CITY OF SEBASTOPOL CITY COUNCIL
AGENDA ITEM REPORT FOR MEETING OF: July 2, 2024
=========================================================================================== To: Honorable Mayor and City Councilmembers
From: Don Schwartz, City Manager
Toni Bertolero, P.E., Engineering Consultant, GHD
Subject: Capital Improvement Program (CIP) FY 2024-25 to FY 2028-29 =========================================================================================== RECOMMENDATIONS:

That the Council adopt a resolution approving the Capital Improvement Plan for Fiscal Year 2024-25, and note changes to the CIP, if any.

EXECUTIVE SUMMARY:

The City of Sebastopol Capital Improvement Program (CIP) is a five-year program and the annual Capital Improvement Plan for Fiscal Year 2024-25 is Year 1 of the five-year CIP and outlines public improvements and estimated expenditures to construct improvements.

Thisitem isfor the review of the five-year program and adoption of a Resolution approving the Capital Improvement Plan for Fiscal Year 2024-25 as listed in the Draft CIP Budget Report dated 6/24/24 (Attachment 4). The Fiscal Year 2024-25 Capital Improvement Plan,showing only those projectsin Fiscal Year 2024-25 with proposed expenditures, are also listed (for ease of reference) in the table in the CIP Summary Memo prepared by Toni Bertolero (Attachment 2).

BACKGROUND:

The City adopts an annual budget for capital projects based on the City’s Capital Improvement Program (CIP). These projectsinclude improvementsto city streets, bike paths, crosswalks, water,sewer,storm water infrastructure, City facilities including offices and parks, and City arts. The CIP is a 5-year forecast approved by Council. The projects in the first year, the Capital Improvement Plan, are those proposed to be funded in Fiscal Year 2024-25. The remainder of the projects in the CIP for Fiscal Years 2025-26 through 2028-29 are a tool to project future funding needs and to assist staff in pursuit of grant funding for future projects.

The State of California Government Code Section 65401 requires the City’s Planning Commission review the Fiscal Year 2024-25 Capital Improvement Plan for consistency with the City’s adopted General Plan prior to final adoption by the City Council. The General Plan consistency review was conducted and approved by the Planning Commission on June 25, 2024. If any new projects are added to the CIP, a General Plan consistency review of that project will be needed.

DISCUSSION:

The Budget Committee reviewed the CIP on June 24, 2024. A summary of the committee’s comments as well as responses to the comments are listed below. The Proposed CIP (see Attachment) includes changes recommended by the committee and are noted on the Question/Response list below.

1. Question: Make the CIP Budget report clearer as to which are New projects as compared to carryover projects that are proposed for Fiscal Year 2024-25 so we know what to focus on.

Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 1 of 64 ends

Response: The attached CIP Summary memo (Attachment 2) has the word “NEW” next to the projects. In addition, the CIP Budget report (Attachment 4) shows NEW projects in bold in the Table of Contents in the CIP Budget report.

2. Question: Why is Parquet Street Sewer and Water Improvement Project shown on the table on the CIP Summary memo? Isn’t this project already completed this year? Response: The Administrative Services Director confirmed that although there are retention monies still left to be paid to the Contractor, the monies have already been set aside in Fiscal Year 2023-24. Therefore, the project is now complete and the table in the Summary Memo has been corrected.

3. Question: Why is the pre-construction cost for the Bodega Ave. Bicycle Connection Ragle Rd. to Atascadero Creek project (“Bike connection project”) so much more than the Covert Lane/Zimpher Drive Crossing project (“Ped Crossing project”) if the work in Fiscal Year 2024-25 involves preparing a grant application? Response: The pre-construction cost for the Bike connection project is for the full design and preparation of the grant application for construction. Staff believes that having the design completed, thereby making it “shovel ready,” will make this project more competitive for obtaining a grant. The Ped Crossing project, will be for preparation of a concept plan and grant application. A concept plan is a lower level of effort for engineering work and will be sufficient for being competitive enough for the type of grant that will be pursued (HSIP – highway safety improvement safety grant). The final design for this project will be conducted when a grant is secured.

4. Question: It is unclear what improvements are being proposed for the Bodega Ave. Bicycle Connection Rd. to Atascadero Creek project and if it will conflict with the future traffic signal project at Bodega Avenue and Ragle Road?
Response: The Bike Connection project is a multi-use trail on Bodega Avenue from Ragle Road to Valley View Drive on an existing City planterstrip, and a two-way bike path on the south shoulder of Bodega Avenue between Valley View Drive and connecting to the County bike trail. There will not be a conflict with the future traffic signal at Bodega/Ragle and the design of the Bike Connection project will take into consideration the future traffic signal. A plan/photo of the scope described above can be found in the CIP Budget report (page 5 in the report).

5. Question: What isthe Cultural Community Center Master Plan and why dowe need to spend this money instead of using it for actual repairs and work at the SCCC?
Response: The scope of the master plan would be to take existing information regarding the SCCC for short and long term repairs and mitigations, update as necessary, update or prepare cost estimates, add additional information in terms of order of magnitude level of cost of securing a new facility (not in a flood plain) and upgrading the existing building on the site, including ADA improvements that will be triggered when significant improvements are made. The master plan will serve as a tool for Council to make informed decisions on next steps, short and long term, on the SCCC at its current location.

6. Question: What about the fire improvements that we have heard is needed in order to keep the SCCC building in operation?
Response: The Fire and Building departments have noted that the current operation and use of the SCCC requires that fire-related building improvements be constructed. The estimated cost of the improvements is $70,000.

This is not included in the CIP Budget but is something that will be brought to the full Council for discussion and consideration of inclusion to the CIP. Funding would be from the 2019 flood mitigation earmark.

7. Question: Why is the Ned Kahn artwork taking so long to complete? Response: There were issues with the contractor’s permit and insurance documents and that added to the delay in the completion of this work as well as the currently wet conditions of the soil.

STAFF ANALYSIS:

The Draft Capital Improvement Program (Attachment 4) incorporates recommendations from the Budget Committee. At the budget committee meeting (during the June 24 meeting discussing CIP projects and June 25 meeting discussing the Public Works budget), there was much discussion regarding the Sebastopol Community Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 2 of 64 ends

Cultural Center (SCCC) and what should be done in the short term and the long term. During the meetings, the committee members were split on spending future monies on the SCCC.

Staff has recommended a master plan for the SCCC to look at options to help inform Council as to next steps, particularly long term, for the building. There is an engineering report that looked at structural changes to the building to mitigate forflooding. There is a list ofshort-term improvementsthat can be made to repair flood damage caused by the 2019 flood. There is a requirement from the Fire and Building departments that fire-related building improvements be made to continue the public use of the building. The Building Official has stated that the City must complete fire-related building improvements within 90 days of notice or be shut down for further operation.

Existing work regarding the future outlook for the SCCC building can be included, as well as updating “order of magnitude” cost estimates for various options for short- and long-term improvements and alternatives.

One of the options to consider in the master plan is to review other replacement facilities, not in a flood plain.

The SCCC is in a place where we know flooding will occur again, and there is no feasible way of truly protecting the building. Staff does not believe that FEMA nor anyone else will return with more flood damage monies for the building in the future. There may be buildings in the city that are sizeable and vacant or have the potential for shared use and if that is the case, then that option should be considered in the master plan as an alternative to continued operation at the current site. This alternative should be explored, even if the master plan is not approved.

PUBLIC COMMENT:

As of the writing of this staff report, the City has not received any public comment on this item. However, if staff receives public comment from interested parties following the publication and distribution of thisstaff report, such comments will be provided to the City Council as supplemental materials before or at the meeting. In addition, public comments may be offered during the public comment portion of this item.

COMMUNITY OUTREACH:

This item has been noticed in accordance with the Ralph M. Brown Act and was available for public viewing and review at least 72 hours prior to the scheduled meeting date. A legal notice of the public hearing was advertised in the Press Democrat on June 20, 2024.

FISCAL IMPACT:

The proposed budget and funding sourcesfor the FY 2024-25 can be found on page 3 of the Final CIP report labeled Global Summary Report and is included in Attachment 3 for ease of reference.

Council may choose to reduce the impacts to the General Fund and the Fiscal Year 2024-25 projects listed in Table 1 below are the projects that have General Fund source of funding.

Table 1: FY 2024-25 CIP Projects with General Fund (GF) Impacts CIP no. Project Title GF
Reserve
Potential
Savings Comments
Legend: Fund 103-Buildings/Infrastructure Reserve; Fund 123-Pavement Reserve 0213-20.05 Youth Annex ADA
Upgrades
Fund 103/
$5,000. $2,000.

The reimbursement request, reporting and CDC
coordination are done by GHD. Savings can be made if the work is performed by in-house staff (Management
Analyst) with review by GHD. Due to the recent vacancy in Engineering, this is not recommended.

Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 3 of 64 ends

CIP no. Project Title GF
Reserve
Potential
Savings Comments
0214-20.07 City Hall ADA Upgrades Fund 103/
$20,000.

0. No potential savings since this project has already been significantly reduced in scope and cost savings with PW staff performing the construction. The original adopted FY 23/24 budget showed Fund 103 allocation of $101,500 for construction.
5000213-

22.04 ADA Transition Plan
Building Improvements
Environmental Assess.

Fund 103/
$5,000.
$0. No potential savings since contracts from environmental consultants have already been executed and nearly
complete.
0513-74.09 Bodega Ave. Bike Lanes
and Rehab Phase 1
Fund 123/
$5,000.
$5,000. Funding source can be moved to SB 1 (Fund 217). Existing practice is to use Fund 123 for lower level expenditures and save SB 1 for larger expenditures. Therefore, it is recommended to keep the expenditures in Fund 123.
0514-22.05 Bodega Ave. Bike Lanes
and Rehab Phase 2
Fund 123/
$50,000.
$50,000. Funding source can be moved to SB 1 (Fund 217) but it is recommended to save the SB 1 funds for the larger
expenditures scheduled for FY25/26 and future Citywide
Pavement Program. Therefore, it is recommended to keep
the expenditures in Fund 123.

Total $80,000. $57,000.

OPTIONS:

1. Approve, or do not approve, the Community Cultural Center Master Plan project for $85,000;

2. Add and approve, or do not add and approve, $70,000 for a Fire-related building improvements project at the SCCC to the Fiscal Year 2024-25 Capital Improvement Plan, subject to a General Plan consistency finding;

3. Identify which projects in Table 1, if any, to save General Fund monies by reallocating to other funding sources;

4. Adopt the FY 2024-25 CIP resolution, as recommended by the Budget Committee, and other changes as noted at the budget hearing.

ATTACHMENTS:
1-Resolution
2-CIP Summary Memo
3-Global Summary Report (page 3 from CIP report)
4-Draft CIP FY 2024-25 to FY 2028-29, dated 6/24/24
APPROVALS:

Department Head Approval: Approval Date: 6/26/24
CEQA Determination (Planning): Approval Date: 6/25/24
The adoption of the Resolution and approval of these projects for timing and funding determinations is not an approval of a project under the California Environmental Quality Act (CEQA). The action does not commit the City to a definite course of action with respect to any project listed on the CIP (CEQA Guidelines, Sections 15352 and 15378(b)(4). The projects in the Capital Improvement Plan are consistent with the General Plan.

Administrative Services (Financial) Approval Date: 6/18/24 Costs authorized in City Approved Budget: ☐ Yes ☐ No  N/A Account Code (f applicable) ___________________________ City Attorney Approval: Approval Date: 6/18/24
City Manager Approval: Approval Date: 6/26/24
Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 4 of 64 ends

RESOLUTION NO. ____

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEBASTOPOL APPROVING THE FISCAL YEAR 2024-25 CAPITAL IMPROVEMENT PLAN WHEREAS, the City Council conducted a Public Hearing on July 2, 2024 to consider the five-year Capital Improvement Program (CIP) for Fiscal Years 2024-25 to 2028-29 and Year 1 of the CIP, herein referred to as the Fiscal Year 2024-25 Capital Improvement Plan (Plan); and WHEREAS, the Fiscal Year 2024-25 Plan is a proposed list of priorities of capital projects; and WHEREAS, the State of California Government Code Section 65401 requires the City’s Planning Commission review the Fiscal Year 2024-25 Plan for consistency with the City’s adopted General Plan prior to final adoption by the City Council and said finding was made and approved by the Planning Commission on June 25, 2024.

NOW, THEREFORE BE IT RESOLVED, that the City Council hereby approves and adopts the final Capital Improvement Plan for Fiscal Year 2024-2025 (Plan) and appropriates budget for said Plan, subject to the changes made by City Council and recorded by the City Clerk, during the public hearing on July 2, 2024 as specifically noted below:

1. Approve the Community Cultural Center Master Plan Project in the amount of $85,000.00, from Fund 127, Flood Mitigation.

2. Add and approve $70,000.00 for the SCCC Fire-Related Building Improvements, subject to a General Plan Consistency Finding by the Planning Commission, from Fund 127, Flood Mitigation.

3. [any other changes noted at the public hearing.]
The above and foregoing Resolution was duly passed, approved, and adopted at a meeting by the City Council on the 2nd day of July 2024, by the following vote:

Ayes:

Noes:

Absent:

Abstain:

APPROVED:__________________________
Mayor Diana Gardner Rich
ATTEST: ________________________________________
Mary Gourley, Assistant City Manager / City Clerk, MMC
Approved as to Form: _____________________________________________ City Attorney
Agenda Item Number 6 Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 5 of 64 ends

Memorandum
June 24, 2024
To Don Schwartz, City Manager
Copy to Department Managers
From Toni Bertolero, GHD Tel 707-523-1010
Subject Proposed CIP Budget FY 2024-25 Project no. 12586143 Introduction
The purpose of this memo is to provide a recap of projects completed in Fiscal Year 2023-24 (FY 23/24) and an overview of the proposed Capital Improvement Program (CIP) budget for FY 24/25. It should be noted that the CIP budget is a “living document” and as such, is continuously updated as new information becomes available.

A list of the CIP projects that have been constructed and completed during FY 23/24:
• SR 116 ADA Ramps and Bodega Avenue intersection improvements. The only work left to be done is requesting final reimbursement of the “Quick Strike” grant for completed work and a final report to Caltrans.
• Ives Park Pathway Replacement and ADA upgrade (Segment 1). The pathway replacement from the picnic area, along Calder Creek, to the restroom facility in Ives Park is complete. • Bodega Ave Bike Lanes and Pavement Rehabilitation Phase 1 project. The only work left to be done is requesting final reimbursement of the OBAG 2 grant for completed work and a final report to Caltrans. • Parquet St Sewer, Water and Street improvements project. This work replaces leaky and aging pipes and resurfaces the street affected by the underground improvements.

A table showing proposed CIP projects for FY 24/25 is shown on the next page. A few key highlights:
• The new FY 24-25 projects can be readily found in the table and they are highlighted with the words NEW on the fourth column. They can also be easily seen on the CIP Budget report in the Table of Contents pages and have the word NEW next to the project name in bold font. All other projects are carryover projects and/or approved by Council in previous years. • Staff has been working with SCTA on finalizing funding agreement for the Bodega Ave. Bike Lanes and Pavement Rehab Phase 2 Project for a $2.24 million grant from the “Go Sonoma” grant program. • Two new pedestrian improvements projects near Analy High School are included in FY 24-25. • The CIP projects for the Water and Wastewater systems are consistent with the June 12, 2024 Water Rate Study for Option 2 rate schedule, the lower level of service option. • The Community Cultural Center (SCCC) Master Plan was not approved to move forward by the Budget Committee but is shown in the Draft CIP budget for consideration by the full Council. • Another SCCC project, not included in the CIP, is $70,000 for fire sprinkler improvements. The improvements were discussed at the Budget Committee meeting and will be brought to the full Council for discussion and consideration.

Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 6 of 64 ends

Annual Capital Improvement Plan
Fiscal Year 2024-25
Project
No. Project Name Proposed
Budget New? Comments
Bikes, Pedestrians & Safety Projects
0113-16.00 Bodega Ave. Bicycle Connection Ragle
Rd. to Atascadero Creek $ 50,000 NEW Year 1 work is the design and applying for a grant for theconstruction work. 0131-23.01 Bodega Ave. Guardrails at City Limits $ 369,000 Safety improvements funded by Highway Safety Improvement Program (HSIP) grant from the State.
0132-23.02 SR 116 Enhanced Crossings at Burnett,
Keating, Hutchins, Walker $ 318,950 Design work is currently underway and construction anticipated to occur in Fall 2025. 0133-23.10 Sunset Ave/Taft St Ped Crossing
Enhancements $ 102,960
Construction underway and estimated to be completed in
July/August 2025. This project is funded by Supervisor Lynda Hopkins infrastructure funding grant and a donation from the School District.
0134-24.01 Covert Ln/Zimpher Dr Ped Crossing
Improvements $ 10,000 NEW RRFB flashing beacons at this intersection. Year 1 work is preparing a concept plan and applying for a grant for the construction. 0135-24.02 Sunset Ave/Johnson St Ped Crossing
Enhancements $ 46,700 NEW Year 1 work is the design and applying for a grant for the construction work. 1000-19.01
SR 116 Ramps and Ped Improvements at
Bodega Ave/Florence Ave Crosswalk &
Bodega Ave/Robinson
$ 5,000 The construction is now complete and work left to be done during FY24/25 is preparation of reimbursement package and final report.

CDBG Projects
0213-20.05 Youth Annex ADA Upgrades $ 5,000
Carryover project is nearly complete except for installation of ADA door hardware which is delayed due to supply chain issues. Final work will also include CDBG grant reimbursement request and final report to the CDC.
0214-20.07 City Hall ADA Upgrades $ 65,000 Construction work in FY24/25 will be performed by Public Works staff and estimated to be completed by Spring 2025.
0215-22.04 ADA Transition Plan Building
Improvements Env. Assessment $ 5,000
The environmental assessment work is nearly complete for the accessibility work at City Hall and Burbank Farm restroom project.

The reports are awaiting final approval from the State Historic Preservation Office (SHPO). Once this work is complete, the CDBG funding agreements for the two projects can be prepared by CDC.

Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 7 of 64 ends

Housing Projects
0300-22.07 Purchase of Market Rate Units $ 0
The project is currently unfunded. Planning staff will be applying for CDBG grant funding for the purchase of market rate units for sale on the open market and add deed restrictions for affordability.

Parks Projects
0409-73.00 AmeriCorps Trail Extension $ 414,455
Project design is complete and environmental review and permitting is underway and nearly complete. The project scope is revised to address environmental issues and avoiding impacts. Project construction is estimated to commence in Fall 2025.
0413-78.00 Burbank Farm ADA path and Public
Restroom Facility $ 10,000
Work in FY24/25 includes CDBG quarterly reporting, funding agreement coordination, and applying for additional grant funding (including T-mobile grant in April 2025). Construction is estimated to commence in summer 2026.

Paving Projects
0511-74.09 Bodega Avenue Bike Lanes and
Pavement Rehabilitation Phase 1 $ 5,000 The construction is now complete and work left to be done during FY24/25 is preparation of reimbursement package and final report. 0514-22.06 Bodega Avenue Bike Lanes and
Pavement Rehabilitation Phase 2 $ 50,000
FY24/25 work includes coordination efforts with SCTA for securing Go Sonoma grant, quarterly reporting, and revalidating the environmental review by Caltrans.

Sewer/Wastewater Projects
0604-37.00 Zimpher Creek Sewer Relocation Part 1 -
Covert Lane Rerouting $ 32,000 Carried over from last fiscal year. This is the only sewer project included in the water rate study.

Stormwater Projects
0711-23.05 Flood Resiliency Master Plan $ 170,000 NEW
This master plan document will identify priority CIP projects and will allow the City to pursue grants for funding flood control and flood management improvements that will mitigate flooding along Calder Creek and the Laguna area.
0712-23.08 Community Cultural Center (SCCC)
Master Plan $ 85,000 NEW
This project was also requested last year to develop flood mitigation and flood proofing alternatives and costs for long range flood mitigation projects. This document will assist the City in making long term decision for the future of the SCCC building at its current site, located in a flood zone.

Water Projects
0821-23.09 Water System Master Plan $ 120,000 NEW This project is the only water project included in the water rate study.

Arts Projects
0901 Ned Kahn: "Sebastopol Spires" $ 27,000 Continuation of work.

Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 8 of 64 ends

Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 9 of 64 ends

City of Sebastopol
5-Year Capital Improvement Program
FY 2024-25 to FY 2028-29 DRAFT 6/24/24
All costs shown are in 2024 dollars.

Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 10 of 64 ends

Table of Contents
Table Of Contents 1
Global Summary: Total Category Expenditures / Total Funding Sources 3 1 - Bikes, Pedestrians & Safety 4
Project # Project Page #
0113-16.00 NEW: Bodega Ave. Bicycle Connection Ragle Rd. to Atascadero 5 Creek
0125-20.01 Ragle Road West Side Bicycles and Pedestrian Access 6 0130-22.08 Undergrounding Overhead Utilities 7
0131-23.01 Bodega Avenue Guardrails at City Limits 8
0132-23.02 SR 116 Enhanced Crossings at Burnett, Keating, Hutchins, Walker 9 0133-23.10 Sunset Ave./Taft St. Pedestrian Crossing Enhancements 10 0134-24.01 NEW: Covert Lane/Zimpher Drive Crossing Improvements 11 0135-24.02 NEW: Sunset/Johnson Street Pedestrian Crossing Enhancements 12 0136-24.03 Johnson, Morris, Eddie Lane Crosswalk and Sidewalk Improvements 13 0137-24.04 Signal at Ragle Rd and Bodega Ave 14
1000-19.01 SR 116 Curb Ramps and Crosswalk Safety Improvements at 15 Bodega/Florence and Bodega/Robinson
137-24.05 Covert Lane and Norlee Street Crosswalk ADA Ramps and Pedestrian 16 Crossing Improvements
2 - Transition Plan ADA Projects 17
Project # Project Page #
0213-20.05 Youth Annex ADA Upgrades 18
0214-20.07 City Hall ADA Upgrades 19
0215-22.04 ADA Transition Plan Building Improvements Environmental 20 Assessment
3 - Housing Projects 21
Project # Project Page #
0300-22.07 Purchase of Market Rate Units 22
4 - Parks Projects 23
Project # Project Page #
0411-73.00 AmeriCorps Trail Extension Project 24
0413-78.00 Burbank Farm: ADA path and Public Restroom Facility 25 0416-95.00 Ives Park Pathway Replacement and ADA Upgrade (Segment 1) 26 0420-22.05 Ives Park Master Plan Implementation Phase 2 27 0423-20.10 Trail connection from Tomodachi Park to the west property line 28 0425-23.07 Ives Park Pathway Replacement and ADA Upgrade (Segment 2) 29 1 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 11 of 64 ends

5 - Paving Projects 30
Project # Project Page #
0513-74.09 Bodega Avenue Bike Lanes and Pavement Rehabilitation Phase 1 31 0514-22.06 Bodega Avenue Bike Lanes and Pavement Rehabilitation Phase 2 32 0520-22.09 Citywide Pavement Repairs and Repaving Program 33 6 - Sewer/Wastewater Projects 34
Project # Project Page #
0604-37.00 Zimpher Creek Sewer Relocation Part 1 - Covert Lane Rerouting 35 0610-70.00 Zimpher Creek Sewer Relocation Part 2 - West End 36 0611-80.00 Zimpher Creek Sewer Relocation Part 3 - Repairs at East End 37 0615-21.01 Parquet Street Sewer Line Replacement (combined City project #1000 38 -19.01)
0615-23.04 Sewer System Master Plan Update 39
0616-24.08 Wastewater System Replacement Program 40
7 - Stormwater Projects 41
Project # Project Page #
0701-34.00 Calder Creek Storm Drain and Outfall Maintenance 42 0702-51.00 Zimpher Creek Storm Drain and Outfall Maintenance 43 0710-64.00 Morris Street Outfall Maintenance 44
0711-23.05 NEW: Flood Resiliency Master Plan 45
0712-23.06 NEW: Community Cultural Center Master Plan 46 8 - Water Projects 47
Project # Project Page #
0819-21.01 Parquet Street Water Line Replacement (combined City project #1000 48 -21.01)
0821-23.09 NEW: Water System Master Plan Update 49
0822-24.06 Well 4 Replacement 50
0823-24.07 Water System Replacement Program 51
9 - Arts Projects 52
Project # Project Page #
0901- Ned Kahn: "Sebastopol Spire" 53
0903- City Sponsorship of New Art Project 54
2 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 12 of 64 ends

City of Sebastopol
Global Summary Report
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated

PROJECT CATEGORY EXPENDITURES
1 Bikes, Pedestrians & Safety 783,097 902,610 908,800 1,648,000 455,000 2,250,000 6,164,410 2 Transition Plan ADA Projects 215,000 75,000 75,000
3 Housing Projects 410,500 410,500
4 Parks Projects 232,445 424,455 732,000 60,000 1,216,455 5 Paving Projects 1,464,009 55,000 2,576,000 100,000 500,000 500,000 3,731,000 6 Sewer/Wastewater Projects 530,000 32,000 133,000 637,200 332,000 935,500 2,069,700 7 Stormwater Projects 255,000 165,000 665,000 1,125,000 2,210,000 8 Water Projects 530,000 120,000 700,000 2,900,000 300,000 600,000 4,620,000 9 Arts Projects 3,000 27,000 28,000 55,000
TOTALS 3,757,551 2,301,565 5,242,800 6,010,200 2,712,000 4,285,500 20,552,065

PROJECT FUNDING SOURCES
000 Unfunded 410,500 859,100 3,818,000 1,775,000 2,500,000 9,362,600 001 Grant - Unsecured 595,700 1,095,000 250,000 1,940,700 103 Bldg./Fac./Infr. Reserve 61,785 30,000 30,000
103 B/F/IR - Donations 20,000
123 Pavement Reserve Fund 109,721 55,000 55,000
127 2019 Flood Mitig Earmark 255,000 255,000
201 Measure M Transportation 275,934 136,000 136,000
202 Measure M Parks 137,674 90,000 130,000 220,000
203 Art-In-Lieu Fund 3,000 27,000 28,000 55,000
211 Transp Grant - TDA3 60,380
Transp Grant - Quick Strike
(MTC)
211 476,000
211 Transp Grant - HSIP 528,120 528,120
211 Transp Grant - OBAG2 1,078,354
Transp Grant - District 5 Infra 102,960 102,960
Funding
211 97,040
Transp Grant - Go Sonoma 2,240,000 50,000 2,290,000
(SCTA)
211
212 Park Improvement Fund 207,512 236,800 60,000 504,312 212 Park Improvement (Sonoma Co.) 126,943 126,943
212 Park Improve Fund (Prop 68) 82,771
213 Traffic Impact Fee Fund (TIF) 98,256 209,830 246,000 55,000 510,830 214 Underground Utilities Fee Fund 855
216 Community Dev. Grant (CDBG) 153,215 45,000 138,200 183,200 SB 1 Road Maintenance & 61,700 200,000 100,000 200,000 561,700 Rehab
217 30,566
501 Water Capital Fund 530,000 120,000 300,000 300,000 300,000 600,000 1,620,000 511 Sewer Capital Fund 542,000 32,000 133,000 637,200 332,000 935,500 2,069,700 TOTALS 3,757,551 2,301,565 5,242,800 6,010,200 2,712,000 4,285,500 20,552,065 3 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 13 of 64 ends

PROJECT TITLE
0113-16.00 NEW: Bodega Ave. Bicycle
Connection Ragle Rd. to
Atascadero Creek
50,000 350,000 400,000
0125-20.01 Ragle Road West Side Bicycles
and Pedestrian Access
400,000 2,000,000 2,400,000
0130-22.08 Undergrounding Overhead Utilities 855
0131-23.01 Bodega Avenue Guardrails at City
Limits
1,900 369,000 369,000
0132-23.02 SR 116 Enhanced Crossings at
Burnett, Keating, Hutchins, Walker
20,500 318,950 318,950
0133-23.10 Sunset Ave./Taft St. Pedestrian
Crossing Enhancements
117,040 102,960 102,960
0134-24.01 NEW: Covert Lane/Zimpher Drive
Crossing Improvements
10,000 51,000 245,000 306,000
0135-24.02 NEW: Sunset/Johnson Street
Pedestrian Crossing
Enhancements
46,700 250,700 297,400
0136-24.03 Johnson, Morris, Eddie Lane
Crosswalk and Sidewalk
Improvements
67,100 553,000 620,100
0137-24.04 Signal at Ragle Rd and Bodega
Ave
190,000 850,000 1,040,000
1000-19.01 SR 116 Curb Ramps and
Crosswalk Safety Improvements at
Bodega/Florence and
Bodega/Robinson
642,802 5,000 5,000
137-24.05 Covert Lane and Norlee Street
Crosswalk ADA Ramps and
Pedestrian Crossing
Improvements
55,000 250,000 305,000
783,097 902,610 908,800 1,648,000 455,000 2,250,000 6,164,410 PROJECT FUNDING SOURCES
000 Unfunded 67,100 553,000 350,000 2,000,000 2,970,100 001 Grant - Unsecured 595,700 1,095,000 250,000 1,940,700 103 B/F/IR - Donations 20,000
211 Transp Grant - District 5 Infra
Funding
97,040 102,960 102,960
211 Transp Grant - HSIP 528,120 528,120
211 Transp Grant - Quick Strike (MTC) 476,000
211 Transp Grant - TDA3 60,380
211 Transp Grant - Go Sonoma
(SCTA)
50,000 50,000
213 Traffic Impact Fee Fund (TIF) 98,256 209,830 246,000 55,000 510,830 214 Underground Utilities Fee Fund 855
217 SB 1 Road Maintenance & Rehab 30,566 61,700 61,700
783,097 902,610 908,800 1,648,000 455,000 2,250,000 6,164,410 Category Summary Report
1 - Bikes, Pedestrians & Safety
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated
4 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 14 of 64 ends

Category
Project Bodega Ave. from Ragle to Atascadero
Creek
Bikes, Pedestrians & Safety
Project No: 0113-16.00
Location:

NEW: Bodega Ave. Bicycle Connection Ragle Rd. to Atascadero Creek 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 50,000 50,000
9200 - Construction 350,000 350,000
EXPENDITURE TOTALS 50,000 350,000 400,000
FUNDING SOURCES
001-Grant - Unsecured 345,000 345,000
213-Traffic Impact Fee Fund (TIF) 50,000 5,000 55,000
FUNDING TOTALS 50,000 350,000 400,000
DESCRIPTION:   Bodega Avenue Class I Multi-Use Trail (from Ragle Road to Valley View Drive on existing City planter strip right-of-way), marked two-way bike/ped crossing at intersection with Valley View Drive, and Class IV striped two-way bike facility on south shoulder of Bodega Avenue with raised separator (between Valley View Drive and existing terminus of County trail). The City will be applying for transportation grant funding in year 1.

JUSTIFICATION:   Provides bicycle path connection on Bodega Avenue from Ragle Road to the County bike trail. This bike path is identified in the City's bicycle and pedestrian master plan. Note: Segment between Pleasant Hill Road and Ragle Road will only require new striping and will be done as part of street maintenance striping.

GENERAL PLAN Goals and Policies:   Circulation CIR 2: Maintain and Expand a Safe and Efficient Pedestrian, Bicycle, and Transit Network that Connects Neighborhoods with Key Destinations to Encourage Travel by Non-Automobile Modes while also Improving Public Health. 5 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 15 of 64 ends

Category
Project Bodega Ave., Ragle Road, Mill Station
Rd.

Bikes, Pedestrians & Safety
Project No: 0125-20.01
Location:

Ragle Road West Side Bicycles and Pedestrian Access
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 400,000 400,000
9200 - Construction 2,000,000 2,000,000
EXPENDITURE TOTALS 400,000 2,000,000 2,400,000
FUNDING SOURCES
000-Unfunded 350,000 2,000,000 2,350,000
211-Transp Grant - Go Sonoma (SCTA) 50,000 50,000
FUNDING TOTALS 400,000 2,000,000 2,400,000
DESCRIPTION:

Provide bicycle lanes and sidewalks/pedestrian paths on Ragle Rd - from Bodega Ave to Mill Station Rd; Mill Station Rd - from Ragle Rd to SR 116. This is a joint City/County endeavor. City applied for ATP grant in 2018 and again in 2022 but was not awarded. This project is updated to exclude the bike lanes on Bodega Ave since the City has already completed the segment from High Street to Nelson Way and has secured a grant for the section up to Pleasant Hill Rd. This project is mostly on County right of way (approximately 75%) and the County will take the lead on applying for a grant for this project.

JUSTIFICATION:   Listed as a regional project with SCTA/Measure M Plan, MTC, and CTC. Sonoma County BPAC has programmed $50,000 in their FY 2024-25 TDA Article 3 grant funding towards this project.

GENERAL PLAN Goals and Policies:   Circulation CIR 2: Maintain and Expand a Safe and Efficient Pedestrian, Bicycle, and Transit Network that Connects Neighborhoods with Key Destinations to Encourage Travel by Non-Automobile Modes while also Improving Public Health 6 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 16 of 64 ends

Category
Project Bodega Avenue
Bikes, Pedestrians & Safety
Project No: 0130-22.08
Location:

Undergrounding Overhead Utilities
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 855 0
EXPENDITURE TOTALS 855 0
FUNDING SOURCES
100-General Fund 0
104-Rule 20A Monies PG&E 0
214-Underground Utilities Fee Fund 855 0
FUNDING TOTALS 855 0
DESCRIPTION:   The project is for undergrounding overhead utilities on Petaluma Avenue using Rule 20A  work credits.

JUSTIFICATION:   Due to the high cost of undergrounding and City commitment of local funds to implement the project, the undergrounding project was cancelled by Council at their 9/19/23 meeting. The Rule 20A work credits were transferred to the County of Sonoma for their undergrounding projects.

GENERAL PLAN Goals and Policies:   Community Development CD-14: Continue to require the undergrounding of utility lines wherever feasible.
7 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 17 of 64 ends

Category
Project Bodega Avenue from West End City
Limits to Valley View Dr.

Bikes, Pedestrians & Safety
Project No: 0131-23.01
Location:

Bodega Avenue Guardrails at City Limits
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 1,900 0
9100 - Pre-construction 69,500 69,500
9200 - Construction 299,500 299,500
EXPENDITURE TOTALS 1,900 369,000 369,000
FUNDING SOURCES
211-Transp Grant - HSIP 312,300 312,300
217-SB 1 Road Maintenance & Rehab 1,900 56,700 56,700
FUNDING TOTALS 1,900 369,000 369,000
DESCRIPTION:   Remove existing bridge guardrail and replace approximately 765 lineal feet of guard rail. Work includes replacing signage and related appurtenances. This project is primarily funded with a Highway Safety Improvement Program (HSIP Cycle 11) grant from the State.

JUSTIFICATION:   This segment of guardrail was identified as deficient (e.g. railing too low, outdated guardrail and end treatment systems) and in need of upgrades. This location was identified in the City's Local Road Safety Plan as an area with an increased number of lane departure collisions due to the narrow shoulder. Many vehicles drop off into the creek bed as the existing conditions do not provide adequate conditions for vehicles to recover. There is a significant drop off (around 1 foot) from the pavement to existing grade and unrecoverable side slopes of 2:1.

GENERAL PLAN Goals and Policies:   Circulation CIR 1-9: Consider all transportation improvements as opportunities to improve safety, access, and mobility for all roadway users and avoid dead-end streets and culde-sacs. 8 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 18 of 64 ends

Category
Project S Main/Burnett St; N Main/Keating Ave;
Gravenstein Hwy/Hutchins Ave;
Petaluma Ave/Walker Ave
Bikes, Pedestrians & Safety
Project No: 0132-23.02
Location:

SR 116 Enhanced Crossings at Burnett, Keating, Hutchins, Walker 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 20,500 0
9100 - Pre-construction 14,200 14,200
9200 - Construction 304,750 304,750
EXPENDITURE TOTALS 20,500 318,950 318,950
FUNDING SOURCES
211-Transp Grant - HSIP 215,820 215,820
213-Traffic Impact Fee Fund (TIF) 103,130 103,130
217-SB 1 Road Maintenance & Rehab 20,500 0
FUNDING TOTALS 20,500 318,950 318,950
DESCRIPTION:   Install pedestrian-activated circular LED rapid flashing beacons replacing existing standard flashing beacons; install perimeter lighted pedestrian crossing signs; install pedestrian push buttons; remove existing in-roadway warning lights. This project is primarily funded with a Highway Safety Improvement Program (HSIP Cycle 11) grant from the State.

JUSTIFICATION:   SR 116 Traffic Corridor Safety Study shows these intersections meet warrant threshold for RRFBs.

GENERAL PLAN Goals and Policies:   Circulation CIR 2-2: Routinely incorporate sidewalks and enhanced pedestrian crossing facilities as part of new street construction or enhancements to existing streets. 9 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 19 of 64 ends

Category
Project Sunset Avenue at Taft Street, Analy
High School
Bikes, Pedestrians & Safety
Project No: 0133-23.10
Location:

Sunset Ave./Taft St. Pedestrian Crossing Enhancements
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 117,040 0
9100 - Pre-construction 0
9200 - Construction 102,960 102,960
EXPENDITURE TOTALS 117,040 102,960 102,960
FUNDING SOURCES
103-B/F/IR - Donations 20,000 0
103-Bldg./Fac./Infr. Reserve 0
211-Transp Grant - District 5 Infra Funding 97,040 102,960 102,960 FUNDING TOTALS 117,040 102,960 102,960
DESCRIPTION:   Taft Street/Sunset Avenue – upgrade crosswalk markings including advanced yield markings and install double-sided flashing pedestrian crossing signs with circular LED beacons in similar style to other Sebastopol crossings. Install advanced pedestrian crossing signage. Upgrade curb ramps to comply with current ADA standards. Install edge line striping for traffic calming on Sunset Avenue between Taft Street and Johnson Street
JUSTIFICATION:   The school district requested pedestrian crossing improvements at the two locations to make the crossing safer for students and other pedestrians. The City received infrastructure grant funding from County Supervisor Lynda Hopkins District 5 and the School District is making a $20,000 contribution towards this project.

GENERAL PLAN Goals and Policies:   Circulation CIR 2-2: Routinely incorporate sidewalks and enhanced pedestrian crossing facilities as part of new street construction or enhancements to existing streets. 10 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 20 of 64 ends

Category
Project Covert Lane/Zimpher Drive
Bikes, Pedestrians & Safety
Project No: 0134-24.01
Location:

NEW: Covert Lane/Zimpher Drive Crossing Improvements
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 10,000 51,000 61,000
9200 - Construction 245,000 245,000
EXPENDITURE TOTALS 10,000 51,000 245,000 306,000
FUNDING SOURCES
001-Grant - Unsecured 245,000 245,000
213-Traffic Impact Fee Fund (TIF) 10,000 51,000 61,000
FUNDING TOTALS 10,000 51,000 245,000 306,000
DESCRIPTION:   Install Rapid rectangular flashing beacons (RRFB) at this intersection including minor lane configuration. The City will apply for HSIP cycle 12 grant from the State due Sept 2024. The application will include a concept plan and preliminary estimate.

JUSTIFICATION:   This is needed for pedestrian safety.

GENERAL PLAN Goals and Policies:   Circulation CIR 2-2: Routinely incorporate sidewalks and enhanced pedestrian crossing facilities as part of new street construction or enhancements to existing streets. 11 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 21 of 64 ends

Category
Project Sunset Avenue/Johnson Street
Bikes, Pedestrians & Safety
Project No: 0135-24.02
Location:

NEW: Sunset/Johnson Street Pedestrian Crossing Enhancements 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 46,700 46,700
9200 - Construction 250,700 250,700
EXPENDITURE TOTALS 46,700 250,700 297,400
FUNDING SOURCES
001-Grant - Unsecured 250,700 250,700
201-Measure M Transportation 0
213-Traffic Impact Fee Fund (TIF) 46,700 46,700
FUNDING TOTALS 46,700 250,700 297,400
DESCRIPTION:   Install a new crosswalk on the west leg of Sunset Drive at the intersection with Johnson Street including ADA curb ramps which may require modification of the sidewalk on the southwest corner due to slipe issues. Pedestrian yield markings approaching the crosswalk should also be added.

JUSTIFICATION:   This project is needed for pedestrian safety and will make the crossing safer for Analy HS students and other pedestrians. Staff is researching grant opportunities for this project.

GENERAL PLAN Goals and Policies:   Circulation CIR: Routinely incorporate sidewalks and enhanced pedestrian crossing facilities as part of new street construction or enhancements to existing streets. 12 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 22 of 64 ends

Category
Project Johnson St/Morris St/Edie Ln
Bikes, Pedestrians & Safety
Project No: 0136-24.03
Location:

Johnson, Morris, Eddie Lane Crosswalk and Sidewalk Improvements 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 67,100 67,100
9200 - Construction 553,000 553,000
EXPENDITURE TOTALS 67,100 553,000 620,100
FUNDING SOURCES
000-Unfunded 67,100 553,000 620,100
201-Measure M Transportation 0
FUNDING TOTALS 67,100 553,000 620,100
DESCRIPTION:   Install a new crosswalk on the Johnson St leg of intersection, southwest of Eddie Ln including pedestrian crossing signs, ADA curb ramps,  and pedestrian yield markings, new curb extension on the western corner for placement of the ramps and for potentially serving as an entry/exit point for cyclists separate from vehicle traffic; new sidewalks on west side of Johnson St between the intersection with Eddie Ln to the southerly point where concrete sidewalk begin near the intersection with Sunset Ave.

JUSTIFICATION:   This project is needed for pedestrian safety and to make the intersection safer for students at Analy HS and other pedestrians.

GENERAL PLAN Goals and Policies:   Circulation CIR 2-2: Routinely incorporate sidewalks and enhanced pedestrian crossing facilities as part of new street construction or enhancements to existing streets. 13 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 23 of 64 ends

Category
Project Ragle Rd/Bodega Ave
Bikes, Pedestrians & Safety
Project No: 0137-24.04
Location:

Signal at Ragle Rd and Bodega Ave
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 190,000 190,000
9200 - Construction 850,000 850,000
EXPENDITURE TOTALS 190,000 850,000 1,040,000
FUNDING SOURCES
001-Grant - Unsecured 850,000 850,000
201-Measure M Transportation 0
213-Traffic Impact Fee Fund (TIF) 190,000 190,000
FUNDING TOTALS 190,000 850,000 1,040,000
DESCRIPTION:   New traffic signal at Ragle Road and Bodega Avenue. Staff will be researching HSIP and other grant opportunities to fund this project.

JUSTIFICATION:   This intersection meets traffic warrants for a traffic signal.

GENERAL PLAN Goals and Policies:   Circulation CIR 1-1: Ensure that the City’s circulation network is maintained and improved over time to support buildout of the General Plan in a manner that is consistent with the General Plan Circulation Map
14 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 24 of 64 ends

Category
Project SR 116, Bodega/Florence,
Bodega/Robinson
Bikes, Pedestrians & Safety
Project No: 1000-19.01
Location:

SR 116 Curb Ramps and Crosswalk Safety Improvements at Bodega/Florence and Bodega/Robinson
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 642,802 0
9001 - Construction/Inspection 5,000 5,000
EXPENDITURE TOTALS 642,802 5,000 5,000
FUNDING SOURCES
201-Measure M Transportation 0
211-Transp Grant - Quick Strike (MTC) 476,000 0
211-Transp Grant - TDA3 60,380 0
213-Traffic Impact Fee Fund (TIF) 98,256 0
217-SB 1 Road Maintenance & Rehab 8,166 5,000 5,000
FUNDING TOTALS 642,802 5,000 5,000
DESCRIPTION:   This project was previously listed as 3 separate projects in prior years but has been combined into one project. The work is for ADA-compliant ramps at seven (7) intersections along SR 116 (old CIP#0105-

4.00), crosswalk and safety improvements at Bodega Ave/Florence Ave (old CIP#0117-74.04), and at Bodega Ave/Robinson Rd (old CIP#0119-74.06). Crosswalk and safety improvements include pedestrian-activated beacons, signage, markings and modifcations to the crosswalks. The project is completed but report to Caltrans and grant reimbursement request will occur in July/August 2024.

JUSTIFICATION:   Provide ADA ramps along SR 1116 in accordance with Americans with Disabilities Act (ADA) guidelines. As part of the "Pedestrian Crossing Safety Study for Bodega Avenue" completed in 2017, pedestrian safety improvements were recommended at the intersections on Bodega Avenue at Florence Ave and Robinson Rd.

GENERAL PLAN Goals and Policies:   Circulation CIR 2-7: Create an accessible circulation network that is consistent with guidelines established by ADA, allowing mobility-impaire users such as the disabled and elderly to safely and effectively travel with and beyond the city.

Circulation CIR 2-2: Routinely incorporate sidewalks and enhanced pedestrian crossing facilities as part of new street construction or enhancements to existing streets. 15 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 25 of 64 ends

Category
Project Covert Ln/Norlee St
Bikes, Pedestrians & Safety
Project No: 137-24.05
Location:

Covert Lane and Norlee Street Crosswalk ADA Ramps and Pedestrian Crossing Improvements
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 55,000 55,000
9200 - Construction 250,000 250,000
EXPENDITURE TOTALS 55,000 250,000 305,000
FUNDING SOURCES
001-Grant - Unsecured 250,000 250,000
213-Traffic Impact Fee Fund (TIF) 55,000 55,000
FUNDING TOTALS 55,000 250,000 305,000
DESCRIPTION:   Install pedestrian crossing signs with Rapid Rectangular Flashing Beacons (RRFB), ADA curb ramps and pedestrian yield markings approaching the crosswalk. Staff will be reasearching grant opportunities for this project.

JUSTIFICATION:   This is a pedestrian safety project.

GENERAL PLAN Goals and Policies:   Circulation CIR 2-2: Routinely incorporate sidewalks and enhanced pedestrian crossing facilities as part of new street construction or enhancements to existing streets. 16 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 26 of 64 ends

PROJECT TITLE
0213-20.05 Youth Annex ADA Upgrades 181,000 5,000 5,000 0214-20.07 City Hall ADA Upgrades 7,500 65,000 65,000
0215-22.04 ADA Transition Plan Building
Improvements Environmental
Assessment
26,500 5,000 5,000
215,000 75,000 75,000
PROJECT FUNDING SOURCES
103 Bldg./Fac./Infr. Reserve 61,785 30,000 30,000
216 Community Dev. Grant (CDBG) 153,215 45,000 45,000
215,000 75,000 75,000
Category Summary Report
2 - Transition Plan ADA Projects
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated
17 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 27 of 64 ends

Category
Project Youth Annex ADA Upgrades
Transition Plan ADA Projects
Project No: 0213-20.05
Location:

Youth Annex ADA Upgrades
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 181,000 0
9001 - Construction/Inspection 5,000 5,000
EXPENDITURE TOTALS 181,000 5,000 5,000
FUNDING SOURCES
103-Bldg./Fac./Infr. Reserve 27,785 5,000 5,000
216-Community Dev. Grant (CDBG) 153,215 0
FUNDING TOTALS 181,000 5,000 5,000
DESCRIPTION:   ADA upgrades to the Youth Annex Building. The original work was to include signing, striping, interior door modifications, public fountain upgrade, and bathroom upgrades. Due to the high cost of the project, the work was down scoped to match available funding and the priority of work that will be completed are the exterior ADA site work, signing, striping, and accessibilty to the front door.

JUSTIFICATION:   Continue to construct improvements in accordance with the City's ADA Transition Plan. The City was awarded a CDBG grant in FY 2020-21. The NEPA review has been completed by the Sonoma County CDC and design and construction will occur in FY 2022-23.

GENERAL PLAN Goals and Policies:   Circulation CIR 2-7: Create an accessible circulation network that is consistent with guidelines established by the Americans with Disabilities Act (ADA), allowing mobility-impaired users such as the disabled and elderly to safely and effectively travel within and beyond the city.

Community Services and Facilities CSF 6-19: Recognize and appreciate the value that teens and the local youth provide to the character and vibrancy of the community, and strive to improve services, facilities, and activities available to serve teens and local youth.
18 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 28 of 64 ends

Category
Project City Hall
Transition Plan ADA Projects
Project No: 0214-20.07
Location:

City Hall ADA Upgrades
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 7,500 0
9100 - Pre-construction 0
9200 - Construction 65,000 65,000
EXPENDITURE TOTALS 7,500 65,000 65,000
FUNDING SOURCES
103-Bldg./Fac./Infr. Reserve 7,500 20,000 20,000
216-Community Dev. Grant (CDBG) 45,000 45,000
FUNDING TOTALS 7,500 65,000 65,000
DESCRIPTION:   ADA Upgrades to interior of City Hall. Exterior ADA site improvements have been completed by Public Works and this project will include additional signage. To save costs, Public Works staff will perform the accessibility improvements to the interior of City Hall which includes replacing existing doors, hardware, information board; remove/replace and/or relocate existing wall-hung information stand, existing electrical switches and receptacles, bathroom plumbing modifications, and post access and path of travel signs.

JUSTIFICATION:   Continue to construct improvements in accordance with the City's ADA transition plan.

GENERAL PLAN Goals and Policies:   Circulation CIR 2-7: Create an accessible circulation network that is consistent with guidelines established by the Americans with Disabilities Act (ADA), allowing mobility-impaired users such as the disabled and elderly to safely and effectively travel within and beyond the city.

Community Services and Facilities CSF 1: Provide High Quality Community Services, Facilities, and Infrastructure to All Residents, Businesses, and Visitors in Sebastopol. 19 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 29 of 64 ends

Category
Project Various City Facilities
Transition Plan ADA Projects
Project No: 0215-22.04
Location:

ADA Transition Plan Building Improvements Environmental Assessment 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 26,500 0
9100 - Pre-construction 5,000 5,000
EXPENDITURE TOTALS 26,500 5,000 5,000
FUNDING SOURCES
103-Bldg./Fac./Infr. Reserve 26,500 5,000 5,000
FUNDING TOTALS 26,500 5,000 5,000
DESCRIPTION:   Implementation of the balance of the 2014 ADA Transition Plan. This Environmental Assessment (EA) has since expired and is in need of an update. This first order of work is needed before future CDBG funding agreement is executed for ADA improvements to City Hall and Burbank Farm Restroom Facility.

The environmental work is nearly complete awaiting approval from SHPO which will extend this project completion to August/September 2024.

JUSTIFICATION:   Continued implementation of the 2014 ADA Transition Plan.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 1: Provide high quality community services, facilities, and infrastructure to all residents, businesses, and visitors in Sebastopol. 20 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 30 of 64 ends

PROJECT TITLE
0300-22.07 Purchase of Market Rate Units 410,500 410,500 410,500 410,500
PROJECT FUNDING SOURCES
000 Unfunded 410,500 410,500
410,500 410,500
Category Summary Report
3 - Housing Projects
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated
21 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 31 of 64 ends

Category
Project Various locations in the city
Housing Projects
Project No: 0300-22.07
Location:

Purchase of Market Rate Units
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9002 - Project Management 10,500 10,500
9004 - Property Purchases 400,000 400,000
EXPENDITURE TOTALS 410,500 410,500
FUNDING SOURCES
000-Unfunded 410,500 410,500
001-Grant - Unsecured 0
100-General Fund 0
204-Housing Linkage Fee 0
FUNDING TOTALS 410,500 410,500
DESCRIPTION:   This program is a joint venture with the Sonoma County Housing Land Trust (HLT) to buy market rate units for sale on open market, deed restricting them through the HLT model to ensure affordability at a certain income level in perpetuity, and reselling to a qualifying household.  The program would be funded through a Community Development Block Grant program application for a grant award.

JUSTIFICATION:   This will support the City’s Sixth Cycle Housing Element as well as the current Element’s policy of preserving existing housing stock.

GENERAL PLAN Goals and Policies:   Housing Element Goal B-2 Preserve Housing Resources  -Sebastopol will strive to maintain and preserve existing housing resources, including both affordable and market rate units.

HE Goal B-3 Expand Affordability Housing Opportunities Through the Use of Existing Housing– Sebastopol will consider the feasibility of converting market rate housing units to affordable housing.

HE Policy B-5 Work with nonprofits to determine whether there are opportunities to expand the affordable housing supply by using formerly market rate properties. 22 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 32 of 64 ends

PROJECT TITLE
0411-73.00 AmeriCorps Trail Extension Project 82,745 414,455 414,455 0413-78.00 Burbank Farm: ADA path and
Public Restroom Facility
18,700 10,000 480,000 490,000
0416-95.00 Ives Park Pathway Replacement
and ADA Upgrade (Segment 1)
131,000
0420-22.05 Ives Park Master Plan
Implementation Phase 2
62,000 62,000
0423-20.10 Trail connection from Tomodachi
Park to the west property line
25,000 60,000 85,000
0425-23.07 Ives Park Pathway Replacement
and ADA Upgrade (Segment 2)
165,000 165,000
232,445 424,455 732,000 60,000 1,216,455
PROJECT FUNDING SOURCES
000 Unfunded 227,000 227,000
202 Measure M Parks 137,674 90,000 130,000 220,000
212 Park Improvement Fund 207,512 236,800 60,000 504,312 212 Park Improvement (Sonoma Co.) 126,943 126,943
212 Park Improve Fund (Prop 68) 82,771
216 Community Dev. Grant (CDBG) 138,200 138,200
511 Sewer Capital Fund 12,000
232,445 424,455 732,000 60,000 1,216,455
Category Summary Report
4 - Parks Projects
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated
23 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 33 of 64 ends

Category
Project Laguna Wetlands Preserve
Parks Projects
Project No: 0411-73.00
Location:

AmeriCorps Trail Extension Project
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 82,745 0
9200 - Construction 414,455 414,455
EXPENDITURE TOTALS 82,745 414,455 414,455
FUNDING SOURCES
202-Measure M Parks 82,745 80,000 80,000
212-Park Improvement (Sonoma Co.) 126,943 126,943
212-Park Improvement Fund 207,512 207,512
FUNDING TOTALS 82,745 414,455 414,455
DESCRIPTION:   This trail extension project located in the Laguna Wetlands Preserve from the Sebastopol Lift Station to Sebastopol Avenue. Design and CEQA review are complete and the construction bid documents are being prepared. The project consists of constructing a trail extension, a pedestrian bridge at Zimpher Creek, improvements to the current trail segments, addition of some benches, addition of trail signs, and a rail  entry south of the Community Center parking lot.

JUSTIFICATION:   The project closes a "critical" missing link in the Laguna Preserve trails system. This project would implement several components of the Laguna Preserve Management Plan. A Grant application from the Sonoma County Open Space District was submitted and awarded in late 2019 for this project, and there is a matching grant from the Laguna Foundation as part of the City's required match. The remaining funding will come from the City's parks budget.

GENERAL PLAN Goals and Policies:   Circulation CIR 2: Maintain and Expand a Safe and Efficient Pedestrian, Bicycle, and Transit Network that Connects Neighborhoods with Key Destinations to Encourage Travel by Non-Automobile Modes while also Improving Public Health. 24 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 34 of 64 ends

Category
Project Burbank Farm
Parks Projects
Project No: 0413-78.00
Location:

Burbank Farm: ADA path and Public Restroom Facility
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 18,700 0
9100 - Pre-construction 10,000 10,000
9200 - Construction 480,000 480,000
EXPENDITURE TOTALS 18,700 10,000 480,000 490,000
FUNDING SOURCES
103-Bldg./Fac./Infr. Reserve 0
202-Measure M Parks 18,700 10,000 130,000 140,000
212-Park Improvement Fund 211,800 211,800
216-Community Dev. Grant (CDBG) 138,200 138,200
FUNDING TOTALS 18,700 10,000 480,000 490,000
DESCRIPTION:   This project consists of a new ADA-compliant public restroom facility at the Luther Burbank Experiment Farm and ADA path to the restroom facility from the existing parking lot. The work includes installation of a new sewer, water and electrical services to support the restroom facility. The City was awarded a FY 2022-23 CDBG grant for construction of the new restroom but is not sufficient to cover all the construction costs. Staff will continue to research additional grant funding for this project (such as T-mobile community grant). However, funding source has been identified in order to secure the awarded FY 2022-23 CDBG grant in case additional grant funding does not happen.

JUSTIFICATION:   The existing bathroom in Burbank Farm does not comply with ADA accessibility and needs to be replaced with an ADA-compliant bathroom.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 6-17: Continue to support the West County Museum and the Luther Burbank Experiment Farm.

Community Services and Facilities CSF 2-21: Continue to provide support to local non-profits providing community recreational services on City-owned land operated by the non-profits, including Ives Pool, the Sebastopol Community Cultural Center, and the Burbank Experiment Farm. 25 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 35 of 64 ends

Category
Project Ives Park
Parks Projects
Project No: 0416-95.00
Location:

Ives Park Pathway Replacement and ADA Upgrade (Segment 1) 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 131,000 0
EXPENDITURE TOTALS 131,000 0
FUNDING SOURCES
202-Measure M Parks 36,229 0
212-Park Improve Fund (Prop 68) 82,771 0
511-Sewer Capital Fund 12,000 0
FUNDING TOTALS 131,000 0
DESCRIPTION:   This project is removing and/or replacing the pathway that runs from the southwest picnic area, along Calder Creek, to the restroom facility in the park. A large section of the replaced pathway will be designed to accommodate Public Works service vehicles to access the existing sewer line in the park. Tree removal and replacement work will occur in FY 2021-22 before the pathway construction occurs.

JUSTIFICATION:   Several paved sections are in need of replacement due to potholes, unevenness, and lack of appropriate ADA access.  The pathway is used for access to picnic areas and along the length of the trail, access for music events, playground access, pedestrian travel throughout the park, and for access near High Street where the new sculpture garden is being installed. This project has been modified from original plans to be consistent with the Ives Park Master Plan (Option B).

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 2-2: Ensure park and trail facilities are accessible to various segments of the population including: specific age groups, persons with special physical requirements, and groups interested in particular activities. 26 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 36 of 64 ends

Category
Project Ives Park
Parks Projects
Project No: 0420-22.05
Location:

Ives Park Master Plan Implementation Phase 2
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 62,000 62,000
9200 - Construction 0
EXPENDITURE TOTALS 62,000 62,000
FUNDING SOURCES
000-Unfunded 62,000 62,000
FUNDING TOTALS 62,000 62,000
DESCRIPTION:   Phase 2 is the preliminary engineering and cost estimating for the implementation of the  Ives Park Master Plan. Preliminary engineering and planning work for the Calder Creek re-naturalization includes channel geometry analysis and creek hydraulic modeling, as well as a desktop environmental constraints analysis. An intersection modification plan may be prepared by the City's traffic engineering consultant if Council chooses to modify the intersection at Jewell Ave. and Willow St. This work will provide information for the Phase 3 design work (future) and competitively apply for a grant for the construction.

JUSTIFICATION:   Phase 1 work is a study of the Calder Creek Streambed Re-naturalization at Ives Park (CIP project #0420-20.08) and completed in FY 2021-22. Phase 1 included a hydrology study.  Concept plan options were completed and Council selected Ives Park Master Plan (Option B) and included realignment of Calder Creek.

GENERAL PLAN Goals and Policies:   Conservation and Open Space COS 3-3: Support rehabilitation of any culverted or open existing channelized waterways, as feasible, to remove concrete linings and allow for a connection between the stream channel and the natural water table. Avoid creating additional culverted or open channelized waterways, unless no other alternative is available to protect human health, safety, and welfare. 27 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 37 of 64 ends

Category
Project Tomodachi Park next to Park Village
Parks Projects
Project No: 0423-20.10
Location:

Trail connection from Tomodachi Park to the west property line 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 25,000 25,000
9200 - Construction 60,000 60,000
EXPENDITURE TOTALS 25,000 60,000 85,000
FUNDING SOURCES
212-Park Improvement Fund 25,000 60,000 85,000
FUNDING TOTALS 25,000 60,000 85,000
DESCRIPTION:

Provide a trail connecting Tomodachi Park and the Laguna Preserve to the Rodota Trail extension and downtown areas. This first phase is to prepare a concept design to seek future funding for this project. A new sidewalk has been constructed by the Barlow Townhomes developer that runs from the connector trail across the new 6736 Sebastopol Ave townhome development to the western edge of Park Village. This extension would continue from that point northeast to Tomadachi Park.

JUSTIFICATION:   This trail connection will provide an pedestrian and bicycle access alternative to the sidewalk along Highway 12 from downtown to Tomodachi Park and Park Village.

GENERAL PLAN Goals and Policies:   Circulation CIR 1-2: Ensure that the City’s circulation network is a wellconnected system of streets, roads, sidewalks, multi-use trails, routes, and paths that effectively accommodates vehicular and non-vehicular traffic in a manner that considers the context of surrounding land uses and the needs of all roadway users.
28 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 38 of 64 ends

Category
Project Ives Park
Parks Projects
Project No: 0425-23.07
Location:

Ives Park Pathway Replacement and ADA Upgrade (Segment 2) 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 25,000 25,000
9200 - Construction 140,000 140,000
EXPENDITURE TOTALS 165,000 165,000
FUNDING SOURCES
000-Unfunded 165,000 165,000
202-Measure M Parks 0
FUNDING TOTALS 165,000 165,000
DESCRIPTION:   This project is removing and/or replacing the pathway that runs from the restroom facility along Calder Creek to High Street. Staff will be researching grant opportunities to implement this project.

JUSTIFICATION:   This work will continue the pathway replacement that will be completed under the Segment 1 work which runs from the southwest picnic area to the restroom facility. The design will not commence until after the Ives Park Master Plan Phase 2 is completed to ensure consistency with the plan.

GENERAL PLAN Goals and Policies:   Community Services and facilities CSF 2-2: Ensure park and trail facilities are accessible to various segments of the population including: specific age groups, persons with special physical requirements, and groups interested in particular activities. 29 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 39 of 64 ends

PROJECT TITLE
0513-74.09 Bodega Avenue Bike Lanes and
Pavement Rehabilitation Phase 1
1,441,509 5,000 5,000
0514-22.06 Bodega Avenue Bike Lanes and
Pavement Rehabilitation Phase 2
22,500 50,000 2,576,000 2,626,000
0520-22.09 Citywide Pavement Repairs and
Repaving Program
100,000 500,000 500,000 1,100,000
1,464,009 55,000 2,576,000 100,000 500,000 500,000 3,731,000 PROJECT FUNDING SOURCES
000 Unfunded 300,000 500,000 800,000
123 Pavement Reserve Fund 109,721 55,000 55,000
201 Measure M Transportation 275,934 136,000 136,000
211 Transp Grant - OBAG2 1,078,354
211 Transp Grant - Go Sonoma
(SCTA)
2,240,000 2,240,000
217 SB 1 Road Maintenance & Rehab 200,000 100,000 200,000 500,000 1,464,009 55,000 2,576,000 100,000 500,000 500,000 3,731,000 Category Summary Report
5 - Paving Projects
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated
30 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 40 of 64 ends

Category
Project Bodega Avenue from High Street to
Robinson Rd/Nelson Way
Paving Projects
Project No: 0513-74.09
Location:

Bodega Avenue Bike Lanes and Pavement Rehabilitation Phase 1 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 1,441,509 0
9001 - Construction/Inspection 5,000 5,000
EXPENDITURE TOTALS 1,441,509 5,000 5,000
FUNDING SOURCES
123-Pavement Reserve Fund 87,221 5,000 5,000
201-Measure M Transportation 275,934 0
211-Transp Grant - OBAG2 1,078,354 0
FUNDING TOTALS 1,441,509 5,000 5,000
DESCRIPTION:   Phase1 is for adding bicycle lanes and repaving Bodega Avenue  from High Street to Robinson Road/Nelson Way. Due to funding constraints, this project was split into two phases (High Street to Nelson; Nelson Way to Pleasant Hill). This Phase 1 project includes the installation of bike lanes and pavement resurfacing.The project is complete but there will need to be a final report to Caltrans as well as reimbursement request that will occur July/August 2024.

JUSTIFICATION:   Bodega Avenue paving is deteriorated and needs resurfacing. The City was awarded an OBAG2 grant of up to $1,195,000 for construction with a 11.47% match.

GENERAL PLAN Goals and Policies:   Circulation CIR 1-11: Provide high quality regular maintenance for existing and future transportation facilities including streets, sidewalks, and paths. 31 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 41 of 64 ends

Category
Project Bodega Ave. Nelson/Robinson Rd. to
Pleasant Hill Rd.

Paving Projects
Project No: 0514-22.06
Location:

Bodega Avenue Bike Lanes and Pavement Rehabilitation Phase 2 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 22,500 0
9100 - Pre-construction 50,000 50,000
9200 - Construction 2,576,000 2,576,000
EXPENDITURE TOTALS 22,500 50,000 2,576,000 2,626,000
FUNDING SOURCES
000-Unfunded 0
123-Pavement Reserve Fund 22,500 50,000 50,000
201-Measure M Transportation 136,000 136,000
211-Transp Grant - Go Sonoma (SCTA) 2,240,000 2,240,000 213-Traffic Impact Fee Fund (TIF) 0
217-SB 1 Road Maintenance & Rehab 200,000 200,000
FUNDING TOTALS 22,500 50,000 2,576,000 2,626,000
DESCRIPTION:   Phase 2 is for installing bike lanes and repaving Bodega Avenue from Robinson Rd./Nelson Way to Pleasant Hill Road. Due to funding constraints, this project was split into two phases with Phase 1 being High Street to Robinson/Nelson and Phase 2 continuing on to Pleasant Hill Road. Due to the extremely poor condition of the road in this Phase 2 section, the roadbed will need to be reconstructed rather than overlayed.

Because of the size of the project, a constructibility review and a review of the Engineer's Estimate and necessary modficiations to the Plans are planned for FY 24/25.

JUSTIFICATION:   Bodega Avenue paving is deteriorated and needs resurfacing. The work also includes addition of bicycle lanes along Bodega Avenue. Due to environmental constraints, there may be a short section in front of Burbank Experimental Farm where bicycle sharrows will be painted in lieu of a bike lane. City applied for and awarded a Go Sonoma transportation grant for a maximum amount of $2.24 million for the construction and inspection. The City's minimum local match is 15% of the grant.

GENERAL PLAN Goals and Policies:   Circulation CIR 1-11: Provide high quality regular maintenance for existing and future transportation facilities including streets, sidewalks, and paths. 32 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 42 of 64 ends

Category
Project Various city streets
Paving Projects
Project No: 0520-22.09
Location:

Citywide Pavement Repairs and Repaving Program
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 100,000 100,000
9200 - Construction 500,000 500,000 1,000,000
EXPENDITURE TOTALS 100,000 500,000 500,000 1,100,000
FUNDING SOURCES
000-Unfunded 300,000 500,000 800,000
123-Pavement Reserve Fund 0
217-SB 1 Road Maintenance & Rehab 100,000 200,000 300,000 FUNDING TOTALS 100,000 500,000 500,000 1,100,000
DESCRIPTION:   Repairs, repaving and rehabilitation of various streets. The preliminary list of streets are: Palm Ave., Western Ave., Jewell Ave., Live Oak Ave., South Ave. Strout St., Washington Ave. Other streets may be added based on the City's Pavement Management Program report and Council direction. The final streets to be selected will be prioritized given final funding availability. Staff is continuing to pursue grant funding for this project.

JUSTIFICATION:   The listed streets are based on the City’s 2023 Pavement Management Program and focuses on streets with a very low pavement condition index. The project is  the rehabilitaƟon of various streets in the City with the goal to maintain the City's exisƟng PCI at 55. No planned replacement projects in years 1 and 2 due to Bodega Avenue paving project (phase 1 and 2) in those years.

GENERAL PLAN Goals and Policies:   Circulation CIR 1-11: Provide high quality regular maintenance for existing and future transportation facilities including streets, sidewalks, and paths. 33 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 43 of 64 ends

PROJECT TITLE
0604-37.00 Zimpher Creek Sewer Relocation
Part 1 - Covert Lane Rerouting
32,000 1,000 222,000 255,000
0610-70.00 Zimpher Creek Sewer Relocation
Part 2 - West End
115,200 1,000 604,500 720,700
0611-80.00 Zimpher Creek Sewer Relocation
Part 3 - Repairs at East End
31,000 31,000 62,000
0615-21.01 Parquet Street Sewer Line
Replacement (combined City
project #1000-19.01)
530,000
0615-23.04 Sewer System Master Plan
Update
132,000 132,000
0616-24.08 Wastewater System Replacement
Program
300,000 300,000 300,000 900,000
530,000 32,000 133,000 637,200 332,000 935,500 2,069,700 PROJECT FUNDING SOURCES
511 Sewer Capital Fund 530,000 32,000 133,000 637,200 332,000 935,500 2,069,700 530,000 32,000 133,000 637,200 332,000 935,500 2,069,700 Category Summary Report
6 - Sewer/Wastewater Projects
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated
34 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 44 of 64 ends

Category
Project Zimpher Creek Sewer Line, Covert Lane
to Healdsburg Ave
Sewer/Wastewater Projects
Project No: 0604-37.00
Location:

Zimpher Creek Sewer Relocation Part 1 - Covert Lane Rerouting 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 32,000 1,000 33,000
9200 - Construction 222,000 222,000
EXPENDITURE TOTALS 32,000 1,000 222,000 255,000
FUNDING SOURCES
511-Sewer Capital Fund 32,000 1,000 222,000 255,000
FUNDING TOTALS 32,000 1,000 222,000 255,000
DESCRIPTION:   Reduce flows to the Zimpher Creek sewer main by rerouting the flows from Covert Lane to Healdsburg Avenue. The project consists of a new 8-inch sewer, approximately 250 LF, which allows for gravity flow.

JUSTIFICATION:   The Zimpher Creek sewer line is due for replacement and should be relocated away from the Creek bed. The rerouting to Covert Lane sewer utility will allow for reduced flows to the Zimpher Creek sewer main.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 4-8: Prioritize sewer service improvements to areas within the City that pose a threat to public health and the environment as a result of deficiencies in existing sewer or septic systems.
35 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 45 of 64 ends

Category
Project Zimpher Creek from Zimpher Road to
Murphy Avenue
Sewer/Wastewater Projects
Project No: 0610-70.00
Location:

Zimpher Creek Sewer Relocation Part 2 - West End
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 115,200 1,000 116,200
9200 - Construction 604,500 604,500
EXPENDITURE TOTALS 115,200 1,000 604,500 720,700
FUNDING SOURCES
511-Sewer Capital Fund 115,200 1,000 604,500 720,700
FUNDING TOTALS 115,200 1,000 604,500 720,700
DESCRIPTION:   This project consists of the Zimpher Creek sewer main relocation and/or replacement. Year 1 is to finalize the pre-design and select a project alternative such as cast-in-place (CIPP) or open-cut trenching.

Year 1 budget also includes CCTV reconnaissance. Once an alternative is selected, the design can be performed, with construction commencing in Year 2 and continuing in Year 3. For purposes of this estimate, it is assumed that the CIPP alternative is selected.

JUSTIFICATION:   The Zimpher Creek sewer line is due for replacement and should be relocated away from the Creek bed.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 4-8: Prioritize sewer service improvements to areas within the City that pose a threat to public health and the environment as a result of deficiencies in existing sewer or septic systems.
36 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 46 of 64 ends

Category
Project Zimpher Creek Sewer from Murphy
Avenue to Huntly Street
Sewer/Wastewater Projects
Project No: 0611-80.00
Location:

Zimpher Creek Sewer Relocation Part 3 - Repairs at East End 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 31,000 31,000 62,000
9200 - Construction 0
EXPENDITURE TOTALS 31,000 31,000 62,000
FUNDING SOURCES
511-Sewer Capital Fund 31,000 31,000 62,000
FUNDING TOTALS 31,000 31,000 62,000
DESCRIPTION:   This project consists of repairs to the sewer system along Zimpher Creek east of Murphy Avenue. Repairs include waterproofing of manholes and sewer mains, and replacement of sewer sections of pipe. The first phase is for the pre-design to determine level of repairs and develop preliminary cost estimate.

JUSTIFICATION:   The Zimpher Creek sewer line is due for replacement and should be relocated away from the Creek bed.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 4-8: Prioritize sewer service improvements to areas within the City that pose a threat to public health and the environment as a result of deficiencies in existing sewer or septic systems.
37 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 47 of 64 ends

Category
Project Parquet Street
Sewer/Wastewater Projects
Project No: 0615-21.01
Location:

Parquet Street Sewer Line Replacement (combined City project #1000-19.01) 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 530,000 0
EXPENDITURE TOTALS 530,000 0
FUNDING SOURCES
511-Sewer Capital Fund 530,000 0
FUNDING TOTALS 530,000 0
DESCRIPTION:   Replacement of approximately 850 lineal feet of 6-inch sewer main on Parquet Street. This work includes slurry seal of Parquet Street that is affected by the sewer line replacement work. The work is being completed with the Parquet Street Water Main Replacement project #0818-20.09 JUSTIFICATION:   Replacement of leaking and aged sewer line.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 4-8: Prioritize sewer service improvements to areas within the City that pose a threat to public health and the environment as a result of deficiencies in existing sewer or septic systems.
38 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 48 of 64 ends

Category
Project Citywide
Sewer/Wastewater Projects
Project No: 0615-23.04
Location:

Sewer System Master Plan Update
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 132,000 132,000
EXPENDITURE TOTALS 132,000 132,000
FUNDING SOURCES
511-Sewer Capital Fund 132,000 132,000
FUNDING TOTALS 132,000 132,000
DESCRIPTION:   This project will update the 2005 Sewer System Master Plan. The plan will include system capacity analysis and identify deficiencies in sewer system that could result in sewer overflows. The master plan will identify a Capital Improvement Program to upgrade system deficiencies and will include maintenance repair and replacement projects identified in Public Works' ongoing CCTV investigations.

JUSTIFICATION:   Master plans should be updated every 5 years and the sewer master plan was last updated in 2005.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 1-5: Require development, infrastructure, and long-term planning projects to be consistent with all applicable City infrastructure plans, including the Water Master Plan, the Sabtary Sewer System Utility Master Plan, Stormwater Management Plan and the Capital Improvement Program.
39 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 49 of 64 ends

Category
Project Citywide
Sewer/Wastewater Projects
Project No: 0616-24.08
Location:

Wastewater System Replacement Program
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 45,000 45,000 45,000 135,000
9200 - Construction 255,000 255,000 255,000 765,000
EXPENDITURE TOTALS 300,000 300,000 300,000 900,000
FUNDING SOURCES
511-Sewer Capital Fund 300,000 300,000 300,000 900,000
FUNDING TOTALS 300,000 300,000 300,000 900,000
DESCRIPTION:   This program is the ongoing replacement of sewer lines and related appurtenances.

JUSTIFICATION:   The City's wastewater system is severely aged and needs to be systematically replaced in order to minimize leaks, ruptures and emergency repairs of failing lines.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 1-5: Require development, infrastructure, and long-term planning projects to be consistent with all applicable City infrastructure plans, including the Water Master Plan, the Sanitary Sewer System Utility Master Plan, Stormwater Management Plan, and the Capital Improvement Program.
40 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 50 of 64 ends

PROJECT TITLE
0701-34.00 Calder Creek Storm Drain and
Outfall Maintenance
260,000 1,125,000 1,385,000
0702-51.00 Zimpher Creek Storm Drain and
Outfall Maintenance
75,000 405,000 480,000
0710-64.00 Morris Street Outfall Maintenance 90,000 90,000 0711-23.05 NEW: Flood Resiliency Master
Plan
170,000 170,000
0712-23.06 NEW: Community Cultural Center
Master Plan
85,000 85,000
255,000 165,000 665,000 1,125,000 2,210,000
PROJECT FUNDING SOURCES
000 Unfunded 165,000 665,000 1,125,000 1,955,000
127 2019 Flood Mitig Earmark 255,000 255,000
255,000 165,000 665,000 1,125,000 2,210,000
Category Summary Report
7 - Stormwater  Projects
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated
41 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 51 of 64 ends

Category
Project Calder Creek Storm Drain - Ives Park to
Joe Rodota trail
Stormwater  Projects
Project No: 0701-34.00
Location:

Calder Creek Storm Drain and Outfall Maintenance
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 260,000 260,000
9200 - Construction 1,125,000 1,125,000
EXPENDITURE TOTALS 260,000 1,125,000 1,385,000
FUNDING SOURCES
000-Unfunded 260,000 1,125,000 1,385,000
100-General Fund 0
127-2019 Flood Mitig Earmark 0
FUNDING TOTALS 260,000 1,125,000 1,385,000
DESCRIPTION:    This project is a multi-year effort including a Maintenance Study to identify the maintenance activities for the storm drain and outfall, priorities, and estimated costs. A "desktop" environmental analysis is being conducted in FY 22/23 to help inform the environmental constraints. FY 23/24 is the commencement of the CEQA documentation and preparation of the cost estimate that will be needed to research grant funding.

The permitting and construction will be started in FY 24/25, assuming the grant funding is secured.

JUSTIFICATION:   The City maintains a storm drain system on Calder Creek between Ives Memorial Park and a storm drain outfall just past Petaluma Avenue near the Joe Rodota Trail. The Calder Creek drainage system conveys stormwater to the Laguna and is nearly silted up. Multiple permits are required in order to do any work in the waterway. The City has stormwater outfalls and Calder Creek is the highest priority for maintenance.

GENERAL PLAN Goals and Policies:   Safety SA 2-6: Maintain unobstructed water flow in the storm drainage system.
42 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 52 of 64 ends

Category
Project Brookhaven and Zimpher Creek
Stormwater  Projects
Project No: 0702-51.00
Location:

Zimpher Creek Storm Drain and Outfall Maintenance
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 75,000 80,000 155,000
9200 - Construction 325,000 325,000
EXPENDITURE TOTALS 75,000 405,000 480,000
FUNDING SOURCES
000-Unfunded 75,000 405,000 480,000
100-General Fund 0
127-2019 Flood Mitig Earmark 0
FUNDING TOTALS 75,000 405,000 480,000
DESCRIPTION:   This project is a multi-year effort including a Maintenance Study to identify the maintenance activities for the storm drain and outfall, priorities, and estimated costs. A "desktop" environmental analysis is being conducted in FY 22/23 to help inform the environmental constraints. FY 23/24 is the commencement of the CEQA documentation. The preparation of the cost estimate that will be needed to research grant funding will be conducted in FY 24/25. The permitting and construction will be started in FY 25/26, assuming the grant funding is secured.

JUSTIFICATION:   Zimpher Creek outfall is silted in and needs maintenance. Upstream of the outfall is the Valentine Avenue storm drain and that section of pipe is also silted in and some sections may need repair or replacement.

GENERAL PLAN Goals and Policies:   Safety SA 2-6: Maintain unobstructed water flow in the storm drainage system.
43 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 53 of 64 ends

Category
Project Morris Street near the Laguna
Stormwater  Projects
Project No: 0710-64.00
Location:

Morris Street Outfall Maintenance
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 90,000 90,000
9200 - Construction 0
EXPENDITURE TOTALS 90,000 90,000
FUNDING SOURCES
000-Unfunded 90,000 90,000
100-General Fund 0
127-2019 Flood Mitig Earmark 0
FUNDING TOTALS 90,000 90,000
DESCRIPTION:   This project is a multi-year effort starting with a Maintenance Study to identify the maintenance for the storm drain and outfall, priorities, and estimated costs. Future permit and maintenance costs will be identified when the Maintenance Study is completed.

JUSTIFICATION:   The Morris Street outfall is obstructed by silt and vegetation which require cleaning and possible rehabilitation.

GENERAL PLAN Goals and Policies:   Safety SA 2-6: Maintain unobstructed water flow in the storm drainage system.
44 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 54 of 64 ends

Category
Project Citywide
Stormwater  Projects
Project No: 0711-23.05
Location:

NEW: Flood Resiliency Master Plan
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 170,000 170,000
EXPENDITURE TOTALS 170,000 170,000
FUNDING SOURCES
127-2019 Flood Mitig Earmark 170,000 170,000
FUNDING TOTALS 170,000 170,000
DESCRIPTION:   This master plan document is a flood control management plan that will identify flood areas and develop a Capital Improvement Program (CIP) for managing and mitigating flooding that occurs in the Calder Creek and the Laguna area. This plan would expand the 2D hydraulic and hydroloy model developed for Calder Creek to other parts of the City using the existing storm drain mapping. The plan would need to apply the new Sonoma Water Hydrology standards.

JUSTIFICATION:   Various areas routinely flood, particularly along Calder Creek and the Laguna area. This work will help support future grant funding applications for flood control and mitigation projects.

GENERAL PLAN Goals and Policies:   Safety SA-2: Reduce risks to human life, property and public services associated with flood hazards.
45 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 55 of 64 ends

Category
Project 390 Morris St.

Stormwater  Projects
Project No: 0712-23.06
Location:

NEW: Community Cultural Center Master Plan
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 85,000 85,000
EXPENDITURE TOTALS 85,000 85,000
FUNDING SOURCES
127-2019 Flood Mitig Earmark 85,000 85,000
FUNDING TOTALS 85,000 85,000
DESCRIPTION:   The master plan will consider flood mitigation and flood proofing alternatives and costs for long range flood mitigation projects. The plan will also include a list of short term flood repairs from previous flood damages to continue to keep the existing building operational.

JUSTIFICATION:   The Sebastopol Community Cultural Center Master Plan (SCCC) is located in a floodplain and routinely floods. The plan will serve as a long range master plan to determine alternatives such as long term flood mitigation improvements or relocating to a different location not in a floodplain.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 6-16: Support improvements to, expansion of, or replacement of the Sebastopol Community Cultural Center to address floodissues, and to improve services and facilities available to the community in order to enhance the quality of life for all Cityresidents through the provision of quality community services and facilities. 46 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 56 of 64 ends

PROJECT TITLE
0819-21.01 Parquet Street Water Line
Replacement (combined City
project #1000-21.01)
530,000
0821-23.09 NEW: Water System Master Plan
Update
120,000 120,000
0822-24.06 Well 4 Replacement 400,000 2,600,000 3,000,000 0823-24.07 Water System Replacement
Program
300,000 300,000 300,000 600,000 1,500,000
530,000 120,000 700,000 2,900,000 300,000 600,000 4,620,000 PROJECT FUNDING SOURCES
000 Unfunded 400,000 2,600,000 3,000,000
501 Water Capital Fund 530,000 120,000 300,000 300,000 300,000 600,000 1,620,000 530,000 120,000 700,000 2,900,000 300,000 600,000 4,620,000 Category Summary Report
8 - Water Projects
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated
47 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 57 of 64 ends

Category
Project Parquet Street
Water Projects
Project No: 0819-21.01
Location:

Parquet Street Water Line Replacement (combined City project #1000-21.01) 2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 530,000 0
EXPENDITURE TOTALS 530,000 0
FUNDING SOURCES
501-Water Capital Fund 530,000 0
FUNDING TOTALS 530,000 0
DESCRIPTION:   Replace approximately 800 lineal feet of 6-inch water line on Parquet Street. This work includes slurry seal of Parquet Street that is affected by the water line replacement work. The work is being completed with the Parquet Street Sewer Line Replacement project #0615-21.01).

JUSTIFICATION:   Replace leaking water lines and lead services.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 1-5: Require development, infrastructure, and long-term planning projects to be consistent with all applicable City infrastructure plans, including the Water Master Plan, the Sanitary Sewer System Utility Master Plan, Stormwater Management Plan, and the Capital Improvement Program.
48 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 58 of 64 ends

Category
Project Citywide
Water Projects
Project No: 0821-23.09
Location:

NEW: Water System Master Plan Update
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 120,000 120,000
EXPENDITURE TOTALS 120,000 120,000
FUNDING SOURCES
501-Water Capital Fund 120,000 120,000
FUNDING TOTALS 120,000 120,000
DESCRIPTION:   This project will update the 2005 Water System Master Plan. The plan will include a hydraulic modeling and system capacity analysis for the entire city and identify a Capital Improvement Program to upgrade system deficiencies.

JUSTIFICATION:   Master plans should be updated every 5 years and the water master plan was last conducted in 2005.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 1-5: Require development, infrastructure, and long-term planning projects to be consistent with all applicable City infrastructure plans, including the Water Master Plan, the Sanitary Sewer System Utility Master Plan, Stormwater Management Plan and the Capital Improvement Program.
49 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 59 of 64 ends

Category
Project Petaluma Avenue at Palm Avenue
Water Projects
Project No: 0822-24.06
Location:

Well 4 Replacement
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 400,000 400,000
9200 - Construction 2,600,000 2,600,000
EXPENDITURE TOTALS 400,000 2,600,000 3,000,000
FUNDING SOURCES
000-Unfunded 400,000 2,600,000 3,000,000
501-Water Capital Fund 0
FUNDING TOTALS 400,000 2,600,000 3,000,000
DESCRIPTION:   Replacement of the City's municipal Well #4 that has groundwater that has been contaminated and is required to be replaced. The City will be looking for outside financing (such as a revenue bond) for this project.

JUSTIFICATION:   The well is currently being treated using a carbon filter system but this is only a temporary solution and the well will need to be replaced. The well currently provide drinking water to approximately half the city's population.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 1-5: Require development, infrastructure, and long-term planning projects to be consistent with all applicable City infrastructure plans, including the Water Master Plan, and the Capital Improvement Program. 50 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 60 of 64 ends

Category
Project Citywide
Water Projects
Project No: 0823-24.07
Location:

Water System Replacement Program
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9100 - Pre-construction 40,000 40,000 40,000 90,000 210,000 9200 - Construction 260,000 260,000 260,000 510,000 1,290,000 EXPENDITURE TOTALS 300,000 300,000 300,000 600,000 1,500,000 FUNDING SOURCES
501-Water Capital Fund 300,000 300,000 300,000 600,000 1,500,000 FUNDING TOTALS 300,000 300,000 300,000 600,000 1,500,000 DESCRIPTION:   This program is the ongoing replacement of water lines and related appurtenances.

JUSTIFICATION:   The City's water system is severely aged and needs to be systematically replaced in order to minimize leaks, ruptures and emergency repairs of failing lines.

GENERAL PLAN Goals and Policies:   Community Services and Facilities CSF 1-5: Require development, infrastructure, and long-term planning projects to be consistent with all applicable City infrastructure plans, including the Water Master Plan, the Sanitary Sewer System Utility Master Plan, Stormwater Management Plan, and the Capital Improvement Program.
51 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 61 of 64 ends

PROJECT TITLE
0901- Ned Kahn: "Sebastopol Spire" 3,000 27,000 27,000
0903- City Sponsorship of New Art
Project
28,000 28,000
3,000 27,000 28,000 55,000
PROJECT FUNDING SOURCES
203 Art-In-Lieu Fund 3,000 27,000 28,000 55,000
3,000 27,000 28,000 55,000
Category Summary Report
9 - Arts Projects
2024-25 2025-26 2026-27 2027-28 2028-29 TOTALS
FY23-24
Estimated
52 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 62 of 64 ends

Category
Project Laguna Preserve
Arts Projects
Project No: 0901-
Location:

Ned Kahn: "Sebastopol Spire"
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9000 - Estimated Actual 3,000 0
9200 - Construction 27,000 27,000
EXPENDITURE TOTALS 3,000 27,000 27,000
FUNDING SOURCES
203-Art-In-Lieu Fund 3,000 27,000 27,000
FUNDING TOTALS 3,000 27,000 27,000
DESCRIPTION:   The Ned Kahn artwork "Sebastopol Spire" will be located along the Americorp Trail extension north of Sebastopol Avenue at the eastern entry to the City.  In the prior year, Council authorized a budget of $52,000 for this artwork to include $45,000 for the Ned Kahn "Sebastopol Spire" art piece.

JUSTIFICATION:   The funding for this project comes from the City's dedicated Art In-Lieu Fund, his public art piece will be paid for through dedicated Art In-Lieu Fund, and implements the City's Art in the community program.

GENERAL PLAN Goals and Policies:   Community Design CD 4-6: Increase the presence of art in public spaces throughout the city.
53 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 63 of 64 ends

Category
Project To be determined
Arts Projects
Project No: 0903-
Location:

City Sponsorship of New Art Project
2024-25 2025-26 2026-27 2028-29

PROJECT
TOTAL

EXPENDITURES
(Thousands of Dollars)
2027-28
FY23-24
Estimated
9200 - Construction 28,000 28,000
EXPENDITURE TOTALS 28,000 28,000
FUNDING SOURCES
000-Unfunded 0
203-Art-In-Lieu Fund 28,000 28,000
FUNDING TOTALS 28,000 28,000
DESCRIPTION:

This project's  Year 1 funding would provide funds to support the Public Art Committee's development of a new "call for artists" for a new public art piece, including advertising/outreach, and honorariums for the finalists in the selection process. It is anticipated that the art project would be commissioned in Year 2. The cost is not yet known and therefore "TBD" is shown in FY 2023-24.

JUSTIFICATION:   The funding for this project comes from the City's dedicated Art In-Lieu Fund and this public art piece will be paid for through dedicated Art In-Lieu Fund, and implements the City's Art in the community program.

GENERAL PLAN Goals and Policies:   Community Design CD 4-6: Increase the presence of art in public spaces throughout the city.
54 Agenda Item Number 6
Agenda Item Number 6
City Council Meeting Packet for July 2, 2024

Page 64 of 64 ends