STATE ROUTE 99 SELMA TO FOWLER
REHABILITATION PROJECT
McCall Avenue Undercrossing,
Selma to Merced Street
Undercrossing, Fowler
SCOPE OF WORK & SCHEDULE
• Limits of Work from McCall Avenue Undercrossing, Selma to Merced Street Undercrossing, Fowler
• Start of Construction July 2021
• Estimated Completion January 2024
• North Half of Project in the City of Fowler is Constructed • Stage 5 (Phases 1-3) and Stage 6 (Phase 1-2)
STAGE 5
PHASE 1 (2 to 3 Week Duration)
Place K-Rail and Restripe NB and SB Lanes
Remove Sections of Concrete Barrier, Sign Structure and Footing Near Second Street Replace Pavement and Concrete Barrier
No Ramps Closed in this Phase of Construction
PHASE 2 (2 to 3 Month Duration)
Place K-Rail and Restripe NB and SB Lanes
NB Lanes #1 and #2 Crossover Median into SB Inside Shoulder SB Lanes Merge from 3 Lanes to 2 Lanes
NB Off-Ramp to Rte 43/Floral Ave. Closed this Phase of Construction NB On-Ramp from Floral Ave. Closed this Phase of Construction Message Board NB99 Directing Trucks to Exit at Mountain View Ave Exit Remove and Replace Existing Pavement
Open Ramps Prior to Moving into the Next Phase of Construction PHASE 3 (2 Month Duration)
Place K-Rail and Restripe NB Ramps
NB On-Ramp from NB Rte 43 Closed this Phase of Construction NB On-Ramp from Second Street Closed this Phase of Construction Remove and Replace Existing Pavement
Open Ramps Prior to Moving into Stage 6
STAGE 5
DETOUR MAP
STAGE 6
PHASE 1 (2 to 3 Month Duration)
Place K-Rail and Restripe NB and SB Lanes
SB On-Ramp from Rte 43/Floral Ave. Closed this Phase of Construction SB Off-Ramp to Second Street Closed this Phase of Construction SB Lanes #1 and #2 Crossover Median into NB Inside Shoulder NB Lanes Merge from 3 lanes to 2 lanes
Remove and Replace Existing Pavement
Open Ramps Prior to Moving into the next Phase of Construction PHASE 2 (2 Month Duration)
Place K-Rail and Restripe SB Ramps
SB Off-Ramp to SB Rte 43 Closed this Phase of Construction SB Off-Ramp to Floral Ave. Closed this Phase of Construction Remove and Replace Existing Pavement
Restripe at NB and SB Lanes and Open Ramps
STAGE 6
DETOUR MAP
PROJECT SCHEDULE
BEGIN STAGE 5 CONSTRUCTION
Scheduled to Start on 04/02/2023 (Weather Permitting)
END STAGE 5 CONSTRUCTION
End Tentatively in August 2023
TRAFFIC MANAGEMENT
1. Truck Mounted Portable Changeable Message Signs.
2. Automated End of Que System. Sensors at 4 set distance apart.
Detects traffic speed and automatically provides warning messages. “Work Ahead”, “Slow Down”, “Traffic Stopped”
3. Towing Service
4. Temporary Lighting at ramps.
5. Partnering with CHP through COZEEP
PROJECT OUTREACH
CAMPAIGN
• Project progress will be
shared via project
website
• Public Affairs will
continue to
communicate with city
staff in Selma.
• Commuter Alerts for
major ramp closures
THANK YOU
THIS CONCLUDES OUR
PRESENTATION
Contact:
Elizabeth Yelton (559) 916-8183
SR 99 Selma to Fowler Rehab
Project website:
https://dot.ca.gov/caltrans-nearme/district-6/district-6-projects/06- 0u420