal. It contains important safety and disposal information.
d. Do not clean out brushes or paint containers on dirt or into streets, gutters, storm drains, Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 126 of 219 ends

or streams. "Paint out" brushes as much as possible. Rinse water-based paints to the sanitary sewer. Filter and reuse thinners and solvents. Dispose of excess oil-based paints and sludge as hazardous waste.
e. Select and site designated hazardous waste storage areas. f. Store hazardous materials and wastes in covered containers and protect from vandalism. Place hazardous material and waste containers in secondary containment. g. Do not mix wastes. Mixing can cause chemical reactions, make recycling impossible, and complicate disposal.
h. Recycle any useful material such as oil or water-based paint. Provide a summary of available recycling and disposal services.
i. Make sure that toxic liquid wastes and chemicals are not disposed of in dumpsters designated for construction debris.
j. Arrange for regular waste collection before containers overflow. k. Make sure that hazardous waste is collected, removed, and disposed of only at authorized disposal areas.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 127 of 219 ends

APPENDIX B

REQUIRED FEDERAL-AID CONTRACT LANGUAGE
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 128 of 219 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
Page of 1 of 29
January 2022
EXHIBIT 12-G: REQUIRED FEDERAL-AID CONTRACT LANGUAGE
(For Local Assistance Construction Projects)
The following language must be incorporated into all Local Assistance Federal-aid construction contracts.

The following language, with minor edits, was taken from the Code of Federal Regulations.

MAINTAIN RECORDS AND SUBMIT REPORTS DOCUMENTING YOUR PERFORMANCE UNDER THIS

SECTION

1. DISADVANTAGED BUSINESS ENTERPRISES (DBE)................................................................................ 2 A. NONDISCRIMINATION STATEMENT.............................................................................................. 2 B. CONTRACT ASSURANCE............................................................................................................... 3 C. PROMPT PROGRESS PAYMENT ................................................................................................... 3 D. PROMPT PAYMENT OF WITHHELD FUNDS TO SUBCONTRACTORS ......................................... 3 E. TERMINATION AND SUBSTITUTION OF DBE SUBCONTRACTORS........................................... 4 F. COMMITMENT AND UTILIZATION.................................................................................................. 5 G. DBE RUNNING TALLY OF ATTAINMENTS.................................................................................... 6

2. BID OPENING............................................................................................................................................... 6

3. BID RIGGING ................................................................................................................................................ 6

4. CONTRACT AWARD.................................................................................................................................... 6

5. CONTRACTOR LICENSE ............................................................................................................................ 6

6. CHANGED CONDITIONS............................................................................................................................. 6 A. DIFFERING SITE CONDITIONS....................................................................................................... 6 B. SUSPENSIONS OF WORK ORDERED BY THE ENGINEER.......................................................... 6 C. SIGNIFICANT CHANGES IN THE CHARACTER OF WORK .......................................................... 7

7. BEGINNING OF WORK, TIME OF COMPLETION AND LIQUIDATED DAMAGES...................................... 7

8. BUY AMERICA............................................................................................................................................. 7

9. QUALITY ASSURANCE............................................................................................................................... 8

10. PROMPT PAYMENT FROM THE AGENCY TO THE CONTRACTORS......................................................... 8

11. FORM FHWA-1273 REQUIRED CONTRACT PROVISIONSFEDERAL-AID CONTRACTS....................... 8

12. FEMALE AND MINORITY GOALS............................................................................................................. 22

13. TITLE VI ASSURANCES ............................................................................................................................ 23

14. USE OF UNITED STATES-FLAG VESSELS (CARGO PREFERENCE ACT)............................................. 27

15. FEDERAL TRAINEE PROGRAM ................................................................................................................ 27

16. PROHIBITIONS OF CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE EQUIPMENT AND SERVICES................................................................................................................................................... 29 Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 129 of 219 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
Page of 2 of 29
January 2022

1. DISADVANTAGED BUSINESS ENTERPRISES (DBE)
The contractor, subrecipient or subcontractor shall take necessary and reasonable steps to ensure that DBEs have opportunity to participate in the contract (49 CFR 26). To ensure equal participation of DBEs provided in 49 CFR 26.5, the Agency shows a contract goal for DBEs. The prime contractor shall make work available to DBEs and select work parts consistent with available DBE subcontractors and suppliers.

The prime contractor shall meet the DBE goal shown elsewhere in these special provisions or demonstrate that they made adequate good faith efforts to meet this goal.

It is the prime contractor’s responsibility to verify that at date of bid opening the DBE firm is certified as a DBE by using the California Unified Certification Program (CUCP) database and possesses the most specific available North American Industry Classification System (NAICS) codes and work code applicable to the type of work the firm will perform on the contract. Additionally, the prime contractor is responsible to document the verification record by printing out the CUCP data for each DBE firm. A list of DBEs certified by the CUCP can be found at: https://dot.ca.gov/programs/civil-rights/dbe-search.

All DBE participation will count toward the California Department of Transportation’s federally mandated statewide overall DBE goal.

Credit for materials or supplies the prime contractor purchases from DBEs counts towards the goal in the following manner:
• 100 percent counts if the materials or supplies are obtained from a DBE manufacturer. • 60 percent counts if the materials or supplies are obtained from a DBE regular dealer. • Only fees, commissions, and charges for assistance in the procurement and delivery of materials or supplies count if obtained from a DBE that is neither a manufacturer nor regular dealer. 49 CFR

26.55 defines "manufacturer" and "regular dealer."
The prime contractor receives credit towards the goal if they employ a DBE trucking company that performs a commercially useful function as defined in 49 CFR 26.55(d)(1) as follows:
• The DBE must be responsible for the management and supervision of the entire trucking operation for which it is responsible on a particular contract, and there cannot be a contrived arrangement for the purpose of meeting DBE goals.
• The DBE must itself own and operate at least one fully licensed, insured, and operational truck used on the contract.
• The DBE receives credit for the total value of the transportation services it provides on the Contract using trucks it owns, insures, and operates using drivers it employs. • The DBE may lease trucks from another DBE firm, including an owner-operator who is certified as a DBE. The DBE who leases trucks from another DBE receives credit for the total value of the transportation services the lessee DBE provides on the Contract. • The DBE may lease trucks without drivers from a non-DBE truck leasing company. If the DBE leases trucks from a non-DBE truck leasing company and uses its own employees as drivers, it is entitled to credit for the total value of these hauling services. • A lease must indicate that the DBE has exclusive use of and control over the truck. This does not preclude the leased truck from working for others during the term of the lease with the consent of the DBE, so long as the lease gives the DBE absolute priority for use of the leased truck. Leased trucks must display the name and identification number of the DBE.

A. Nondiscrimination Statement
The contractor, subrecipient or subcontractor will never exclude any person from participation in, deny any person the benefits of, or otherwise discriminate against anyone in connection with the award and performance of any contract covered by 49 CFR 26 on the basis of race, color, sex, or national origin. In administering the Local Agency components of the DBE Program Plan, the contractor, subrecipient or subcontractor will not, directly, or through contractual or other arrangements, use criteria or methods of administration that have the effect of defeating or substantially impairing accomplishment of the objectives of the DBE Program Plan with respect to individuals of a particular race, color, sex, or national origin.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 130 of 219 ends

Page of 3 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
B. Contract Assurance
Under 49 CFR 26.13(b):

The contractor, subrecipient or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of 49 CFR 26 in the award and administration of federal-aid contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the recipient deems appropriate, which may include, but is not limited to:
(1) Withholding monthly progress payments;
(2) Assessing sanctions;
(3) Liquidated damages; and/or
(4) Disqualifying the contractor from future bidding as non-responsible.

C. Prompt Progress Payment
The prime contractor or subcontractor shall pay to any subcontractor, not later than seven days after receipt of each progress payment, unless otherwise agreed to in writing, the respective amounts allowed the contractor on account of the work performed by the subcontractors, to the extent of each subcontractor’s interest therein. In the event that there is a good faith dispute over all or any portion of the amount due on a progress payment from the prime contractor or subcontractor to a subcontractor, the prime contractor or subcontractor may withhold no more than 150 percent of the disputed amount. Any violation of this requirement shall constitute a cause for disciplinary action and shall subject the licensee to a penalty, payable to the subcontractor, of 2 percent of the amount due per month for every month that payment is not made.

In any action for the collection of funds wrongfully withheld, the prevailing party shall be entitled to his or her attorney’s fees and costs. The sanctions authorized under this requirement shall be separate from, and in addition to, all other remedies, either civil, administrative, or criminal. This clause applies to both DBE and non-DBE subcontractors.

D. Prompt Payment of Withheld Funds to Subcontractors
The Agency may hold retainage from the prime contractor and shall make prompt and regular incremental acceptances of portions, as determined by the Agency, of the contract work, and pay retainage to the prime contractor based on these acceptances. The Agency shall designate one of the methods below in the contract to ensure prompt and full payment of any retainage kept by the prime contractor or subcontractor to a subcontractor. The Agency shall include either Method 1, Method 2, or Method 3 below and delete the other two.

Method 1: No retainage will be held by the Agency from progress payments due to the prime contractor.

Prime contractors and subcontractors are prohibited from holding retainage from subcontractors. Any delay or postponement of payment may take place only for good cause and with the Agency’s prior written approval. Any violation of these provisions shall subject the violating contractor or subcontractor to the penalties, sanctions, and other remedies specified in Section 7108.5 of the California Business and Professions Code and Section 10262 of the California Public Contract Code. This requirement shall not be construed to limit or impair any contractual, administrative or judicial remedies, otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the contractor, deficient subcontractor performance and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.

Method 2: No retainage will be held by the Agency from progress payments due to the prime contractor.

Any retainage kept by the prime contractor or by a subcontractor must be paid in full to the earning subcontractor within seven (7) days after the subcontractor’s work is satisfactorily completed. Any delay or postponement of payment may take place only for good cause and with the Agency’s prior written approval. Any violation of these provisions shall subject the violating contractor or subcontractor to the penalties, sanctions, and remedies specified in Section 7108.5 of the California Business and Professions Code and Section 10262 of the California Public Contract Code. This requirement shall not be construed to limit or impair any contractual, administrative or judicial remedies, otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the contractor, deficient subcontractor performance and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 131 of 219 ends

Page of 4 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
Method 3: The Agency shall hold retainage from the prime contractor and shall make prompt and regular incremental acceptances of portions, as determined by the Agency of the contract work and pay retainage to the prime contractor based on these acceptances. The prime contractor or subcontractor shall return all monies withheld in retention from all subcontractors within seven (7) days after receiving payment for work satisfactorily completed and accepted including incremental acceptances of portions of the contract work by the Agency. Any delay or postponement of payment may take place only for good cause and with the Agency’s prior written approval. Any violation of these provisions shall subject the violating prime contractor or subcontractor to the penalties, sanctions, and other remedies specified in Section 7108.5 of the California Business and Professions Code and Section 10262 of the California Public Contract Code. This requirement shall not be construed to limit or impair any contractual, administrative or judicial remedies otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the contractor; deficient subcontractor performance and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.

Any violation of these provisions of Prompt Progress Payment and Prompt Payment of Withheld Funds to Subcontractors shall subject the violating prime contractor or subcontractor to the penalties, sanctions and other remedies specified therein. These requirements shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the prime contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the prime contractor, deficient subcontract performance, or noncompliance by a subcontractor.

E. Termination and Substitution of DBE Subcontractors
The prime contractor shall utilize the specific DBEs listed to perform the work and supply the materials for which each is listed unless the contractor obtains the Agency’s written consent. The prime contractor shall not terminate or substitute a listed DBE for convenience and perform the work with their own forces or obtain materials from other sources without prior written authorization from the Agency. Unless the Agency’s prior written consent is provided, the contractor shall not be entitled to any payment for work or material unless it is performed or supplied by the listed DBE on the Exhibit 15-G Construction Contract DBE Commitment form, included in the Bid.

The Agency authorizes a request to use other forces or sources of materials if the bidder shows any of the following justifications:

1. Listed DBE fails or refuses to execute a written contract based on plans and specifications for the project.

2. The Local Agency stipulated that a bond is a condition of executing the subcontract and the listed DBE fails to meet the Local Agency’s bond requirements.

3. Work requires a contractor's license and listed DBE does not have a valid license under Contractors License Law.

4. Listed DBE fails or refuses to perform the work or furnish the listed materials (failing or refusing to perform is not an allowable reason to remove a DBE if the failure or refusal is a result of bad faith or discrimination).

5. Listed DBE's work is unsatisfactory and not in compliance with the contract.

6. Listed DBE is ineligible to work on the project because of suspension or debarment.

7. Listed DBE becomes bankrupt or insolvent.

8. Listed DBE voluntarily withdraws with written notice from the Contract

9. Listed DBE is ineligible to receive credit for the type of work required.

10. Listed DBE owner dies or becomes disabled resulting in the inability to perform the work on the Contract.

11. The Agency determines other documented good cause.

The prime contractor shall notify the original DBE of the intent to use other forces or material sources and provide the reasons, allowing the DBE 5 days to respond to the notice and advise the prime contractor and the Agency of the reasons why the use of other forces or sources of materials should not occur.

The prime contractor’s request to use other forces or material sources must include:

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 132 of 219 ends

Page of 5 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language

1. One or more of the reasons listed in the preceding paragraph.

2. Notices from the prime contractor to the DBE regarding the request.

3. Notices from the DBEs to the prime contractor regarding the request.

If the Agency authorizes the termination or substitution of a listed DBE, the prime contractor must make good faith efforts to find another DBE to substitute for the original DBE. The substitute DBE must (1) perform at least the same amount of work as the original DBE under the contract to the extent needed to meet or exceed the DBE goal, and (2) be certified as a DBE with the most specific available NAICS codes and work codes applicable to the type of work the DBE will perform on the contract at the time of the prime contractor’s request for substitution. The prime contractor shall submit their documentation of good faith efforts within 7 days of their request for authorization of the substitution. The Agency may authorize a 7-day extension of this submittal period at the prime contractor’s request. More guidance can be found at 49 CFR 26 app A regarding evaluation of good faith efforts to meet the DBE goal.

F. Commitment and Utilization
Note: In the Agency’s reports of DBE participation to Caltrans, the Agency must display both commitments and attainments.

The Agency’s DBE program must include a monitoring and enforcement mechanism to ensure that DBE commitments reconcile to DBE utilization.

The bidder shall submit the Exhibit 15-G Construction Contract DBE Commitment, included in the Bid book.

This exhibit is the bidder’s DBE commitment form. If the form is not submitted with the bid, the bidder must remove the form from the Bid book before submitting their bid.

The bidder shall complete and sign Exhibit 15-G Construction Contract DBE Commitment included in the contract documents regardless of whether DBE participation is reported. The bidder shall provide written confirmation from each DBE that the DBE is participating in the Contract. A copy of a DBE's quote serves as written confirmation. If a DBE is participating as a joint venture partner, the bidder shall submit a copy of the joint venture agreement.

If the DBE Commitment form, Exhibit 15-G, is not submitted with the bid, it must be completed and submitted by all bidders to the Agency within five (5) days of bid opening. If the bidder does not submit the DBE Commitment form within the specified time, the Agency will find the bidder’s bid nonresponsive.

The prime contractor shall use each DBE subcontractor as listed on Exhibit 12-B Bidder’s List of Subcontractors (DBE and Non-DBE), and Exhibit 15-G Construction Contract DBE Commitment form unless they receive authorization for a substitution.

The Agency shall request the prime contractor to:

1. Notify the Resident Engineer or Inspector of any changes to its anticipated DBE participation

2. Provide this notification before starting the affected work

3. Maintain records including:
• Name and business address of each 1st-tier subcontractor • Name and business address of each DBE subcontractor, DBE vendor, and DBE trucking company, regardless of tier
• Date of payment and total amount paid to each business (see Exhibit 9-F Monthly Disadvantaged Business Enterprise Payment)
If the prime contractor is a DBE contractor, they shall include the date of work performed by their own forces and the corresponding value of the work.

Before the 15th of each month, the prime contractor shall submit a Monthly DBE Trucking Verification (LAPM Exhibit 16-Z1) form.

If a DBE is decertified before completing its work, the DBE must notify the prime contractor in writing of the decertification date. If a business becomes a certified DBE before completing its work, the business must notify the prime contractor in writing of the certification date. The prime contractor shall submit the Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 133 of 219 ends

Page of 6 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
notifications. Upon work completion, the prime contractor shall complete a Disadvantaged Business Enterprises (DBE) Certification Status Change, Exhibit 17-O, form and submit the form within 30 days of contract acceptance.

Upon work completion, the prime contractor shall complete Exhibit 17-F Final Report – Utilization of Disadvantaged Business Enterprises (DBE), First-Tier Subcontractors and submit it within 90 days of contract acceptance. The Agency will withhold $10,000 until the form is submitted. The Agency releases the withhold upon submission of the completed form.

G. DBE RUNNING TALLY OF ATTAINMENTS
After submitting an invoice for reimbursement that includes a payment to a DBE, but no later than the 10th of the following month, the prime contractor/consultant shall complete and email the Exhibit 9- F: Disadvantaged Business Enterprise Running Tally of Payments to [email protected] with a copy to the Agency.

2. BID OPENING The Agency publicly opens and reads bids at the time and place shown on the Notice to Contractors.

3. BID RIGGING The U.S. Department of Transportation (DOT) provides a toll-free hotline to report bid rigging activities. Use the hotline to report bid rigging, bidder collusion, and other fraudulent activities. The hotline number is (800) 424-9071. The service is available 24 hours 7 days a week and is confidential and anonymous. The hotline is part of the DOT's effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector General.

4. CONTRACT AWARD If the Agency awards the contract, the award is made to the lowest responsible and responsive bidder.

5. CONTRACTOR LICENSE
The Contractor must be properly licensed as a contractor from contract award through Contract acceptance (Public Contract Code § 10164).

6. CHANGED CONDITIONS
A. Differing Site Conditions

1. During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before the site is disturbed and before the affected work is performed.

2. Upon written notification, the engineer will investigate the conditions, and if it is determined that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an adjustment, excluding anticipated profits, will be made and the contract modified in writing accordingly. The engineer will notify the contractor of the determination whether or not an adjustment of the contract is warranted.

3. No contract adjustment which results in a benefit to the contractor will be allowed unless the contractor has provided the required written notice.

4. No contract adjustment will be allowed under this clause for any effects caused on unchanged work. (This provision may be omitted by the Local Agency, at their option.) B. Suspensions of Work Ordered by the Engineer

1. If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the engineer in writing a request for adjustment within 7 calendar days of receipt of the notice to resume work. The request shall set forth the reasons and support for such adjustment.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 134 of 219 ends

Page of 7 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language

2. Upon receipt, the engineer will evaluate the contractor's request. If the engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly. The contractor will be notified of the engineer's determination whether or not an adjustment of the contract is warranted.

3. No contract adjustment will be allowed unless the contractor has submitted the request for adjustment within the time prescribed.

4. No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this contract.

C. Significant Changes in the Character of Work

1. The engineer reserves the right to make, in writing, at any time during the work, such changes in quantities and such alterations in the work as are necessary to satisfactorily complete the project.

Such changes in quantities and alterations shall not invalidate the contract nor release the surety, and the contractor agrees to perform the work as altered.

2. If the alterations or changes in quantities significantly change the character of the work under the contract, whether such alterations or changes are in themselves significant changes to the character of the work or by affecting other work cause such other work to become significantly different in character, an adjustment, excluding anticipated profit, will be made to the contract.

The basis for the adjustment shall be agreed upon prior to the performance of the work. If a basis cannot be agreed upon, then an adjustment will be made either for or against the contractor in such amount as the engineer may determine to be fair and equitable.

3. If the alterations or changes in quantities do not significantly change the character of the work to be performed under the contract, the altered work will be paid for as provided elsewhere in the contract.

4. The term “significant change” shall be construed to apply only to the following circumstances:
• When the character of the work as altered differs materially in kind or nature from that involved or included in the original proposed construction; or • When a major item of work, as defined elsewhere in the contract, is increased in excess of 125 percent or decreased below 75 percent of the original contract quantity. Any allowance for an increase in quantity shall apply only to that portion in excess of 125 percent of original contract item quantity, or in case of a decrease below 75 percent, to the actual amount of work performed.

7. BEGINNING OF WORK, TIME OF COMPLETION AND LIQUIDATED DAMAGES The Contractor shall begin work within 15 calendar days after the issuance of the Notice to Proceed.

This work shall be diligently prosecuted to completion before the expiration of WORKING DAYS beginning on the fifteenth calendar day after the date shown on the Notice to Proceed.

The Contractor shall pay to the City/County the sum of $ per day, for each and every calendar days’ delay in finishing the work in excess of the number of working days prescribed above.

8. BUY AMERICA
Furnish steel and iron materials to be incorporated into the work with certificates of compliance and certified mill test reports. Mill test reports must indicate where the steel and iron were melted and manufactured. Steel and iron materials must be produced in the U.S. except:

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 135 of 219 ends

Page of 8 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language

1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials [60 Fed Reg 15478 (03/24/1995)];

2. If the total combined cost of the materials does not exceed the greater of 0.1 percent of the total bid or $2,500, materials produced outside the U.S. may be used.

Production includes:

1. Processing steel and iron materials, including smelting or other processes that alter the physical form or shape (such as rolling, extruding, machining, bending, grinding, and drilling) or chemical composition;

2. Coating application, including epoxy coating, galvanizing, and painting, that protects or enhances the value of steel and iron materials.

9. QUALITY ASSURANCE
The Local Agency uses a Quality Assurance Program (QAP) to ensure a material is produced to comply with the Contract. The Local Agency may examine the records and reports of tests the prime contractor performs if they are available at the job site. Schedule work to allow time for QAP.

10. PROMPT PAYMENT FROM THE AGENCY TO THE CONTRACTORS
The Agency shall make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract. If the Agency fails to pay promptly, the Agency shall pay interest to the contractor, which accrues at the rate of 10 percent per annum on the principal amount of a money judgment remaining unsatisfied. Upon receipt of a payment request, the Agency shall act in accordance with both of the following:

1. Each payment request shall be reviewed by the Agency as soon as practicable after receipt for the purpose of determining that it is a proper payment request.

2. Any payment request determined not to be a proper payment request suitable for payment shall be returned to the contractor as soon as practicable, but not later than seven (7) days, after receipt. A request returned pursuant to this paragraph shall be accompanied by a document setting forth in writing the reasons why the payment request is not proper.

11. FORM FHWA-1273 REQUIRED CONTRACT PROVISIONS FEDERAL-AID CONTRACTS (Excluding ATTACHMENT A - EMPLOYMENT AND MATERIALS PREFERENCE FOR APPALACHIAN

DEVELOPMENT HIGHWAY SYSTEM OR APPALACHIAN LOCAL ACCESS ROAD CONTRACTS) Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 136 of 219 ends

Page of 9 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract
[The following 12 pages must be physically inserted into the contract without modification.] Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 137 of 219 ends

Page of 10 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract
FHWA-1273 -- Revised May 1, 2012

REQUIRED CONTRACT

PROVISIONS FEDERAL-AID

CONSTRUCTION CONTRACTS
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 138 of 219 ends

Page of 11 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract
I. General
II. Nondiscrimination
III. No segregated Facilities
IV. Davis-Bacon and Related Act Provisions
V. Contract Work Hours and Safety Standards Act Provisions VI. Subletting or Assigning the Contract
VII. Safety: Accident Prevention
VIII. False Statements Concerning Highway Projects
IX. Implementation of Clean Air Act and Federal Water Pollution Control Act
X. Compliance with Government wide Suspension and Debarment Requirements
XI. Certification Regarding Use of Contract Funds for Lobbying

ATTACHMENTS
A. Employment and Materials Preference for Appalachian Development Highway System or Appalachian Local Access Road Contracts (included in Appalachian contracts only)
I. GENERAL

1. Form FHWA-1273 must be physically incorporated in each construction contract funded under Title 23 (excluding emergency contracts solely intended for debris removal). The contractor (or subcontractor) must insert this form in each subcontract and further require its inclusion in all lower tier subcontracts (excluding purchase orders, rental agreements and other agreements for supplies or services).

The applicable requirements of Form FHWA-1273 are incorporated by reference for work done under any purchase order, rental agreement or agreement for other services. The prime contractor shall be responsible for compliance by any subcontractor, lower-tier subcontractor or service provider.

Form FHWA-1273 must be included in all Federal-aid design-build contracts, in all subcontracts and in lower tier subcontracts (excluding subcontracts for design services, purchase orders, rental agreements and other agreements for supplies or services). The design-builder shall be responsible for compliance by any subcontractor, lower-tier subcontractor or service provider.

Contracting agencies may reference Form FHWA-1273 in bid proposal or request for proposal documents, however, the Form FHWA-1273 must be physically incorporated (not referenced) in all contracts, subcontracts and lower-tier subcontracts (excluding purchase orders, rental agreements and other agreements for supplies or services related to a construction contract).

2. Subject to the applicability criteria noted in the following sections, these contract provisions shall apply to all work performed on the contract by the contractor's own organization and with the assistance of workers under the contractor's immediate superintendence and to all work performed on the contract by piecework, station work, or by subcontract.

3. A breach of any of the stipulations contained in these Required Contract Provisions may be sufficient grounds for withholding of progress payments, withholding of final payment, termination of the contract, suspension / debarment or any other action determined to be appropriate by the contracting agency and FHWA.

4. Selection of Labor: During the performance of this contract, the contractor shall not use convict labor for any purpose within the limits of a construction project on a Federal-aid highway unless it is labor performed by convicts who are on parole, supervised release, or probation. The term Federal-aid highway does not include roadways functionally classified as local roads or rural minor collectors.

II. NONDISCRIMINATION
The provisions of this section related to 23 CFR Part 230 are applicable to all Federal-aid construction contracts and to all related construction subcontracts of $10,000 or more. The provisions of 23 CFR Part 230 are not applicable to material supply, engineering, or architectural service contracts.

In addition, the contractor and all subcontractors must comply with the following policies: Executive Order 11246, 41 CFR 60, 29 CFR 1625- 1627, Title 23 USC Section 140, the Rehabilitation Act of 1973, as amended (29 USC 794), Title VI of the Civil Rights Act of 1964, as amended, and related regulations including 49 CFR Parts 21, 26 and 27; and 23 CFR Parts 200, 230, and 633.

The contractor and all subcontractors must comply with: the requirements of the Equal Opportunity Clause in 41 CFR 60-1.4(b) and, for all construction contracts exceeding $10,000, the Standard Federal Equal Employment Opportunity Construction Contract Specifications in 41 CFR 60-4.3.

Note: The U.S. Department of Labor has exclusive authority to determine compliance with Executive Order 11246 and the policies of the Secretary of Labor including 41 CFR 60, and 29 CFR 1625-1627. The contracting agency and the FHWA have the authority and the responsibility to ensure compliance with Title 23 USC Section 140, the Rehabilitation Act of 1973, as amended (29 USC 794), and Title VI of the Civil Rights Act of 1964, as amended, and related regulations including 49 CFR Parts 21, 26 and 27; and 23 CFR Parts 200, 230, and
633.

The following provision is adopted from 23 CFR 230, Appendix A, with appropriate revisions to conform to the U.S. Department of Labor (US DOL) and FHWA requirements.

1. Equal Employment Opportunity: Equal employment opportunity (EEO) requirements not to discriminate and to take affirmative action to assure equal opportunity as set forth under laws, executive orders, rules, regulations (28 CFR 35, 29 CFR 1630, 29 CFR 1625-1627, 41 CFR 60 and 49 CFR 27) and orders of the Secretary of Labor as modified by the provisions prescribed herein, and imposed pursuant to 23 U.S.C. 140 shall constitute the EEO and specific affirmative action standards for the contractor's project activities under this contract. The provisions of the Americans with Disabilities Act of 1990 (42 U.S.C. 12101 et seq.) set forth under 28 CFR 35 and 29 CFR 1630 are incorporated by reference in this contract. In the execution of this contract, the contractor agrees to comply with the following minimum specific requirement activities of EEO:
a. The contractor will work with the contracting agency and the Federal Government to ensure that it has made every good faith effort to provide equal opportunity with respect to all of its terms and conditions of employment and in their review of activities under the contract.
b. The contractor will accept as its operating policy the following statement:
"It is the policy of this Company to assure that applicants are employed, and that employees are treated during employment, without regard to their race, religion, sex, color, national origin, age or disability. Such action shall include: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship, pre-apprenticeship, and/or on-the-job training." FHWA-1273 -- Revised May 1, 2012
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 139 of 219 ends

Page of 12 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract

2. EEO Officer: The contractor will designate and make known to the contracting officers and EEO Officer who will have the responsibility for and must be capable of effectively administering and promoting and active EEO program and who must be assigned adequate authority and responsibility to do so.

3. Dissemination of Policy: All members of the contractor's staff who are authorized to hire, supervise, promote, and discharge employees, or who recommend such action, or who are
substantially involved in such action, will be made fully cognizant of, and will implement, the contractor's EEO policy and contractual responsibilities to provide EEO in each grade and classification of employment. To ensure that the above agreement will be met, the following actions will be taken as a minimum:
a. Periodic meetings of supervisory and personnel office employees will be conducted before the start of work and then not less often than once every six months, at which time the contractor's EEO policy and its implementation will bereviewed and explained. The meetings will be conducted by the EEO Officer.
b. All new supervisory or personnel office employees will be given a thorough indoctrination by the EEO Officer, covering all major aspects of the contractor's EEO obligations within thirty days following their reporting for duty with the contractor. c. All personnel who are engaged in direct recruitment for the project will be instructed by the EEO Officer in the contractor's procedures for locating and hiring minorities and women. d. Notices and posters setting forth the contractor's EEO policywill be placed in areas readily accessible to employees, applicants for employment and potential employees.
e. The contractor's EEO policy and the procedures to implement such policy will be brought to the attention of employees by means of meetings, employee handbooks, or other appropriate means.

4. Recruitment: When advertising for employees, the contractor will include in all advertisements for employees the notation: "An Equal Opportunity Employer." All such advertisements will be placed in publications having a large circulation among minorities and women in the area from which the project work force would normally be derived.
a. The contractor will, unless precluded by a valid bargaining agreement, conduct systematic and direct recruitment through public and private employee referral sources likely to yield qualified minorities and women. To meet this requirement, the contractor will identify sources of potential minority group employees, and establish with such identified sources
procedures whereby minority and women applicants may be referred to the contractor for employment consideration. b. In the event the contractor has a valid bargaining agreement providing for exclusive hiring hall referrals, the contractor is expected to observe the provisions of that agreement to the extent that the system meets the contractor's compliance with EEO contract provisions. Where implementation of such an agreement has the effect of discriminating against minorities or women, or obligates the contractor to do the same, such implementation violates Federal nondiscrimination provisions. c. The contractor will encourage its present employees to refer minorities and women as applicants for employment.

Information and procedures with regard to referring such applicants will be discussed with employees.

5. Personnel Actions: Wages, working conditions, and employee benefits shall be established and administered, and personnel actions of every type, including hiring, upgrading, promotion, transfer, demotion, layoff, and termination, shall be taken without regard to race, color, religion, sex, national origin, age or disability.

The following procedures shall be followed:
a. The contractor will conduct periodic inspections of project sitesto insure that working conditions and employee facilities do not indicate discriminatory treatment of project site personnel. b. The contractor will periodically evaluate the spread of wagespaid within each classification to determine any evidence of discriminatory wage practices.
c. The contractor will periodically review selected personnel actions in depth to determine whether there is evidence ofdiscrimination.

Where evidence is found, the contractor will promptly take corrective action. If the review indicates that the discrimination may extend beyond the actions reviewed, such corrective action shall include all affected persons.
d. The contractor will promptly investigate all complaints of alleged discrimination made to the contractor in connection with its obligations under this contract, will attempt to resolve such complaints, and will take appropriate corrective action within a reasonable time. If the investigation indicates that the discrimination may affect persons other than the complainant, such corrective action shall include such other persons. Upon completion of each investigation, the contractor will inform every complainant of all of their avenues of appeal.

6. Training and Promotion:
a. The contractor will assist in locating, qualifying, and increasing the skills of minorities and women who are applicants for employment or current employees. Such efforts should be aimed at developing full journey level status employees in the type of trade or job classification involved.
b. Consistent with the contractor's work force requirements and as permissible under Federal and State regulations, the contractor shall make full use of training programs, i.e., apprenticeship, and on-the-job training programs for the geographical area of contract performance. In the event a special provision for training is provided under this contract, this subparagraph will be superseded as indicated in the special provision. The contracting agency may reserve training positions for persons who receive welfare assistance in accordance with 23 U.S.C. 140(a). c. The contractor will advise employees and applicants for employment of available training programs and entrance
requirements for each.
d. The contractor will periodically review the training andpromotion potential of employees who are minorities and women and will encourage eligible employees to apply for such training and promotion.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 140 of 219 ends

Page of 13 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract

7. Unions: If the contractor relies in whole or in part upon unionsas a source of employees, the contractor will use good faith efforts to obtain the cooperation of such unions to increase opportunities for minorities and women. Actions by the contractor, either directly or through a contractor's association acting as agent, will include the procedures set forth below:
a. The contractor will use good faith efforts to develop, in cooperation with the unions, joint training programs aimed toward qualifying more minorities and women for membership in the unions and increasing the skills of minorities and women so that they may qualify for higher paying employment.
b. The contractor will use good faith efforts to incorporate an EEO clause into each union agreement to the end that such union will be contractually bound to refer applicants without regard to their race, color, religion, sex, national origin, age or disability. c. The contractor is to obtain information as to the referral practices and policies of the labor union except that to the extent such information is within the exclusive possession of the labor union and such labor union refuses to furnish such information to the contractor, the contractor shall so certify to the contracting agency and shall set forth what efforts have been made to obtain such information.
d. In the event the union is unable to provide the contractor with a reasonable flow of referrals within the time limit set forth in the collective bargaining agreement, the contractor will, through independent recruitment efforts, fill the employment vacancies without regard to race, color, religion, sex, national origin, age or disability; making full efforts to obtain qualified and/or qualifiable minorities and women. The failure of a union to provide sufficient referrals (even though it is obligated to provide exclusive referrals under the terms of a collective bargaining agreement) does not relieve the contractor from the requirements of this paragraph. In the event the union referral practice prevents the contractor from meeting the obligations pursuant to Executive Order 11246, as amended, and these special provisions, such contractor shall immediately notify the contracting agency.

8. Reasonable Accommodation for Applicants / Employees
with Disabilities: The contractor must be familiar with the requirements for and comply with the Americans with Disabilities Act and all rules and regulations established there under.

Employers must provide reasonable accommodation in all
employment activities unless to do so would cause an undue hardship.

9. Selection of Subcontractors, Procurement of Materials and Leasing of Equipment: The contractor shall not discriminate on the grounds of race, color, religion, sex, national origin, age or disability in the selection and retention of subcontractors, including procurement of materials and leases of equipment. The contractor shall take all necessary and reasonable steps to ensure nondiscrimination in the administration of this contract. a.The contractor shall notify all potential subcontractors and suppliers and lessors of their EEO obligations under this contract. b.The contractor will use good faith efforts to ensure subcontractor compliance with their EEO obligations.

FHWA-1273 -- Revised May 1, 2012

10.Assurance Required by 49 CFR 26.13(b):
a. The requirements of 49 CFR Part 26 and the State DOT’s U.S.

DOT-approved DBE program are incorporated by reference. b. The contractor or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of 49 CFR Part 26 in the award and administration of DOT-assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the contracting agency deems appropriate.

11. Records and Reports: The contractor shall keep such records as necessary to document compliance with the EEO requirements.

Such records shall be retained for a period of three years following the date of the final payment to the contractor for all contract work and shall be available at reasonable times and places for inspection by authorized representatives of the contracting agency and the FHWA.
a. The records kept by the contractor shall document the following:
(1) The number and work hours of minority and non-minority group members and women employed in each work classification on the project;
(2) The progress and efforts being made in cooperation with unions, when applicable, to increase employment opportunities for minorities and women; and
(3) The progress and efforts being made in locating, hiring, training, qualifying, and upgrading minorities and women.
b. The contractors and subcontractors will submit an annual report to the contracting agency each July for the duration of the project, indicating the number of minority, women, and nonminority group employees currently engaged in each work classification required by the contract work. This information is to be reported on Form FHWA-1391. The staffing data should represent the project work force on board in all or any part of the last payroll period preceding the end of July. If on-the-job training is being required by special provision, the contractor will be required to collect and report training data. The employment data should reflect the work force on board during all or any part of the last payroll period preceding the end of July.

III. NONSEGREGATED FACILITIES
This provision is applicable to all Federal-aid construction contracts and to all related construction subcontracts of $10,000 or more.

The contractor must ensure that facilities provided for employees are provided in such a manner that segregation on the basis of race, color, religion, sex, or national origin cannot result. The contractor may neither require such segregated use by written or oral policies nor tolerate such use by employee custom. The contractor's obligation extends further to ensure that its employees are not assigned to perform their services at any location, under the contractor's control, where the facilities are segregated. The term "facilities" includes waiting rooms, work areas, restaurants and other eating areas, time clocks, restrooms, washrooms, locker rooms, and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing provided for employees. The contractor shall provide separate or single-user restrooms and necessary dressing or sleeping areas to assure privacy between sexes.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 141 of 219 ends

Page of 14 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract
IV. DAVIS-BACON AND RELATED ACT PROVISIONS
This section is applicable to all Federal-aid construction projects exceeding $2,000 and to all related subcontracts and lower-tier subcontracts (regardless of subcontract size). The requirements apply to all projects located within the right-of-way of a roadway that is functionally classified as Federal-aid highway. This excludes roadways functionally classified as local roads or rural minor collectors, which are exempt. Contracting agencies may elect to apply these requirements to other projects.

The following provisions are from the U.S. Department of Labor regulations in 29 CFR 5.5 “Contract provisions and related matters” with minor revisions to conform to the FHWA-1273 format and FHWA program requirements.

1. Minimum wages
a. All laborers and mechanics employed or working upon the site of the work, will be paid unconditionally and not less often than once a week, and without subsequent deduction or rebate on any account (except such payroll deductions as are permitted by regulations issued by the Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages and bona fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of Labor which is attached hereto and made a part hereof, regardless of any contractual relationship which may be alleged to exist between the contractor and such laborers and mechanics.

Contributions made or costs reasonably anticipated for bona fide fringe benefits under section 1(b)(2) of the Davis-Bacon Act on behalf of laborers or mechanics are considered wages paid to such laborers or mechanics, subject to the provisions of paragraph 1.d. of this section; also, regular contributions made or costs incurred for more than a weekly period (but not less often than quarterly) under plans, funds, or programs which cover the particular weekly period, are deemed to be constructively made or incurred during such weekly period. Such laborers and mechanics shall be paid the appropriate wage rate and fringe benefits on the wage
determination for the classification of work actually performed, without regard to skill, except as provided in 29 CFR 5.5(a)(4).

Laborers or mechanics performing work in more than one
classification may be compensated at the rate specified for each classification for the time actually worked therein: Provided, That the employer's payroll records accurately set forth the time spent in each classification in which work is performed. The wage determination (including any additional classification and wage rates conformed under paragraph 1.b. of this section) and the Davis-Bacon poster (WH–1321) shall be posted at all times by the contractor and its subcontractors at the site of the work in a prominent and accessible place where it can be easily seen by the workers.
b. (1) The contracting officer shall require that any class of laborers or mechanics, including helpers, which is not listed in the wage determination and which is to be employed under the contract shall be classified in conformance with the wage determination. The contracting officer shall approve an additional classification and wage rate and fringe benefits therefore only when the following criteria have been met:

FHWA-1273 -- Revised May 1, 2012
(i) The work to be performed by the classification requested is not performed by a classification in the wage determination; and (ii) The classification is utilized in the area by the construction industry; and
(iii) The proposed wage rate, including any bona fide fringe benefits, bears a reasonable relationship to the wage rates contained in the wage determination.
(2) If the contractor and the laborers and mechanics to be employed in the classification (if known), or their
representatives, and the contracting officer agree on the classification and wage rate (including the amount designated for fringe benefits where appropriate), a report of the action taken shall be sent by the contracting officer to the Administrator of the Wage and Hour Division, Employment Standards
Administration, U.S. Department of Labor, Washington, DC 20210. The Administrator, or an authorized representative, will approve, modify, or disapprove every additional classification action within 30 days of receipt and so advise the contracting officer or will notify the contracting officer within the 30-day period that additional time is necessary.
(3) In the event the contractor, the laborers or mechanics to be employed in the classification or their representatives, and the contracting officer do not agree on the proposed classification and wage rate (including the amount designated for fringe benefits, where appropriate), the contracting officer shall refer the questions, including the views of all interested parties and the recommendation of the contracting officer, to the Wage and Hour Administrator for determination. The Wage and Hour Administrator, or an authorized representative, will issue a determination within 30 days of receipt and so advise the contracting officer or will notify the contracting officer within the 30-day period that additional time is necessary.
(4) The wage rate (including fringe benefits where appropriate) determined pursuant to paragraphs 1.b.(2) or 1.b.(3) of this section, shall be paid to all workers performing work in the classification under this contract from the first day on which work is performed in the classification.
c. Whenever the minimum wage rate prescribed in the contract for a class of laborers or mechanics includes a fringe benefit which is not expressed as an hourly rate, the contractor shall either pay the benefit as stated in the wage determination or shall pay another bona fide fringe benefit or an hourly cash equivalent thereof.
d. If the contractor does not make payments to a trustee or other third person, the contractor may consider as part of the wages of any laborer or mechanic the amount of any costs reasonably anticipated in providing bona fide fringe benefits under a plan or program, Provided, That the Secretary of Labor has found, upon the written request of the contractor, that the applicable standards of the Davis-Bacon Act have been met. The Secretary of Labor may require the contractor to set aside in a separate account assets for the meeting of obligations under the plan or program.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 142 of 219 ends

Page of 15 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract

2.Withholding
The contracting agency shall upon its own action or upon written request of an authorized representative of the Department of Labor, withhold or cause to be withheld from the contractor under this contract, or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to DavisBacon prevailing wage requirements, which is held by the same prime contractor, so much of the accrued payments or advances as may be considered necessary to pay laborers and mechanics, including apprentices, trainees, and helpers, employed by the contractor or any subcontractor the full amount of wages required by the contract. In the event of failure to pay any laborer or mechanic, including any apprentice, trainee, or helper, employed or working on the site of the work, all or part of the wages required by the contract, the contracting agency may, after written notice to the contractor, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds until such violations have ceased.

3.Payrolls and basic records
a. Payrolls and basic records relating thereto shall be maintained by the contractor during the course of the work and preserved for a period of three years thereafter for all laborers and mechanics working at the site of the work. Such records shall contain the name, address, and social security number of each such worker, his or her correct classification, hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in section 1(b)(2)(B) of the Davis-Bacon Act), daily and weekly number of hours worked, deductions made and actual wages paid.

Whenever the Secretary of Labor has found under 29 CFR

5.5(a)(1)(iv) that the wages of any laborer or mechanic include the amount of any costs reasonably anticipated in providing benefits under a plan or program described in section 1(b)(2)(B) of the Davis-Bacon Act, the contractor shall maintain records which show that the commitment to provide such benefits is enforceable, that the plan or program is financially responsible, and that the plan or program has been communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated or the actual cost incurred in providing such benefits. Contractors employing apprentices or trainees under approved programs shall maintain written evidence of the registration of apprenticeship programs and certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs.
b. (1) The contractor shall submit weekly for each week in which any contract work is performed a copy of all payrolls to the contracting agency. The payrolls submitted shall set out accurately and completely all of the information required to be maintained under 29 CFR 5.5(a)(3)(i), except that full social security numbers and home addresses shall not be included on weekly transmittals.

Instead the payrolls shall only need to include an individually identifying number for each employee ( e.g. , the last four digits of the employee's social security number). The required weekly payroll information may be submitted in any form desired. Optional Form WH–347 is available for this purpose from the Wage and Hour Division Web site at
http://www.dol.gov/esa/whd/forms/wh347instr.htm or its successor site. The prime contractor is responsible for the submission of copies of payrolls by all subcontractors. Contractors and subcontractors shall maintain the full social security number and FHWA-1273 -- Revised May 1, 2012
current address of each covered worker, and shall provide them upon request to the contracting agency for transmission to the State DOT, the FHWA or the Wage and Hour Division of the Department of Labor for purposes of an investigation or audit of compliance with prevailing wage requirements. It is not a violation of this section for a prime contractor to require a subcontractor to provide addresses and social security numbers to the prime contractor for its own records, without weekly submission to the contracting agency.
(2) Each payroll submitted shall be accompanied by a “Statement of Compliance,” signed by the contractor or subcontractor or his or her agent who pays or supervises the payment of the
persons employed under the contract and shall certify the following:
(i) That the payroll for the payroll period contains the information required to be provided under §5.5 (a)(3)(ii) of Regulations, 29 CFR part 5, the appropriate information is being maintained under §5.5 (a)(3)(i) of Regulations, 29 CFR part 5, and that such information is correct and complete;
(ii)That each laborer or mechanic (including each helper, apprentice, and trainee) employed on the contract during the payroll period has been paid the full weekly wages earned, without rebate, either directly or indirectly, and that no deductions have been made either directly or indirectly from the full wages earned, other than permissible deductions as set forth in Regulations, 29 CFR part 3;
(iii) That each laborer or mechanic has been paid not less than the applicable wage rates and fringe benefits or cash equivalents for the classification of work performed, as specified in the applicable wage determination incorporated into the contract. (3) The weekly submission of a properly executed certification set forth on the reverse side of Optional Form WH–347 shall satisfy the requirement for submission of the “Statement of Compliance” required by paragraph 3.b.(2) of this section. (4) The falsification of any of the above certifications may subject the contractor or subcontractor to civil or criminal prosecution under section 1001 of title 18 and section 231 of title 31 of the United States Code.
c. The contractor or subcontractor shall make the records required under paragraph 3.a. of this section available for inspection, copying, or transcription by authorized
representatives of the contracting agency, the State DOT, the FHWA, or the Department of Labor, and shall permit such representatives to interview employees during working hours on the job. If the contractor or subcontractor fails to submit the required records or to make them available, the FHWA may, after written notice to the contractor, the contracting agency or the State DOT, take such action as may be necessary to
cause the suspension of any further payment, advance, or guarantee of funds. Furthermore, failure to submit the required records upon request or to make such records available may be grounds for debarment action pursuant to 29 CFR 5.12.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 143 of 219 ends

Page of 16 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract
FHWA-1273 -- Revised May 1, 2012

4. Apprentices and trainees
a.Apprentices (programs of the USDOL).

Apprentices will be permitted to work at less than the predetermined rate for the work they performed when they are employed pursuant to and individually registered in a bona fide apprenticeship program registered with the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer and Labor Services, or with a State Apprenticeship Agency recognized by the Office, or if a person is employed in his or her first 90 days of probationary employment as an apprentice in such an apprenticeship program, who is not individually registered in the program, but who has been certified by the Office of Apprenticeship Training, Employer and Labor Services or a State Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice.

The allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be greater than the ratio permitted to the contractor as to the entire work force under the registered program. Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated above, shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any apprentice performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. Where a contractor is performing construction on a project in a locality other than that in which its program is registered, the ratios and wage rates (expressed in percentages of the journeyman's hourly rate) specified in the contractor's or subcontractor's registered program shall be observed.

Every apprentice must be paid at not less than the rate specified in the registered program for the apprentice's level of progress, expressed as a percentage of the journeymen hourly rate specified in the applicable wage determination. Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the wage determination for the applicable classification. If the Administrator determines that a different practice prevails for the applicable apprentice classification, fringes shall be paid in accordance with that determination.

In the event the Office of Apprenticeship Training, Employer and Labor Services, or a State Apprenticeship Agency recognized by the Office, withdraws approval of an apprenticeship program, the contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed until an acceptable program is approved.
b. Trainees (programs of the USDOL).

Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification by the U.S. Department of Labor, Employment and Training Administration.

The ratio of trainees to journeymen on the job site shall not be greater than permitted under the plan approved by the Employment and Training Administration.

Every trainee must be paid at not less than the rate specified in the approved program for the trainee's level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination. Trainees shall be paid fringe benefits in accordance with the provisions of the trainee program. If the trainee program does not mention fringe benefits, trainees shall be paid the full amount of fringe benefits listed on the wage determination unless the Administrator of the Wage and Hour Division determines that there is an apprenticeship program associated with the corresponding journeyman wage rate on the wage determination which provides for less than full fringe benefits for apprentices. Any employee listed on the payroll at a trainee rate who is not registered and participating in a training plan approved by the Employment and Training Administration shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any trainee performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed.

In the event the Employment and Training Administration withdraws approval of a training program, the contractor will no longer be permitted to utilize trainees at less than the applicable predetermined rate for the work performed until an acceptable program is approved.
c. Equal employment opportunity. The utilization of apprentices, trainees and journeymen under this part shall be in conformity with the equal employment opportunity requirements of Executive Order 11246, as amended, and 29 CFR part 30.
d. Apprentices and Trainees (programs of the U.S. DOT).

Apprentices and trainees working under apprenticeship and skill training programs which have been certified by the Secretary of Transportation as promoting EEO in connection with Federal-aid highway construction programs are not subject to the requirements of paragraph 4 of this Section IV. The straight time hourly wage rates for apprentices and trainees under such programs will be established by the particular programs. The ratio of apprentices and trainees to journeymen shall not be greater than permitted by the terms of the particular program.

5. Compliance with Copeland Actrequirements. The contractor shall comply with the requirements of 29 CFR part 3, which are incorporated by reference in this contract.

6. Subcontracts. The contractor or subcontractor shall insert Form FHWA-1273 in any subcontracts and also require the subcontractors to include Form FHWA-1273 in any lower tier subcontracts. The prime contractor shall be responsible for the compliance by any subcontractor or lower tier subcontractor with all the contract clauses in 29 CFR 5.5.

7. Contract termination: debarment. A breach of the contract clauses in 29 CFR 5.5 may be grounds for termination of the contract, and for debarment as a contractor and a subcontractor as provided in 29 CFR 5.12.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 144 of 219 ends

Page of 17 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract
FHWA-1273 -- Revised May 1, 2012

8. Compliance with Davis-Bacon and Related Actrequirements.

All rulings and interpretations of the Davis-Bacon and Related Acts contained in 29 CFR parts 1, 3, and 5 are herein incorporated by reference in this contract.

9. Disputes concerning labor standards. Disputes arising out of the labor standards provisions of this contract shall not be subject to the general disputes clause of this contract. Such disputes shall be resolved in accordance with the procedures of the Department of Labor set forth in 29 CFR parts 5, 6, and 7. Disputes within the meaning of this clause include disputes between the contractor (or any of its subcontractors) and the contracting agency, the U.S.

Department of Labor, or the employees or their representatives.

10. Certification of eligibility.
a.By entering into this contract, the contractor certifies that neither it (nor he or she) nor any person or firm who has an interest in the contractor's firm is a person or firm ineligible to be awarded Government contracts by virtue of section 3(a) of the DavisBacon Act or 29 CFR 5.12(a)(1). b. No part of this contract shall be subcontracted to any person or firm ineligible for award of a Government contract by virtue of section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1). c. The penalty for making false statements is prescribed in theU.S.

Criminal Code, 18 U.S.C. 1001.

V. CONTRACT WORK HOURS AND SAFETY STANDARDS
ACT
The following clauses apply to any Federal-aid construction contract in an amount in excess of $100,000 and subject to the overtime provisions of the Contract Work Hours and Safety Standards Act.

These clauses shall be inserted in addition to the clauses required by 29 CFR 5.5(a) or 29 CFR 4.6. As used in this paragraph, the terms laborers and mechanics include watchmen and guards.

1. Overtime requirements. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives
compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.

2.Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in paragraph (1.) of this section, the contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth inparagraph(1.) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (1.) of this section.

3. Withholding for unpaid wages and liquidated damages. The FHWA or the contacting agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (2.) of this section.

4. Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clauses set forth in paragraph (1.) through (4.) of this section and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (1.) through (4.) of this section.

VI. SUBLETTING OR ASSIGNING THE CONTRACT
This provision is applicable to all Federal-aid construction contracts on the National Highway System.

1. The contractor shall perform with its own organization contract work amounting to not less than 30 percent (or a greater percentage if specified elsewhere in the contract) of the total original contract price, excluding any specialty items designated by the contracting agency. Specialty items may be performed by subcontract and the amount of any such specialty items performed may be deducted from the total original contract price before computing the amount of work required to be performed by the contractor's own organization (23 CFR 635.116).
a. The term “perform work with its own organization” refers to workers employed or leased by the prime contractor, and equipment owned or rented by the prime contractor, with or without operators. Such term does not include employees or equipment of a subcontractor or lower tier subcontractor, agents of the prime contractor, or any other assignees. The term may include payments for the costs of hiring leased employees from an employee leasing firm meeting allrelevant Federal and State regulatory requirements. Leased
employees may only be included in this term if the prime contractor meets all of the following conditions:
(1) the prime contractor maintains control over the supervision of the day-to-day activities of the leased employees;
(2) the prime contractor remains responsible for the quality of the work of the leased employees;
(3) the prime contractor retains all power to accept or exclude individual employees from work on the project; and
(4) the prime contractor remains ultimately responsible for the payment of predetermined minimum wages, the submission of payrolls, statements of compliance and all other Federal regulatory requirements.
b. "Specialty Items" shall be construed to be limited to work that requires highly specialized knowledge, abilities, or equipment not ordinarily available in the type of contracting organizations qualified and expected to bid or propose on the contract as a whole and in general are to be limited to minor components of the overall contract.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 145 of 219 ends

Page of 18 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract

2. The contract amount upon which the requirements set forth in VIII. FALSE STATEMENTS CONCERNING HIGHWAY paragraph (1) of Section VI is computed includes the cost of PROJECTS material and manufactured products which are to be purchasedor produced by the contractor under the contract provisions. This provision is applicable to all Federal-aid construction contracts and to all related subcontracts.

3. The contractor shall furnish (a) a competent superintendent or supervisor who is employed by the firm, has full authority todirect performance of the work in accordance with the contract requirements, and is in charge of all construction operations (regardless of who performs the work) and (b) such other of its own organizational resources (supervision, management, and engineering services) as the contracting officer determines is necessary to assure the performance of the contract.

4. No portion of the contract shall be sublet, assigned orotherwise disposed of except with the written consent of the contracting officer, or authorized representative, and such consent when given shall not be construed to relieve the contractor of any responsibility for the fulfillment of the contract. Written consent will be given only after the contracting agency has assured that each subcontract is evidenced in writing and that it contains all pertinent provisions and requirements of the prime contract.

5. The 30% self-performance requirement of paragraph (1) is not applicable to design-build contracts; however, contracting agencies may establish their own self-performancerequirements.

VII. SAFETY: ACCIDENT PREVENTION
This provision is applicable to all Federal-aid construction contracts and to all related subcontracts.

1. In the performance of this contract the contractor shall comply with all applicable Federal, State, and local laws governing safety, health, and sanitation (23 CFR 635). The contractor shall provide all safeguards, safety devices and protective equipment and take any other needed actions as it determines, or as the contracting officer may determine, to be reasonably necessary to protect the life and health of employees on the job and the safety of thepublic and to protect property in connection with the performance of the work covered by the contract.

2. It is a condition of this contract, and shall be made a condition of each subcontract, which the contractor enters into pursuant to this contract, that the contractor and any subcontractor shall not permit any employee, in performance of the contract, to work in surroundings or under conditions which are unsanitary, hazardous or dangerous to his/her health or safety, as determined under construction safety and health standards (29 CFR 1926)
promulgated by the Secretary of Labor, in accordance with Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C. 3704).

3. Pursuant to 29 CFR 1926.3, it is a condition of this contract that the Secretary of Labor or authorized representative thereof, shall have right of entry to any site of contract performance to inspector investigate the matter of compliance with the construction safety and health standards and to carry out the duties of the Secretary under Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C.3704).

In order to assure high quality and durable construction in conformity with approved plans and specifications and a high degree of reliability on statements and representations made by engineers, contractors, suppliers, and workers on Federal-aid highway projects, it is essential that all persons concerned with the project perform their functions as carefully, thoroughly, and honestly as possible.

Willful falsification, distortion, or misrepresentation with respect to any facts related to the project is a violation of Federal law. To prevent any misunderstanding regarding the seriousness ofthese and similar acts, Form FHWA-1022 shall be posted on each Federal-aid highway project (23 CFR 635) in one or more places where it is readily available to all persons concerned with the project:
18 U.S.C. 1020 reads as follows:
"Whoever, being an officer, agent, or employee of the United States, or of any State or Territory, or whoever, whether a person, association, firm, or corporation, knowingly makes any false statement, false representation, or false report as to the character, quality, quantity, or cost of the material used or to be used, or the quantity or quality of the work performed or to be performed, or the cost thereof in connection with the submission of plans, maps, specifications, contracts, or costs of construction on any highway or related project submitted for approval to the Secretary of Transportation; or
Whoever knowingly makes any false statement, false
representation, false report or false claim with respect to the character, quality, quantity, or cost of any work performed or to be performed, or materials furnished or to be furnished, in connection with the construction of any highway or related project approved by the Secretary of Transportation; or
Whoever knowingly makes any false statement or false
representation as to material fact in any statement, certificate, or report submitted pursuant to provisions of the Federal-aid Roads Act approved July 1, 1916, (39 Stat. 355), as amended and
supplemented;
Shall be fined under this title or imprisoned not more than 5 years or both."
IX. IMPLEMENTATION OF CLEAN AIR ACT AND FEDERAL

WATER POLLUTION CONTROL ACT
This provision is applicable to all Federal-aid construction contracts and to all related subcontracts.

By submission of this bid/proposal or the execution of this contract, or subcontract, as appropriate, the bidder, proposer, Federal-aid construction contractor, or subcontractor, as appropriate, will be deemed to have stipulated as follows:

1. That any person who is or will be utilized in the
performance of this contract is not prohibited from receiving an award due to a violation of Section 508 of the Clean Water Act or Section 306 of the Clean Air Act.

2. That the contractor agrees to include or cause to be included the requirements of paragraph (1) of this Section X in every subcontract, and further agrees to take such action as the contracting agency may direct as a means of enforcing such requirements.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 146 of 219 ends

Page of 19 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract
FHWA-1273 -- Revised May 1, 2012
X. CERTIFICATION REGARDING DEBARMENT, SUSPENSION,

INELIGIBILITY AND VOLUNTARY EXCLUSION
This provision is applicable to all Federal-aid construction contracts, design-build contracts, subcontracts, lower-tier subcontracts, purchase orders, lease agreements, consultant contracts or any other covered transaction requiring FHWA approval or that is estimated to cost $25,000 or more – as defined in 2 CFR Parts 180 and 1200.

9. Instructions for Certification – First Tier Participants:
a. By signing and submitting this proposal, the prospective first tier participant is providing the certification set out below. b. The inability of a person to provide the certification set out below will not necessarily result in denial of participation in this covered transaction. The prospective first tier participant shall submit an explanation of why it cannot provide the certification set outbelow.

The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective first tier participant to furnish a certification or an explanation shall disqualify such a person from participation in this transaction. c. The certification in this clause is a material representation of fact upon which reliance was placed when the contracting agency determined to enter into this transaction. If it is later determined that the prospective participant knowingly rendered an erroneous certification, in addition to other remedies available to the Federal Government, the contracting agency may terminate this
transaction for cause of default.
d. The prospective first tier participant shall provide immediatewritten notice to the contracting agency to whom this proposal is submitted if any time the prospective first tier participant learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.
e. The terms "covered transaction," "debarred," "suspended," "ineligible," "participant," "person," "principal," and "voluntarily excluded," as used in this clause, are defined in 2 CFR Parts 180 and 1200. “First Tier Covered Transactions” refers to any covered transaction between a grantee or subgrantee of Federal funds and a participant (such as the prime or general contract). “Lower Tier Covered Transactions” refers to any covered transaction under a First Tier Covered Transaction (such as subcontracts). “First Tier Participant” refers to the participant who has entered into a covered transaction with a grantee or subgrantee of Federal funds (such as the prime or general contractor). “Lower Tier Participant” refers any participant who has entered into a covered transaction with a First Tier Participant or other Lower Tier Participants (such as subcontractors and suppliers).
f. The prospective first tier participant agrees by submitting this proposal that, should the proposed covered transaction be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department or agency entering into this transaction.
g. The prospective first tier participant further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transactions," provided by the department or contracting agency, entering into this covered transaction, without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions exceeding the $25,000 threshold.
h. A participant in a covered transaction may rely upon a certification of a prospective participant in a lower tier covered transaction that is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A participant is responsible for ensuring that its principals are not suspended, debarred, or otherwise ineligible to participate in covered transactions. To verify the eligibility of its principals, as well as the eligibility of any lower tier prospective participants, each participant may, but is not required to, checkthe Excluded Parties List System website (https://www.epls.gov/), which is compiled by the General Services Administration. i. Nothing contained in the foregoing shall be construed to require the establishment of a system of records in order to render ingood faith the certification required by this clause. The knowledge and information of the prospective participant is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.
j. Except for transactions authorized under paragraph (f) of these instructions, if a participant in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible, or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department or agency may terminate this transaction for cause or default.
* * *

10.Certification Regarding Debarment, Suspension,Ineligibility and Voluntary Exclusion – First Tier Participants:
a. The prospective first tier participant certifies to the best ofits knowledge and belief, that it and its principals:
(1) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participating in covered transactions by any Federal department or agency;
(2) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered againstthem for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property;
(3) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offenses enumerated in paragraph (a)(2) of this certification; and
(4) Have not within a three-year period preceding this
application/proposal had one or more public transactions (Federal, State or local) terminated for cause or default. b. Where the prospective participant is unable to certify to any of the statements in this certification, such prospective participant shall attach an explanation to this proposal.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 147 of 219 ends

Page of 20 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract

2. Instructions for Certification - Lower Tier Participants:
(Applicable to all subcontracts, purchase orders and other lower tier transactions requiring prior FHWA approval or estimated to cost $25,000 or more - 2 CFR Parts 180 and 1200)
a. By signing and submitting this proposal, the prospective lowertier is providing the certification set out below.
b. The certification in this clause is a material representation of fact upon which reliance was placed when this transaction was entered into. If it is later determined that the prospective lower tier participant knowingly rendered an erroneous certification, in addition to other remedies available to the Federal Government, the department, or agency with which this transaction originated may pursue available remedies, including suspension and/or debarment.
c. The prospective lower tier participant shall provide immediate written notice to the person to which this proposal is submitted if at any time the prospective lower tier participant learns that its certification was erroneous by reason of changed circumstances. d. The terms "covered transaction," "debarred," "suspended," "ineligible," "participant," "person," "principal," and "voluntarily excluded," as used in this clause, are defined in 2 CFR Parts 180 and 1200. You may contact the person to which this proposal is submitted for assistance in obtaining a copy of those regulations. “First Tier Covered Transactions” refers to any covered transaction between a grantee or subgrantee of Federal funds and a participant (such as the prime or general contract). “Lower Tier Covered Transactions” refers to any covered transaction under a First Tier Covered Transaction (such as subcontracts). “First Tier Participant” refers to the participant who has entered into a covered transaction with a grantee or subgrantee of Federal funds (such as the prime or general contractor). “Lower Tier Participant” refers any participant who has entered into a covered transaction with a First Tier Participant or other Lower Tier Participants (such as subcontractors and suppliers). e. The prospective lower tier participant agrees by submitting this proposal that, should the proposed covered transaction be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department or agency with which this transaction originated.
f. The prospective lower tier participant further agrees by submitting this proposal that it will include this clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transaction," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions exceeding the $25,000 threshold. g. A participant in a covered transaction may rely upon a certification of a prospective participant in a lower tier covered transaction that is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A participant is responsible for ensuring that its principals are not suspended, debarred, or otherwise ineligible to participate in covered transactions. To verify the eligibility of its principals, as well as the eligibility of any lower tier prospective participants, each participant may, but is not required to, check the Excluded Parties List System website (https://www.epls.gov/), which is compiled by the General Services Administration.

FHWA-1273 -- Revised May 1, 2012
h. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and normally possessed by a prudent person in the ordinary course of business dealings.
i. Except for transactions authorized under paragraph e of these instructions, if a participant in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible, or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department or agency with which this transaction originated may pursue available remedies, including suspension and/or debarment.
* * * * *
Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion--Lower Tier Participants:

1. The prospective lower tier participant certifies, by submission of this proposal, that neither it nor its principals is presently debarred, suspended, proposed for debarment, declared
ineligible, or voluntarily excluded from participating in covered transactions by any Federal department or agency.

2. Where the prospective lower tier participant is unable to certify to any of the statements in this certification, such prospective participant shall attach an explanation to this proposal. * * * * *
XI. CERTIFICATION REGARDING USE OF CONTRACT FUNDS

FOR LOBBYING
This provision is applicable to all Federal-aid construction contracts and to all related subcontracts which exceed $100,000 (49 CFR 20).

9. The prospective participant certifies, by signing andsubmitting this bid or proposal, to the best of his or her knowledge and belief, that:
a. No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in
connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement. b. If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form-LLL, "Disclosure Form to Report Lobbying," in accordance with its instructions.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 148 of 219 ends

Page of 21 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract

2. This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by 31 U.S.C. 1352.

Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.

3. The prospective participant also agrees by submitting its bid or proposal that the participant shall require that the language of this certification be included in all lower tier subcontracts, which exceed information of participant is not required to exceed that which is $100,000 and that all such recipients shall certify and disclose accordingly.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 149 of 219 ends

Page of 22 of 29
January 2022
Local Assistance Procedures Exhibit 12-G
Required Federal-Aid Contract

12. FEMALE AND MINORITY GOALS
To comply with Section II, "Nondiscrimination," of "Required Contract Provisions Federal-Aid Construction Contracts," the following are for female and minority utilization goals for Federal-aid construction contracts and subcontracts that exceed $10,000:

The nationwide goal for female utilization is 6.9 percent.

The goals for minority utilization [45 Fed Reg 65984 (10/3/1980)] are as follows:

MINORITY UTILIZATION GOALS
Economic
Area
Goal
(Percent)
174 Redding CA:

Non-SMSA (Standard Metropolitan Statistical Area) Counties:

CA Lassen; CA Modoc; CA Plumas; CA Shasta; CA Siskiyou; CA Tehama

6.8 175
Eureka, CA
Non-SMSA Counties:

CA Del Norte; CA Humboldt; CA Trinity

6.6 San Francisco-Oakland-San Jose, CA:

SMSA Counties:

28.9 7120 Salinas-Seaside-Monterey, CA
CA Monterey
7360 San Francisco-Oakland 25.6
CA Alameda; CA Contra Costa; CA Marin; CA San Francisco; CA San Mateo 176
7400 San Jose, CA
CA Santa Clara, CA 7485
Santa Cruz, CA
CA Santa Cruz

19.6 14.9
7500 Santa Rosa 9.1
CA Sonoma
8720 Vallejo-Fairfield-Napa, CA 17.1
CA Napa; CA Solano
Non-SMSA Counties: 23.2
CA Lake; CA Mendocino; CA San Benito
Sacramento, CA:
177
SMSA Counties:
6920 Sacramento, CA
CA Placer; CA Sacramento; CA Yolo
Non-SMSA Counties

16.1 14.3
CA Butte; CA Colusa; CA El Dorado; CA Glenn; CA Nevada; CA Sierra; CA Sutter; CA Yuba
178
Stockton-Modesto, CA:

SMSA Counties:
5170 Modesto, CA 12.3
CA Stanislaus 8120
Stockton, CA
CA San Joaquin

24.3 Non-SMSA Counties
CA Alpine; CA Amador; CA Calaveras; CA Mariposa; CA Merced; CA Tuolumne

19.8 Fresno-Bakersfield, CA
SMSA Counties:
179 0680 Bakersfield, CA 19.1
CA Kern
2840 Fresno, CA 26.1
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 150 of 219 ends

Page of 23 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
CA Fresno
Non-SMSA Counties:

CA Kings; CA Madera; CA Tulare

23.6 180
Los Angeles, CA:

SMSA Counties:
0360 Anaheim-Santa Ana-Garden Grove, CA 11.9
CA Orange
4480 Los Angeles-Long Beach, CA 28.3
CA Los Angeles
6000 Oxnard-Simi Valley-Ventura, CA CA
Ventura
6780 Riverside-San Bernardino-Ontario, CA

21.5 19.0
CA Riverside; CA San Bernardino
7480 Santa Barbara-Santa Maria-Lompoc, CA

19.7 CA Santa Barbara
Non-SMSA Counties
CA Inyo; CA Mono; CA San Luis Obispo

24.6 181
San Diego, CA:

SMSA Counties

16.9 7320 San Diego, CA
CA San Diego
Non 18.2 -SMSA Counties
CA Imperial
For the last full week of July during which work is performed under the contract, the prime contractor and each non material-supplier subcontractor with a subcontract of $10,000 or more must complete Form FHWA PR-1391 (Appendix C to 23 CFR 230). Submit the forms by August 15.

13. TITLE VI ASSURANCES
The U.S. Department of Transportation Order No.1050.2A requires all federal-aid Department of Transportation contracts between an agency and a contractor to contain Appendix A and E. Appendix B only requires inclusion if the contract impacts deeds effecting or recording the transfer of real property, structures, or improvements thereon, or granting interest therein. Appendices C and D only require inclusion if the contract impacts deeds, licenses, leases, permits, or similar instruments entered into by the recipient.

APPENDIX A
During the performance of this Agreement, the contractor, for itself, its assignees and successors in interest (hereinafter collectively referred to as CONTRACTOR) agrees as follows:
a. Compliance with Regulations: CONTRACTOR shall comply with the regulations relative to nondiscrimination in federally assisted programs of the Department of Transportation, Title 49, Code of Federal Regulations, Part 21, as they may be amended from time to time, (hereinafter referred to as the REGULATIONS), which are herein incorporated by reference and made a part of this agreement.
b. Nondiscrimination: CONTRACTOR, with regard to the work performed by it during the AGREEMENT, shall not discriminate on the grounds of race, color, sex, national origin, religion, age, or disability in the selection and retention of sub-applicants, including procurements of materials and leases of equipment. CONTRACTOR shall not participate either directly or indirectly in the discrimination prohibited by Section 21.5 of the Regulations, including employment practices when the agreement covers a program set forth in Appendix B of the Regulations. c. Solicitations for Sub-agreements, Including Procurements of Materials and Equipment: In all solicitations either by competitive bidding or negotiation made by CONTRACTOR for work to be performed under a Sub- agreement, including procurements of materials or leases of equipment, Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 151 of 219 ends

Page of 24 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
each potential sub-applicant or supplier shall be notified by CONTRACTOR of the CONTRACTOR’S obligations under this Agreement and the Regulations relative to nondiscrimination on the grounds of race, color, or national origin.
d. Information and Reports: CONTRACTOR shall provide all information and reports required by the Regulations, or directives issued pursuant thereto, and shall permit access to its books, records, accounts, other sources of information, and its facilities as may be determined by the recipient or FHWA to be pertinent to ascertain compliance with such Regulations or directives. Where any information required of CONTRACTOR is in the exclusive possession of another who fails or refuses to furnish this information, CONTRACTOR shall so certify to the recipient or FHWA as appropriate, and shall set forth what efforts CONTRACTOR has made to obtain the information. e. Sanctions for Noncompliance: In the event of CONTRACTOR’s noncompliance with the nondiscrimination provisions of this agreement, the recipient shall impose such agreement sanctions as it or the FHWA may determine to be appropriate, including, but not limited to:
i. withholding of payments to CONTRACTOR under the Agreement within a reasonable period of time, not to exceed 90 days; and/or
ii. cancellation, termination or suspension of the Agreement, in whole or in part. f. Incorporation of Provisions: CONTRACTOR shall include the provisions of paragraphs (1) through (6) in every sub-agreement, including procurements of materials and leases of equipment, unless exempt by the Regulations, or directives issued pursuant thereto.

CONTRACTOR shall take such action with respect to any sub-agreement or procurement as the recipient or FHWA may direct as a means of enforcing such provisions including sanctions for noncompliance, provided, however, that, in the event CONTRACTOR becomes involved in, or is threatened with, litigation with a sub-applicant or supplier as a result of such direction, CONTRACTOR may request the recipient enter into such litigation to protect the interests of the State, and, in addition, CONTRACTOR may request the United States to enter into such litigation to protect the interests of the United States.

APPENDIX B

CLAUSES FOR DEEDS TRANSFERRING UNITED STATES PROPERTY
The following clauses will be included in deeds effecting or recording the transfer of real property, structures, or improvements thereon, or granting interest therein from the United States pursuant to the provisions of Assurance 4:

NOW THEREFORE, the U.S. Department of Transportation as authorized by law and upon the condition that the recipient will accept title to the lands and maintain the project constructed thereon in accordance with Title 23 U.S.C., the regulations for the administration of the preceding statute, and the policies and procedures prescribed by the FHWA of the U.S. Department of Transportation in accordance and in compliance with all requirements imposed by Title 49, Code of Federal Regulations, U.S. Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Non-discrimination in Federally-assisted programs of the U.S. Department of Transportation pertaining to and effectuating the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252; 42 U.S.C. § 2000d to 2000d-4), does hereby remise, release, quitclaim and convey unto the recipient all the right, title and interest of the U.S. Department of Transportation in and to said lands described in Exhibit A attached hereto and made a part hereof. (HABENDUM CLAUSE)
TO HAVE AND TO HOLD said lands and interests therein unto the recipient and its successors forever, subject, however, to the covenants, conditions, restrictions and reservations herein contained as follows, which will remain in effect for the period during which the real property or structures are used for a purpose for which Federal financial assistance is extended or for another purpose involving the provision of similar services or benefits and will be binding on the recipient, its successors and assigns. The recipient, in consideration of the conveyance of said lands and interest in lands, does hereby covenant and agree as a covenant running with the land for itself, its successors and assigns, that (1) no person Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 152 of 219 ends

Page of 25 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
will on the grounds of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination with regard to any facility located wholly or in part on, over, or under such lands hereby conveyed [,] [and]* (2) that the recipient will use the lands and interests in lands and interest in lands so conveyed, in compliance with all requirements imposed by or pursuant to Title 49, Code of Federal Regulations, U.S. Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Non-discrimination in Federally-assisted programs of the U.S. Department of Transportation, Effectuation of Title VI of the Civil Rights Act of 1964, and as said Regulations and Acts may be amended[, and (3) that in the event of breach of any of the above-mentioned non-discrimination conditions, the Department will have a right to enter or re-enter said lands and facilities on said lands, and that above described land and facilities will thereon revert to and vest in and become the absolute property of the U.S. Department of Transportation and its assigns as such interest existed prior to this instruction].*
(*Reverter clause and related language to be used only when it is determined that such a clause is necessary in order to make clear the purpose of Title VI.)

APPENDIX C

CLAUSES FOR TRANSFER OF REAL PROPERTY ACQUIRED OR IMPROVED UNDER THE

ACTIVITY, FACILITY, OR PROGRAM
The following clauses will be included in deeds, licenses, leases, permits, or similar instruments entered into by the recipient pursuant to the provisions of Assurance 7(a):

A. The (grantee, lessee, permittee, etc. as appropriate) for himself/herself, his/her heirs, personal representatives, successors in interest, and assigns, as a part of the consideration hereof, does hereby covenant and agree [in the case of deeds and leases add “as a covenant running with the land”] that:

1. In the event facilities are constructed, maintained, or otherwise operated on the property described in this (deed, license, lease, permit, etc.) for a purpose for which a U.S. Department of Transportation activity, facility, or program is extended or for another purpose involving the provision of similar services or benefits, the (grantee, licensee, lessee, permittee, etc.) will maintain and operate such facilities and services in compliance with all requirements imposed by the Acts and Regulations (as may be amended) such that no person on the grounds of race, color, or national origin, will be excluded from participation in, denied the benefits of, or be otherwise subjected to discrimination in the use of said facilities.

B. With respect to licenses, leases, permits, etc., in the event of breach of any of the above Nondiscrimination covenants, the recipient will have the right to terminate the (lease, license, permit, etc.) and to enter, re-enter, and repossess said lands and facilities thereon, and hold the same as if the (lease, license, permit, etc.) had never been made or issued.*
C. With respect to a deed, in the event of breach of any of the above Non-discrimination covenants, the recipient will have the right to enter or re-enter the lands and facilities thereon, and the above described lands and facilities will there upon revert to and vest in and become the absolute property of the recipient and its assigns.*
(*Reverter clause and related language to be used only when it is determined that such a clause is necessary to make clear the purpose of Title VI.)
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 153 of 219 ends

Page of 26 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language

APPENDIX D

CLAUSES FOR CONSTRUCTION/USE/ACCESS TO REAL PROPERTY ACQUIRED UNDER THE

ACTIVITY, FACILITY OR PROGRAM
The following clauses will be included in deeds, licenses, permits, or similar instruments/agreements entered into by the recipient pursuant to the provisions of Assurance 7(b):

A. The (grantee, licensee, permittee, etc., as appropriate) for himself/herself, his/her heirs, personal representatives, successors in interest ,and assigns, as a part of the consideration hereof, does hereby covenant and agree (in the case of deeds and leases add, “as a covenant running with the land”) that (1) no person on the ground of race, color, or national origin, will be excluded from participation in, denied the benefits of, or be otherwise subjected to discrimination in the use of said facilities, (2) that in the construction of any improvements on, over, or under such land, and the furnishings of services thereon, no person on the ground of race, color, or national origin, will be excluded from participation in, denied the benefits or, or otherwise be subjected to discrimination, (3) that the (grantee, licensee, lessee, permittee, etc.) will use the premises in compliance with all other requirements imposed by or pursuant to the Acts and Regulations, as amended, set forth in this Assurance.

B. With respect to (licenses, leases, permits, etc.) in the event of breach of any of the above of the above Non-discrimination covenants, the recipient will have the right to terminate the (license, permits, etc., as appropriate) and to enter or re-enter and repossess said land and the facilities thereon, and hold the same as if said (license, permit, etc., as appropriate) had never been made or issued.* C. With respect to deeds, in the event of breach of any of the above Non-discrimination covenants, the recipient will there upon revert to and vest in and become the absolute property of the recipient and its assigns.
(*Reverter clause and related language to be used only when it is determined that such a clause is necessary to make clear the purpose of Title VI.)

APPENDIX E
During the performance of this contract, the contractor, for itself, its assignees, and successors in interest (hereinafter referred to as the “contractor”) agrees to comply with the following non-discrimination statutes and authorities, including, but not limited to:

Pertinent Non-Discrimination Authorities:
• Title VI of the Civil Rights Act of 1964 (42 U.S.C. § 2000d et seq., 78 stat. 252), prohibits discrimination on the basis of race, color, national origin); and 49 CFR Part 21. • The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, (42 U.S.C. § 4601), (prohibits unfair treatment of persons displaced or whose property has been acquired because of Federal or Federal-aid programs and projects);
• Federal-Aid Highway Act of 1973, (23 U.S.C. § 324 et seq.), prohibits discrimination on the basis of sex; • Section 504 of the Rehabilitation Act of 1973, (29 U.S.C. § 794 et seq.), as amended, (prohibits discrimination on the basis of disability); and 49 CR Part 27; • The Age Discrimination Act of 1975, as amended, (42 U.S.C. § 6101 et seq.), prohibits discrimination on the basis of age);
• Airport and Airway Improvement Act of 1982, (49 U.S.C. § 471, Section 47123), as amended, (prohibits discrimination based on race, creed, color, national origin, or sex); • The Civil Rights Restoration Act of 1987, (PL 100-209), (Broadened the scope, coverage and applicability of Title VI of the Civil Rights Act of 1964, The Age Discrimination Act of 1975 and Section 504 of the Rehabilitation Act of 1973, by expanding the definition of the terms “programs or activities” to include all of the programs or activities of the Federal-aid recipients, sub-recipients and contractors, whether such programs or activities are Federally funded or not); Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 154 of 219 ends

Page of 27 of 29
January 2022
Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language

14. USE OF UNITED STATES-FLAG VESSELS (CARGO PREFERENCE ACT) The CONTRACTOR agrees1. To utilize privately owned United States-flag commercial vessels to ship at least 50 percent of the gross tonnage (computed separately for dry bulk carries, dry cargo liners, and tankers) involved, whenever shipping any equipment, material, or commodities pursuant to this contract, to the extent such vessels are available at fair and reasonable rates for United States-flag commercial vessels.

2. To Furnish within 20 days following the date of loading for shipments originating within the United State or within 30 working days following the date of loading for shipments originating outside the United States, a legible copy of a rated “on-board” commercial ocean bill-of-lading in English for each shipment of cargo described in paragraph (1) of this section to both the Contracting Officer (through the prime contractor in the case of subcontractor bills-of-lading) and to the Division of National Cargo, Office of Market Development, Maritime Administration, Washington, DC 20590.

3. To insert the substance of the provisions of this clause in all subcontracts issued pursuant to this contract.

Federal Trainee Program Special Provisions
(to be used when applicable)

15. FEDERAL TRAINEE PROGRAM
For the Federal training program, the number of trainees or apprentices is .

This section applies if a number of trainees or apprentices is specified in the special provisions.

As part of the prime contractor’s equal opportunity affirmative action program, provide on-the-job training to develop full journeymen in the types of trades or job classifications involved.

The prime contractor has primary responsibility for meeting this training requirement.

If the prime contractor subcontracts a contract part, they shall determine how many trainees or apprentices are to be trained by the subcontractor. Include these training requirements in each subcontract.

Where feasible, 25 percent of apprentices or trainees in each occupation must be in their 1st year of apprenticeship or training.

Distribute the number of apprentices or trainees among the work classifications on the basis of the prime contractor’s needs and the availability of journeymen in the various classifications within a reasonable recruitment area.

Before starting work, the prime contractor shall submit to the City of Sebastopol:
• Titles II and III of the Americans with Disabilities Act, which prohibit discrimination of the basis of disability in the operation of public entities, public and private transportation systems, places of public accommodation, and certain testing entities (42 U.S.C. §§ 12131 – 12189) as implemented by Department of Transportation regulations 49 C.F.R. parts 37 and 38; • The Federal Aviation Administration’s Non-discrimination statute (49 U.S.C. § 47123) (prohibits discrimination on the basis of race, color, national origin, and sex); • Executive Order 12898, Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations, which ensures discrimination against minority populations by discouraging programs, policies, and activities with disproportionately high and adverse human health or environmental effects on minority and low-income populations; • Executive Order 13166, Improving Access to Services for Persons with Limited English Proficiency, and resulting agency guidance, national origin discrimination includes discrimination because of limited English proficiency (LEP). To ensure compliance with Title VI, you must take reasonable steps to ensure that LEP persons have meaningful access to your programs (70 Fed. Reg. at 74087 to 74100); • Title IX of the Education Amendments of 1972, as amended, which prohibits you from discriminating because of sex in education programs or activities (20 U.S.C. 1681 et seq).

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 155 of 219 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
Page of 28 of 29
January 2022

1. Number of apprentices or trainees to be trained for each classification

2. Training program to be used

3. Training starting date for each classification
The prime contractor shall obtain the City of Sebastopol approval for this submitted information before the prime contractor starts work. The City of Sebastopol credits the prime contractor for each apprentice or trainee the prime contractor employs on the job who is currently enrolled or becomes enrolled in an approved program.

The primary objective of this section is to train and upgrade minorities and women toward journeyman status.

The prime contractor shall make every effort to enroll minority and women apprentices or trainees, such as conducting systematic and direct recruitment through public and private sources likely to yield minority and women apprentices or trainees, to the extent they are available within a reasonable recruitment area and show that they have made the efforts. In making these efforts, the prime contractor shall not discriminate against any applicant for training.

The prime contractor shall not employ as an apprentice or trainee an employee:

1. In any classification in which the employee has successfully completed a training course leading to journeyman status or in which the employee has been employed as a journeyman

2. Who is not registered in a program approved by the US Department of Labor, Bureau of Apprenticeship and Training
The prime contractor shall ask the employee if the employee has successfully completed a training course leading to journeyman status or has been employed as a journeyman. The prime contractor’s records must show the employee's answers to the questions.

In the training program, the prime contractor shall establish the minimum length and training type for each classification. The City of Sebastopol and FHWA approves a program if one of the following is met:

1. It is calculated to:
 Meet the your equal employment opportunity responsibilities  Qualify the average apprentice or trainee for journeyman status in the classification involved by the end of the training period

2. It is registered with the U.S. Department of Labor, Bureau of Apprenticeship and Training, and it is administered in a way consistent with the equal employment responsibilities of Federalaid highway construction contracts The prime contractor shall obtain the State's approval for their training program before they start work involving the classification covered by the program.

The prime contractor shall provide training in the construction crafts, not in clerk-typist or secretarial-type positions. Training is allowed in lower level management positions such as office engineers, estimators, and timekeepers if the training is oriented toward construction applications. Training is allowed in the laborer classification if significant and meaningful training is provided and approved by the division office. Off-site training is allowed if the training is an integral part of an approved training program and does not make up a significant part of the overall training.

The City of Sebastopol reimburses the prime contractor 80 cents per hour of training given an employee on this contract under an approved training program:

1. For on-site training

2. For off-site training if the apprentice or trainee is currently employed on a Federal-aid project and prime contractor does at least one of the following:
a. Contribute to the cost of the training
b. Provide the instruction to the apprentice or trainee c. Pay the apprentice's or trainee's wages during the off-site training period

3. If the prime contractor complies with this section.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 156 of 219 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
Page of 29 of 29
January 2022
Each apprentice or trainee must:

1. Begin training on the project as soon as feasible after the start of work involving the apprentice's or trainee's skill

2. Remain on the project as long as training opportunities exist in the apprentice's or trainee's work classification or until the apprentice or trainee has completed the training program The prime contractor shall furnish the apprentice or trainee with a copy of the program that the prime contractor will comply with in providing the training.

16. PROHIBITION OF CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE EQUIPMENT

AND SERVICES
In response to significant national security concerns, the agency shall check the prohibited vendor list before making any telecommunications and video surveillance purchase because recipients and subrecipients of federal funds are prohibited from obligating or expending loan or grant funds to:
• Procure or obtain;
• Extend or renew a contract to procure or obtain; or
• Enter into a contract (or extend or renew a contract) to procure or obtain equipment, services, or systems that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.

The prohibited vendors (and their subsidiaries or affiliates) are:
• Huawei Technologies Company;
• ZTE Corporation;
• Hytera Communications Corporation;
• Hangzhou Hikvision Digital Technology Company;
• Dahua Technology Company; and
• Subsidiaries or affiliates of the above-mentioned companies.

In implementing the prohibition, the agency administering loan, grant, or subsidy programs shall prioritize available funding and technical support to assist affected businesses, institutions and organizations as is reasonably necessary for those affected entities to transition from covered communications equipment and services, to procure replacement equipment and services, and to ensure that communications service to users and customers is sustain
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 157 of 219 ends

APPENDIX C

OTHER REQUIRED FORMS
Exhibit 15-G: Local Agency Bidder DBE Commitment (Construction Contracts) Exhibit 15-H: DBE Information – Good Faith Efforts (if DBE Goal not met) Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 158 of 219 ends

Local Assistance Procedures Manual Exhibit 15-G
Construction Contract DBE Commitment
LPP 18-01 Page 1 of 3
January 2019
EXHIBIT 15-G CONSTRUCTION CONTRACT DBE COMMITMENT

1. Local Agency: 2. Contract DBE Goal:

3. Project Description:

4. Project Location:

5. Bidder's Name: 6. Prime Certified DBE:  7. Bid Amount:

8. Total Dollar Amount for ALL Subcontractors: 9. Total Number of ALL Subcontractors:

10. Bid
Item
Number

11. Description of Work, Service, or Materials
Supplied

12. DBE
Certification
Number

13. DBE Contact Information
(Must be certified on the date bids are opened)

14. DBE
Dollar
Amount
Local Agency to Complete this Section upon Execution of Award

15. TOTAL CLAIMED DBE PARTICIPATION
$

21. Local Agency Contract Number:

22. Federal-Aid Project Number: %

23. Bid Opening Date:

24. Contract Award Date:

IMPORTANT: Identify all DBE firms being claimed for credit, regardless of tier. Names of the First Tier DBE Subcontractors and their respective item(s) of work listed above must be consistent, where applicable with the names and items of the work in the "Subcontractor List" submitted with your bid. Written confirmation of each listed DBE is required.

Local Agency certifies that all DBE certifications are valid and information on this form is complete and accurate.

26. Local Agency Representative's Signature 27. Date 16. Preparer's Signature 17. Date

28. Local Agency Representative's Name 29. Phone 18. Preparer's Name 19. Phone

30. Local Agency Representative's Title 20. Preparer's Title DISTRIBUTION: 1. Original – Local Agency

2. Copy – Caltrans District Local Assistance Engineer (DLAE). Failure to submit to DLAE within 30 days of contract execution may result in de-obligation of federal funds on contract.

3. Include additional copy with award package.

25. Award Amount:
________________________________________________________ Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 159 of 219 ends

Local Assistance Procedures Manual Exhibit 15-G
Construction Contract DBE Commitment
LPP 18-01 Page 2 of 3
January 2019
ADA Notice: For individuals with sensory disabilities, this document is available in alternate formats. For information call (916) 654-6410 or TDD (916) 654- 3880 or write Records and Forms Management, 1120 N Street, MS-89, Sacramento, CA 95814.

INSTRUCTIONS – CONSTRUCTION CONTRACT DBE COMMITMENT

CONTRACTOR SECTION

1. Local Agency - Enter the name of the local agency that is administering the contract.

2. Contract DBE Goal - Enter the contract DBE goal percentage as it appears on the project advertisement.

3. Project Location - Enter the project location(s) as it appears on the project advertisement.

4. Project Description - Enter the project description as it appears on the project advertisement (Bridge Rehab, Seismic Rehab, Overlay, Widening, etc).

5. Bidder’s Name - Enter the contractor’s firm name.

6. Prime Certified DBE - Check box if prime contractor is a certified DBE.

7. Bid Amount - Enter the total contract bid dollar amount for the prime contractor.

8. Total Dollar Amount for ALL Subcontractors – Enter the total dollar amount for all subcontracted contractors.

SUM = (DBEs + all Non-DBEs). Do not include the prime contractor information in this count.

9. Total number of ALL subcontractors – Enter the total number of all subcontracted contractors. SUM = (DBEs + all Non-DBEs). Do not include the prime contractor information in this count.

10. Bid Item Number - Enter bid item number for work, services, or materials supplied to be provided.

11. Description of Work, Services, or Materials Supplied - Enter description of work, services, or materials to be provided. Indicate all work to be performed by DBEs including work performed by the prime contractor’s own forces, if the prime is a DBE. If 100% of the item is not to be performed or furnished by the DBE, describe the exact portion to be performed or furnished by the DBE. See LAPM Chapter 9 to determine how to count the participation of DBE firms.

12. DBE Certification Number - Enter the DBE’s Certification Identification Number. All DBEs must be certified on the date bids are opened.

13. DBE Contact Information - Enter the name, address, and phone number of all DBE subcontracted contractors.

Also, enter the prime contractor’s name and phone number, if the prime is a DBE.

14. DBE Dollar Amount - Enter the subcontracted dollar amount of the work to be performed or service to be provided. Include the prime contractor if the prime is a DBE. See LAPM Chapter 9 for how to count full/partial participation.

15. Total Claimed DBE Participation - $: Enter the total dollar amounts entered in the “DBE Dollar Amount” column. %: Enter the total DBE participation claimed (“Total Claimed DBE Participation Dollars” divided by item “Bid Amount”). If the total % claimed is less than item “Contract DBE Goal,” an adequately documented Good Faith Effort (GFE) is required (see Exhibit 15-H DBE Information - Good Faith Efforts of the LAPM).

16. Preparer’s Signature - The person completing the DBE commitment form on behalf of the contractor’s firm must sign their name.

17. Date - Enter the date the DBE commitment form is signed by the contractor’s preparer.

18. Preparer’s Name - Enter the name of the person preparing and signing the contractor’s DBE commitment form.

19. Phone - Enter the area code and phone number of the person signing the contractor’s DBE commitment form.

20. Preparer’s Title - Enter the position/title of the person signing the contractor’s DBE commitment form.

LOCAL AGENCY SECTION

21. Local Agency Contract Number - Enter the Local Agency contract number or identifier.

22. Federal-Aid Project Number - Enter the Federal-Aid Project Number(s).

23. Bid Opening Date - Enter the date contract bids were opened.

24. Contract Award Date - Enter the date the contract was executed.

25. Award Amount – Enter the contract award amount as stated in the executed contract.

26. Local Agency Representative’s Signature - The person completing this section of the form for the Local Agency must sign their name to certify that the information in this and the Contractor Section of this form is complete and accurate.

27. Date - Enter the date the DBE commitment form is signed by the Local Agency Representative.

28. Local Agency Representative’s Name - Enter the name of the Local Agency Representative certifying the contractor’s DBE commitment form.

29. Phone - Enter the area code and phone number of the person signing the contractor’s DBE commitment form.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 160 of 219 ends

Local Assistance Procedures Manual Exhibit 15-G
Construction Contract DBE Commitment
LPP 18-01 Page 3 of 3
January 2019

30. Local Agency Representative Title - Enter the position/title of the Local Agency Representative certifying the contractor’s DBE commitment form.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 161 of 219 ends

Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Effort

Page 1 of 3 ends

May 2020
EXHIBIT 15-H: PROPOSER/CONTRACTOR GOOD FAITH EFFORTS
Cost Proposal Due Date ___________________ PE/CE
Federal-aid Project No(s). ___STPL-5123(016)____ Bid Opening Date ___________________ CON The City of Sebastopol established a Disadvantaged Business Enterprise (DBE) goal of __6__% for this contract. The information provided herein shows the required good faith efforts to meet or exceed the DBE contract goal.

Proposers or bidders submit the following information to document their good faith efforts within five (5) calendar days from cost proposal due date or bid opening. Proposers and bidders are recommended to submit the following information even if the Exhibit 10-O1: Consultant Proposal DBE Commitments or Exhibit 15-G: Construction Contract DBE Commitment indicate that the proposer or bidder has met the DBE goal. This form protects the proposer’s or bidder’s eligibility for award of the contract if the administering agency determines that the bidder failed to meet the goal for various reasons, e.g., a DBE firm was not certified at bid opening, or the bidder made a mathematical error.

The following items are listed in the Section entitled “Submission of DBE Commitment” of the Special Provisions, please attach additional sheets as needed:

A. The names and dates of each publication in which a request for DBE participation for this project was placed by the bidder (please attach copies of advertisements or proofs of publication):

Publications Dates of Advertisement

B. The names and dates of written notices sent to certified DBEs soliciting bids for this project and the dates and methods used for following up initial solicitations to determine with certainty whether the DBEs were interested (please attach copies of solicitations, telephone records, fax confirmations, etc.):

Names of DBEs Solicited Date of Initial Solicitation Follow Up Methods and Dates

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 162 of 219 ends

Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Effort

Page 2 of 3 ends

May 2020
C. The items of work made available to DBE firms including those unbundled contract work items into economically feasible units to facilitate DBE participation. It is the bidder's responsibility to demonstrate that sufficient work to facilitate DBE participation in order to meet or exceed the DBE contract goal.

0.00%

0.00%

0.00%

0.00%

D. The names, addresses and phone numbers of rejected DBE firms, the reasons for the bidder's rejection of the DBEs, the firms selected for that work (please attach copies of quotes from the firms involved), and the price difference for each DBE if the selected firm is not a DBE:

Names, addresses and phone numbers of rejected DBEs and the reasons for the bidder's rejection of the DBEs:

Names, addresses and phone numbers of firms selected for the work above:

E. Efforts (e.g. in advertisements and solicitations) made to assist interested DBEs in obtaining information related to the plans, specifications and requirements for the work which was provided to DBEs:

Items of
Work
Proposer or Bidder
Normally Performs Item
(Y/N)
Breakdown of
Items
Amount
($)
Percentage
Of
Contract
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 163 of 219 ends

Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Effort

Page 3 of 3 ends

May 2020
F. Efforts (e.g. in advertisements and solicitations) made to assist interested DBEs in obtaining bonding, lines of credit or insurance, necessary equipment, supplies, materials, or related assistance or services, excluding supplies and equipment the DBE subcontractor purchases or leases from the prime contractor or its affiliate:

G. The names of agencies, organizations or groups contacted to provide assistance in contacting, recruiting and using DBE firms (please attach copies of requests to agencies and any responses received, i.e., lists, Internet page download, etc.):

Name of Agency/Organization Method/Date of Contact Results H. Any additional data to support a demonstration of good faith efforts:

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 164 of 219 ends

APPENDIX D

FEDERAL

WAGE RATES
(Within ten (10) days before bid opening, these wage rates shall be reviewed and if the applicable rates have changed an addendum to bidders shall be issue.)
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 165 of 219 ends

"General Decision Number: CA20230007 02/03/2023
Superseded General Decision Number: CA20220007
State: California
Construction Types: Building, Heavy (Heavy and Dredging) and Highway
Counties: Alpine, Amador, Butte, Colusa, El Dorado, Glenn, Lassen, Marin, Modoc, Napa, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Siskiyou, Solano, Sonoma, Sutter, Tehama, Trinity, Yolo and Yuba Counties in California.

BUILDING CONSTRUCTION PROJECTS (excluding Amador County only); DREDGING CONSTRUCTION PROJECTS (does not include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does not include water well drilling); AND HIGHWAY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).
______________________________________________________________ |If the contract is entered |. Executive Order 14026 |
|into on or after January 30, | generally applies to the | |2022, or the contract is | contract. |
|renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at |
|after January 30, 2022: | least $16.20 per hour (or |
| | the applicable wage rate |
| | listed on this wage |
| | determination, if it is |
| | higher) for all hours |
| | spent performing on the |
| | contract in 2023. |
|______________________________|_____________________________| |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. |
|contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.15 per hour (or the |
| | applicable wage rate listed|
| | on this wage determination,|
| | if it is higher) for all |
| | hours spent performing on |
| | that contract in 2023. |
|______________________________|_____________________________| The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a
conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at
http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date
0 01/06/2023
1 01/13/2023
2 01/20/2023
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 166 of 219 ends

3 02/03/2023
ASBE0016-001 08/01/2022
AREA 1: MARIN, NAPA, SAN BENITO, SAN FRANCISCO, SOLANO, &

SONOMA COUNTIES
AREA 2: ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN,

MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA,

SISKIYOU, SUTTER, TEHEMA, TRINITY, YOLO, & YUBA COUNTIES Rates Fringes
Asbestos Workers/Insulator
(Includes the application of
all insulating materials,
Protective Coverings,
Coatings, and Finishes to all
types of mechanical systems)
Area 1......................$ 81.16 23.57
Area 2......................$ 62.51 23.57
---------------------------------------------------------------- ASBE0016-007 01/01/2021
AREA 1 : ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN,

LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA,

SIERRA, SISKIYOU, SOLANO, SONOMA, SUTTER, TEHAMA, TRINITY, YOLO & YUBA COUNTIES
AREA 2: MARIN & NAPA COUNTIES
Rates Fringes
Asbestos Removal
worker/hazardous material
handler (Includes
preparation, wetting,
stripping, removal,
scrapping, vacuuming, bagging
and disposing of all
insulation materials from
mechanical systems, whether
they contain asbestos or not)
AREA 1......................$ 30.45 10.60
AREA 2......................$ 36.53 9.27
---------------------------------------------------------------- BOIL0549-002 01/01/2021
Rates Fringes

BOILERMAKER
(1) Marin & Solano Counties.$ 49.62 41.27
(2) Remaining Counties......$ 45.60 38.99
---------------------------------------------------------------- BRCA0003-001 08/01/2022
Rates Fringes
MARBLE FINISHER..................$ 39.20 18.31
---------------------------------------------------------------- BRCA0003-004 05/01/2022
AREA 1: ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN,

LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA,

SIERRA, SUTTER, TEHAMA, YOLO AND YUBA COUNTIES
AREA 2: MARIN, NAPA, SISKIYOU, SOLANO, SONOMA AND TRINITY

COUNTIES
Rates Fringes

BRICKLAYER
AREA 1......................$ 49.32 22.65
AREA 2......................$ 53.69 26.03
SPECIALTY PAY:
(A) Underground work such as tunnel work, sewer work,
manholes, catch basins, sewer pipes and telephone conduit Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 167 of 219 ends

shall be paid $1.25 per hour above the regular rate. Work in direct contact with raw sewage shall receive $1.25 per hour in addition to the above.
(B) Operating a saw or grinder shall receive $1.25 per hour above the regular rate.
(C) Gunite nozzle person shall receive $1.25 per hour above the regular rate.
---------------------------------------------------------------- BRCA0003-008 07/01/2022
Rates Fringes
TERRAZZO FINISHER................$ 41.93 18.98
TERRAZZO WORKER/SETTER...........$ 56.84 27.53
---------------------------------------------------------------- BRCA0003-010 04/01/2022
Rates Fringes

TILE FINISHER
Area 1......................$ 31.12 16.11
Area 2......................$ 30.90 17.87
Area 3......................$ 33.86 17.74
Area 4......................$ 31.89 17.18
Tile Layer
Area 1......................$ 51.02 19.35
Area 2......................$ 50.66 20.77
Area 3......................$ 55.41 20.87
Area 4......................$ 52.28 20.79
AREA 1: Butte, Colusa, El Dorado, Glenn, Lassen, Modoc, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Sutter, Tehema, Yolo, Yuba
AREA 2: Alpine, Amador
AREA 3: Marin, Napa, Solano, Siskiyou
AREA 4: Sonoma
---------------------------------------------------------------- BRCA0003-014 08/01/2022
Rates Fringes
MARBLE MASON.....................$ 56.98 28.54
---------------------------------------------------------------- CARP0034-001 07/01/2021
Rates Fringes
Diver
Assistant Tender, ROV
Tender/Technician...........$ 54.10 34.69
Diver standby...............$ 60.51 34.69
Diver Tender................$ 59.51 34.69
Diver wet...................$ 103.62 34.69
Manifold Operator (mixed
gas)........................$ 64.51 34.69
Manifold Operator (Standby).$ 59.51 34.69
DEPTH PAY (Surface Diving):
050 to 100 ft $2.00 per foot
101 to 150 ft $3.00 per foot
151 to 220 ft $4.00 per foot
221 ft.-deeper $5.00 per foot
SATURATION DIVING:

The standby rate shall apply until saturation starts. The saturation diving rate applies when divers are under
pressure continuously until work task and decompression are complete. The diver rate shall be paid for all saturation hours.

DIVING IN ENCLOSURES:

Where it is necessary for Divers to enter pipes or tunnels, Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 168 of 219 ends

or other enclosures where there is no vertical ascent, the following premium shall be paid: Distance traveled from entrance 26 feet to 300 feet: $1.00 per foot. When it is necessary for a diver to enter any pipe, tunnel or other enclosure less than 48"" in height, the premium will be $1.00 per foot.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.
---------------------------------------------------------------- CARP0034-003 07/01/2021
Rates Fringes
Piledriver.......................$ 54.10 34.69
---------------------------------------------------------------- CARP0035-001 08/01/2020
AREA 1: MARIN, NAPA, SOLANO & SONOMA
AREA 3: SACRAMENTO, WESTERN EL DORADO (Territory west of an including highway 49 and the territory inside the city limits of Placerville), WESTERN PLACER (Territory west of and
including highway 49), & YOLO
AREA 4: ALPINE, BUTTE, COLUSA, EASTERN EL DORADO, GLENN,

LASSEN, MODOC, NEVADA, EASTERN PLACER, PLUMAS, SHASTA, SIERRA,

SISKIYOU, SUTTER, TEHAMA, TRINITY, & YUBA
Rates Fringes
Drywall Installers/Lathers:

Area 1......................$ 52.65 31.26
Area 3......................$ 47.27 31.26
Area 4......................$ 45.92 31.26
Drywall Stocker/Scrapper
Area 1......................$ 26.33 18.22
Area 3......................$ 23.64 18.22
Area 4......................$ 22.97 18.22
---------------------------------------------------------------- CARP0035-009 07/01/2020
Marin County
Rates Fringes

CARPENTER
Bridge Builder/Highway
Carpenter...................$ 52.65 30.82
Hardwood Floorlayer,
Shingler, Power Saw
Operator, Steel Scaffold &
Steel Shoring Erector, Saw
Filer.......................$ 52.80 30.82
Journeyman Carpenter........$ 52.65 30.82
Millwright..................$ 52.75 32.41
---------------------------------------------------------------- CARP0035-010 07/01/2020
AREA 1: Marin, Napa, Solano & Sonoma Counties
AREA 2: Monterey, San Benito and Santa Cruz
AREA 3: Alpine, Butte, Colusa, El Dorado, Glenn, Lassen, Modoc, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Siskiyou, Sutter, Tehama, Trinity, Yolo & Yuba counties
Rates Fringes
Modular Furniture Installer
Area 1
Installer..................$ 28.76 22.53
Lead Installer.............$ 32.21 23.03
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 169 of 219 ends

Master Installer...........$ 36.43 23.03
Area 2
Installer..................$ 26.11 22.53
Lead Installer.............$ 29.08 23.03
Master Installer...........$ 32.71 23.03
Area 3
Installer..................$ 25.16 22.53
Lead Installer.............$ 27.96 23.03
Master Installer...........$ 31.38 23.03
---------------------------------------------------------------- CARP0046-001 07/01/2021
El Dorado (West), Placer (West), Sacramento and Yolo Counties Rates Fringes
Carpenters
Bridge Builder/Highway
Carpenter...................$ 54.85 31.49
Hardwood Floorlayer,
Shingler, Power Saw
Operator, Steel Scaffold &
Steel Shoring Erector, Saw
Filer.......................$ 49.12 31.49
Journeyman Carpenter........$ 48.97 31.49
Millwright..................$ 51.47 33.08
Footnote: Placer County (West) includes territory West of and including Highway 49 and El Dorado County (West) includes territory West of and including Highway 49 and territory inside the city limits of Placerville.
---------------------------------------------------------------- CARP0046-002 07/01/2021
Alpine, Colusa, El Dorado (East), Nevada, Placer (East), Sierra, Sutter and Yuba Counties
Rates Fringes
Carpenters
Bridge Builder/Highway
Carpenter...................$ 54.85 31.49
Hardwood Floorlayer,
Shingler, Power Saw
Operator, Steel Scaffold &
Steel Shoring Erector, Saw
Filer.......................$ 47.77 31.49
Journeyman Carpenter........$ 47.62 31.49
Millwright..................$ 50.12 33.08
---------------------------------------------------------------- CARP0152-003 07/01/2020
Amador County
Rates Fringes
Carpenters
Bridge Builder/Highway
Carpenter...................$ 52.65 30.82
Hardwood Floorlayer,
Shingler, Power Saw
Operator, Steel Scaffold &
Steel Shoring Erector, Saw
Filer.......................$ 45.57 30.82
Journeyman Carpenter........$ 45.42 30.82
Millwright..................$ 47.92 32.41
---------------------------------------------------------------- CARP0180-001 07/01/2021
Solano County
Rates Fringes
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 170 of 219 ends

Carpenters
Bridge Builder/Highway
Carpenter...................$ 54.85 31.49
Hardwood Floorlayer,
Shingler, Power Saw
Operator, Steel Scaffold &
Steel Shoring Erector, Saw
Filer.......................$ 55.00 31.49
Journeyman Carpenter........$ 54.85 31.49
Millwright..................$ 54.95 33.08
---------------------------------------------------------------- CARP0751-001 07/01/2021
Napa and Sonoma Counties
Rates Fringes
Carpenters
Bridge Builder/Highway
Carpenter...................$ 54.85 31.49
Hardwood Floorlayer,
Shingler, Power Saw
Operator, Steel Scaffold &
Steel Shoring Erector, Saw
Filer.......................$ 55.00 31.49
Journeyman Carpenter........$ 54.85 31.49
Millwright..................$ 54.95 33.08
---------------------------------------------------------------- CARP1599-001 07/01/2020
Butte, Glenn, Lassen, Modoc, Plumas, Shasta, Siskiyou, Tehama and Trinity Counties
Rates Fringes
Carpenters
Bridge Builder/Highway
Carpenter...................$ 52.65 30.82
Hardwood Floorlayer,
Shingler, Power Saw
Operator, Steel Scaffold &
Steel Shoring Erector, Saw
Filer.......................$ 45.57 30.82
Journeyman Carpenter........$ 45.42 30.82
Millwright..................$ 47.92 32.41
---------------------------------------------------------------- ELEC0180-001 06/01/2021

NAPA AND SOLANO COUNTIES
Rates Fringes
CABLE SPLICER....................$ 59.69 3%+24.38
ELECTRICIAN......................$ 53.06 3%+24.38
---------------------------------------------------------------- ELEC0180-003 12/01/2022

NAPA AND SOLANO COUNTIES
Rates Fringes
Sound & Communications
Installer...................$ 46.64 25.30
Technician..................$ 53.64 25.51

SCOPE OF WORK INCLUDES-
SOUND & VOICE TRANSMISSION (Music, Intercom, Nurse Call, Telephone); FIRE ALARM SYSTEMS [excluding fire alarm work when installed in raceways (including wire and cable
pulling) and when performed on new or major remodel
building projects or jobs],

TELEVISION & VIDEO SYSTEMS, SECURITY SYSTEMS, COMMUNICATIONS SYSTEMS that transmit or receive information and/or control Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 171 of 219 ends

systems that are intrinsic to the above.

EXCLUDES-
Excludes all other data systems or multiple systems which include control function or power supply; excludes
installation of raceway systems, line voltage work,
industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access); excludes energy management
systems.
---------------------------------------------------------------- ELEC0340-002 02/01/2018

ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN,

NEVADA, PLACER, PLUMAS, SACRAMENTO, TRINITY, YOLO, YUBA COUNTIES Rates Fringes
Communications System
Sound & Communications
Installer...................$ 29.35 3%+15.35
Sound & Communications
Technician..................$ 33.75 3%+15.35

SCOPE OF WORK
Includes the installation testing, service and maintenance, of the following systems which utilize the transmission and/or transference of voice, sound, vision and digital for commercial, education, security and entertainment purposes for the following TV monitoring and surveillance,
background-foreground music, intercom and telephone
interconnect, inventory control systems, microwave
transmission, multi-media, multiplex, nurse call system, radio page, school intercom and sound, burglar alarms, and low voltage master clock systems.

A. SOUND AND VOICE TRANSMISSION/TRANSFERENCE SYSTEMS
Background foreground music Intercom and telephone
interconnect systems, Telephone systems, Nurse call
systems, Radio page systems, School intercom and sound
systems, Burglar alarm systems, Low voltage master clock systems, Multi-media/multiplex systems, Sound and musical entertainment systems, RF systems, Antennas and Wave Guide.

B. FIRE ALARM SYSTEMS
Installation, wire pulling and testing
C. TELEVISION AND VIDEO SYSTEMS Television monitoring and surveillance systems, Video security systems, Video
entertainment systems, Video educational systems, Microwave transmission systems, CATV and CCTV
D. SECURITY SYSTEMS Perimeter security systems
Vibration sensor systems Card access systems Access
control systems Sonar/infrared monitoring equipment
E. COMMUNICATIONS SYSTEMS THAT TRANSMIT OR RECEIVE

INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO THE ABOVE LISTED SYSTEMS SCADA (Supervisory Control and Data Acquisition) PCM (Pulse Code Modulation)
Inventory Control Systems Digital Data Systems
Broadband and Baseband and Carriers Point of Sale
Systems VSAT Data Systems Data Communication
Systems RF and Remote Control Systems Fiber Optic
Data Systems WORK EXCLUDED Raceway systems are not covered (excluding Ladder-Rack for the purpose of the above listed systems). Chases and/or nipples (not to exceed 10 feet) may be installed on open wiring systems. Energy management systems. SCADA (Supervisory Control and Data Acquisition) when not intrinsic to the above listed systems (in the
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 172 of 219 ends

scope). Fire alarm systems when installed in raceways
(including wire and cable pulling) shall be performed at the electrician wage rate, when either of the following two (2) conditions apply:

1. The project involves new or major remodel building trades construction.

2. The conductors for the fire alarm system are installed in conduit.
---------------------------------------------------------------- ELEC0340-003 08/01/2022
ALPINE (West of Sierra Mt. Watershed), AMADOR, BUTTE, COLUSA, EL DORADO (West of Sierra Mt. Watershed), GLENN, LASSEN, NEVADA (West of Sierra Mt. Watershed), PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA (West of Sierra Mt. Watershed), SUTTER, TEHAMA,

TRINITY, YOLO & YUBA COUNTIES
Rates Fringes

ELECTRICIAN
Remaining area..............$ 45.06 34.09
Sierra Army Depot, Herlong..$ 48.83 18.54
Tunnel work.................$ 41.01 18.54
CABLE SPLICER: Receives 110% of the Electrician basic hourly rate.
---------------------------------------------------------------- ELEC0401-005 01/01/2022
ALPINE (east of the main watershed divide), EL DORADO (east of the main watershed divide), NEVADA (east of the main
watershed), PLACER (east of the main watershed divide) and SIERRA (east of the main watershed divide) COUNTIES:

Rates Fringes
ELECTRICIAN......................$ 42.50 20.95
ZONE RATE:
70-90 miles - $8.00 per hour
91+ miles - $10.00 per hour
---------------------------------------------------------------- ELEC0551-004 06/01/2022

MARIN AND SONOMA COUNTIES
Rates Fringes
ELECTRICIAN......................$ 55.60 28.06
---------------------------------------------------------------- ELEC0551-005 12/01/2022

MARIN & SONOMA COUNTIES
Rates Fringes
Sound & Communications
Installer...................$ 46.64 25.30
Technician..................$ 53.64 25.65

SCOPE OF WORK INCLUDES-
SOUND & VOICE TRANSMISSION (Music, Intercom, Nurse Call, Telephone); FIRE ALARM SYSTEMS [excluding fire alarm work when installed in raceways (including wire and cable
pulling) and when performed on new or major remodel
building projects or jobs],

TELEVISION & VIDEO SYSTEMS, SECURITY SYSTEMS, COMMUNICATIONS SYSTEMS that transmit or receive information and/or control systems that are intrinsic to the above.

EXCLUDES-
Excludes all other data systems or multiple systems which include control function or power supply; excludes
installation of raceway systems, line voltage work,
industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 173 of 219 ends

having building access); excludes energy management
systems.
---------------------------------------------------------------- * ELEC0659-006 01/01/2023
DEL NORTE, MODOC and SISKIYOU COUNTIES
Rates Fringes
ELECTRICIAN......................$ 43.97 19.26
---------------------------------------------------------------- * ELEC0659-008 02/01/2023

DEL NORTE, MODOC & SISKIYOU COUNTIES
Rates Fringes
Line Construction
(1) Cable Splicer...........$ 67.80 4.5%+22.15
(2) Lineman, Pole Sprayer,
Heavy Line Equipment Man....$ 60.54 4.5%+22.15
(3) Tree Trimmer............$ 37.84 4.5%+14.30
(4) Line Equipment Man......$ 53.82 4.5%+19.40
(5) Powdermen,
Jackhammermen...............$ 40.37 4.5%+14.30
(6) Groundman...............$ 33.37 4.5%+14.30
---------------------------------------------------------------- ELEC1245-004 06/01/2022

ALL COUNTIES EXCEPT DEL NORTE, MODOC & SISKIYOU
Rates Fringes

LINE CONSTRUCTION
(1) Lineman; Cable splicer..$ 64.40 22.58
(2) Equipment specialist
(operates crawler
tractors, commercial motor
vehicles, backhoes,
trenchers, cranes (50 tons
and below), overhead &
underground distribution
line equipment)...........$ 50.00 21.30
(3) Groundman...............$ 38.23 20.89
(4) Powderman...............$ 51.87 18.79
HOLIDAYS: New Year's Day, M.L. King Day, Memorial Day,
Independence Day, Labor Day, Veterans Day, Thanksgiving Day and day after Thanksgiving, Christmas Day
---------------------------------------------------------------- ELEV0008-001 01/01/2023
Rates Fringes
ELEVATOR MECHANIC................$ 77.61 37.335+a+b
FOOTNOTE:
a. PAID VACATION: Employer contributes 8% of regular hourly rate as vacation pay credit for employees with more than 5 years of service, and 6% for 6 months to 5 years of service. b. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.
---------------------------------------------------------------- ENGI0003-008 08/01/2022
Rates Fringes
Dredging: (DREDGING:

CLAMSHELL & DIPPER DREDGING;
HYDRAULIC SUCTION DREDGING:)
AREA 1:
(1) Leverman...............$ 55.15 35.46
(2) Dredge Dozer; Heavy
duty repairman.............$ 50.19 35.46
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 174 of 219 ends

(3) Booster Pump
Operator; Deck
Engineer; Deck mate;
Dredge Tender; Winch
Operator...................$ 49.07 35.46
(4) Bargeman; Deckhand;
Fireman; Leveehand; Oiler..$ 45.77 35.46
AREA 2:
(1) Leverman...............$ 57.15 35.46
(2) Dredge Dozer; Heavy
duty repairman.............$ 52.19 35.46
(3) Booster Pump
Operator; Deck
Engineer; Deck mate;
Dredge Tender; Winch
Operator...................$ 51.07 35.46
(4) Bargeman; Deckhand;
Fireman; Leveehand; Oiler..$ 47.77 35.46

AREA DESCRIPTIONS
AREA 1: ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN, MERCED,

NAPA, SACRAMENTO, SAN BENITO, SAN FRANCISCO, SAN JOAQUIN,

SAN MATEO, SANTA CLARA, SANTA CRUZ, SOLANO, STANISLAUS,

SUTTER, YOLO, AND YUBA COUNTIES
AREA 2: MODOC COUNTY
THE REMAINGING COUNTIES ARE SPLIT BETWEEN AREA 1 AND AREA 2 AS NOTED BELOW:

ALPINE COUNTY:

Area 1: Northernmost part
Area 2: Remainder
CALAVERAS COUNTY:

Area 1: Remainder
Area 2: Eastern part
COLUSA COUNTY:

Area 1: Eastern part
Area 2: Remainder
ELDORADO COUNTY:

Area 1: North Central part
Area 2: Remainder

FRESNO COUNTY:

Area 1: Remainder
Area 2: Eastern part
GLENN COUNTY:

Area 1: Eastern part
Area 2: Remainder
LASSEN COUNTY:

Area 1: Western part along the Southern portion of border with Shasta County
Area 2: Remainder
MADERA COUNTY:

Area 1: Except Eastern part
Area 2: Eastern part

MARIPOSA COUNTY
Area 1: Except Eastern part
Area 2: Eastern part

MONTERREY COUNTY
Area 1: Except Southwestern part
Area 2: Southwestern part
NEVADA COUNTY:

Area 1: All but the Northern portion along the border of Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 175 of 219 ends

Sierra County
Area 2: Remainder
PLACER COUNTY:

Area 1: Al but the Central portion
Area 2: Remainder
PLUMAS COUNTY:

Area 1: Western portion
Area 2: Remainder
SHASTA COUNTY:

Area 1: All but the Northeastern corner
Area 2: Remainder
SIERRA COUNTY:

Area 1: Western part
Area 2: Remainder
SISKIYOU COUNTY:

Area 1: Central part
Area 2: Remainder
SONOMA COUNTY:

Area 1: All but the Northwestern corner
Area 2: Remainder
TEHAMA COUNTY:

Area 1: All but the Western border with Mendocino & Trinity Counties
Area 2: Remainder
TRINITY COUNTY:

Area 1: East Central part and the Northeastern border with Shasta County
Area 2: Remainder
TUOLUMNE COUNTY:

Area 1: Except Eastern part
Area 2: Eastern part
---------------------------------------------------------------- ENGI0003-019 06/29/2020

SEE AREA DESCRIPTIONS BELOW
Rates Fringes
OPERATOR: Power Equipment
(LANDSCAPE WORK ONLY)
GROUP 1
AREA 1.....................$ 39.95 30.28
AREA 2.....................$ 41.95 30.28
GROUP 2
AREA 1.....................$ 36.35 30.28
AREA 2.....................$ 38.35 30.28
GROUP 3
AREA 1.....................$ 31.74 30.28
AREA 2.....................$ 33.74 30.28
GROUP DESCRIPTIONS:

GROUP 1: Landscape Finish Grade Operator: All finish grade work regardless of equipment used, and all equipment with a rating more than 65 HP.

GROUP 2: Landscape Operator up to 65 HP: All equipment with a manufacturer's rating of 65 HP or less except equipment covered by Group 1 or Group 3. The following equipment
shall be included except when used for finish work as long as manufacturer's rating is 65 HP or less: A-Frame and
Winch Truck, Backhoe, Forklift, Hydragraphic Seeder
Machine, Roller, Rubber-Tired and Track Earthmoving
Equipment, Skiploader, Straw Blowers, and Trencher 31 HP up to 65 HP.

GROUP 3: Landscae Utility Operator: Small Rubber-Tired
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 176 of 219 ends

Tractor, Trencher Under 31 HP.

AREA DESCRIPTIONS:

AREA 1: ALAMEDA, BUTTE, CONTRA COSTA, KINGS, MARIN, MERCED,

NAPA, SACRAMENTO, SAN BENITO, SAN FRANCISCO, SAN JOAQUIN,

SAN MATEO, SANTA CLARA, SANTA CRUZ, SOLANO, STANISLAUS,

SUTTER, YOLO, AND YUBA COUNTIES
AREA 2 - MODOC COUNTY
THE REMAINING COUNTIES ARE SPLIT BETWEEN AREA 1 AND AREA 2 AS NOTED BELOW:

ALPINE COUNTY:

Area 1: Northernmost part
Area 2: Remainder
CALAVERAS COUNTY:

Area 1: Except Eastern part
Area 2: Eastern part
COLUSA COUNTY:

Area 1: Eastern part
Area 2: Remainder
DEL NORTE COUNTY:

Area 1: Extreme Southwestern corner
Area 2: Remainder
ELDORADO COUNTY:

Area 1: North Central part
Area 2: Remainder

FRESNO COUNTY
Area 1: Except Eastern part
Area 2: Eastern part
GLENN COUNTY:

Area 1: Eastern part
Area 2: Remainder
HUMBOLDT COUNTY:

Area 1: Except Eastern and Southwestern parts
Area 2: Remainder
LAKE COUNTY:

Area 1: Southern part
Area 2: Remainder
LASSEN COUNTY:

Area 1: Western part along the Southern portion of border with Shasta County
Area 2: Remainder

MADERA COUNTY
Area 1: Remainder
Area 2: Eastern part

MARIPOSA COUNTY
Area 1: Remainder
Area 2: Eastern part
MENDOCINO COUNTY:

Area 1: Central and Southeastern parts
Area 2: Remainder

MONTEREY COUNTY
Area 1: Remainder
Area 2: Southwestern part
NEVADA COUNTY:

Area 1: All but the Northern portion along the border of Sierra County
Area 2: Remainder
PLACER COUNTY:

Area 1: All but the Central portion
Area 2: Remainder
PLUMAS COUNTY:

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 177 of 219 ends

Area 1: Western portion
Area 2: Remainder
SHASTA COUNTY:

Area 1: All but the Northeastern corner
Area 2: Remainder
SIERRA COUNTY:

Area 1: Western part
Area 2: Remainder
SISKIYOU COUNTY:

Area 1: Central part
Area 2: Remainder
SONOMA COUNTY:

Area 1: All but the Northwestern corner
Area 2: Reaminder
TEHAMA COUNTY:

Area 1: All but the Western border with mendocino & Trinity Counties
Area 2: Remainder
TRINITY COUNTY:

Area 1: East Central part and the Northeaster border with Shasta County
Area 2: Remainder
TULARE COUNTY;
Area 1: Remainder
Area 2: Eastern part
TUOLUMNE COUNTY:

Area 1: Remainder
Area 2: Eastern Part
---------------------------------------------------------------- ENGI0003-038 06/29/2020
""AREA 1"" WAGE RATES ARE LISTED BELOW
""AREA 2"" RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1 RATES.

SEE AREA DEFINITIONS BELOW
Rates Fringes
OPERATOR: Power Equipment
(AREA 1:)
GROUP 1.....................$ 51.42 31.15
GROUP 2.....................$ 49.89 31.15
GROUP 3.....................$ 48.41 31.15
GROUP 4.....................$ 47.03 31.15
GROUP 5.....................$ 45.76 31.15
GROUP 6.....................$ 44.44 31.15
GROUP 7.....................$ 43.30 31.15
GROUP 8.....................$ 42.16 31.15
GROUP 8-A...................$ 39.95 31.15
OPERATOR: Power Equipment
(Cranes and Attachments -
AREA 1:)
GROUP 1
Cranes.....................$ 52.30 31.15
Oiler......................$ 43.79 31.15
Truck crane oiler..........$ 46.08 31.15
GROUP 2
Cranes.....................$ 50.54 31.15
Oiler......................$ 42.83 31.15
Truck crane oiler..........$ 45.07 31.15
GROUP 3
Cranes.....................$ 48.80 31.15
Hydraulic..................$ 44.44 31.15
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 178 of 219 ends

Oiler......................$ 42.55 31.15
Truck crane oiler..........$ 44.83 31.15
GROUP 4
Cranes.....................$ 45.76 31.15
OPERATOR: Power Equipment
(Piledriving - AREA 1:)
GROUP 1
Lifting devices............$ 52.64 31.15
Oiler......................$ 43.38 31.15
Truck Crane Oiler..........$ 45.66 31.15
GROUP 2
Lifting devices............$ 50.82 31.15
Oiler......................$ 43.11 31.15
Truck Crane Oiler..........$ 45.41 31.15
GROUP 3
Lifting devices............$ 49.14 31.15
Oiler......................$ 42.89 31.15
Truck Crane Oiler..........$ 45.12 31.15
GROUP 4
Lifting devices............$ 47.37 31.15
GROUP 5
Lifting devices............$ 44.73 31.15
GROUP 6
Lifting devices............$ 42.50 31.15
OPERATOR: Power Equipment
(Steel Erection - AREA 1:)
GROUP 1
Cranes.....................$ 53.27 31.15
Oiler......................$ 43.72 31.15
Truck Crane Oiler..........$ 45.95 31.15
GROUP 2
Cranes.....................$ 51.50 31.15
Oiler......................$ 43.45 31.15
Truck Crane Oiler..........$ 45.73 31.15
GROUP 3
Cranes.....................$ 50.02 31.15
Hydraulic..................$ 45.07 31.15
Oiler......................$ 43.23 31.15
Truck Crane Oiler..........$ 45.46 31.15
GROUP 4
Cranes.....................$ 48.00 31.15
GROUP 5
Cranes.....................$ 46.70 31.15
OPERATOR: Power Equipment
(Tunnel and Underground Work
- AREA 1:)
SHAFTS, STOPES, RAISES:

GROUP 1....................$ 47.52 31.15
GROUP 1-A..................$ 49.99 31.15
GROUP 2....................$ 46.26 31.15
GROUP 3....................$ 44.93 31.15
GROUP 4....................$ 43.79 31.15
GROUP 5....................$ 42.65 31.15
UNDERGROUND:

GROUP 1....................$ 47.42 31.15
GROUP 1-A..................$ 49.89 31.15
GROUP 2....................$ 46.16 31.15
GROUP 3....................$ 44.83 31.15
GROUP 4....................$ 43.69 31.15
GROUP 5....................$ 42.55 31.15
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 179 of 219 ends

FOOTNOTE: Work suspended by ropes or cables, or work on a Yo-Yo Cat: $.60 per hour additional.

POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Operator of helicopter (when used in erection work); Hydraulic excavator, 7 cu. yds. and over; Power shovels, over 7 cu. yds.

GROUP 2: Highline cableway; Hydraulic excavator, 3-1/2 cu. yds. up to 7 cu. yds.; Licensed construction work boat
operator, on site; Power blade operator (finish); Power shovels, over 1 cu. yd. up to and including 7 cu. yds.
m.r.c.

GROUP 3: Asphalt milling machine; Cable backhoe; Combination backhoe and loader over 3/4 cu. yds.; Continuous flight tie back machine assistant to engineer or mechanic; Crane
mounted continuous flight tie back machine, tonnage to
apply; Crane mounted drill attachment, tonnage to apply; Dozer, slope brd; Gradall; Hydraulic excavator, up to 3 1/2 cu. yds.; Loader 4 cu. yds. and over; Long reach excavator; Multiple engine scraper (when used as push pull); Power shovels, up to and including 1 cu. yd.; Pre-stress wire wrapping machine; Side boom cat, 572 or larger; Track
loader 4 cu. yds. and over; Wheel excavator (up to and
including 750 cu. yds. per hour)
GROUP 4: Asphalt plant engineer/box person; Chicago boom; Combination backhoe and loader up to and including 3/4 cu. yd.; Concrete batch plant (wet or dry); Dozer and/or push cat; Pull- type elevating loader; Gradesetter, grade
checker (GPS, mechanical or otherwise); Grooving and
grinding machine; Heading shield operator; Heavy-duty
drilling equipment, Hughes, LDH, Watson 3000 or similar; Heavy-duty repairperson and/or welder; Lime spreader;
Loader under 4 cu. yds.; Lubrication and service engineer (mobile and grease rack); Mechanical finishers or spreader machine (asphalt, Barber-Greene and similar); Miller
Formless M-9000 slope paver or similar; Portable crushing and screening plants; Power blade support; Roller operator, asphalt; Rubber-tired scraper, self-loading (paddle-wheels, etc.); Rubber- tired earthmoving equipment (scrapers); Slip form paver (concrete); Small tractor with drag; Soil
stabilizer (P & H or equal); Spider plow and spider puller; Tubex pile rig; Unlicensed constuction work boat operator, on site; Timber skidder; Track loader up to 4 yds.;
Tractor-drawn scraper; Tractor, compressor drill
combination; Welder; Woods-Mixer (and other similar Pugmill equipment)
GROUP 5: Cast-in-place pipe laying machine; Combination slusher and motor operator; Concrete conveyor or concrete pump, truck or equipment mounted; Concrete conveyor,
building site; Concrete pump or pumpcrete gun; Drilling equipment, Watson 2000, Texoma 700 or similar; Drilling and boring machinery, horizontal (not to apply to waterliners, wagon drills or jackhammers); Concrete mixer/all; Person and/or material hoist; Mechanical finishers (concrete)
(Clary, Johnson, Bidwell Bridge Deck or similar types); Mechanical burm, curb and/or curb and gutter machine,
concrete or asphalt); Mine or shaft hoist; Portable
crusher; Power jumbo operator (setting slip-forms, etc., in tunnels); Screed (automatic or manual); Self-propelled
compactor with dozer; Tractor with boom D6 or smaller;
Trenching machine, maximum digging capacity over 5 ft.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 180 of 219 ends

depth; Vermeer T-600B rock cutter or similar
GROUP 6: Armor-Coater (or similar); Ballast jack tamper; Boom- type backfilling machine; Assistant plant engineer; Bridge and/or gantry crane; Chemical grouting machine,
truck-mounted; Chip spreading machine operator; Concrete saw (self-propelled unit on streets, highways, airports and canals); Deck engineer; Drilling equipment Texoma 600,
Hughes 200 Series or similar up to and including 30 ft. m.r.c.; Drill doctor; Helicopter radio operator;
Hydro-hammer or similar; Line master; Skidsteer loader, Bobcat larger than 743 series or similar (with
attachments); Locomotive; Lull hi-lift or similar; Oiler, truck mounted equipment; Pavement breaker, truck-mounted, with compressor combination; Paving fabric installation and/or laying machine; Pipe bending machine (pipelines
only); Pipe wrapping machine (tractor propelled and
supported); Screed (except asphaltic concrete paving);
Self- propelled pipeline wrapping machine; Tractor;
Self-loading chipper; Concrete barrier moving machine
GROUP 7: Ballast regulator; Boom truck or dual-purpose
A-frame truck, non-rotating - under 15 tons; Cary lift or similar; Combination slurry mixer and/or cleaner; Drilling equipment, 20 ft. and under m.r.c.; Firetender (hot plant); Grouting machine operator; Highline cableway signalperson; Stationary belt loader (Kolman or similar); Lift slab
machine (Vagtborg and similar types); Maginnes internal full slab vibrator; Material hoist (1 drum); Mechanical trench shield; Pavement breaker with or without compressor combination); Pipe cleaning machine (tractor propelled and supported); Post driver; Roller (except asphalt); Chip
Seal; Self-propelled automatically applied concrete curing mahcine (on streets, highways, airports and canals);
Self-propelled compactor (without dozer); Signalperson; Slip-form pumps (lifting device for concrete forms); Tie spacer; Tower mobile; Trenching machine, maximum digging capacity up to and including 5 ft. depth; Truck- type loader GROUP 8: Bit sharpener; Boiler tender; Box operator;
Brakeperson; Combination mixer and compressor
(shotcrete/gunite); Compressor operator; Deckhand; Fire tender; Forklift (under 20 ft.); Generator;
Gunite/shotcrete equipment operator; Hydraulic monitor; Ken seal machine (or similar); Mixermobile; Oiler; Pump
operator; Refrigeration plant; Reservoir-debris tug (self- propelled floating); Ross Carrier (construction site);
Rotomist operator; Self-propelled tape machine; Shuttlecar; Self-propelled power sweeper operator (includes vacuum
sweeper); Slusher operator; Surface heater; Switchperson; Tar pot firetender; Tugger hoist, single drum; Vacuum
cooling plant; Welding machine (powered other than by
electricity)
GROUP 8-A: Elevator operator; Skidsteer loader-Bobcat 743 series or smaller, and similar (without attachments); Mini excavator under 25 H.P. (backhoe-trencher); Tub grinder wood chipper
----------------------------------------------------------

ALL CRANES AND ATTACHMENTS
GROUP 1: Clamshell and dragline over 7 cu. yds.; Crane, over 100 tons; Derrick, over 100 tons; Derrick barge
pedestal-mounted, over 100 tons; Self-propelled boom-type Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 181 of 219 ends

lifting device, over 100 tons
GROUP 2: Clamshell and dragline over 1 cu. yd. up to and including 7 cu. yds.; Crane, over 45 tons up to and
including 100 tons; Derrick barge, 100 tons and under;
Self-propelled boom-type lifting device, over 45 tons;
Tower crane
GROUP 3: Clamshell and dragline up to and including 1 cu. yd.; Cranes 45 tons and under; Self-propelled boom-type lifting device 45 tons and under;
GROUP 4: Boom Truck or dual purpose A-frame truck,
non-rotating over 15 tons; Truck-mounted rotating
telescopic boom type lifting device, Manitex or similar (boom truck) over 15 tons; Truck-mounted rotating
telescopic boom type lifting device, Manitex or similar (boom truck) - under 15 tons;
-----------------------------------------------------------

PILEDRIVERS
GROUP 1: Derrick barge pedestal mounted over 100 tons;
Clamshell over 7 cu. yds.; Self-propelled boom-type lifting device over 100 tons; Truck crane or crawler, land or barge mounted over 100 tons
GROUP 2: Derrick barge pedestal mounted 45 tons to and
including 100 tons; Clamshell up to and including 7 cu. yds.; Self-propelled boom-type lifting device over 45 tons; Truck crane or crawler, land or barge mounted, over 45 tons up to and including 100 tons; Fundex F-12 hydraulic pile rig GROUP 3: Derrick barge pedestal mounted under 45 tons; Self- propelled boom-type lifting device 45 tons and under;
Skid/scow piledriver, any tonnage; Truck crane or crawler, land or barge mounted 45 tons and under
GROUP 4: Assistant operator in lieu of assistant to engineer; Forklift, 10 tons and over; Heavy-duty repairperson/welder GROUP 5: Deck engineer
GROUP 6: Deckhand; Fire tender
-------------------------------------------------------------

STEEL ERECTORS
GROUP 1: Crane over 100 tons; Derrick over 100 tons; Self- propelled boom-type lifting device over 100 tons
GROUP 2: Crane over 45 tons to 100 tons; Derrick under 100 tons; Self-propelled boom-type lifting device over 45 tons to 100 tons; Tower crane
GROUP 3: Crane, 45 tons and under; Self-propelled boom-type lifting device, 45 tons and under
GROUP 4: Chicago boom; Forklift, 10 tons and over; Heavy-duty repair person/welder
GROUP 5: Boom cat
-------------------------------------------------------------- --

TUNNEL AND UNDERGROUND WORK
GROUP 1-A: Tunnel bore machine operator, 20' diameter or more

GROUP 1: Heading shield operator; Heavy-duty repairperson; Mucking machine (rubber tired, rail or track type); Raised bore operator (tunnels); Tunnel mole bore operator
GROUP 2: Combination slusher and motor operator; Concrete pump or pumpcrete gun; Power jumbo operator
GROUP 3: Drill doctor; Mine or shaft hoist
GROUP 4: Combination slurry mixer cleaner; Grouting Machine operator; Motorman
GROUP 5: Bit Sharpener; Brakeman; Combination mixer and Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 182 of 219 ends

compressor (gunite); Compressor operator; Oiler; Pump
operator; Slusher operator
----------------------------------------------------------- AREA DESCRIPTIONS:

POWER EQUIPMENT OPERATORS, CRANES AND ATTACHMENTS,TUNNEL AND UNDERGROUND [These areas do not apply to Piledrivers and Steel Erectors]
AREA 1: DEL NORTE, HUMBOLDT, LAKE, MENDOCINO
AREA 2 -NOTED BELOW
THE REMAINING COUNTIES ARE SPLIT BETWEEN AREA 1 AND AREA 2 AS NOTED BELOW:

DEL NORTE COUNTY:

Area 1: Extreme Southwest corner
Area 2: Remainder
HUMBOLDT COUNTY:

Area 1: Except Eastern and Southwestern parts
Area 2: Remainder
LAKE COUNTY:

Area 1: Southern part
Area 2: Remainder
MENDOCINO COUNTY:

Area 1: Central and Southeastern Parts
Area 2: Remainder
---------------------------------------------------------------- IRON0118-012 01/01/2023
ALPINE, LASSEN, MODOC, SISKIYOU and TRINITY COUNTIES
Rates Fringes
IRONWORKER.......................$ 41.00 33.70
---------------------------------------------------------------- IRON0118-013 01/01/2023

AMADOR, BUTTE, COLUSA,EL DORADO, GLENN,MARIN, NAPA, NEVADA,

PLACER,PLUMAS, SACRAMENTO, SHASTA, SIERRA, SOLANO, SONOMA, SUTTER, TEHAMA, YOLO and YUBA COUNTIES
Rates Fringes
IRONWORKER.......................$ 46.20 34.30
---------------------------------------------------------------- LABO0067-001 06/27/2022
AREA ""A"" - MARIN COUNTY
AREA ""B"" - ALPINE, AMADOR, BUTTE COLUSA EL DORADO, GLENN,

LASSEN, MODOC, NAPA, NEVADA, PLACER, PLUMAS, SACRAMENTO,

SHASTA, SIERRA, SISKIYOU, SOLANO, SONOMA, SUTTER, TEHAMA,

TRINITY, YOLO, AND YUBA COUNTIES
Rates Fringes
Asbestos Removal Laborer.........$ 27.05 13.50
LABORER (Lead Removal)
Marin County................$ 35.37 26.95
Remaining Counties..........$ 34.37 26.95
---------------------------------------------------------------- LABO0067-005 06/27/2017
AREA ""A"" - ALAMEDA, CONTRA COSTA, SAN FRANCISCO, SAN MATEO AND

SANTA CLARA COUNTIES
AREA ""B"" - ALPINE, AMADOR, BUTTE, CALAVERAS, COLUSA, DEL

NORTE, EL DORADO, FRESNO, GLENN, HUMBOLDT, KINGS, LAKE, LASSEN,

MADERA, MARIPOSA, MENDOCINO, MERCED, MODOC, MONTEREY, NEVADA,

PLACER, PLUMAS, SANCREMENTO, SAN BENITO, SAN JOAQUIN, SANTA

CRUZ, SIERRA, SHASTA, SISKIYOU, STANISLAUS, TEHAMA, TRINITY,

TULARE, TUOLUMNE, YOLO AND YOUBA COUNTIES
Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 183 of 219 ends

Escort Driver, Flag Person
Area A.....................$ 29.54 22.17
Area B.....................$ 28.54 22.17
Traffic Control Person I
Area A.....................$ 29.84 22.17
Area B.....................$ 28.84 22.17
Traffic Control Person II
Area A.....................$ 27.34 22.17
Area B.....................$ 26.34 22.17
TRAFFIC CONTROL PERSON I: Layout of traffic control, crash cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of
temporary/permanent signs, markers, delineators and crash cushions.
---------------------------------------------------------------- LABO0185-002 07/01/2022

ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC,

NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU,

SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES
Rates Fringes

LABORER
Mason Tender-Brick..........$ 35.29 25.21
---------------------------------------------------------------- LABO0185-005 07/01/2021

ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC,

NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU,

SUTTER, TEHAMA, TRINITY, YOLO AND YUBA COUNTIES
Rates Fringes
Tunnel and Shaft Laborers:

GROUP 1.....................$ 42.00 25.71
GROUP 2.....................$ 41.77 25.71
GROUP 3.....................$ 41.52 25.71
GROUP 4.....................$ 41.07 25.71
GROUP 5.....................$ 40.53 25.71
Shotcrete Specialist........$ 42.52 25.71

TUNNEL AND SHAFT CLASSIFICATIONS
GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete nozzlemen
GROUP 2: Rodmen; Shaft work & raise (below actual or
excavated ground level)
GROUP 3: Bit grinder; Blaster, driller, powdermen, heading; Cherry pickermen - where car is lifted; Concrete finisher in tunnel; Concrete screedman; Grout pumpman and potman; Gunite & shotcrete gunman & potman; Headermen; High
pressure nozzleman; Miner - tunnel, including top and
bottom man on shaft and raise work; Nipper; Nozzleman on slick line; Sandblaster - potman, Robotic Shotcrete Placer, Segment Erector, Tunnel Muck Hauler, Steel Form raiser and setter; Timberman, retimberman (wood or steel or substitute materials therefore); Tugger (for tunnel laborer work); Cable tender; Chuck tender; Powderman - primer house
GROUP 4: Vibrator operator, pavement breaker; Bull gang - muckers, trackmen; Concrete crew - includes rodding and spreading, Dumpmen (any method)
GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman
---------------------------------------------------------------- LABO0185-006 06/25/2018

ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC,

NEVADA, PLACER, PLUMAS, SACRAMENTO, SHIASTA, SIERRA, SISKIYOU,

SUTTER, TEHAMA, TRINITY, YOLO, YUBA COUNTIES
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 184 of 219 ends

Rates Fringes

LABORER (CONSTRUCTION CRAFT
LABORERS - AREA B:)
Construction Specialist
Group.......................$ 30.49 23.20
GROUP 1.....................$ 29.79 23.20
GROUP 1-a...................$ 30.01 23.20
GROUP 1-c...................$ 30.01 23.20
GROUP 1-e...................$ 30.34 23.20
GROUP 1-f...................$ 30.37 23.20
GROUP 2.....................$ 29.64 23.20
GROUP 3.....................$ 29.54 23.20
GROUP 4.....................$ 23.23 23.20
See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE
LABORERS - AREA B:)
(1) New Construction........$ 29.54 23.20
(2) Establishment Warranty
Period......................$ 23.23 23.20
LABORER (GUNITE - AREA B:)
GROUP 1.....................$ 29.75 22.31
GROUP 2.....................$ 29.25 22.31
GROUP 3.....................$ 28.66 22.31
GROUP 4.....................$ 28.54 22.31
LABORER (WRECKING - AREA B:)
GROUP 1.....................$ 29.79 23.20
GROUP 2.....................$ 29.64 23.20
FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging scaffolds, belts shall receive $0.25 per hour above the applicable wage rate. This shall not apply to workers
entitled to receive the wage rate set forth in Group 1-a below.
---------------------------------------------------------

LABORER CLASSIFICATIONS
CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker; Chainsaw; Laser beam in connection with laborers' work; Cast-in- place manhole form setter; Pressure pipelayer; Davis trencher - 300 or similar type (and all small
trenchers); Blaster; Diamond driller; Multiple unit drill; Hydraulic drill
GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker and similar type tampers; Buggymobile; Caulker, bander, pipewrapper, conduit layer, plastic pipelayer; Certified hazardous waste worker including Leade Abatement;
Compactors of all types; Concrete and magnesite mixer, 1/2 yd. and under; Concrete pan work; Concrete sander; Concrete saw; Cribber and/or shoring; Cut granite curb setter;
Dri-pak-it machine; Faller, logloader and bucker; Form
raiser, slip forms; Green cutter; Headerboard, Hubsetter, aligner, by any method; High pressure blow pipe (1-1/2"" or over, 100 lbs. pressure/over); Hydro seeder and similar type; Jackhammer operator; Jacking of pipe over 12 inches; Jackson and similar type compactor; Kettle tender, pot and worker applying asphalt, lay-kold, creosote, lime, caustic and similar type materials (applying means applying,
dipping or handling of such materials); Lagging, sheeting, whaling, bracing, trenchjacking, lagging hammer; Magnesite, Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 185 of 219 ends

epoxyresin, fiberglass, mastic worker (wet or dry); No
joint pipe and stripping of same, including repair of
voids; Pavement breaker and spader, including tool grinder; Perma curb; Pipelayer (including grade checking in
connection with pipelaying); Precast-manhole setter;
Pressure pipe tester; Post hole digger, air, gas and
electric; Power broom sweeper; Power tampers of all types (except as shown in Group 2); Ram set gun and stud gun; Riprap stonepaver and rock-slinger, including placing of sacked concrete and/or sand (wet or dry) and gabions and similar type; Rotary scarifier or multiple head concrete chipping scarifier; Roto and Ditch Witch; Rototiller;
Sandblaster, pot, gun, nozzle operators; Signalling and rigging; Tank cleaner; Tree climber; Turbo blaster;
Vibrascreed, bull float in connection with laborers' work; Vibrator; Hazardous waste worker (lead removal); Asbestos and mold removal worker
GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143 and similar type drills; Track driller; Jack leg driller; Wagon driller; Mechanical drillers, all types regardless of type or method of power; Mechanical pipe layers, all types regardless of type or method of power; Blaster and powder; All work of loading, placing and blasting of all powder and explosives of whatever type regardless of method used for such loading and placing; High scalers (including drilling of same); Tree topper; Bit grinder
GROUP 1-b: Sewer cleaners shall receive $4.00 per day above Group 1 wage rates. ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small
diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer
manholes shal receive $5.00 per day above Group 1 wage
rates.

GROUP 1-c: Burning and welding in connection with laborers' work; Synthetic thermoplastics and similar type welding GROUP 1-d: Maintenance and repair track and road beds. All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work
performed on underground structures not specifically
covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall
apply to cut and cover work of subway construction after the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts thereof, and work on and in deep footings. (A deep footing is a hole 15 feet or more in depth.) In the event the
depth of the footing is unknown at the commencement of
excavation, and the final depth exceeds 15 feet, the deep footing wage rate would apply to all employees for each and every day worked on or in the excavation of the footing from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting or shot crete
GROUP 2: Asphalt shoveler; Cement dumper and handling dry cement or gypsum; Choke-setter and rigger (clearing work); Concrete bucket dumper and chute; Concrete chipping and grinding; Concrete laborer (wet or dry); Driller tender, chuck tender, nipper; Guinea chaser (stake), grout crew; High pressure nozzle, adductor; Hydraulic monitor (over 100 lbs. pressure); Loading and unloading, carrying and hauling Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 186 of 219 ends

of all rods and materials for use in reinforcing concrete construction; Pittsburgh chipper and similar type brush shredders; Sloper; Single foot, hand-held, pneumatic
tamper; All pneumatic, air, gas and electric tools not
listed in Groups 1 through 1-f; Jacking of pipe - under 12 inches
GROUP 3: Construction laborers, including bridge and general laborer; Dump, load spotter; Flag person; Fire watcher; Fence erector; Guardrail erector; Gardener, horticultural and landscape laborer; Jetting; Limber, brush loader and piler; Pavement marker (button setter); Maintenance, repair track and road beds; Streetcar and railroad construction track laborer; Temporary air and water lines, Victaulic or similar; Tool room attendant (jobsite only)
GROUP 4: Final clean-up work of debris, grounds and building including but not limited to: street cleaner; cleaning and washing windows; brick cleaner (jobsite only); material cleaner (jobsite only). The classification ""material
cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or temporary jobsite yard.

The material cleaner classification should not be used in the performance of ""form stripping, cleaning and oiling and moving to the next point of erection"".
--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS
GROUP 1: Structural Nozzleman
GROUP 2: Nozzleman, Gunman, Potman, Groundman
GROUP 3: Reboundman
GROUP 4: Gunite laborer
----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS
GROUP 1: Skilled wrecker (removing and salvaging of sash, windows and materials)
GROUP 2: Semi-skilled wrecker (salvaging of other building materials)
---------------------------------------------------------------- LABO0185-008 07/01/2021
Rates Fringes
Plasterer tender.................$ 35.82 28.45
Work on a swing stage scaffold: $1.00 per hour additional. ---------------------------------------------------------------- LABO0261-002 06/28/2021

MARIN COUNTY
Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)
Escort Driver, Flag Person..$ 34.48 26.21
Traffic Control Person I....$ 34.78 26.21
Traffic Control Person II...$ 32.28 26.21
TRAFFIC CONTROL PERSON I: Layout of traffic control, crash cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of
temporary/permanent signs, markers, delineators and crash cushions.
---------------------------------------------------------------- LABO0261-004 07/01/2021
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 187 of 219 ends

MARIN COUNTY
Rates Fringes
Tunnel and Shaft Laborers:

GROUP 1.....................$ 42.00 25.71
GROUP 2.....................$ 41.77 25.71
GROUP 3.....................$ 41.52 25.71
GROUP 4.....................$ 41.07 25.71
GROUP 5.....................$ 40.53 25.71
Shotcrete Specialist........$ 42.52 25.71

TUNNEL AND SHAFT CLASSIFICATIONS
GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete nozzlemen
GROUP 2: Rodmen; Shaft work & raise (below actual or
excavated ground level)
GROUP 3: Bit grinder; Blaster, driller, powdermen, heading; Cherry pickermen - where car is lifted; Concrete finisher in tunnel; Concrete screedman; Grout pumpman and potman; Gunite & shotcrete gunman & potman; Headermen; High
pressure nozzleman; Miner - tunnel, including top and
bottom man on shaft and raise work; Nipper; Nozzleman on slick line; Sandblaster - potman, Robotic Shotcrete Placer, Segment Erector, Tunnel Muck Hauler, Steel Form raiser and setter; Timberman, retimberman (wood or steel or substitute materials therefore); Tugger (for tunnel laborer work); Cable tender; Chuck tender; Powderman - primer house
GROUP 4: Vibrator operator, pavement breaker; Bull gang - muckers, trackmen; Concrete crew - includes rodding and spreading, Dumpmen (any method)
GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman
---------------------------------------------------------------- LABO0261-007 07/01/2018

MARIN AND NAPA COUNTIES
Rates Fringes

LABORER
Mason Tender-Brick..........$ 32.45 22.20
---------------------------------------------------------------- LABO0261-010 06/25/2018

MARIN COUNTY
Rates Fringes

LABORER (CONSTRUCTION CRAFT
LABORERS - AREA A:)
Construction Specialist
Group.......................$ 31.49 23.20
GROUP 1.....................$ 30.79 23.20
GROUP 1-a...................$ 31.01 23.20
GROUP 1-c...................$ 30.84 23.20
GROUP 1-e...................$ 31.34 23.20
GROUP 1-f...................$ 31.37 23.20
GROUP 2.....................$ 30.64 23.20
GROUP 3.....................$ 30.54 23.20
GROUP 4.....................$ 24.23 23.20
See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE
LABORERS - AREA A:)
(1) New Construction........$ 30.54 23.20
(2) Establishment Warranty
Period......................$ 24.23 23.20
LABORER (GUNITE - AREA A:)
GROUP 1.....................$ 30.75 22.31
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 188 of 219 ends

GROUP 2.....................$ 30.25 22.31
GROUP 3.....................$ 29.66 22.31
GROUP 4.....................$ 29.54 22.31
LABORER (WRECKING - AREA A:)
GROUP 1.....................$ 30.79 23.20
GROUP 2.....................$ 30.64 23.20
FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging scaffolds, belts shall receive $0.25 per hour above the applicable wage rate. This shall not apply to workers
entitled to receive the wage rate set forth in Group 1-a below.
---------------------------------------------------------

LABORER CLASSIFICATIONS
CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker; Chainsaw; Laser beam in connection with laborers' work; Cast-in- place manhole form setter; Pressure pipelayer; Davis trencher - 300 or similar type (and all small
trenchers); Blaster; Diamond driller; Multiple unit drill; Hydraulic drill
GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker and similar type tampers; Buggymobile; Caulker, bander, pipewrapper, conduit layer, plastic pipelayer; Certified hazardous waste worker including Leade Abatement;
Compactors of all types; Concrete and magnesite mixer, 1/2 yd. and under; Concrete pan work; Concrete sander; Concrete saw; Cribber and/or shoring; Cut granite curb setter;
Dri-pak-it machine; Faller, logloader and bucker; Form
raiser, slip forms; Green cutter; Headerboard, Hubsetter, aligner, by any method; High pressure blow pipe (1-1/2"" or over, 100 lbs. pressure/over); Hydro seeder and similar type; Jackhammer operator; Jacking of pipe over 12 inches; Jackson and similar type compactor; Kettle tender, pot and worker applying asphalt, lay-kold, creosote, lime, caustic and similar type materials (applying means applying,
dipping or handling of such materials); Lagging, sheeting, whaling, bracing, trenchjacking, lagging hammer; Magnesite, epoxyresin, fiberglass, mastic worker (wet or dry); No
joint pipe and stripping of same, including repair of
voids; Pavement breaker and spader, including tool grinder; Perma curb; Pipelayer (including grade checking in
connection with pipelaying); Precast-manhole setter;
Pressure pipe tester; Post hole digger, air, gas and
electric; Power broom sweeper; Power tampers of all types (except as shown in Group 2); Ram set gun and stud gun; Riprap stonepaver and rock-slinger, including placing of sacked concrete and/or sand (wet or dry) and gabions and similar type; Rotary scarifier or multiple head concrete chipping scarifier; Roto and Ditch Witch; Rototiller;
Sandblaster, pot, gun, nozzle operators; Signalling and rigging; Tank cleaner; Tree climber; Turbo blaster;
Vibrascreed, bull float in connection with laborers' work; Vibrator; Hazardous waste worker (lead removal); Asbestos and mold removal worker
GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143 and similar type drills; Track driller; Jack leg driller; Wagon driller; Mechanical drillers, all types regardless of type or method of power; Mechanical pipe layers, all types regardless of type or method of power; Blaster and powder; Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 189 of 219 ends

All work of loading, placing and blasting of all powder and explosives of whatever type regardless of method used for such loading and placing; High scalers (including drilling of same); Tree topper; Bit grinder
GROUP 1-b: Sewer cleaners shall receive $4.00 per day above Group 1 wage rates. ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small
diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer
manholes shal receive $5.00 per day above Group 1 wage
rates.

GROUP 1-c: Burning and welding in connection with laborers' work; Synthetic thermoplastics and similar type welding GROUP 1-d: Maintenance and repair track and road beds. All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work
performed on underground structures not specifically
covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall
apply to cut and cover work of subway construction after the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts thereof, and work on and in deep footings. (A deep footing is a hole 15 feet or more in depth.) In the event the
depth of the footing is unknown at the commencement of
excavation, and the final depth exceeds 15 feet, the deep footing wage rate would apply to all employees for each and every day worked on or in the excavation of the footing from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting or shot crete
GROUP 2: Asphalt shoveler; Cement dumper and handling dry cement or gypsum; Choke-setter and rigger (clearing work); Concrete bucket dumper and chute; Concrete chipping and grinding; Concrete laborer (wet or dry); Driller tender, chuck tender, nipper; Guinea chaser (stake), grout crew; High pressure nozzle, adductor; Hydraulic monitor (over 100 lbs. pressure); Loading and unloading, carrying and hauling of all rods and materials for use in reinforcing concrete construction; Pittsburgh chipper and similar type brush shredders; Sloper; Single foot, hand-held, pneumatic
tamper; All pneumatic, air, gas and electric tools not
listed in Groups 1 through 1-f; Jacking of pipe - under 12 inches
GROUP 3: Construction laborers, including bridge and general laborer; Dump, load spotter; Flag person; Fire watcher; Fence erector; Guardrail erector; Gardener, horticultural and landscape laborer; Jetting; Limber, brush loader and piler; Pavement marker (button setter); Maintenance, repair track and road beds; Streetcar and railroad construction track laborer; Temporary air and water lines, Victaulic or similar; Tool room attendant (jobsite only)
GROUP 4: Final clean-up work of debris, grounds and building including but not limited to: street cleaner; cleaning and washing windows; brick cleaner (jobsite only); material cleaner (jobsite only). The classification ""material
cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be salvaged and stocked to be reused on another job.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 190 of 219 ends

C: for the cleaning of salvage material at the jobsite or temporary jobsite yard.

The material cleaner classification should not be used in the performance of ""form stripping, cleaning and oiling and moving to the next point of erection"".
--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS
GROUP 1: Structural Nozzleman
GROUP 2: Nozzleman, Gunman, Potman, Groundman
GROUP 3: Reboundman
GROUP 4: Gunite laborer
----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS
GROUP 1: Skilled wrecker (removing and salvaging of sash, windows and materials)
GROUP 2: Semi-skilled wrecker (salvaging of other building materials)
---------------------------------------------------------------- LABO0261-015 07/01/2021
Rates Fringes
Plasterer tender.................$ 35.82 28.45
Work on a swing stage scaffold: $1.00 per hour additional. ---------------------------------------------------------------- LABO0324-004 06/28/2021

NAPA, SOLANO, AND SONOMA, COUNTIES
Rates Fringes

LABORER (TRAFFIC CONTROL/LANE

CLOSURE)
Escort Driver, Flag Person..$ 33.48 26.21
Traffic Control Person I....$ 33.78 26.21
Traffic Control Person II...$ 31.28 26.21
TRAFFIC CONTROL PERSON I: Layout of traffic control, crash cushions, construction area and roadside signage.

TRAFFIC CONTROL PERSON II: Installation and removal of
temporary/permanent signs, markers, delineators and crash cushions.
---------------------------------------------------------------- LABO0324-008 06/25/2018

NAPA, SOLANO, AND SONOMA COUNTIES
Rates Fringes
Tunnel and Shaft Laborers:

GROUP 1.....................$ 37.82 24.11
GROUP 2.....................$ 37.59 24.11
GROUP 3.....................$ 37.34 24.11
GROUP 4.....................$ 36.89 24.11
GROUP 5.....................$ 36.35 24.11
Shotcrete Specialist........$ 38.34 24.11

TUNNEL AND SHAFT CLASSIFICATIONS
GROUP 1: Diamond driller; Groundmen; Gunite and shotcrete nozzlemen
GROUP 2: Rodmen; Shaft work & raise (below actual or
excavated ground level)
GROUP 3: Bit grinder; Blaster, driller, powdermen, heading; Cherry pickermen - where car is lifted; Concrete finisher in tunnel; Concrete screedman; Grout pumpman and potman; Gunite & shotcrete gunman & potman; Headermen; High
pressure nozzleman; Miner - tunnel, including top and
bottom man on shaft and raise work; Nipper; Nozzleman on slick line; Sandblaster - potman, Robotic Shotcrete Placer, Segment Erector, Tunnel Muck Hauler, Steel Form raiser and Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 191 of 219 ends

setter; Timberman, retimberman (wood or steel or substitute materials therefore); Tugger (for tunnel laborer work); Cable tender; Chuck tender; Powderman - primer house
GROUP 4: Vibrator operator, pavement breaker; Bull gang - muckers, trackmen; Concrete crew - includes rodding and spreading, Dumpmen (any method)
GROUP 5: Grout crew; Reboundman; Swamper/ Brakeman
---------------------------------------------------------------- LABO0324-010 07/01/2022

SOLANO AND SONOMA COUNTIES
Rates Fringes

LABORER
Mason Tender-Brick..........$ 35.84 25.91
---------------------------------------------------------------- LABO0324-013 06/25/2018

NAPA, SOLANO, AND SONOMA COUNTIES
Rates Fringes

LABORER (CONSTRUCTION CRAFT
LABORERS - AREA B:)
Construction Specialist
Group.......................$ 30.49 23.20
GROUP 1.....................$ 29.79 23.20
GROUP 1-a...................$ 30.01 23.20
GROUP 1-c...................$ 29.84 23.20
GROUP 1-e...................$ 30.34 23.20
GROUP 1-f...................$ 29.37 23.20
GROUP 2.....................$ 29.64 23.20
GROUP 3.....................$ 29.54 23.20
GROUP 4.....................$ 23.23 23.20
See groups 1-b and 1-d under laborer classifications.

LABORER (GARDENERS,

HORTICULTURAL & LANDSCAPE
LABORERS - AREA B:)
(1) New Construction........$ 29.54 23.20
(2) Establishment Warranty
Period......................$ 23.23 23.20
LABORER (GUNITE - AREA B:)
GROUP 1.....................$ 29.75 22.31
GROUP 2.....................$ 29.25 22.31
GROUP 3.....................$ 28.66 22.31
GROUP 4.....................$ 28.54 22.31
LABORER (WRECKING - AREA B:)
GROUP 1.....................$ 29.79 23.20
GROUP 2.....................$ 29.64 23.20
FOOTNOTES:

Laborers working off or with or from bos'n chairs, swinging scaffolds, belts shall receive $0.25 per hour above the applicable wage rate. This shall not apply to workers
entitled to receive the wage rate set forth in Group 1-a below.
---------------------------------------------------------

LABORER CLASSIFICATIONS
CONSTRUCTION SPECIALIST GROUP: Asphalt ironer and raker; Chainsaw; Laser beam in connection with laborers' work; Cast-in- place manhole form setter; Pressure pipelayer; Davis trencher - 300 or similar type (and all small
trenchers); Blaster; Diamond driller; Multiple unit drill; Hydraulic drill
GROUP 1: Asphalt spreader boxes (all types); Barko, Wacker Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 192 of 219 ends

and similar type tampers; Buggymobile; Caulker, bander, pipewrapper, conduit layer, plastic pipelayer; Certified hazardous waste worker including Leade Abatement;
Compactors of all types; Concrete and magnesite mixer, 1/2 yd. and under; Concrete pan work; Concrete sander; Concrete saw; Cribber and/or shoring; Cut granite curb setter;
Dri-pak-it machine; Faller, logloader and bucker; Form
raiser, slip forms; Green cutter; Headerboard, Hubsetter, aligner, by any method; High pressure blow pipe (1-1/2"" or over, 100 lbs. pressure/over); Hydro seeder and similar type; Jackhammer operator; Jacking of pipe over 12 inches; Jackson and similar type compactor; Kettle tender, pot and worker applying asphalt, lay-kold, creosote, lime, caustic and similar type materials (applying means applying,
dipping or handling of such materials); Lagging, sheeting, whaling, bracing, trenchjacking, lagging hammer; Magnesite, epoxyresin, fiberglass, mastic worker (wet or dry); No
joint pipe and stripping of same, including repair of
voids; Pavement breaker and spader, including tool grinder; Perma curb; Pipelayer (including grade checking in
connection with pipelaying); Precast-manhole setter;
Pressure pipe tester; Post hole digger, air, gas and
electric; Power broom sweeper; Power tampers of all types (except as shown in Group 2); Ram set gun and stud gun; Riprap stonepaver and rock-slinger, including placing of sacked concrete and/or sand (wet or dry) and gabions and similar type; Rotary scarifier or multiple head concrete chipping scarifier; Roto and Ditch Witch; Rototiller;
Sandblaster, pot, gun, nozzle operators; Signalling and rigging; Tank cleaner; Tree climber; Turbo blaster;
Vibrascreed, bull float in connection with laborers' work; Vibrator; Hazardous waste worker (lead removal); Asbestos and mold removal worker
GROUP 1-a: Joy drill model TWM-2A; Gardner-Denver model DH143 and similar type drills; Track driller; Jack leg driller; Wagon driller; Mechanical drillers, all types regardless of type or method of power; Mechanical pipe layers, all types regardless of type or method of power; Blaster and powder; All work of loading, placing and blasting of all powder and explosives of whatever type regardless of method used for such loading and placing; High scalers (including drilling of same); Tree topper; Bit grinder
GROUP 1-b: Sewer cleaners shall receive $4.00 per day above Group 1 wage rates. ""Sewer cleaner"" means any worker who handles or comes in contact with raw sewage in small
diameter sewers. Those who work inside recently active, large diameter sewers, and all recently active sewer
manholes shal receive $5.00 per day above Group 1 wage
rates.

GROUP 1-c: Burning and welding in connection with laborers' work; Synthetic thermoplastics and similar type welding GROUP 1-d: Maintenance and repair track and road beds. All employees performing work covered herein shall receive $ .25 per hour above their regular rate for all work
performed on underground structures not specifically
covered herein. This paragraph shall not be construed to apply to work below ground level in open cut. It shall
apply to cut and cover work of subway construction after the temporary cover has been placed.

GROUP 1-e: Work on and/or in bell hole footings and shafts Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 193 of 219 ends

thereof, and work on and in deep footings. (A deep footing is a hole 15 feet or more in depth.) In the event the
depth of the footing is unknown at the commencement of
excavation, and the final depth exceeds 15 feet, the deep footing wage rate would apply to all employees for each and every day worked on or in the excavation of the footing from the date of inception.

GROUP 1-f: Wire winding machine in connection with guniting or shot crete
GROUP 2: Asphalt shoveler; Cement dumper and handling dry cement or gypsum; Choke-setter and rigger (clearing work); Concrete bucket dumper and chute; Concrete chipping and grinding; Concrete laborer (wet or dry); Driller tender, chuck tender, nipper; Guinea chaser (stake), grout crew; High pressure nozzle, adductor; Hydraulic monitor (over 100 lbs. pressure); Loading and unloading, carrying and hauling of all rods and materials for use in reinforcing concrete construction; Pittsburgh chipper and similar type brush shredders; Sloper; Single foot, hand-held, pneumatic
tamper; All pneumatic, air, gas and electric tools not
listed in Groups 1 through 1-f; Jacking of pipe - under 12 inches
GROUP 3: Construction laborers, including bridge and general laborer; Dump, load spotter; Flag person; Fire watcher; Fence erector; Guardrail erector; Gardener, horticultural and landscape laborer; Jetting; Limber, brush loader and piler; Pavement marker (button setter); Maintenance, repair track and road beds; Streetcar and railroad construction track laborer; Temporary air and water lines, Victaulic or similar; Tool room attendant (jobsite only)
GROUP 4: Final clean-up work of debris, grounds and building including but not limited to: street cleaner; cleaning and washing windows; brick cleaner (jobsite only); material cleaner (jobsite only). The classification ""material
cleaner"" is to be utilized under the following conditions:

A: at demolition site for the salvage of the material.

B: at the conclusion of a job where the material is to be salvaged and stocked to be reused on another job.

C: for the cleaning of salvage material at the jobsite or temporary jobsite yard.

The material cleaner classification should not be used in the performance of ""form stripping, cleaning and oiling and moving to the next point of erection"".
--------------------------------------------------------

GUNITE LABORER CLASSIFICATIONS
GROUP 1: Structural Nozzleman
GROUP 2: Nozzleman, Gunman, Potman, Groundman
GROUP 3: Reboundman
GROUP 4: Gunite laborer
----------------------------------------------------------

WRECKING WORK LABORER CLASSIFICATIONS
GROUP 1: Skilled wrecker (removing and salvaging of sash, windows and materials)
GROUP 2: Semi-skilled wrecker (salvaging of other building materials)
---------------------------------------------------------------- LABO0324-019 07/01/2021
Rates Fringes
Plasterer tender.................$ 35.82 28.45
Work on a swing stage scaffold: $1.00 per hour additional.

Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 194 of 219 ends

---------------------------------------------------------------- PAIN0016-004 01/01/2022

MARIN, NAPA, SOLANO & SONOMA COUNTIES
Rates Fringes
Painters:........................$ 46.37 26.33
PREMIUMS:

EXOTIC MATERIALS - $1.25 additional per hour.

SPRAY WORK: - $0.50 additional per hour.

INDUSTRIAL PAINTING - $0.25 additional per hour
[Work on industrial buildings used for the manufacture and processing of goods for sale or service; steel construction (bridges), stacks, towers, tanks, and similar structures] HIGH WORK:
over 50 feet - $2.00 per hour additional
100 to 180 feet - $4.00 per hour additional
Over 180 feet - $6.00 per houir additional
---------------------------------------------------------------- PAIN0016-005 07/01/2022
ALPINE, BUTTE, COLUSA, EL DORADO (west of the Sierra Nevada Mountains), GLENN, LASSEN (west of Hwy. 395, excluding Honey Lake); MARIN, MODOC, NAPA, NEVADA (west of the Sierra Nevada Mountains), PLACER (west of the Sierra Nevada Mountains), PLUMAS, SACRAMENTO, SHASTA, SIERRA (west of the Sierra Nevada Mountains), SISKIYOU, SOLANO, SONOMA, SUTTER, TEHAMA, TRINITY,

YOLO AND YUBA COUNTIES
Rates Fringes
DRYWALL FINISHER/TAPER...........$ 53.03 28.84
---------------------------------------------------------------- PAIN0016-007 01/01/2021
ALPINE, AMADOR, BUTTE, COLUSA. EL DORADO (west of the Sierra Nevada Mountains), GLENN, LASSEN (west of Highway 395,
excluding Honey Lake), MODOC, NEVADA (west of the Sierra Nevada Mountains), PLACER (west of the Sierra Nevada Mountains), PLUMAS, SACRAMENTO, SHASTA, SIERRA (west of the Sierra Nevada Mountains), SISKIYOU, SUTTER, TEHAMA, TRINITY, YOLO & YUBA

COUNTIES
Rates Fringes
Painters:........................$ 35.88 21.16
SPRAY/SANDBLAST: $0.50 additional per hour.

EXOTIC MATERIALS: $1.25 additional per hour.

HIGH TIME: Over 50 ft above ground or water level $2.00 additional per hour. 100 to 180 ft above ground or water level $4.00 additional per hour. Over 180 ft above ground or water level $6.00 additional per hour.
---------------------------------------------------------------- PAIN0016-008 07/01/2022

MARIN, NAPA, SOLANO AND SONOMA COUNTIES
Rates Fringes
SOFT FLOOR LAYER.................$ 54.25 32.28
---------------------------------------------------------------- PAIN0169-004 01/01/2022
MARIN , NAPA & SONOMA COUNTIES; SOLANO COUNTY (west of a line defined as follows: Hwy. 80 corridor beginning at the City of Fairfield, including Travis Air Force Base and Suisun City; going north of Manakas Corner Rd., continue north on Suisun Valley Rd. to the Napa County line; Hwy. 80 corridor south on Grizzly Island Rd. to the Grizzly Island Management area) Rates Fringes
GLAZIER..........................$ 54.77 31.45
---------------------------------------------------------------- Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 195 of 219 ends

* PAIN0567-001 07/01/2022
EL DORADO COUNTY (east of the Sierra Nevada Mountains); LASSEN COUNTY (east of Highway 395, beginning at Stacey and including Honey Lake); NEVADA COUNTY (east of the Sierra Nevada
Mountains); PLACER COUNTY (east of the Sierra Nevada
Mountains); AND SIERRA COUNTY (east of the Sierra Nevada Mountains)
Rates Fringes
Painters:

Brush and Roller............$ 33.15 14.29
Spray Painter & Paperhanger.$ 34.81 14.29
PREMIUMS:

Special Coatings (Brush), and Sandblasting = $0.50/hr
Special Coatings (Spray), and Steeplejack = $1.00/hr
Special Coating Spray Steel = $1.25/hr
Swing Stage = $2.00/hr
*A special coating is a coating that requires the mixing of 2 or more products.
---------------------------------------------------------------- PAIN0567-007 07/01/2022
EL DORADO COUNTY (east of the Sierra Nevada Mountains); LASSEN COUNTY (east of Highway 395, beginning at Stacey and including Honey Lake); NEVADA COUNTY (east of the Sierra Nevada
Mountains); PLACER COUNTY (east of the Sierra Nevada Mountains) AND SIERRA COUNTY (east of the Sierra Nevada Mountains) Rates Fringes
SOFT FLOOR LAYER.................$ 34.27 16.47
---------------------------------------------------------------- PAIN0567-010 07/01/2022
EL DORADO COUNTY (east of the Sierra Nevada Mountains); LASSEN COUNTY (east of Highway 395, beginning at Stacey and including Honey Lake); NEVADA COUNTY (east of the Sierra Nevada
Mountains); PLACER COUNTY (east of the Sierra Nevada
Mountains); AND SIERRA COUNTY (east of the Sierra Nevada Mountains)
Rates Fringes
Drywall
(1) Taper...................$ 38.92 14.99
(2) Steeplejack - Taper,
over 40 ft with open space
below.......................$ 40.42 14.99
---------------------------------------------------------------- PAIN0767-004 01/01/2022

ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC,

NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SOLANO (Remainder), SUTTER, TEHAMA, TRINITY, YOLO, YUBA Rates Fringes
GLAZIER..........................$ 41.78 33.09
PAID HOLIDAYS: New Year's Day, Martin Luther King, Jr. Day, President's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, and Christmas Day.

Employee rquired to wear a body harness shall receive $1.50 per hour above the basic hourly rate at any elevation.
---------------------------------------------------------------- PAIN1176-001 07/01/2022
HIGHWAY IMPR0VEMENT
Rates Fringes
Parking Lot Striping/Highway
Marking:

GROUP 1.....................$ 40.83 17.62
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 196 of 219 ends

GROUP 2.....................$ 34.71 17.62
GROUP 3.....................$ 35.11 17.62

CLASSIFICATIONS
GROUP 1: Striper: Layout and application of painted traffic stripes and marking; hot thermo plastic; tape, traffic
stripes and markings
GROUP 2: Gamecourt & Playground Installer
GROUP 3: Protective Coating, Pavement Sealing
---------------------------------------------------------------- PAIN1237-001 08/01/2022
ALPINE; COLUSA; EL DORADO (west of the Sierra Nevada
Mountains); GLENN; LASSEN (west of Highway 395, beginning at Stacey and including Honey Lake); MODOC; NEVADA (west of the Sierra Nevada Mountains); PLACER (west of the Sierra Nevada Mountains); PLUMAS; SACRAMENTO; SHASTA; SIERRA (west of the Sierra Nevada Mountains); SISKIYOU; SUTTER; TEHAMA; TRINITY;

YOLO AND YUBA COUNTIES
Rates Fringes
SOFT FLOOR LAYER.................$ 44.72 24.98
---------------------------------------------------------------- PLAS0300-003 07/01/2018
Rates Fringes

PLASTERER
AREA 295: Alpine, Amador,
Butte, Colusa, El Dorado,
Glenn, Lassen, Modoc,
Nevada, Placer, Plumas,
Sacramento, Shasta,
Sierra, Siskiyou, Solano,
Sutter, Tehema, Trinity,
Yolo & Yuba Counties........$ 32.70 31.68
AREA 355: Marin.............$ 36.73 31.68
AREA 355: Napa & Sonoma
Counties....................$ 32.70 31.68
---------------------------------------------------------------- PLAS0300-005 07/01/2016
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 32.15 23.27
---------------------------------------------------------------- PLUM0038-002 07/01/2022

MARIN AND SONOMA COUNTIES
Rates Fringes
PLUMBER (Plumber,
Steamfitter, Refrigeration
Fitter)
(1) Work on wooden frame
structures 5 stories or
less excluding high-rise
buildings and commercial
work such as hospitals,
prisons, hotels, schools,
casinos, wastewater
treatment plants, and
resarch facilities as well
as refrigeration
pipefitting, service and
repair work - MARKET
RECOVERY RATE...............$ 69.70 46.38
(2) All other work - NEW
CONSTRUCTION RATE...........$ 82.00 48.18
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 197 of 219 ends

---------------------------------------------------------------- PLUM0038-006 07/01/2022

MARIN & SONOMA COUNTIES
Rates Fringes
Landscape/Irrigation Fitter
(Underground/Utility Fitter).....$ 69.70 33.15
---------------------------------------------------------------- PLUM0228-001 01/01/2023

BUTTE, COLUSA, GLENN, LASSEN, MODOC, PLUMAS, SHASTA, SIERRA,

SISKIYOU, SUTTER, TEHAMA, TRINITY & YUBA COUNTIES
Rates Fringes
PLUMBER..........................$ 44.75 37.89
---------------------------------------------------------------- PLUM0343-001 07/01/2022

NAPA AND SOLANO COUNTIES
Rates Fringes

PLUMBER/PIPEFITTER
Light Commercial............$ 30.85 20.40
All Other Work..............$ 58.00 40.48
DEFINITION OF LIGHT COMMERICIAL:

Work shall include strip shopping centers, office buildings, schools and other commercial structures which the total plumbing bid does not exceed Two Hundred and Fifty Thousand ($250,000) and the total heating and cooling does not
exceed Two Hundred Fifty Thousand ($250,000); or Any
projects bid in phases shall not qualify unless the total project is less than Two Hundred Fifty Thousand ($250,000) for the plumbing bid; and Two Hundred Fifty Thousand
($250,000) for the heating and cooling bid. Excluded are hospitals, jails, institutions and industrial projects, regardless size of the project
FOOTNOTES: While fitting galvanized material: $.75 per hour additional. Work from trusses, temporary staging,
unguarded structures 35' from the ground or water: $.75 per hour additional. Work from swinging scaffolds, boatswains chairs or similar devices: $.75 per hour additional.
---------------------------------------------------------------- PLUM0350-001 08/01/2021
EL DORADO COUNTY (Lake Tahoe area only); NEVADA COUNTY (Lake Tahoe area only); AND PLACER COUNTY (Lake Tahoe area only) Rates Fringes
PLUMBER/PIPEFITTER...............$ 47.54 17.11
---------------------------------------------------------------- PLUM0355-001 07/01/2022

ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC,

NAPA, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA,

SISKIYOU, SOLANO, SUTTER, TEHAMA, TRINITY, YOLO, AND YUBA

COUNTIES
Rates Fringes
Underground Utility Worker
/Landscape Fitter...........$ 32.22 17.55
---------------------------------------------------------------- PLUM0442-003 01/01/2023
AMADOR (South of San Joaquin River) and ALPINE COUNTIES Rates Fringes
PLUMBER..........................$ 50.75 35.14
---------------------------------------------------------------- PLUM0447-001 07/01/2022
AMADOR (north of San Joaquin River), EL DORADO (excluding Lake Tahoe area), NEVADA (excluding Lake Tahoe area); PLACER Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 198 of 219 ends

(excluding Lake Tahoe area), SACRAMENTO AND YOLO COUNTIES Rates Fringes

PLUMBER/PIPEFITTER
Journeyman..................$ 58.37 28.00
Light Commercial Work.......$ 36.23 17.72
---------------------------------------------------------------- ROOF0081-006 08/01/2022

MARIN, NAPA, SOLANO AND SONOMA COUNTIES
Rates Fringes
Roofer...........................$ 50.27 20.66
---------------------------------------------------------------- ROOF0081-007 08/01/2022

ALPINE, BUTTE, COLUSA, EL DORADO, GLENN,LASSEN, MODOC, NEVADA,

PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER,

TEHAMA, TRINITY, YOLO, AND YUBA COUNTIES
Rates Fringes
Roofer...........................$ 43.13 19.71
---------------------------------------------------------------- SFCA0483-003 01/01/2023

MARIN, NAPA, SOLANO AND SONOMA COUNTIES
Rates Fringes
SPRINKLER FITTER (Fire
Sprinklers)......................$ 72.59 36.95
---------------------------------------------------------------- SFCA0669-003 01/01/2023

ALPINE, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA,

PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER,

TEHAMA, TRINITY, YOLO AND YUBA COUNTIES
Rates Fringes
SPRINKLER FITTER.................$ 44.36 27.39
---------------------------------------------------------------- SHEE0104-006 06/29/2020

MARIN, NAPA, SOLANO SONOMA & TRINITY COUNTIES
Rates Fringes
Sheet Metal Worker
Mechanical Contracts
$200,000 or less............$ 55.92 45.29
All other work..............$ 64.06 46.83
---------------------------------------------------------------- SHEE0104-009 07/01/2021

AMADOR, COLUSA, EL DORADO, NEVADA, PLACER, SACRAMENTO, SUTTER,

YOLO AND YUBA COUNTIES
Rates Fringes
SHEET METAL WORKER...............$ 47.85 41.90
---------------------------------------------------------------- SHEE0104-010 07/01/2020
AlPINE COUNTY
Rates Fringes
SHEET METAL WORKER...............$ 43.50 37.42
---------------------------------------------------------------- SHEE0104-011 07/01/2020

BUTTE, COLUSA, EL DORADO, GLENN, LASSEN, MODOC, NEVADA, PLACER,

PLUMAS, SACRAMENTO, SHASTA, SIERRA, SISKIYOU, SUTTER, TEHAMA,

YOLO AND YUBA COUNTIES
Rates Fringes
Sheet Metal Worker (Metal
decking and siding only).........$ 44.45 35.55
---------------------------------------------------------------- SHEE0104-014 07/01/2020

MARIN, NAPA, SOLANO, SONOMA AND TRINITY COUNTIES
Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 199 of 219 ends

Rates Fringes
SHEET METAL WORKER (Metal
Decking and Siding only).........$ 44.45 35.55
---------------------------------------------------------------- SHEE0104-019 07/01/2020

BUTTE, GLENN, LASSEN, MODOC, PLUMAS, SHASTA, SIERRA, SISKIYOU

AND TEHAMA COUNTIES
Rates Fringes

SHEET METAL WORKER
Mechanical Jobs $200,000 &
under.......................$ 35.16 35.88
Mechanical Jobs over
$200,000....................$ 46.60 40.21
---------------------------------------------------------------- TEAM0094-001 07/01/2022
Rates Fringes
Truck drivers:

GROUP 1.....................$ 36.95 31.14
GROUP 2.....................$ 37.25 31.14
GROUP 3.....................$ 37.55 31.14
GROUP 4.....................$ 37.90 31.14
GROUP 5.....................$ 38.25 31.14
FOOTNOTES:

Articulated dump truck; Bulk cement spreader (with or without auger); Dumpcrete truck; Skid truck (debris box); Dry
pre-batch concrete mix trucks; Dumpster or similar type; Slurry truck: Use dump truck yardage rate.

Heater planer; Asphalt burner; Scarifier burner; Industrial lift truck (mechanical tailgate); Utility and clean-up
truck: Use appropriate rate for the power unit or the
equipment utilized.

TRUCK DRIVER CLASSIFICATIONS
GROUP 1: Dump trucks, under 6 yds.; Single unit flat rack (2- axle unit); Nipper truck (when flat rack truck is used
appropriate flat rack shall apply); Concrete pump truck (when flat rack truck is used appropriate flat rack shall apply); Concrete pump machine; Fork lift and lift jitneys; Fuel and/or grease truck driver or fuel person; Snow buggy; Steam cleaning; Bus or personhaul driver; Escort or pilot car driver; Pickup truck; Teamster oiler/greaser and/or serviceperson; Hook tender (including loading and
unloading); Team driver; Tool room attendant (refineries) GROUP 2: Dump trucks, 6 yds. and under 8 yds.; Transit
mixers, through 10 yds.; Water trucks, under 7,000 gals.; Jetting trucks, under 7,000 gals.; Single-unit flat rack (3-axle unit); Highbed heavy duty transport; Scissor truck; Rubber-tired muck car (not self-loaded); Rubber-tired truck jumbo; Winch truck and ""A"" frame drivers; Combination winch truck with hoist; Road oil truck or bootperson;
Buggymobile; Ross, Hyster and similar straddle carriers; Small rubber-tired tractor
GROUP 3: Dump trucks, 8 yds. and including 24 yds.; Transit mixers, over 10 yds.; Water trucks, 7,000 gals. and over; Jetting trucks, 7,000 gals. and over; Vacuum trucks under 7500 gals. Trucks towing tilt bed or flat bed pull
trailers; Lowbed heavy duty transport; Heavy duty transport tiller person; Self- propelled street sweeper with
self-contained refuse bin; Boom truck - hydro-lift or
Swedish type extension or retracting crane; P.B. or similar type self-loading truck; Tire repairperson; Combination Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 200 of 219 ends

bootperson and road oiler; Dry distribution truck (A
bootperson when employed on such equipment, shall receive the rate specified for the classification of road oil
trucks or bootperson); Ammonia nitrate distributor, driver and mixer; Snow Go and/or plow
GROUP 4: Dump trucks, over 25 yds. and under 65 yds.; Water pulls - DW 10's, 20's, 21's and other similar equipment when pulling Aqua/pak or water tank trailers; Helicopter pilots (when transporting men and materials); Lowbedk Heavy Duty Transport up to including 7 axles; DW10's, 20's, 21's and other similar Cat type, Terra Cobra, LeTourneau Pulls, Tournorocker, Euclid and similar type equipment when
pulling fuel and/or grease tank trailers or other
miscellaneous trailers; Vacuum Trucks 7500 gals and over and truck repairman
GROUP 5: Dump trucks, 65 yds. and over; Holland hauler; Low bed Heavy Duty Transport over 7 axles
---------------------------------------------------------------- WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
================================================================ Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at
https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
---------------------------------------------------------------- The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this
classification, which in this example would be Plumbers. 0198 Agenda Item Number 10 Agenda Item Number 10
City Council Meeting Packet for February 21, 2023

Page 201 of 219 ends