DATE: March 3, 2026
TO: Mary Gourley| City Manager
City of Sebastopol | 7120 Bodega Avenue | Sebastopol, CA 95472 Email: [email protected]
SUBJECT: Gravenstein Commons Progress Report

PROJECT SCHEDULE UPDATE
• Construction percentage complete: 50%
• Framing, Roof trusses, and sheathing install continue. Electrical started • Permanent Supportive Housing Standards under development through DHS Working Group • Community update in Spring

HOMEKEY COMPLIANCE (HCD) UPDATE
• Milestone Extension Request – Approved
• HCD Annual Report due March 31, 2026

PROJECT FINANCIALS
Construction Accounts: $ 3,921,756
Construction Contract Sum to Date: $ 7,709,561 Total Complete to Date: $ 3,083,666 Lines of Credit available as backstop while other funding is secured: $2,091,641 Private fundraising: $856,500 awarded or received
Funding Awarded: $1,000,000 Measure O, PLHA request: $200,000 Other funding currently being sought: 1,700,000 future NOFAs

PROGRESS PHOTO