July 2026
Building Department AcƟvity Report
Steve Brown
[email protected]
Monthly StaƟsƟcs
32 Building Permits Issued
19 Contractor’s Business Licenses Issued
$58,215.35 Building Permit Fees Collected
$436,317.00 Building Permit ValuaƟon
$41,460.05 Impact fees
Noteworthy InformaƟon:
Canopy: 27 total permits issued to date. All foundaƟons have been poured for the 27 units and four (Models) have been completed and finaled. Remaining 23 issued permits are in some stage between being framed and almost complete. 13 permits to sƟll be pulled in phase one. Currently PG&E has not yet provided power so move in may slip based on power availability. Work is progressing on second phase ground/street/uƟlity for the remaining 40 units. Underground uƟliƟes are in with curb/guƩer/sidewalk installaƟon in progress. AnƟcipated compleƟon of infrastructure for second phase by late September.
Huntley Square: Project is moving forward with all ten foundaƟons poured and ready to start framing. UƟliƟes have been completed with work moving forward on the front street improvements. AnƟcipaƟng front improvements completed by early October, including new sidewalk.
Habitat: Project nearing compleƟon but we are not expecƟng move-in unƟl September. First two units finaled today, remaining two are looking for the final next week. There is sƟll some outside work to complete before ready for move-in.
There is fed money in the project and the financing/paperwork through the fed agency is lengthy. These are ownership units
Gravenstein Commons: Units are rapping up with most units ready for final. SƟll have a good amount of outside work to complete before final sign-off.
Landscaping has started, and driveways and parking conƟnue. ExpecƟng compleƟon at the end of September or early October.