DATE: December 10, 2025
TO: Mary Gourley| City Manager
City of Sebastopol | 7120 Bodega Avenue | Sebastopol, CA 95472 Email: [email protected]
SUBJECT: Gravenstein Commons Progress Report
PROJECT SCHEDULE UPDATE
• Construction percentage complete: 17%
• Fire Sprinkler plans approved
• Site work continues with underground plumbing testing and inspections going smoothly • Foundations pouring started (see photo)
PROJECT FINANCIALS
Construction Accounts: $5,304,591.93
Construction Contract Sum to Date: $7,589,383
Lines of Credit available as backstop while other funding is secured : $2,091,641 Private fundraising: $497,578 committed, $771,778 in pending requests Other funding currently being sought: $1,000,000 Measure O (awards out 12/26/25) + PLHA $550,000
PROGRESS PHOTO