June 2025
Building Department Activity Report
[email protected]
Monthly Statistics
30 Building permits issued
31 Contractor’s business licenses issued
$35,227.10 Building permit fees collected
Impact fees – none collected this month
Noteworthy Information
1. Canopy project is finally fully underway with foundation work expected early July and framing to begin by late July.
2. Gravenstein Commons expected to begin construction in early July. Looks as if we have smoothed over all the obstacles and am told permit fees will be paid early July.
3. Continued meeting with the Barlow Hotel Folks on some value engineering. They are attempting to lower overall costs on the construction of the building without sacrificing any code or esthetics for the building.
4. We have had some inquires about the empty parcel next to Big-O-Tire about the possibility of putting a commercial project on site. Nothing definitive yet, but at least some pre-liminary discussions.