55728.00300\33360134.1
i SECTION 00010
TABLE OF CONTENTS
CITY OF SIGNAL HILL
WATER SERVICES AND VALVE REPLACEMENTS
PHASE II
PW 95.18012
55728.00300\33360134.1
i SECTION 00010
TABLE OF CONTENTS
SECTION 00010
TABLE OF CONTENTS
Page
SECTION 00010 TABLE OF CONTENTS................................................................................... I SECTION 00100 NOTICE INVITING BIDS ................................................................................ 1 SECTION 00200 INSTRUCTIONS TO BIDDERS...................................................................... 3 SECTION 00400 BID FORM.....................................................................................................11 SECTION 00405 CONTRACTOR’S CERTIFICATE REGARDING WORKERS’ COMPENSATION.....................................................................................................................13 SECTION 00410 BID BOND.....................................................................................................14 SECTION 00420 NONCOLLUSION DECLARATION................................................................16 SECTION 00430 CONTRACTOR INFORMATION AND EXPERIENCE FORM........................17 SECTION 00440 LIST OF SUBCONTRACTORS FORM..........................................................24 SECTION 00450 IRAN CONTRACTING ACT CERTIFICATION...............................................27 SECTION 00460 PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION..........28 SECTION 00500 CONTRACT ..................................................................................................29 SECTION 00610 PERFORMANCE BOND ...............................................................................32 SECTION 00620 PAYMENT BOND..........................................................................................36 SECTION 00700 GENERAL CONDITIONS..............................................................................40 SECTION 00750 SPECIAL CONDITIONS................................................................................81 APPENDIX INSURANCE REQUIREMENTS ............................................................................85 55728.00300\33360134.1
1 SECTION 00100
NOTICE INVITING BIDS
SECTION 00100
NOTICE INVITING BIDS
The City of Signal Hill (“City”) will receive electronic bids only for the Water Services and Valve Replacements Phase II Project, no later than 10:00 AM on April 11th, 2022. he electronic bid management system will not accept late bids. Bids shall be valid for 90 calendar days after the bid opening date.
Bids must be submitted on City’s Bid Forms, available to registered vendors through the City’s electronic bid management system, PlanetBids, at:
https://pbsystem.planetbids.com/portal/36746/bo/bo-detail/90301 Contract Documents may be downloaded at no charge. Electronic modifications to or withdrawal of bids may be made by the bidder prior to the bid closing deadline. Contract Documents will not be available for sale at City Hall.
Plan rooms that register may also download the contract documents and offer them for review.
All parties downloading Contract Documents will be listed under the solicitation’s “Prospective Bidders” tab.
A non-mandatory Pre-Bid Conference will be held at 2550 Cherry Ave, Signal Hill, CA 90755 on the following date(s) and time(s): March 23rd, 2022 at 11:00 AM. Each and every Bidder is encouraged to attend the Pre-Bid Conference. Prospective bidders may visit the Project locations without making arrangements; however, they may not open the meter boxes and may not cause disturbances to the residents or businesses. Bids will be accepted from any bidder who did not attend the Pre-Bid Conference.
Bids must be accompanied by cash, a certified or cashier’s check, or a Bid Bond in favor of the City in an amount not less than ten percent (10%) of the submitted Total Bid Price.
The successful bidder will be required to furnish City with a Performance Bond equal to 100% of the successful bid, and a Payment Bond equal to 100% of the successful bid, prior to execution of the Contract. All bonds are to be secured from a surety that meets all of the State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120, and is admitted by the State of California.
Pursuant to Public Contract Code Section 22300, the successful bidder may substitute certain securities for funds withheld by City to ensure his performance under the Contract.
The Director of Industrial Relations has determined the general prevailing rate of per diem wages in the locality in which this work is to be performed for each craft or type of worker needed to execute the Contract which will be awarded to the successful bidder, copies of which are on file and will be made available to any interested party upon request at Signal Hill Public Works Department or online at http://www.dir.ca.gov/dlsr. A copy of these rates shall be posted by the successful bidder at the job site. The successful bidder and all subcontractor(s) under him, shall comply with all applicable Labor Code provisions, which include, but are not limited to the payment of not less than the required prevailing rates to all workers employed by them in the execution of the Contract, the employment of apprentices, the hours of labor and the debarment of contractors and subcontractors.
55728.00300\33360134.1
SECTION 00100
NOTICE INVITING BIDS
2 SECTION 00100
NOTICE INVITING BIDS
Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded a Contract, the Bidder and its subcontractors, of any tier, shall maintain active registration with the Department of Industrial Relations for the duration of the Project.
This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. In bidding on this project, it shall be the Bidder’s sole responsibility to evaluate and include the cost of complying with all labor compliance requirements under this contract and applicable law in its bid. Contractors and subcontractors on Public Works projects will be required to submit Certified Payroll Records (CPRs) to the Labor commissioner unless excused from this requirement by the Department of Industrial Regulations.
Each bidder shall be a licensed contractor pursuant to the Business and Professions Code and shall be licensed in the following appropriate classification(s) of contractor’s license(s), for the work bid upon, and must maintain the license(s) throughout the duration of the Contract: Class A license. In addition. the successful bidder will be required to self-perform at least 50% of the work.
Award of Contract: City shall award the Contract for the Project to the lowest responsible bidder as determined from the base bid alone. City reserves the right to reject any or all bids or to waive any irregularities or informalities in any bids or in the bidding process.
For further information, contact the City’s Associate Engineer, Jesus Saldana at [email protected] or (562) 989-7352, or Public Work’s Management Assistant, Ethan Rucker at [email protected] or 562-989-7353.
Posted in the Signal Tribune Newspaper on: March 11th, 2022 and March 18th, 2022 Posted in accordance with S.H.M.C. Section 1.08.010 on or before: March 11th, 2022 Published on PlanetBids on: March 11th, 2022
END OF NOTICE INVITING BIDS
55728.00300\33360134.1
3 SECTION 00200
INSTRUCTIONS TO BIDDERS
SECTION 00200
INSTRUCTIONS TO BIDDERS
1. AVAILABILITY OF CONTRACT DOCUMENTS
Bids must be submitted to City on the Bid Forms which are a part of the Bid Package for the Project. Prospective bidders may download a complete set of Contract Documents at no charge as stated in the Notice Inviting Bids.
The Contract Documents may be made available for review at one or more plan rooms that have registered with Planet Bids. Please Note: Prospective bidders who choose to review the Contract Documents at a plan room must also register with the City’s electronic bid management system to ensure it receives all relevant updates and to submit a bid electronically, if authorized in the Notice Inviting Bids.
2. EXAMINATION OF CONTRACT DOCUMENTS
City has made copies of the Contract Documents available, as indicated above. Bidders shall be solely responsible for examining the Project Site and the Contract Documents, including any Addenda issued during the bidding period, and for informing itself with respect to local labor availability, means of transportation, necessity for security, laws and codes, local permit requirements, wage scales, local tax structure, contractors’ licensing requirements, availability of required insurance, and other factors that could affect the Work. Bidders are responsible for consulting the standards referenced in the Contract. Failure of Bidder to so examine and inform itself shall be at its sole risk, and no relief for error or omission will be given except as required under State law.
3. INTERPRETATION OF CONTRACT DOCUMENTS
Discrepancies in, and/or omissions from the Plans, Specifications or other Contract Documents or questions as to their meaning shall be immediately brought to the attention of City by submission of a written request for an interpretation or correction to City. Such submission, if any, must be sent via the electronic bid management system and received no later than April 4th, 2022 at 4:30 PM.
Any interpretation of the Contract Documents will be made only by written addenda duly issued and posted to the bid management system. All plan holders will be notified by e-mail when an addendum is posted. City will not be responsible for any explanations or interpretations provided in any other manner. No person is authorized to make any oral interpretation of any provision in the Contract Documents to any bidder, and no bidder should rely on any such oral interpretation.
Bids shall include complete compensation for all items that are noted in the Contract Documents as the responsibility of the Contractor.
4. INSPECTION OF SITE; PRE-BID CONFERENCE AND SITE WALK Each prospective bidder is responsible for fully acquainting itself with the conditions of the Project Site (which may include more than one site), as well as those relating to the construction and labor of the Project, to fully understand the facilities, difficulties and restrictions which may impact the cost or effort required to complete the Project. To this end, a Pre-Bid Conference and Site 55728.00300\33360134.1
SECTION 00200
INSTRUCTIONS TO BIDDERS
4 SECTION 00200
INSTRUCTIONS TO BIDDERS
Walk will be held on the date(s) and time(s) indicated in the Notice Inviting Bids. Storm, surface, ground, nuisance, or other waters may be encountered at various times during construction of the Project. Federal and State laws require the City and its contractors to appropriately manage such waters pursuant to the requirements of California State Water Resources Control Board Order Number 2009-0009-DWQ and any amendment or renewal thereof, the Federal Clean Water Act, the California Porter Cologne Water Quality Control Act, Signal Hill Municipal Code, and any orders issued pursuant to these requirements. By submitting a Bid, each bidder acknowledges that it has investigated the risk arising from such waters, has prepared its Bid accordingly, and assumes any and all risks and liabilities arising therefrom.
5. ADDENDA
City reserves the right to revise the Contract Documents prior to the bid opening date. Revisions, if any, shall be made by written Addenda. All Addenda issued by City shall be included in the bid and made part of the Contract Documents. Pursuant to Public Contract Code Section 4104.5, if City issues an Addendum which includes material changes to the Project less than 72 hours prior to the deadline for submission of bids, City will extend the deadline for submission of bids. City may determine, in its sole discretion, whether an Addendum warrants postponement of the bid submission date. Announcement of any extension shall be made via the electronic bid management system to all plan holders. Please Note: Bidders are responsible for ensuring that they have received any and all Addenda. To this end, the electronic bid management system requires each bidder acknowledge receipt of all addenda before submission of the bid.
6. ALTERNATE BIDS
If alternate bid items are called for in the Contract Documents, the lowest bid will be determined on the basis of the base bid only, unless otherwise specified in the Notice Inviting Bids. However, City may choose to award the contract on the basis of the base bid alone or the base bid and any alternate or combination of alternates. The time required for completion of the alternate bid items has been factored into the Contract duration and no additional Contract time will be awarded for any of the alternate bid items. City may elect to include one or more of the alternate bid items, or to otherwise remove certain work from the Project scope of work, accordingly each Bidder must ensure that each bid item contains a proportionate share of profit, overhead and other costs or expenses which will be incurred by the Bidder.
7. COMPLETION OF BID FORMS
Bids shall only be prepared using copies of the Bid Forms which are included in the Contract Documents and available on PlanetBids. The use of substitute bid forms will not be permitted.
Bids shall be executed by an authorized signatory as described in these Instructions to Bidders.
Deviations in the bid form may result in the bid being deemed non-responsive. Refer to Bid Form for items that require electronic and paper submittal at the time of bid.
8. ELECTRONIC SUBMISSION REQUIREMENTS
The bidder must enter pricing in the electronic bid form for any and all line items or a lump sum bid amount, as required. The pricing provided in the electronic bid form will be the only valid bid pricing for determination of low bid.
55728.00300\33360134.1
SECTION 00200
INSTRUCTIONS TO BIDDERS
5 SECTION 00200
INSTRUCTIONS TO BIDDERS
The bidder must enter subcontractor information in the electronic bid form. The subcontractor information provided electronically will be the only valid subcontractor information.
The bidder must attach a pdf file(s) to the electronic bid submission containing all of the completed and signed Bid Documents.
9. MODIFICATIONS OF BIDS
Each Bidder shall submit its Bid in strict conformity with the requirements of the Contract Documents. Unauthorized additions, modifications, revisions, conditions, limitations, exclusions or provisions attached to a Bid may render it non-responsive and may cause its rejection. Bidders shall neither delete, modify, nor supplement the printed matter on the Bid Forms, nor make substitutions thereon. Oral, telephonic, and electronic modifications will not be considered, unless the Notice Inviting Bids authorizes the submission of electronic bids and modifications thereto and such modifications are made in accordance with the Notice Inviting Bids.
10. SIGNING OF BIDS
All Bids submitted shall be executed by the Bidder or its authorized representative. Bidder shall upload an electronic scanned copy of the executed Bid Form to the electronic bid management system. Bidders may be asked to provide evidence in the form of an authenticated resolution of its Board of Directors or a Power of Attorney evidencing the capacity of the person signing the Bid to bind the Bidder to each Bid and to any Contract arising therefrom.
If a Bidder is a joint venture or partnership, it may be asked to submit an authenticated Power of Attorney executed by each joint venturer or partner appointing and designating one of the joint venturers or partners as a management sponsor to execute the Bid on behalf of Bidder. Only that joint venturer or partner shall execute the Bid. The Power of Attorney shall also: (1) authorize that particular joint venturer or partner to act for and bind Bidder in all matters relating to the Bid; and (2) provide that each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations of Bidder assumed under the Bid and under any Contract arising therefrom. The Bid shall be executed by the designated joint venturer or partner on behalf of the joint venture or partnership in its legal name.
11. DESIGNATION OF SUBCONTRACTORS
Pursuant to State law, the Bidders must designate the name, license number, and location of each subcontractor who will perform work or render services for the Bidder in an amount that exceeds one half of one percent (1/2%) of the Bidder’s Total Bid Price, as well as the portion of work each such subcontractor will perform on the form provided herein by City. No additional time will be provided to bidders to submit any of the requested information in the Designation of Subcontractor form. The successful bidder will be required to self-perform at least 50% of the work per Standard Specification for Public Works Construction.
12. BID GUARANTEE (BOND)
Each bid shall be accompanied by: (a) cash; (b) a certified check made payable to City; (c) a cashier’s check made payable to City; or (d) a bid bond payable to City executed by the bidder as principal and surety as obligor in an amount not less than 10% of the maximum amount of the bid. Personal sureties and unregistered surety companies are unacceptable. The surety insurer 55728.00300\33360134.1
SECTION 00200
INSTRUCTIONS TO BIDDERS
6 SECTION 00200
INSTRUCTIONS TO BIDDERS
shall be California admitted surety insurer, as defined in Code of Civil Procedure Section 995.120.
The cash, check or bid bond shall be given as a guarantee that the bidder shall execute the Contract if it be awarded to the bidder, shall provide the payment and performance bonds and insurance certificates and endorsements as required herein within ten (10) calendar days after notification of the award of the Contract to the bidder. Failure to provide the required documents may result in forfeiture of the bidder’s bid deposit or bond to City and City may award the Contract to the next lowest responsive, responsible bidder, or may call for new bids.
THE BID SECURITY MUST BE RECEIVED PRIOR TO THE SPECIFIED DATE AND TIME FOR BID OPENING.
The Bid Security must be submitted directly to the City Clerk at City Hall, 2175 Cherry Avenue Signal Hill, CA 90755, in an envelope clearly labeled with the Project Name/Number and Bidder’s Name and Address.
If Bidder elects to provide the required Bid Security in the form of a Bid Bond, the original hard copy Bid Bond must be submitted to the City at the address indicated above prior to the specified date and time for bid opening.
13. SUBMISSION OF SEALED BIDS
Bidders may submit their bids via electronic transmission pursuant to Public Contract Code Sections 1600 and 1601. The acceptable method(s) of electronic transmission are stated in the Notice Inviting Bids. City shall not accept bids otherwise transmitted. No oral, telephonic, or facsimile bids will be considered.
It is the sole responsibility of each bidder to see that its Bid is properly submitted to PlanetBids in the proper form and prior to the stated closing time. THE ELECTRONIC BID MANAGEMENT SYSTEM WILL NOT ACCEPT LATE BIDS. The City will only consider bids that have transmitted successfully and have been issued a confirmation number with a time stamp from PlanetBids indicating that the Bid was submitted successfully.
Bidders experiencing any technical difficulties with the bid submission process may contact the PlanetBids system support at 818-992-1771. Neither the City, nor the City’s bid management system, make any guarantee as to the timely availability of assistance, or assurance that any given problem will be resolved by the bid submission date and/or time.
14. DELIVERY AND OPENING OF BIDS
Bids will be received by the City via the electronic bid management system up to the date and time shown in the Notice Inviting Bids. It is the Bidder’s sole responsibility to ensure that its Bid is received as specified. Bids may be submitted earlier than the dates(s) and time(s) indicated.
Bid results are immediately available to the public at the closing deadline on the City’s website in the electronic bid management system. The City’s City Clerk’s office will also have bid results, immediately following bid opening. The City Clerk’s office is located at: 2175 Cherry Avenue Signal Hill, CA 90755. City reserves the right to reject any or all Bids and to waive any informality or irregularity in any Bid.
55728.00300\33360134.1
SECTION 00200
INSTRUCTIONS TO BIDDERS
7 SECTION 00200
INSTRUCTIONS TO BIDDERS
15. WITHDRAWAL OF BID
Prior to the bid closing deadline, a Bid may be electronically withdrawn by the Bidder. Any request to withdraw a bid after bid closing must be made in accordance with Public Contract Code section 5100 et seq. and must be submitted in writing within five (5) working days, excluding Saturday, Sundays and State holidays, specifying in detail how the mistake was made.
16. BASIS OF AWARD; BALANCED BIDS
City shall award the Contract to the lowest responsive, responsible Bidder submitting a responsive Bid. City may reject any Bid which, in its opinion when compared to other bids received or to City’s internal estimates, does not accurately reflect the cost to perform the Work. City may reject as non-responsive any bid which unevenly weights or allocates costs, including but not limited to overhead and profit to one or more particular bid items.
17. LICENSING REQUIREMENTS
Pursuant to Section 7028.15 of the Business and Professions Code and Section 3300 of the Public Contract Code, all bidders must possess proper licenses for performance of this Contract.
Subcontractors must possess the appropriate licenses for each specialty subcontracted. Pursuant to Section 7028.5 of the Business and Professions Code, City shall consider any bid submitted by a contractor not currently licensed in accordance with state law and pursuant to the requirements found in the Contract Documents to be non-responsive, and City shall reject the Bid. City shall have the right to request, and Bidders shall provide within five (5) calendar days, evidence satisfactory to City of all valid license(s) currently held by that Bidder and each of the Bidder’s subcontractors, before awarding the Contract.
18. DISQUALIFICATION OF BIDDERS; INTEREST IN MORE THAN ONE BID No bidder shall be allowed to make, submit or be interested in more than one prime bid on the same Project. However, a person, firm, corporation or other entity that has submitted a subproposal to a bidder, or that has quoted prices of materials to a bidder, is not thereby disqualified from submitting a subproposal or quoting prices to other bidders submitting a bid to City. No person, firm, corporation, or other entity may submit subproposal to a bidder, or quote prices of materials to a bidder, when also submitting a prime bid on the same Project.
19. INSURANCE REQUIREMENTS
The successful bidder shall procure the insurance in the form and in the amount specified in the Contract Documents.
20. AWARD PROCESS
Once all Bids are opened and reviewed to determine the lowest responsive and responsible Bidder, City Council may award the contract. The apparent successful Bidder should begin to prepare the following documents: (1) the Performance Bond; (2) the Payment Bond; and (3) the required insurance certificates and endorsements. Once City notifies the Bidder of the award, the Bidder will have ten (10) consecutive calendar days from the date of this notification to execute the Contract and supply City with all the required documents and certifications. Regardless of whether the Bidder supplies the required documents and certifications in a timely manner, the 55728.00300\33360134.1
SECTION 00200
INSTRUCTIONS TO BIDDERS
8 SECTION 00200
INSTRUCTIONS TO BIDDERS
Contract time will begin to run ten (10) calendar days from the date of the notification. Once City receives all the properly drafted and executed documents and certifications from the Bidder, City shall issue a Notice to Proceed to that Bidder.
21. FILING OF BID PROTESTS
Bidders may file a “protest” of a Bid with City’s City Clerk. In order for a Bidder’s protest to be considered valid, the protest must:
A. Be filed in writing within five (5) calendar days after the bid opening date; B. Clearly identify the specific irregularity or accusation; C. Specify, in detail, the grounds of the protest and the facts supporting the protest; and
D. Include all relevant, supporting documentation with the protest at time of filing.
If the protest does not comply with each of these requirements, it may be rejected without further review.
If the protest is valid, City’s Public Works Director, or other designated City staff member, shall review the basis of the protest and all relevant information. The Public Works Director will provide a written decision to the protestor. The protestor may then appeal the decision of the Public Works Director to the City Manager.
The procedure and time limits set forth in this section are mandatory and are the sole and exclusive remedy in the event of a bid protest. Failure to comply with these procedures shall constitute a failure to exhaust administrative remedies and a waiver of any right to further pursue the bid protest,
22. WORKERS COMPENSATION
Each bidder shall submit the Contractor’s Certificate Regarding Workers’ Compensation form.
23. SUBSTITUTION OF SECURITY
The Contract Documents call for monthly progress payments based upon the percentage of the work completed. The City will retain five percent (5%) of each progress payment as provided by the Contract Documents. At the request and expense of the successful Bidder, the City will substitute securities for the amount so retained in accordance with Public Contract Code Section 22300.
55728.00300\33360134.1
SECTION 00200
INSTRUCTIONS TO BIDDERS
9 SECTION 00200
INSTRUCTIONS TO BIDDERS
24. PREVAILING WAGES
City has obtained from the Director of the Department of Industrial Relations the general prevailing rate of per diem wages in the locality in which this work is to be performed for each craft or type of worker needed to execute the Contract. These rates may be obtained online at http://www.dir.ca.gov/dlsr. Bidders are advised that a copy of these rates must be posted by the successful Bidder at the job site(s).
25. DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS
In accordance with the provisions of the Labor Code, contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Section 1777.1 or Section 1777.7 of the Labor Code. Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract. Any public money that is paid to a debarred subcontractor by the Contractor for the Project shall be returned to City. The Contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the Project.
26. IRAN CONTRACTING ACT CERTIFICATION
Each bidder shall submit the certification required by the Iran Contracting Act of 2010, Public Contract Code section 2200 et seq. as provided with the Bid Documents.
27. PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION
Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded a Contract, the Bidder and its subcontractors, of any tier, shall maintain active registration with the Department of Industrial Relations for the duration of the Project. To this end, Bidder shall sign and submit with its Bid the Public Works Contractor Registration Certification on the form provided, attesting to the facts contained therein. Failure to submit this form may render the Bid non-responsive. In addition, each Bidder shall provide the registration number for each listed subcontractor in the space provided in the Designation of Subcontractors Form.
28. PERFORMANCE BOND AND PAYMENT BOND REQUIREMENTS
Within the time specified in the Contract Documents, the Bidder to whom a Contract is awarded shall deliver to City four identical counterparts of the Performance Bond and Payment Bond in the form supplied by City and included in the Contract Documents. Failure to do so may, in the sole discretion of City, result in the forfeiture of the Bid Guarantee. The surety supplying the bond must be an admitted surety insurer, as defined in Code of Civil Procedure Section 995.120, authorized to do business as such in the State of California and satisfactory to City. The Performance Bond and the Payment Bond shall be for one hundred percent (100%) of the Total Bid Price.
55728.00300\33360134.1
SECTION 00200
INSTRUCTIONS TO BIDDERS
10 SECTION 00200
INSTRUCTIONS TO BIDDERS
29. REQUEST FOR SUBSTITUTIONS
The successful bidder shall comply with the substitution request procedures set forth in the Bid and Contract Documents. Any deadlines for substitution requests that occur prior to the bid opening date are set forth in the Special Conditions.
30. SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES AND FEES Contractor and its subcontractors performing work under this Contract will be required to pay California sales tax and other applicable taxes, and to pay for permits, licenses and fees required by the agencies with authority in the jurisdiction in which the work will be located, unless otherwise expressly provided by the Contract Documents.
31. EXECUTION OF CONTRACT
As required herein the Bidder to whom an award is made shall execute the Contract in the amount determined by the Contract Documents. City may require appropriate evidence that the persons executing the Contract are duly empowered to do so.
END OF INSTRUCTIONS TO BIDDERS
55728.00300\33360134.1
11 SECTION 00400
BID FORM PROPOSAL
SECTION 00400
BID FORM PROPOSAL
NAME OF BIDDER:
The undersigned, hereby declare that we have carefully examined the location of the proposed Work, and have read and examined the Contract Documents, including all plans, specifications, and all addenda, if any, for the following Project:
Water Services and Valve Replacements Phase II
We hereby propose to furnish all labor, materials, equipment, tools, transportation, and services, and to discharge all duties and obligations necessary and required to perform and complete the Project for the Total Bid Price indicated in the electronically submitted bid schedule via PlanetBids.
In the event the electronic bid schedule requires unit pricing, final payment shall be determined by the City from measured quantities of work performed based upon the unit price.
The undersigned agrees that the electronic bid accompanied by this Bid Form constitutes a firm offer to the City which cannot be withdrawn for the number of calendar days indicated in the Notice Inviting Bids from and after the bid opening, or until a Contract for the Work is fully executed by the City and a third party, whichever is earlier.
If the Contract Documents specify alternate bid items, the Alternate Additive or Deductive Bid amounts shall be added to or deducted from the Total Bid Price at the City’s sole option. The City can choose to include one or more of the Alternate Bids in the Project. If any of the Alternate Bids are selected by the City, the resulting amount shall be added to or deducted from Total Bid Price for the Project. The City may select one or more of the Alternate Bids at the stated Bid Price up to sixty (60) days following award of the Contract. The City can award/select Alternate Bid items at any time(s). All bids shall be valid for a period of sixty (60) days after City's bid opening date, notwithstanding any award of the Contract by City to another bidder.
The Contract duration shall commence on the date stated in City’s Notice to Proceed, and shall be completed by the Contractor in the time specified in the Contract Documents. In no case shall the Contractor commence construction prior to the date stated in City’s Notice to Proceed.
Bidder certifies that it is licensed in accordance with the law providing for the registration of Contractors, License No. _________, Expiration Date _______, class of license _____. If the bidder is a joint venture, each member of the joint venture must include the above information.
The undersigned acknowledges understanding and full consideration of the electronically issued addenda to the Contract Documents.
55728.00300\33360134.1
SECTION 00400
BID FORM PROPOSAL
12 SECTION 00400
BID FORM PROPOSAL
Bidder has attached and incorporates the following in its bid:
A Bid Form Proposal (Section 00400) Fill-in, Sign, Scan, and Upload B Bid Item Schedule Input Bid Item values on-line on PlanetBids C Certificate Regarding Workers’
Compensation form (Section 00405)
Fill-in, Sign, Scan, and Upload
D Bid Bond form (10% of the total bid)
(Section 00410)
1. Fill-in, Sign, Scan, and Upload
2. Original wet signature hard-copy submitted
in person until Bid Opening Date
E Noncollusion Declaration form
(Section 00420)
Fill-in, Sign, Scan, and Upload
F Contractor Information and
Experience Form (Section 00430)
Fill-in, Sign, Scan, and Upload
G List of Subcontractors Form (Section
00440)
Fill-in, Sign, Scan, and Upload
H Iran Contracting Act Certification form
(Section 00450)
Fill-in, Sign, Scan, and Upload
I Public Works Contractor Registration
Certification form (Section 00460)
Fill-in, Sign, Scan, and Upload
J Addenda(s), if issued Fill-in, Sign, Scan, and Upload I hereby certify under penalty of perjury under the laws of the State of California, that all of the information submitted in connection with this Bid and all of the representations made herein are true and correct.
Total Proposed Amount $
Name of Bidder
Signature
Name
Title
Dated
END OF BID FORM PROPOSAL
55728.00300\33360134.1
13 SECTION 00405
CONTRACTOR’S CERTIFICATE REGARDING
WORKERS’ COMPENSATION
SECTION 00405
CONTRACTOR’S CERTIFICATE REGARDING WORKERS’ COMPENSATION I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this Contract.
Name of Bidder
Signature
Name
Title
Dated
END OF CONTRACTOR’S CERTIFICATE REGARDING WORKERS’ COMPENSATION 55728.00300\33360134.1
14 SECTION 00410
BID BOND
SECTION 00410
BID BOND
The makers of this bond are __________________________________________, as Principal, and __________________________________________, as Surety and are held and firmly bound unto the City of Signal Hill, hereinafter called City, in the penal sum of TEN PERCENT (10%) OF THE TOTAL BID PRICE of the Principal submitted to City for the work described below, for the payment of which sum in lawful money of the United States, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that whereas the Principal has submitted the accompanying bid dated _____________, 2022 for the Water Services and Valve Replacements Phase II Project.
If the Principal does not withdraw its bid within the time specified in the Contract Documents; and if the Principal is awarded the Contract and provides all documents to City as required by the Contract Documents; then this obligation shall be null and void. Otherwise, this bond will remain in full force and effect.
Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents shall in affect its obligation under this bond, and Surety does hereby waive notice of any such changes.
In the event a lawsuit is brought upon this bond by City and judgment is recovered, the Surety shall pay all litigation expenses incurred by City in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and expenses.
IN WITNESS WHEREOF, the above-bound parties have executed this instrument under their several seals this _____________ day of _____________, 2022, the name and corporate seal of each corporation.
(Corporate Seal) _______________________
Contractor/ Principal
By
Title
(Corporate Seal) ________________________
Surety
By
Attorney-in-Fact
(Attach Attorney-in-Fact Certificate) Title_______________________________ 55728.00300\33360134.1
SECTION 00410
BID BOND
15 SECTION 00410
BID BOND
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
55728.00300\33360134.1
16 SECTION 00420
NONCOLLUSION DECLARATION
SECTION 00420
NONCOLLUSION DECLARATION
The undersigned declares:
I am the ______________ of _________________, the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham.
The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true.
The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on ____________________[date], at ___________________[city], ___________________[state].
Name of Bidder
Signature
Name
Title
Dated
END OF NONCOLLUSION DECLARATION
55728.00300\33360134.1
17 SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
A. INFORMATION ABOUT BIDDER
**Failure to complete all information may render your bid nonresponsive - indicate not applicable (“N/A”) where appropriate.**
NOTE: Where Bidder is a joint venture, pages shall be duplicated and information provided for all parties to the joint venture.
1.0 Name of Bidder: ___________________________________________
2.0 Type, if Entity: ___________________________________________
3.0 Bidder Address: ___________________________________________ _____________________________________________________________ _____________________________________________________________ ____________________________________________________________ Facsimile Number _______________ Telephone Number _____________ Website Address______________________________________________
4.0 How many years has Bidder’s organization been in business as a Contractor? _______
5.0 How many years has Bidder’s organization been in business under its present name? ________________________
5.1 Under what other or former names has Bidder’s organization operated? _______________________________________________
6.0 If Bidder’s organization is a corporation, answer the following:
6.1 Date of Incorporation: ________________________________
6.2 State of Incorporation: ________________________________
6.3 President’s/CEO Name: ________________________________
6.4 Vice President’s Name(s): ________________________________
6.5 Secretary’s Name: ________________________________
6.6 Treasurer’s Name: ________________________________
7.0 If an individual or a partnership, answer the following:
7.1 Date of Organization: ____________________________________ 55728.00300\33360134.1
SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
18 SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
7.2 Name and address of all partners (state whether general or limited partnership):
__________________________________________________________ __________________________________________________________ __________________________________________________________
8.0 If other than a corporation or partnership, describe organization and name principals:
___________________________________________________________ ___________________________________________________________
9.0 List other states in which Bidder’s organization is legally qualified to do business. ___________________________________________________________ ___________________________________________________________ __________________________________________________________
10.0 What type of work does the Bidder normally perform with its own forces? ___________________________________________________________ ___________________________________________________________ __________________________________________________________
11.0 Has Bidder ever failed to complete any work awarded to it? If so, note when, where, and why:
___________________________________________________________ ___________________________________________________________ __________________________________________________________
12.0 Has the Bidder ever been in default, debarred or suspended in any way? If so, note when and why:
___________________________________________________________ ___________________________________________________________ __________________________________________________________
13.0 Within the last five years, has any officer or partner of Bidder’s organization ever been an officer or partner of another organization when it failed to complete a contract? If so, attach a separate sheet of explanation:
___________________________________________________________ ___________________________________________________________ __________________________________________________________
14.0 List Trade References (Materials Suppliers, Vendors, Union Representatives, etc.:
___________________________________________________________ ___________________________________________________________ __________________________________________________________ ___________________________________________________________ ___________________________________________________________ __________________________________________________________
15.0 List Bank References (Bank and Branch Address):
___________________________________________________________ 55728.00300\33360134.1
SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
19 SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
___________________________________________________________ __________________________________________________________
16.0 Name of Bonding Company and Name and Address, email address and phone number of Agent:
___________________________________________________________ ___________________________________________________________ __________________________________________________________ 55728.00300\33360134.1
SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
20 SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
B. LIST OF CURRENT PROJECTS (BACKLOG)
**Duplicate Page if needed for listing additional current projects.** Project and
Client Contact
Person and
Phone Number
Description of
Bidder’s Work
Completion Date Cost of
Bidder’s Work
Amounted
Bonded
55728.00300\33360134.1
SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
21 SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
C. LIST OF COMPLETED PROJECTS LAST THREE YEARS
**Duplicate Page if needed for listing additional completed projects.** Please include only those projects which are similar enough to demonstrate Bidder’s ability to perform the required Work.
Client Description of
Bidder’s Work
Period of
Performance
Cost of Bidder’s
Work
Contact Name &
Phone
55728.00300\33360134.1
SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
22 SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
D. EXPERIENCE AND TECHNICAL QUALIFICATIONS QUESTIONNAIRE Personnel:
The Bidder shall identify the key personnel to be assigned to this project in a management, construction supervision or engineering capacity.
1. List each person’s job title, name and percent of time to be allocated to this project:
2. Summarize each person’s specialized education:
3. List each person’s years of construction experience relevant to the project:
4. Summarize such experience:
Bidder agrees that any personnel named in this Bid will remain on this Project until completion of all relevant Work, unless substituted by personnel of equivalent experience and qualifications approved in advance by City.
55728.00300\33360134.1
SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
23 SECTION 00430
CONTRACTOR INFORMATION AND EXPERIENCE FORM
Additional Bidder’s Statements:
If the Bidder feels that there is additional information which has not been included in the questionnaire above, and which would contribute to the qualification review, it may add that information in a statement here or on an attached sheet, appropriately marked:
E. VERIFICATION AND EXECUTION
These Bid Forms shall be executed only by a duly authorized official of the Bidder:
I declare under penalty of perjury under the laws of the State of California that the foregoing information is true and correct:
Name of Bidder
Signature
Name
Title
Dated
END OF CONTRACTOR INFORMATION AND EXPERIENCE FORM
55728.00300\33360134.1
24 SECTION 00440
LIST OF SUBCONTRACTORS FORM
SECTION 00440
LIST OF SUBCONTRACTORS FORM
In compliance with the Subletting and Subcontracting Fair Practices Act of the Public Contract Code of the State of California, each bidder shall set forth below: (a) the name and the location of the place of business, (b) the California contractor license number, and (c) the portion of the work which will be done by each subcontractor who will perform work or labor or render service to the Contractor in or about the construction of the work in an amount in excess of one-half of one percent (1/2%) of the Contractor’s Total Bid Price.
Notwithstanding the foregoing, if the work involves streets and highways, then the Contractor shall list each subcontractor who will perform work or labor or render service to Contractor in or about the work in an amount in excess of one-half of one percent (1/2%) of the Contractor’s Total Bid Price. No additional time shall be granted to provide the below requested information.
If no subcontractor is specified, for a portion of the work, or if more than one subcontractor is specified for the same portion of Work, then the Contractor shall be deemed to have agreed that it is fully qualified to perform that Work, and that it shall perform that portion itself. The Prime Contractor is required to complete at least 50% of the contract value with its own forces.
Work to be done
by
Subcontractor Subcontractor
Location of
Business
CSLB Contractor
License No.
DIR Registration
Number
% of the
Work
55728.00300\33360134.1
SECTION 00440
LIST OF SUBCONTRACTORS FORM
25 SECTION 00440
LIST OF SUBCONTRACTORS FORM
Work to be done
by
Subcontractor Subcontractor
Location of
Business
CSLB Contractor
License No.
DIR Registration
Number
% of the
Work
55728.00300\33360134.1
SECTION 00440
LIST OF SUBCONTRACTORS FORM
26 SECTION 00440
LIST OF SUBCONTRACTORS FORM
Work to be done
by
Subcontractor Subcontractor
Location of
Business
CSLB Contractor
License No.
DIR Registration
Number
% of the
Work
Name of Bidder
Signature
Name
Title
Dated
END OF LIST OF SUBCONTRACTORS FORM
55728.00300\33360134.1
27 SECTION 00450
IRAN CONTRACTING ACT CERTIFICATION
SECTION 00450
IRAN CONTRACTING ACT CERTIFICATION(Public Contract Code Section 2200 et seq.) As required by California Public Contract Code Section 2204, the Contractor certifies subject to penalty for perjury that the option checked below relating to the Contractor's status in regard to the Iran Contracting Act of 2010 (Public Contract Code Section 2200 et seq.) is true and correct:
□ The Contractor is not:
(i) identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203; or
(ii) a financial institution that extends, for 45 days or more, credit in the amount of $20,000,000 or more to any other person or entity identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203, if that person or entity uses or will use the credit to provide goods or services in the energy sector in Iran. □ The City has exempted the Contractor from the requirements of the Iran Contracting Act of 2010 after making a public finding that, absent the exemption, the City will be unable to obtain the goods and/or services to be provided pursuant to the Contract. □ The amount of the Contract payable to the Contractor for the Project does not exceed $1,000,000.
Signed:
Titled:
Firm:
Date:
Note: In accordance with Public Contract Code Section 2205, false certification of this form shall be reported to the California Attorney General and may result in civil penalties equal to the greater of $250,000 or twice the Contract amount, termination of the Contract and/or ineligibility to bid on contracts for three years.
END OF IRAN CONTRACTING ACT CERTIFICATION
55728.00300\33360134.1
28 SECTION 00460
PUBLIC WORKS CONTRACTOR REGISTRATION
CERTIFICATION
SECTION 00460
PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION
Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. See http://www.dir.ca.gov/PublicWorks/PublicWorks.html for additional information.
No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work.
Bidder hereby certifies that it is aware of the registration requirements set forth in Labor Code sections 1725.5 and 1771.1 and is currently registered as a contractor with the Department of Industrial Relations.
Name of Bidder:
DIR Registration Number:
Bidder further acknowledges:
1. Bidder shall maintain a current DIR registration for the duration of the project.
2. Bidder shall include the requirements of Labor Code sections 1725.5 and 1771.1 in its contract with subcontractors and ensure that all subcontractors are registered at the time of bid opening and maintain registration status for the duration of the project.
3. Failure to submit this form or comply with any of the above requirements may result in a finding that the bid is non-responsive.
Name of Bidder
Signature
Name
Title
Dated
END OF PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION 55728.00300\33360134.1
29 SECTION 00500
CONTRACT
SECTION 00500
CONTRACT
THIS CONTRACT is made this _____ day of _________, 2022, in the County of Los Angeles, State of California, by and between the City of Signal Hill hereinafter called City, and ______________________________, hereinafter called Contractor. City and the Contractor for the considerations stated herein agree as follows:
ARTICLE 1. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated the contract and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all of the Work required in strict compliance with the Contract Documents as specified in Article 5 below for the following Project:
Water Services and Valve Replacements Phase II
The Contractor and its surety shall be liable to City for any damages arising as a result of the Contractor’s failure to comply with this obligation.
ARTICLE 2. TIME FOR COMPLETION. The Work shall be commenced on the date stated in City’s Notice to Proceed. The Contractor shall complete all Work required by the Contract Documents within 60 work days from the commencement date stated in the Notice to Proceed.
By its signature hereunder, Contractor agrees the time for completion set forth above is adequate and reasonable to complete the Work.
ARTICLE 3. CONTRACT PRICE. City shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs, the sum of ____________________________________________________________ Dollars ($_________________________________). Payment shall be made as set forth in the General Conditions.
ARTICLE 4. LIQUIDATED DAMAGES. In accordance with Government Code section 53069.85, it is agreed that the Contractor will pay City the sum of $1000 for each and every work day of delay beyond the time prescribed in the Contract Documents for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event that Liquidated Damages are not paid, the Contractor agrees City may deduct that amount from any money due or that may become due the Contractor under the Contract. This Article does not affect the City’s rights to other damages or remedies specified in the Contract Documents or allowed by law.
ARTICLE 5. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the following:
Notice Inviting Bids
Instructions to Bidders
Bid Form
Contractor’s Certificate Regarding Workers’ Compensation Bid Bond
Designation of Subcontractors
Information Required of Bidders
Noncollusion Declaration form
55728.00300\33360134.1
SECTION 00500
CONTRACT
30 SECTION 00500
CONTRACT
Iran Contracting Act Certification
Public Works Contractor Registration Certification
Contract
Performance Bond
Payment Bond
General Conditions
Special Conditions
Technical Specifications
Addenda(s)
Plans and Drawings
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract The Contactor shall complete the Work in strict accordance with all the Contract Documents.
All the Contract Documents are intended to be complementary. Work required by one of the Contract Documents and not by others shall be done as if required by all. This Contract shall supersede any prior agreement of the parties.
ARTICLE 6. PROVISIONS REQUIRED BY LAW. Each and every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, including, but not limited to, the provisions of the California Labor Code and California Public Contract Code which are applicable to this Project.
ARTICLE 7. INDEMNIFICATION. Contractor shall provide indemnification as set forth in the General Conditions.
ARTICLE 8. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in accordance with the Labor Code which such rates shall be made available at City Hall or may be obtained online at http//www.dir.ca.gov/dlsr. and which must be posted at the job site.
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on the day and year above written.
[NAME OF CONTRACTOR]
By
Name:
Title:
License No.
CITY OF SIGNAL HILL
By______________________________
55728.00300\33360134.1
SECTION 00500
CONTRACT
31 SECTION 00500
CONTRACT
By
Name:
Title:
(If Corporation, TWO SIGNATURES,
President OR Vice President AND Secretary
OR Treasurer REQUIRED)]
Attest:
Carmen R. Brooks
City Clerk
Approved as to Form:
__________________________________
Best Best & Krieger, LLP
City Attorney
END OF CONTRACT
55728.00300\33360134.1
32 SECTION 00610
PERFORMANCE BOND
SECTION 00610
PERFORMANCE BOND
KNOW ALL PERSONS BY THESE PRESENTS:
THAT WHEREAS, the City of Signal Hill (hereinafter referred to as “City”) has awarded to ____________________________________________________, (hereinafter referred to as the “Contractor”) an agreement for ___________________________________________________ (hereinafter referred to as the “Project”).
WHEREAS, the work to be performed by the Contractor is more particularly set forth in the Contract Documents for the Project dated ________________, (hereinafter referred to as “Contract Documents”), the terms and conditions of which are expressly incorporated herein by reference; and
WHEREAS, the Contractor is required by said Contract Documents to perform the terms thereof and to furnish a bond for the faithful performance of said Contract Documents.
NOW, THEREFORE, we, _______________________________________________________, the undersigned Contractor and
__________________________________________________as Surety, a corporation organized and duly authorized to transact business under the laws of the State of California, are held and firmly bound unto the City in the sum of ______________________________ _______________________________________ DOLLARS and ________________________ CENTS ($_________________________), said sum being not less than one hundred percent (100%) of the total amount of the Contract, for which amount well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that, if the Contractor, his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract Documents and any alteration thereof made as therein provided, on its part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their intent and meaning; and shall faithfully fulfill all obligations including, if provided as part of the Contract Documents, the one-year guarantee of all materials and workmanship; and shall indemnify and save harmless the City, its officers and agents, as stipulated in said Contract Documents, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.
As a condition precedent to the satisfactory completion of the Contract Documents, unless otherwise provided for in the Contract Documents, the guarantee obligation shall hold good for a period of one (1) year after the acceptance of the work by City, during which time if Contractor shall fail to make full, complete, and satisfactory repair and replacements and totally protect the City from loss or damage resulting from or caused by defective materials or faulty workmanship the above obligation in penal sum thereof shall remain in full force and effect. However, anything in this paragraph to the contrary notwithstanding, the obligations of Surety hereunder shall continue so long as any obligation of Contractor remains. Nothing herein shall limit the City’s rights or the Contractor or Surety’s obligations under the Contract Documents, law or equity, including, but not limited to, California Code of Civil Procedure section 337.15. 55728.00300\33360134.1
SECTION 00610
PERFORMANCE BOND
33 SECTION 00610
PERFORMANCE BOND
Whenever Contractor shall be, and is declared by the City to be, in default under the Contract Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall promptly, at the City’s option:
(1) Take over and complete the Project in accordance with all terms and conditions in the Contract Documents; or
(2) Obtain a bid or bids for completing the Project in accordance with all terms and conditions in the Contract Documents and upon determination by Surety of the lowest responsive and responsible bidder, arrange for a contract between such bidder, the Surety and the City, and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract Documents and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents. (3) Permit the City to complete the Project in any manner consistent with California law and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract Documents and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents.
Surety expressly agrees that the City may reject any contractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Contractor.
Surety shall not utilize Contractor in completing the Project nor shall Surety accept a bid from Contractor for completion of the Project if the City, when declaring the Contractor in default, notifies Surety of the City’s objection to Contractor’s further participation in the completion of the Project.
The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project to be performed thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project and the provisions of Section 2819 and 2845 of the California Civil Code. Without limiting the foregoing, such changes, extensions of time and alterations or additions shall include, but are not limited to, changes or alterations to the Contract Documents (including, without limitation, an increase in the total dollar amount of the Contract Documents), extensions of time, or modifications of the time, terms, or conditions of payment to the Contractor. 55728.00300\33360134.1
SECTION 00610
PERFORMANCE BOND
34 SECTION 00610
PERFORMANCE BOND
IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of __________________________, 20___.
CONTRACTOR/PRINCIPAL
(Corporate Seal of Contractor/ _________________________________________ Principal, if a Corporation) Name of Contractor/Principal (Type or Print) By: ___________________________________
Name (Signature)
___________________________________
Name (Type or Print)
___________________________________
Title (Type or Print)
SURETY
(Seal of Surety) _________________________________________ Name of Surety (Type or Print)
By:____________________________________
Attorney-In-Fact
Signatures of those signing for the Contractor and Surety must be notarized and evidence of corporate authority attached.
The rate of premium on this bond is ____________ per thousand. The total amount of premium charges, $_______________________________.
(The above must be filled in by corporate attorney.)
THIS IS A REQUIRED FORM
Any claims under this bond may be addressed to:
(Name and Address of Surety) ___________________________________________ ___________________________________________
___________________________________________
(Name and Address of Agent or ___________________________________________ Representative for service of ___________________________________________ process in California, if different ___________________________________________ from above)
(Telephone number of Surety and ___________________________________________ Agent or Representative for service ___________________________________________ of process in California) ___________________________________________ 55728.00300\33360134.1
SECTION 00610
PERFORMANCE BOND
35 SECTION 00610
PERFORMANCE BOND
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: A copy of the Power-of-Attorney to local representatives of the bonding company must be attached hereto.
END OF PERFORMANCE BOND FORM
55728.00300\33360134.1
36 SECTION 00620
PAYMENT BOND
SECTION 00620
PAYMENT BOND
KNOW ALL MEN BY THESE PRESENTS That
WHEREAS, the City of Signal Hill (hereinafter designated as the “City”), by action taken or a resolution passed ___________ , 20____ has awarded to ______________________________ ______________________________ hereinafter designated as the “Principal,” a contract for the work described as follows: ________________________________________ ____________________________________________________________ (the “Project”); and WHEREAS, the work to be performed by the Principal is more particularly set forth in the Contract Documents for the Project dated ________________, (hereinafter referred to as “Contract Documents”), the terms and conditions of which are expressly incorporated herein by reference; and
WHEREAS, said Principal is required to furnish a bond in connection with said Contract Documents; providing that if said Principal or any of its Subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its Subcontractors with respect to such work or labor, the Surety on this bond will pay for the same to the extent hereinafter set forth.
NOW THEREFORE, we, the Principal and __________________________________________ as Surety, are held and firmly bound unto the City in the penal sum of ____________________ _________________________________ DOLLARS and ________________________ CENTS ($_________________________) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Section 9100 of the Civil Code, fail to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amounts due under the Unemployment Insurance Code with respect to work or labor performed under the Contract Documents, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Section 18663 of the Revenue and Taxation Code, with respect to such work and labor the Surety or Sureties will pay for the same, in an amount not exceeding the sum herein above specified, and also, in case suit is brought upon this bond, all litigation expenses incurred by the City in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses.
This bond shall inure to the benefit of any of the persons named in Section 9100 of the Civil Code so as to give a right of action to such persons or their assigns in any suit brought upon this bond. 55728.00300\33360134.1
SECTION 00620
PAYMENT BOND
37 SECTION 00620
PAYMENT BOND
It is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change, extension of time for performance, addition, alteration or modification in, to, or of any contract (including the Contract Documents), plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted rescission or attempted rescission of the Contract Documents, agreement or bond, nor by any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond, nor by any fraud practiced by any person other than the claimant seeking to recover on the bond and that this bond be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or City and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Section 9100 of the Civil Code, and has not been paid the full amount of his claim and that Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned.
Notwithstanding any other provision of this bond, it is expressly understood, acknowledged and agreed that it shall provide all of the protections required by California Civil Code Sections 9550 through 9566, including the specific coverage protections required by Section 9554.
REMAINDER OF PAGE LEFT INTENTIONALLY BLANK
SIGNATURES ON FOLLOWING PAGE
55728.00300\33360134.1
SECTION 00620
PAYMENT BOND
38 SECTION 00620
PAYMENT BOND
IN WITNESS WHEREOF, two (2) identical counterparts of this instrument, each of which shall for all purposes be deemed an original thereof, have been duly executed by the Principal and Surety above named, on the _____ day of ______________________ 20______ the name and corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative pursuant to authority of its governing body.
CONTRACTOR/PRINCIPAL
(Corporate Seal of Contractor/ _________________________________________ Principal, if a Corporation) Name of Contractor/Principal (Type or Print) By: ___________________________________
Name (Signature)
___________________________________
Name (Type or Print)
___________________________________
Title (Type or Print)
SURETY
(Seal of Surety) _________________________________________ Name of Surety (Type or Print)
By:____________________________________
Attorney-In-Fact
55728.00300\33360134.1
SECTION 00620
PAYMENT BOND
39 SECTION 00620
PAYMENT BOND
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: A copy of the Power-of-Attorney to local representatives of the bonding company must be attached hereto.
END OF PAYMENT BOND FORM
55728.00300\33360134.1
40 SECTION 00700
GENERAL CONDITIONS
SECTION 00700
GENERAL CONDITIONS
ARTICLE 1. DEFINITIONS
a. Acceptable, Acceptance or words of similar import shall be understood to be the acceptance of the Engineer and/or City.
b. Act of God is an earthquake in excess of a magnitude of 3.5 on the Richter scale and tidal waves.
c. Approval means written authorization by Engineer and/or City. d. Contract Documents includes all documents as stated in the Contract. e. City and Contractor are those stated in the Contract. The terms City and Owner may be used interchangeably.
f. Day shall mean calendar day unless otherwise specifically designated. g. Engineer shall mean the City Engineer, or his or her designee, of the City, acting either directly or through properly authorized agents, such as agents acting within the scope of the particular duties entrusted to them. Also sometimes referred to as “City’s Representative” or “Representative” in the Contract Documents. h. Equal, Equivalent, Satisfactory, Directed, Designated, Selected, As Required and similar words shall mean the written approval, selection, satisfaction, direction, or similar action of the Engineer and/or City.
i. Indicated, Shown, Detailed, Noted, Scheduled or words of similar meaning shall mean that reference is made to the drawings, unless otherwise noted. It shall be understood that the direction, designation, selection, or similar import of the Engineer and/or City is intended, unless stated otherwise. j. Install means the complete installation of any item, equipment or material. k. Material shall include machinery, equipment, manufactured articles, or construction such as form work, fasteners, etc., and any other classes of material to be furnished in connection with the Contract. All materials shall be new unless specified otherwise.
l. Perform shall mean that the Contractor, at Contractor’s expense, shall take all actions necessary to complete The Work, including furnishing of necessary labor, tools, and equipment, and providing and installing Materials that are indicated, specified, or required to complete such performance.
m. Project is The Work planned by City as provided in the Contract Documents. n. Provide shall include provide, complete in place, that is furnish, install, test and make ready for use.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
41 SECTION 00700
GENERAL CONDITIONS
o. Recyclable Waste Materials shall mean materials removed from the Project site which are required to be diverted to a recycling center rather than an area landfill.
Recyclable Waste Materials include asphalt, concrete, brick, concrete block, and rock.
p. Specifications means that portion of the Contract Documents consisting of the written requirements for materials, equipment, construction systems, standards and workmanship for the work. Except for Sections 1-9 of the Standard Specifications for Public Works Construction (“Greenbook”), 2015 Edition which are specifically excluded from incorporation into these Contract Documents, the Work shall be done in accordance with the Greenbook, including all current supplements, addenda, and revisions thereof. In the case of conflict between the Greenbook and the Contract Documents, the Contract Documents shall prevail. q. The Work means the entire improvement planned by City pursuant to the Contract Documents.
r. Work means labor, equipment and materials incorporated in, or to be incorporated in the construction covered by the Contract Documents.
ARTICLE 2. CONTRACT DOCUMENTS
a. Contract Documents. The Contract Documents are complementary, and what is called for by one shall be as binding as if called for by all. b. Interpretations. The Contract Documents are intended to be fully cooperative and to be complementary. If Contractor observes that any documents are in conflict, the Contractor shall promptly notify the Engineer in writing. In case of conflicts between the Contract Documents, the order of precedence shall be as follows:
1) Change Orders or Work Change Directives
2) Addenda(s)
3) Special Provisions (or Special Conditions)
4) Technical Specifications
5) Plans (Contract Drawings)
6) Contract
7) General Conditions
8) Instructions to Bidders
9) Notice Inviting Bids
10) Contractor’s Bid Forms
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
42 SECTION 00700
GENERAL CONDITIONS
11) Greenbook Standard Specifications (Sections 1-9 Excluded) 12) Standard Plans
13) Reference Documents
With reference to the Drawings, the order of precedence shall be as follows:
1) Figures govern over scaled dimensions
2) Detail drawings govern over general drawings
3) Addenda(s) or Change Order drawings govern over Contract Drawings 4) Contract Drawings govern over Standard Drawings
5) Contract Drawings govern over Shop Drawings
c. Conflicts in Contract Documents. Notwithstanding the orders of precedence established above, in the event of conflicts, the higher standard shall always apply. d. Organization of Contract Documents. Organization of the Contract Documents into divisions, sections, and articles, and arrangement of drawings shall not control the Contractor in dividing The Work among subcontractors or in establishing the extent of Work to be performed by any trade.
ARTICLE 3. BID DOCUEMNTS
The City will not provide hard copies of bid documents. Contractor shall maintain a clean, undamaged set of Contract Documents at the Project site.
ARTICLE 4. DETAIL DRAWINGS AND INSTRUCTIONS
a. Examination of Contract Documents. Before commencing any portion of The Work, Contractor shall again carefully examine all applicable Contract Documents, the Project site and other information given to Contractor as to materials and methods of construction and other Project requirements. Contractor shall immediately notify the Engineer of any potential error, inconsistency, ambiguity, conflict or lack of detail or explanation. If Contractor performs, permits, or causes the performance of any Work which is in error, inconsistent or ambiguous, or not sufficiently detailed or explained, Contractor shall bear any and all resulting costs, including, without limitation, the cost of correction. In no case shall the Contractor or any subcontractor proceed with Work if uncertain as to the applicable requirements.
b. Additional Instructions. After notification of any error, inconsistency, ambiguity, conflict or lack of detail or explanation, the Engineer will provide any required additional instructions, by means of drawings or other written direction, necessary for proper execution of Work.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
43 SECTION 00700
GENERAL CONDITIONS
c. Quality of Parts, Construction and Finish. All parts of The Work shall be of the best quality of their respective kinds and the Contractor must use all diligence to inform itself fully as to the required construction and finish. In no case shall Contractor proceed with The Work without obtaining first from the Engineer such Approval may be necessary for the proper performance of Work.
d. Contractor’s Variation from Contract Document Requirements. If it is found that the Contractor has varied from the requirements of the Contract Documents including the requirement to comply with all applicable laws, ordinances, rules and regulations, the Engineer may at any time, before or after completion of the Work, order the improper Work removed, remade or replaced by the Contractor at the Contractor’s expense.
ARTICLE 5. EXISTENCE OF UTILITIES AT THE WORK SITE
a. City has endeavored to determine the existence of utilities at the Project site from the records of the owners of known utilities in the vicinity of the Project. b. No excavations were made to verify the locations for underground utilities. It shall be the Contractor’s responsibility alone to determine the exact location of underground utilities or substructures of every nature and to protect them from damage.
c. The service connections to these utilities are not shown on the plans. It shall be the responsibility of the Contractor to determine the exact location of all service connections and, if necessary, Contractor shall arrange for the relocation of service connections. The Contractor shall make its own investigations, including exploratory excavations, to determine the locations and type of service connections, prior to commencing Work which could result in damage to such utilities. The Contractor shall immediately notify City in writing of any utility discovered in a different position than shown on the Plans or which is not shown on the Plans.
d. All water meters, water valves, fire hydrants, electrical utility vaults, telephone vaults, gas utility valves, and other subsurface structures shall be relocated or adjusted to final grade by the Contractor. Locations of existing utilities shown on the Plans are approximate and may not be complete. The Contractor shall be responsible for coordinating its Work with all utility companies during the construction of The Work. The Contractor will not be entitled to damages or additional payment for delays attributable to utility relocations or alterations e. Notwithstanding the above, pursuant to Section 4215 of the Government Code, City has the responsibility to identify, with reasonable accuracy, main or trunkline facilities on the plans and specifications.
f. Contractor, except in an emergency, shall contact the appropriate regional notification center, Southern California Underground Service Alert at 1-800-227- 2600 at least two working days prior to commencing any excavation if the excavation will be performed in an area which is known, or reasonably should be known, to contain subsurface installations other than the underground facilities 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
44 SECTION 00700
GENERAL CONDITIONS
owned or operated by City, and obtain an inquiry identification number from that notification center. No excavation shall be commenced or carried out by the Contractor unless such an inquiry identification number has been assigned to the Contractor or any subcontractor of the Contractor and City has been given the identification number by the Contractor for each individual location identified in the Project plans.
ARTICLE 6. SCHEDULE
a. Estimated Schedule. Within fourteen (14) Days after the issuance of the Notice to Proceed, Contractor shall prepare a Project schedule in Critical Path Method (CPM) format and shall submit this to the Engineer for Approval. The receipt or Approval of any schedules by the Engineer or City shall not in any way relieve the Contractor of its obligations under the Contract Documents. The Contractor is fully responsible to determine and provide for any and all staffing and resources at levels which allow for good quality and timely completion of the Project.
Contractor’s failure to incorporate all elements of Work required for the performance of the Contract or any inaccuracy in the schedule shall not excuse the Contractor from performing all Work required for a completed Project within the specified Contract time period. If the required schedule is not received by the time the first payment under the Contract is due, Contractor shall not be paid until the schedule is received, reviewed and accepted by the Engineer. b. Schedule Contents. The schedule shall indicate the beginning and completion dates of all phases of construction; critical path for all critical, sequential time related activities; and “float time” for all “slack” or “gaps” in the non-critical activities.
The schedule shall clearly identify all staffing and other resources which in the Contractor’s judgment are needed to complete the Project within the time specified for completion. Schedule duration shall match the Contract time. Schedule should indicate the duration of time at each location.
c. Schedule Updates. Contractor shall continuously update its construction schedule. Contractor shall submit an updated and accurate construction schedule to the Engineer whenever requested to do so by Engineer and with each progress payment request. The Engineer may withhold progress payments or other amounts due under the Contract Documents if Contractor fails to submit an updated and accurate construction schedule.
ARTICLE 7. SUBSTITUTIONS
a. Pursuant to Public Contract Code Section 3400(b) City may make a finding that is described in the invitation for bids that designates certain products, things, or services by specific brand or trade name.
b. Unless specifically designated in the Contract Documents, whenever any material, process, or article is indicated or specified by grade, patent, or proprietary name or by name of manufacturer, such Specifications shall be deemed to be used for the purpose of facilitating the description of the material, process or article desired and shall be deemed to be followed by the words “or equal.” Contractor may, unless otherwise stated, offer for substitution any material, process or article which 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
45 SECTION 00700
GENERAL CONDITIONS
shall be substantially equal or better in every respect to that so indicated or specified in the Contract Documents. However, City may have adopted certain uniform standards for certain materials, processes and articles. c. Contractor shall submit requests, together with substantiating data, for substitution of any “or equal” material, process or article no later than ten (10) Days after award of the Contract. To facilitate the construction schedule and sequencing, some requests may need to be submitted before ten (10) Days after award of Contract.
Provisions regarding submission of “or equal” requests shall not in any way authorize an extension of time for performance of this Contract. If a proposed “or equal” substitution request is rejected, Contractor shall be responsible for providing the specified material, process or article. The burden of proof as to the equality of any material, process or article shall rest with the Contractor. City has the complete and sole discretion to determine if a material, process or article is an “or equal” material, process or article that may be substituted. d. Data required to substantiate requests for substitutions of an “or equal” material, process or article data shall include a signed affidavit from the Contractor stating that, and describing how, the substituted “or equal” material, process or article is equivalent to that specified in every way except as listed on the affidavit.
Substantiating data shall include any and all illustrations, specifications, and other relevant data including catalog information which describes the requested substituted “or equal” material, process or article, and substantiates that it is an “or equal” to the material, process or article. The substantiating data must also include information regarding the durability and lifecycle cost of the requested substituted “or equal” material, process or article. Failure to submit all the required substantiating data, including the signed affidavit, to City in a timely fashion will result in the rejection of the proposed substitution.
e. The Contractor shall bear all of City’s costs associated with the review of substitution requests.
f. The Contractor shall be responsible for all costs related to a substituted “or equal” material, process or article.
g. Contractor is directed to the Special Conditions (if any) to review any findings made pursuant to Public Contract Code section 3400.
ARTICLE 8. SHOP DRAWINGS
a. Contractor shall check and verify all field measurements and shall submit with such promptness as to provide adequate time for review and cause no delay in his own Work or in that of any other contractor, subcontractor, or worker on the Project, electronic PDF copies of all shop or setting drawings, calculations, schedules, and materials list, and all other provisions required by the Contract. Contractor shall sign all submittals affirming that submittals have been reviewed and approved by Contractor prior to submission to Engineer. Each signed submittal shall affirm that the submittal meets all the requirements of the Contract Documents except as specifically and clearly noted and listed on the cover sheet of the submittal. The City may elect shop drawing to be submitted electronically. 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
46 SECTION 00700
GENERAL CONDITIONS
b. Contractor shall make any corrections required by the Engineer, and file with the Engineer electronic PDF corrected copies each, and furnish such other copies as may be needed for completion of the Work. Engineer’s approval of shop drawings shall not relieve Contractor from responsibility for deviations from the Contract Documents unless Contractor has, in writing, called Engineer’s attention to such deviations at time of submission and has secured the Engineer’s written Approval.
Engineer’s Approval of shop drawings shall not relieve Contractor from responsibility for errors in shop drawings.
ARTICLE 9. SUBMITTALS
a. Contractor shall furnish to the Engineer for approval, prior to purchasing or commencing any Work, a log of all samples, material lists and certifications, mix designs, schedules, and other submittals, as required in the specifications. Work cannot start prior to approved submittal. Installation shall not begin prior to verification of materials by inspector in the field. Contractor shall have copy of approved submittal along with approved materials available for inspection prior to installation. Installation of unverified materials may result in the inspector requesting installed materials to be exposed. The log shall indicate whether samples will be provided in accordance with other provisions of this Contract. b. Contractor will provide samples and submittals, together with catalogs and supporting data required by the Engineer, to the Engineer within a reasonable time period to provide for adequate review and avoid delays in the Work. c. These requirements shall not authorize any extension of time for performance of this Contract. Engineer will check and approve such samples, but only for conformance with design concept of work and for compliance with information given in the Contract Documents. Work shall be in accordance with approved samples and submittals.
d. Preparing submittal documents does not warrant payment to the contractor and as such will not be included in estimate for progress payment.
ARTICLE 10. MATERIALS
a. Except as otherwise specifically stated in the Contract Documents, Contractor shall provide and pay for all materials, labor, tools, equipment, water, lights, power, transportation, superintendence, temporary constructions of every nature, and all other services and facilities of every nature whatsoever necessary to execute and complete this Contract within specified time. The City will not compensate Contractor for equipment and materials stored in the field and not incorporated into the work product.
b. Unless otherwise specified, all materials shall be new and the best of their respective kinds and grades as noted and/or specified, and workmanship shall be of good quality.
c. Materials shall be furnished in ample quantities and at such times as to ensure uninterrupted progress of The Work and shall be stored properly and protected as 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
47 SECTION 00700
GENERAL CONDITIONS
required by the Contract Documents. Contractor shall be entirely responsible for damage or loss by weather or other causes to materials or Work. d. No materials, supplies, or equipment for Work under this Contract shall be purchased subject to any chattel mortgage or under a conditional sale or other agreement by which an interest therein or in any part thereof is retained by the seller or supplier. Contractor warrants good title to all material, supplies, and equipment installed or incorporated in the work and agrees upon completion of all work to deliver the Project, to City free from any claims, liens, or charges. e. Materials shall be stored on the Project site in such manner so as not to interfere with any operations of City or any independent contractor. f. Materials and equipment delivered but not incorporated into the work will not be included in the estimates for progress payment.
ARTICLE 11. CONTRACTOR’S SUPERVISION
Contractor shall continuously keep at the Project site, a competent and experienced full-time Project superintendent approved by City. Superintendent must be able to proficiently speak, read and write in English. Contractor shall continuously provide efficient supervision of the Project.
ARTICLE 12. WORKERS
a. Contractor shall at all times enforce strict discipline and good order among its employees. Contractor shall not employ on the Project any unfit person or any one not skilled in the Work assigned to him or her.
b. Any employee of the Contractor whom City determines is incompetent or unfit shall be removed from this Project.
ARTICLE 13. SUBCONTRACTORS
a. Contractor agrees to bind every subcontractor to the terms of the Contract Documents as far as such terms are applicable to subcontractor’s portion of The Work. All subcontracts entered into by Contractor relating to any of the Work under this Contract shall comply with and be limited to the extent required by Civil Code section 2872.05. Contractor shall be as fully responsible to City for the acts and omissions of its subcontractors and of persons either directly or indirectly employed by its subcontractors, as Contractor is for acts and omissions of persons directly employed by Contractor. Nothing contained in these Contract Documents shall create any contractual relationship between any subcontractor and City. b. City reserves the right to Approve all subcontractors. City’s Approval of any subcontractor under this Contract shall not in any way relieve Contractor of its obligations in the Contract Documents.
c. Prior to substituting any subcontractor listed in the Bid Forms, Contractor must comply with the requirements of the Subletting and Subcontracting Fair Practices Act pursuant to California Public Contract Code section 4100 et seq. 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
48 SECTION 00700
GENERAL CONDITIONS
ARTICLE 14. PERMITS AND LICENSES
Permits and licenses necessary for prosecution of The Work shall be secured and paid for by Contractor, unless otherwise specified in the Contract Documents. a. Contractor shall obtain a right of way encroachment permit from City prior to commencing any work by submitting a permit application through City’s iWorQ portal. A Contractor’s State License, Contractor’s City Business License, and Certificate of Insurance must be included with the application. Please contact the Associate Engineer at 562-989-7352 for information on the permitting process. b. Contractor shall obtain and pay for all other permits and licenses required for The Work, including excavation permit and for plumbing, mechanical and electrical work and for operations in or over public streets or right of way under jurisdiction of public agencies other than City.
c. Before Acceptance of the Project, the Contractor shall submit all licenses, permits, certificates of inspection and required approvals to City.
ARTICLE 15. UTILITY USAGE
a. All temporary utilities, including but not limited to electricity, water, gas, and telephone, used on the Work shall be furnished and paid for by Contractor.
Contractor shall Provide necessary temporary distribution systems, including meters, if necessary, from distribution points to points on The Work where the utility is needed. Upon completion of The Work, Contractor shall remove all temporary distribution systems.
b. Contractor shall provide necessary and adequate utilities and pay all costs for water, electricity, gas, oil, and sewer charges required for completion of the Project.
c. All permanent meters Installed shall be listed in the Contractor’s name until the Work is accepted.
d. If the Contract is for construction in existing facilities, Contractor may, with prior written Approval of City, use City’s existing utilities by compensating City for utilities used by Contractor.
ARTICLE 16. INSPECTION FEES FOR PERMANENT UTILITIES
All inspection fees and other municipal charges for permanent utilities including, but not limited to, sewer, electrical, phone, gas, water, and irrigation shall be paid for by City. Contractor shall be responsible for arranging the payment of such fees, but inspection fees and other municipal fees relating to permanent utilities shall be paid by City. Contractor may either request reimbursement from City for such fees, or shall be responsible for arranging and coordination with City for the payment of such fees.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
49 SECTION 00700
GENERAL CONDITIONS
ARTICLE 17. TRENCHES
a. Trenches Five Feet or More in Depth. The Contractor shall submit to City, in advance of excavation, a detailed plan showing the design of shoring, bracing, sloping or other provisions to be made for worker protection from the hazard of caving ground during the excavation of any trench or trenches five feet or more in depth. If the plan varies from shoring system standards, the plan shall be prepared by a registered civil or structural engineer. The plan shall not be less effective than the shoring, bracing, sloping, or other provisions of the Construction Safety Orders, as defined in the California Code of Regulations. The City will acknowledge the shoring plan, however, will not approve the shoring plan prepared by the Licensed Civil or Structural Engineer.
b. Excavations Deeper than Four Feet. If work under this Contract involves digging trenches or other excavation that extends deeper than four feet below the surface, Contractor shall promptly, and before the following conditions are disturbed, notify City, in writing, of any:
1) Material that the Contractor believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.
2) Subsurface or latent physical conditions at the site differing from those indicated.
3) Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract.
City shall promptly investigate the conditions, and if it finds that the conditions do so materially differ, or do involve hazardous waste, and cause a decrease or increase in Contractor’s cost of, or the time required for, performance of any part of The Work, shall issue a change order under the procedures described in the Contract Documents.
In the event that a dispute arises between City and the Contractor as to whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the Contractor’s cost of, or time required for, performance of any part of The Work, the Contractor shall not be excused from any scheduled completion date provided for by the Contract, but shall proceed with all Work to be performed under the Contract. Contractor shall retain any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the parties.
ARTICLE 18. DIVERSION OF RECYCLABLE WASTE MATERIALS
In compliance with the applicable City’s waste reduction and recycling efforts, Contractor shall divert all Recyclable Waste Materials to appropriate recycling centers. Contractor will be required to submit weight tickets and written proof of diversion with its monthly progress payment requests, 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
50 SECTION 00700
GENERAL CONDITIONS
with an electronic copy of those documents to Glenn Kriechbaum, Public Works Inspector, at [email protected]. Contractor shall complete and execute any certification forms required by City or other applicable agencies to document Contractor’s compliance with these diversion requirements. All costs incurred for these waste diversion efforts shall be the responsibility of the Contractor.
ARTICLE 19. REMOVAL OF HAZARDOUS MATERIALS
Should Contractor encounter material reasonably believed to be polychlorinated biphenyl (PCB) or other toxic wastes and hazardous materials which have not been rendered harmless at the Project site, the Contractor shall immediately stop work at the affected Project site and shall report the condition to City in writing. City shall contract for any services required to directly remove and/or abate PCBs and other toxic wastes and hazardous materials, if required by the Project site(s), and shall not require the Contractor to subcontract for such services. The Work in the affected area shall not thereafter be resumed except by written agreement of City and Contractor.
ARTICLE 20. SANITARY FACILITIES
Contractor shall provide sanitary temporary toilet buildings for the use of all workers. All toilets shall comply with all applicable federal, state, and local codes ordinances, and regulations.
Toilets shall be kept supplied with toilet paper and shall have workable door fasteners. Toilets shall be serviced no less than once weekly and shall be present in a quantity of not less than 1 per 20 workers as required by CAL-OSHA regulation. The toilets shall be maintained in a sanitary condition at all times. Use of toilet facilities in The Work under construction shall not be permitted.
Any other Sanitary Facilities required by CAL-OSHA shall be the responsibility of the Contractor.
ARTICLE 21. AIR POLLUTION CONTROL
Contractor shall comply with all air pollution control rules, regulations, ordinances and statutes.
All containers of paint, thinner, curing compound, solvent or liquid asphalt shall be labeled to indicate that the contents fully comply with the applicable material requirements.
Without limiting the foregoing, Contractor must fully comply with all applicable laws, rules and regulations in furnishing or using equipment and/or providing services, including, but not limited to, emissions limits and permitting requirements imposed by the South Coast Air Quality Management District (SCAQMD) and/or California Air Resources Board (CARB). Although the SCAQMD and CARB limits and requirements are more broad, Contractor shall specifically be aware of their application to "portable equipment", which definition is considered by SCAQMD and CARB to include any item of equipment with a fuel-powered engine. Contractor shall indemnify City against any fines or penalties imposed by SCAQMD, CARB, or any other governmental or regulatory agency for violations of applicable laws, rules and/or regulations by Contractor, its subcontractors, or others for whom Contractor is responsible under its indemnity obligations provided for in Article 50.
ARTICLE 22. WATER QUALITY MANAGEMENT AND COMPLIANCE
This section is supplemented by the addition of the following requirements in accordance with City Ordinances that establishes stormwater and urban runoff pollution prevention controls. 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
51 SECTION 00700
GENERAL CONDITIONS
a. Storm or construction generated water containing sediment such as construction waste, soil, slurry from concrete/asphalt concrete saw cutting operations, cleanup of concrete transit mixers or other pollutants from construction sites and parking areas shall be retained or controlled on site and shall not be permitted to enter the storm drain system.
b. Temporary sediment filtering systems such as sandbags, silt fences, or gravel berms shall be utilized to trap sediment so that only filtered water enters the City’s storm drain system. Proper clean up and disposal of settled sediment and the filtering system shall be the responsibility of the Contractor. c. Discharge of concrete transit mixer wash water on to approved dirt areas (subgrade area designated for new concrete construction, for example) is acceptable.
Discharge on to private property, parkway areas, or the street is not permitted. d. Plastic or other impervious covering shall be installed where appropriate to prevent erosion of an otherwise unprotected area, along with any other runoff control devices deemed appropriate by the City.
e. Excavated soil stored on the site shall be covered in a manner that minimizes the amount of sediment running into the storm drain system, street, or adjoining properties.
f. No washing of construction or other industrial vehicles and equipment shall be allowed adjacent to a construction site.
g. During the rainy season (October 1 to April 15), Contractor shall keep at the construction site sufficient materials and labor to install temporary sediment filtering systems and other water pollution prevention control measures. These control measures shall be in place and maintained by the Contractor on a daily basis on days when construction is not in progress due to rain. h. All costs associated with water pollution control shall be borne by the Contractor.
Any expense incurred by the City to expeditiously respond to storm drain contamination resulting from Contractor’s failure to implement water pollution control measures will be charged to the Contractor.
i. Contractor is required to comply with all aspects of the Construction General Permit for all projects that involve construction on or disturbance of one acre or more of land or which are part of a larger common area of development. j. City may require Contractor to file the Notice of Intent and obtain coverage for the Project under the Construction General Permit. This may include filing all necessary documentation including the Permit Registration Documents (“PRDs”) through the Stormwater Multiple Applications and Report Tracking System (SMARTS); preparing and implementing a Storm Water Pollution Prevention Plan (“SWPPP”) for the Work site; implementing all other provisions, and monitoring and reporting requirements required by the Construction General Permit; and providing a Qualified SWPPP Developer and Qualified SWPPP Practitioner, as necessary for all Work site activities, including but not limited to preparation and 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
52 SECTION 00700
GENERAL CONDITIONS
submittal of all reports, plans, inspections, and monitoring information in compliance with the Construction General Permit. City retains the right to develop its own documentation for the project site, including but not limited to the SWPPP, and in the alternative may require Contractor to adopt and implement portions of the City-developed SWPPP. Specific requirements for the Work site shall be set forth in the Special Conditions. Contractor shall include all costs of compliance with specified requirements in the Contract amount.
k. For those Work sites where construction activity results in the disturbance of less than one acre of total land area and/or do not need coverage under the Construction General Permit, the Contractor is responsible for preparing and implementing an Erosion and Sediment Control Plan in accordance with the Los Angeles County MS4 Permit and any amendment or renewal thereof. l. Notwithstanding the above, before any PRDs, SWPPP, or other Construction General Permit related document may be submitted to the State Water Resources Control Board or implemented on the Work site, it must first be reviewed by the City and/or the City’s designee, who retains the right to reject or require revisions thereto. The City expressly reserves the right to procure coverage under the Construction General Permit for the Work site if Contractor fails to draft satisfactory PRDs or SWPPP or otherwise fails to proceed in a manner that complies with the requirements of the Construction General Permit. The City additionally reserves the right to hire additional contractors to maintain compliance at the Work site.
Whether Contractor has adequately maintained compliance with the Construction General Permit shall be the City’s sole determination. Any costs incurred by the City in procuring coverage under the Construction General Permit, or drafting and/or implementing a SWPPP for the Work site shall be paid by Contractor. m. Failure to comply with laws, regulations, and ordinances listed in this Article 22 is a violation of federal and state law. Notwithstanding any other indemnity contained in this Agreement, Contractor agrees to indemnify and hold harmless the City, its officials, officers, agents, employees and authorized volunteers from and against any and all claims, demands, losses or liabilities of any kind or nature which the City, its officials, officers, agents, employees and authorized volunteers may sustain or incur for noncompliance with the laws, regulations, and ordinances listed above, arising out of or in connection with the Work, except for liability resulting from the sole established negligence, willful misconduct or active negligence of the City, its officials, officers, agents, employees or authorized volunteers. n. City reserves the right to defend any enforcement action or civil action brought against the City for Contractor’s failure to comply with any applicable water quality law, regulation, or policy. Contractor agrees to be bound by, and to reimburse the City for the costs associated with, any enforcement action and/or settlement reached between the City and any relevant enforcement entity. o. City may seek damages from Contractor for delay in completing the Work in accordance with the Contract Documents, caused by Contractor’s failure to comply with the laws, regulations and policies described in this Article 22, or any other relevant water quality law, regulation, or policy.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
53 SECTION 00700
GENERAL CONDITIONS
ARTICLE 23. CLEANING UP
a. Contractor at all times shall keep premises free from debris such as waste, rubbish, and excess materials and equipment. Contractor shall not store debris under, in, or about the premises. Upon completion of Work, Contractor shall clean the interior and exterior of the building or improvement including fixtures, equipment, walls, floors, ceilings, roofs, window sills and ledges, horizontal projections, and any areas where debris has collected so surfaces are free from foreign material or discoloration. Contractor shall clean and polish all glass, plumbing fixtures, and finish hardware and similar finish surfaces and equipment and contractor shall also remove temporary fencing, barricades, planking and construction toilet and similar temporary facilities from site. Contractor shall also clean all buildings, asphalt and concrete areas to the degree necessary to remove oil, grease, fuel, or other stains caused by Contractor operations or equipment.
b. Contractor shall fully clean up the site at the completion of The Work. If the Contractor fails to immediately clean up at the completion of The Work, City may do so and the cost of such clean up shall be charged back to the Contractor.
ARTICLE 24. LAYOUT AND FIELD ENGINEERING
All field engineering required for laying out The Work and establishing grades for earthwork operations, location and alignment of any and all site elements (buildings, paving, walks, fencing, furnishings, etc.) shall be furnished by the Contractor at its expense. A digital AutoCAD file shall be provided to the Contractor by the City indicating the location and layout of all site elements for the use by the Contractors surveyor. Layout shall be done by a registered civil engineer or a licensed land surveyor Approved by the Engineer. Any surveying necessary to establish the grade and line of the work is to be done by a properly licensed land surveyor retained by the contractor.
ARTICLE 25. EXCESSIVE NOISE
a. The Contractor shall use only such equipment on the work and in such state of repair so that the emission of sound therefrom is within the noise tolerance level of that equipment as established by CAL-OSHA.
b. The Contractor shall comply with the most restrictive of the following: (1) local sound control and noise level rules, regulations and ordinances and (2) the requirements contained in these Contract Documents, including hours of operation requirements. No internal combustion engine shall be operated on the Project without a muffler of the type recommended by the manufacturer. Should any muffler or other control device sustain damage or be determined to be ineffective or defective, the Contractor shall promptly remove the equipment and shall not return said equipment to the job until the device is repaired or replaced. Said noise and vibration level requirements shall apply to all equipment on the job or related to the job, including but not limited to, trucks, transit mixers or transit equipment that may or may not be owned by the Contractor.
c. The contractor should adhere to noise ordinance requirements noted in the City of Signal Hill’s Municipal Code section 9.16.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
54 SECTION 00700
GENERAL CONDITIONS
ARTICLE 26. TESTS AND INSPECTIONS
a. If the Contract Documents, the Engineer, or any instructions, laws, ordinances, or public authority require any part of The Work to be tested or Approved, Contractor shall provide the Engineer at least two (2) working days notice of its readiness for observation or inspection. If inspection is by a public authority other than City, Contractor shall promptly inform City of the date fixed for such inspection.
Required certificates of inspection (or similar) shall be secured by Contractor.
Costs for City testing and City inspection shall be paid by City. Costs of tests for Work found not to be in compliance shall be paid by the Contractor. b. If any Work is done or covered up without the required testing or approval, the Contractor shall uncover or deconstruct the Work, and the Work shall be redone after completion of the testing at the Contractor’s cost in compliance with the Contract Documents.
c. Where inspection and testing are to be conducted by an independent laboratory or agency, materials or samples of materials to be inspected or tested shall be selected by such laboratory or agency, or by City, and not by Contractor. All tests or inspections of materials shall be made in accordance with the commonly recognized standards of national organizations.
d. In advance of manufacture of materials to be supplied by Contractor which must be tested or inspected, Contractor shall notify City so that City may arrange for testing at the source of supply. Any materials which have not satisfactorily passed such testing and inspection shall not be incorporated into The Work. e. If the manufacture of materials to be inspected or tested will occur in a plant or location outside the geographic limits of City, the Contractor shall pay for any excessive or unusual costs associated with such testing or inspection, including but not limited to excessive travel time, standby time and required lodging. f. Reexamination of Work may be ordered by City. If so ordered, Work must be uncovered or deconstructed by Contractor. If Work is found to be in accordance with the Contract Documents, City shall pay the costs of reexamination and reconstruction. If such work is found not to be in accordance with the Contract Documents, Contractor shall pay all costs.
ARTICLE 27. PROTECTION OF WORK AND PROPERTY
a. The Contractor shall be responsible for all damages to persons or property that occur as a result of The Work. Contractor shall be responsible for the proper care and protection of all materials delivered and Work performed until completion and final Acceptance by City. All Work shall be solely at the Contractor’s risk.
Contractor shall adequately protect adjacent property from settlement or loss of lateral support as necessary. Contractor shall comply with all applicable safety laws and building codes to prevent accidents or injury to persons on, about, or adjacent to the Project site where Work is being performed. Contractor shall erect and properly maintain at all times, as required by field conditions and progress of work, all necessary safeguards, signs, barriers, lights, and watchmen for protection 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
55 SECTION 00700
GENERAL CONDITIONS
of workers and the public, and shall post danger signs warning against hazards created in the course of construction.
b. In an emergency affecting safety of life or of work or of adjoining property, Contractor, without special instruction or authorization from the Engineer, is hereby permitted to act to prevent such threatened loss or injury; and Contractor shall so act, without appeal, if so authorized or instructed by the Engineer or City. Any compensation claimed by Contractor on account of emergency work shall be determined by and agreed upon by City and the Contractor. c. Contractor shall provide such heat, covering, and enclosures as are necessary to protect all Work, materials, equipment, appliances, and tools against damage by weather conditions.
d. Contractor shall take adequate precautions to protect existing sidewalks, curbs, pavements, utilities, and other adjoining property and structures, and to avoid damage thereto, and Contractor shall repair any damage thereto caused by The Work operations. Contractor shall:
1) Enclose the working area with a substantial barricade, and arrange work to cause minimum amount of inconvenience and danger to the public. 2) Provide substantial barricades around any shrubs or trees indicated to be preserved.
3) Deliver materials to the Project site over a route designated by the Engineer.
4) Provide any and all dust control required and follow the Applicable air quality regulations as appropriate. If the Contractor does not comply, City shall have the immediate authority to provide dust control and deduct the cost from payments to the Contractor.
5) Confine Contractor’s apparatus, the storage of materials, and the operations of its workers to limits required by law, ordinances, permits, or directions of the Engineer. Contractor shall not unreasonably encumber the Project site with its materials.
6) Take care to prevent disturbing or covering any survey markers, monuments, or other devices marking property boundaries or corners. If such markers are disturbed by accident, they shall be replaced by an approved civil engineer or land surveyor, at no cost to City. 7) Ensure that existing facilities, fences and other structures are all adequately protected and that, upon completion of all Work, all facilities that may have been damaged are restored to a condition acceptable to City.
8) Preserve and protect from injury all buildings, pole lines and all direction, warning and mileage signs that have been placed within the right-of-way. 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
56 SECTION 00700
GENERAL CONDITIONS
9) At the completion of work each day, leave the Project site in a clean, safe condition.
10) Comply with any stage construction and traffic handling plans. Access to residences and businesses shall be maintained at all times. e. These precautionary measures will apply continuously and not be limited to normal working hours. Full compensation for the Work involved in the preservation of life, safety and property as above specified shall be considered as included in the prices paid for the various contract items of Work, and no additional allowance will be made therefor.
f. Should damage to persons or property occur as a result of The Work, Contractor shall be responsible for proper investigation, documentation, including video or photography, to adequately memorialize and make a record of what transpired.
City shall be entitled to inspect and copy any such documentation, video, or photographs.
ARTICLE 28. CONTRACTORS MEANS AND METHODS
Contractor is solely responsible for the means and methods utilized to Perform The Work. In no case shall the Contractor’s means and methods deviate from commonly used industry standards.
ARTICLE 29. [NOT USED]
ARTICLE 30. AUTHORIZED REPRESENTATIVES
City shall designate representatives, who shall have the right to be present at the Project site at all times. City may designate an inspector who shall have the right to observe all of the Contractor’s Work. The inspector is not authorized to make changes in the Contract Documents.
The inspector shall not be responsible for the Contractor’s failure to carry out The Work in accordance with the Contract Documents. Contractor shall provide safe and proper facilities for such access.
ARTICLE 31. HOURS OF WORK
a. Eight (8) hours of work shall constitute a legal day’s work. The Contractor and each subcontractor shall forfeit, as penalty to City, twenty-five dollars ($25) for each worker employed in the execution of Work by the Contractor or any subcontractor for each day during which such worker is required or permitted to work more than eight (8) hours in any one day and forty (40) hours in any week in violation of the provisions of the Labor Code, and in particular, Section 1810 to Section 1815, except as provided in Labor Code Section 1815. b. Unless otherwise provided in the Special Conditions, Work shall be accomplished on a regularly scheduled eight (8) hour per day work shift basis, Monday through Friday, between the hours of 8:00 a.m. and 4:30 p.m., except on arterial streets, where work hours are between 9:00 a.m. and 4:30 p.m.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
57 SECTION 00700
GENERAL CONDITIONS
c. It shall be unlawful for any person to operate, permit, use, or cause to operate any of the following at the Project site, other than between the hours of 8:00 a.m. to 4:30 p.m., Monday through Friday, with no Work allowed on City-observed holidays, unless otherwise Approved by the Engineer:
1) Powered Vehicles
2) Construction Equipment
3) Loading and Unloading Vehicles
4) Domestic Power Tool.
ARTICLE 32. PAYROLL RECORDS
a. Pursuant to Labor Code Section 1776, the Contractor and each subcontractor shall maintain weekly certified payroll records showing the name, address, social security number, work classification, straight time and overtime hours paid each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker or other employee employed in connection with the work.
Contractor shall certify under penalty of perjury that records maintained and submitted by Contractor are true and accurate. Contractor shall also require subcontractor(s) to certify weekly payroll records under penalty of perjury. b. In accordance with Labor Code section 1771.4, the Contractor and each subcontractor shall furnish the certified payroll records directly to the Department of Industrial Relations (“DIR”) on a weekly basis and in the format prescribed by the DIR, which may include electronic submission. Contractor shall comply with all requirements and regulations from the DIR relating to labor compliance monitoring and enforcement.
c. The payroll records described herein shall be certified and submitted by the Contractor at a time designated by City. The Contractor shall also provide the following:
1) A certified copy of the employee’s payroll records shall be made available for inspection or furnished to such employee or his or her authorized representative on request.
2) A certified copy of all payroll records described herein shall be made available for inspection or furnished upon request of the Department of Industrial Relations (“DIR”).
d. The certified payroll records shall be on forms provided by the Division of Labor Standards Enforcement (“DLSE”) of the DIR or shall contain the same information as the forms provided by the DLSE.
e. Any copy of records made available for inspection and furnished upon request to the public shall be marked or obliterated in such a manner as to prevent disclosure 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
58 SECTION 00700
GENERAL CONDITIONS
of an individual’s name, address, and social security number. The name and address of the Contractor or any subcontractor shall not be marked or obliterated. f. In the event of noncompliance with the requirements of this Section, the Contractor shall have ten (10) days in which to comply subsequent to receipt of written notice specifying any item or actions necessary to ensure compliance with this section.
Should noncompliance still be evident after such ten (10) day period, the Contractor shall, as a penalty to City, forfeit one hundred dollars ($100.00) for each day, or portion thereof, for each worker until strict compliance is effectuated. Upon the request of the DIR, such penalties shall be withheld from contract payments.
ARTICLE 33. PREVAILING RATES OF WAGES
a. The Contractor is aware of the requirements of Labor Code Sections 1720 et seq. and 1770 et seq., as well as California Code of Regulations, Title 8, Section 16000 et seq. (“Prevailing Wage Laws”), which require the payment of prevailing wage rates and the performance of other requirements on certain “public works” and “maintenance” projects. Since this Project involves an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws. The Contractor shall obtain a copy of the prevailing rates of per diem wages at the commencement of this Agreement from the website of the Division of Labor Statistics and Research of the Department of Industrial Relations located at www.dir.ca.gov/dlsr/. In the alternative, the Contractor may view a copy of the prevailing rates of per diem wages at City. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to perform work on the Project available to interested parties upon request, and shall post copies at the Contractor’s principal place of business and at the Project site. Contractor shall defend, indemnify and hold City, its elected officials, officers, employees and agents free and harmless from any claims, liabilities, costs, penalties or interest arising out of any failure or allege failure to comply with the Prevailing Wage Laws.
b. The Contractor and each subcontractor shall forfeit as a penalty to City not more than two hundred dollars ($200) for each calendar day, or portion thereof, for each worker paid less than the stipulated prevailing wage rate for any work done by him, or by any subcontract under him, in violation of the provisions of the Labor Code.
The difference between such stipulated prevailing wage rate and the amount paid to each worker for each calendar day or portion thereof for which each worker was paid less than the stipulated prevailing wage rate shall be paid to each worker by the Contractor.
c. Contractor shall post, at appropriate conspicuous points on the Project site, a schedule showing all determined general prevailing wage rates and all authorized deductions, if any, from unpaid wages actually earned.
ARTICLE 34. EMPLOYMENT OF APPRENTICES
The Contractor’s attention is directed to the provisions of Sections 1777.5, 1777.6, and 1777.7 of the Labor Code concerning employment of apprentices by the Contractor or any subcontractor. 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
59 SECTION 00700
GENERAL CONDITIONS
The Contractor shall obtain a certificate of apprenticeship before employing any apprentice pursuant to Section 1777.5, 1777.6, and 1777.7 of the Labor Code. Information relative to apprenticeship standards, wage schedules, and other requirements may be obtained from the Director of Industrial Relations, the Administrator of Apprenticeships, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.
ARTICLE 35. NONDISCRIMINATION/EQUAL EMPLOYMENT OPPORTUNITY Pursuant to Labor Code Section 1735 and other applicable provisions of law, the Contractor and its subcontractors shall not discriminate against any employee or applicant for employment because of race, color, religion, sex, national origin, age, political affiliation, marital status, or handicap on this Project. The Contractor will take affirmative action to insure that employees are treated during employment or training without regard to their race, color, religion, sex, national origin, age, political affiliation, marital status, or handicap.
ARTICLE 36. LABOR/EMPLOYMENT SAFETY
The Contractor shall maintain emergency first aid treatment for his employees which complies with the Federal Occupational Safety and Health Act of 1970 (29 U.S.C. § 651 et seq.), and California Code of Regulations, Title 8, Industrial Relations Division 1, Department of Industrial Relations, Chapter 4.
ARTICLE 37. INSURANCE
Contractor agrees to procure and maintain, at Contractor’s expense all insurance specified in Appendix “1” attached hereto and by this reference incorporated herein. Contractor shall require all subcontractors to carry the same policies and limits of insurance that the Contractor is required to maintain, unless otherwise approved in writing by the City.
ARTICLE 38. TIME FOR COMPLETION AND LIQUIDATED DAMAGES
a. Time for Completion/Liquidated Damages. Work shall be commenced within ten (10) days of the date stated in City’s Notice to Proceed and shall be completed by Contractor in the time specified in the Contract Documents. City is under no obligation to consider early completion of the Project; and the Contract completion date shall not be amended by City’s receipt or acceptance of the Contractor’s proposed earlier completion date. Furthermore, Contractor shall not, under any circumstances, receive additional compensation from City (including but not limited to indirect, general, administrative or other forms of overhead costs) for the period between the time of earlier completion proposed by the Contractor and the Contract completion date. If The Work is not completed as stated in the Contract Documents, it is understood that City will suffer damage. In accordance with Government Code section 53069.85, being impractical and infeasible to determine the amount of actual damage, it is agreed that Contractor shall pay to City as fixed and liquidated damages, and not as a penalty, the sum stipulated in the Contract for each day of delay until The Work is fully completed. Contractor and its surety shall be liable for any liquidated damages. Any money due or to become due the Contractor may be retained to cover liquidated damages. The Liquidated Damage for this project is $1000 per working day.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
60 SECTION 00700
GENERAL CONDITIONS
b. Inclement Weather. Contractor shall abide the Engineer’s determination of what constitutes inclement weather. Time extensions for inclement weather shall only be granted when the Work stopped during inclement weather is on the critical path of the Project schedule.
c. Extension of Time. Contractor shall not be charged liquidated damages because of any delays in completion of The Work due to unforeseeable causes beyond the control and without the fault or negligence of Contractor (or its subcontractors or suppliers). Contractor shall within five (5) Days of identifying any such delay notify City in writing of causes of delay. City shall ascertain the facts and extent of delay and grant extension of time for completing The Work when, in its judgment, the facts justify such an extension. Time extensions to the Project shall be requested by the Contractor as they occur and without delay. No delay claims shall be permitted unless the event or occurrence delays the completion of the Project beyond the Contract completion date.
d. No Damages for Reasonable Delay. City’s liability to Contractor for delays for which City is responsible shall be limited to only an extension of time unless such delays were unreasonable under the circumstances. In no case shall City be liable for any costs which are borne by the Contractor in the regular course of business, including, but not limited to, home office overhead and other ongoing costs.
Damages caused by unreasonable City delay, including delays caused by items that are the responsibility of City pursuant to Government Code section 4215, shall be based on actual costs only, no proportions or formulas shall be used to calculate any delay damages.
ARTICLE 39. COST BREAKDOWN AND PERIODIC ESTIMATES
Contractor shall furnish on forms Approved by City:
a. Within ten (10) Days of award of the Contract a detailed estimate giving a complete breakdown of the Contract price;
b. A monthly itemized estimate of Work done for the purpose of making progress payments. In order for City to consider and evaluate each progress payment application, the Contractor shall submit a detailed measurement of Work performed and a progress estimate of the value thereof before the tenth (10th) Day of the following month.
c. Contractor shall submit, with each of its payment requests, an adjusted list of actual quantities, verified by the Engineer, for unit price items listed, if any, in the Bid Form.
d. Following City’s Acceptance of the Work, the Contractor shall submit to City a written statement of the final quantities of unit price items for inclusion in the final payment request.
e. City shall have the right to adjust any estimate of quantity and to subsequently correct any error made in any estimate for payment.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
61 SECTION 00700
GENERAL CONDITIONS
Contractor shall certify under penalty of perjury, that all cost breakdowns and periodic estimates accurately reflect the Work on the Project.
ARTICLE 40. MOBILIZATION
a. When a bid item is included in the Bid Form for mobilization, the costs of Work in advance of construction operations and not directly attributable to any specific bid item will be included in the progress estimate (“Initial Mobilization”). When no bid item is provided for “Initial Mobilization,” payment for such costs will be deemed to be included in the other items of The Work.
b. Payment for Initial Mobilization based on the lump sum provided in the Bid Form, which shall constitute full compensation for all such Work. No payment for Initial Mobilization will be made until all of the listed items have been completed to the satisfaction of the Engineer. The scope of the Work included under Initial Mobilization shall include, but shall not be limited to, the following principal items:
1) Obtaining and paying for all bonds, insurance, and permits. 2) Moving on to the Project site of all Contractor’s plant and equipment required for first week’s operations.
3) Submittal of detailed Preliminary Construction Schedule and Traffic Control Plan.
4) Submittal of Initial Construction Schedule, embodying all corrections required by the Engineer. No Payment for mobilization can be made until the Engineer has approved the schedule in writing.
5) Installing temporary construction power, wiring, and lighting facilities. 6) Establishing fire protection system.
7) Developing and installing a construction water supply. 8) Providing and maintaining the field office trailers for the Contractor and the Engineer, complete, with all specified furnishings and utility services including telephones, telephone appurtenances, computer and printer, and copying machine.
9) Providing on-site communication facilities for the Owner and the Engineer, including telephones, radio pagers, and fax machines.
10) Providing on-site sanitary facilities and potable water facilities as specified per Cal-OSHA and these Contract Documents.
11) Furnishing, installing, and maintaining all storage buildings or sheds required for temporary storage of products, equipment, or materials that have not yet been installed in the Work. All such storage shall meet manufacturer’s specified storage requirements, and the specific provisions 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
62 SECTION 00700
GENERAL CONDITIONS
of the specifications, including temperature and humidity control, if recommended by the manufacturer, and for all security.
12) Arranging for and erection of Contractor’s work and storage yard. 13) Submittal and City approval of required Contractor notices and door hangers.
14) Posting all OSHA required notices and establishment of safety programs per Cal-OSHA.
15) Full-time presence of Contractor’s superintendent at the job site as required herein.
ARTICLE 41. PAYMENTS
a. City shall make monthly progress payments following receipt of undisputed and properly submitted payment requests. Contractor shall be paid a sum equal to ninety-five percent (95%) of the value of Work performed up to the last day of the previous month, less the aggregate of previous payments. b. The Contractor shall, after the full completion of The Work, submit a final payment application. All prior progress estimates shall be subject to correction in the final estimate and payment.
c. Unless otherwise required by law, the final payment of five percent (5%) of the value of the Work (or ten percent (10%) in the event the City has adopted a finding that the Work under the Contract is substantially complex), if unencumbered, shall be paid no later than sixty (60) Days after the date of recordation of the Notice of Completion.
d. Acceptance by Contractor of the final payment shall constitute a waiver of all claims against City arising from this Contract.
e. Payments to the Contractor shall not be construed to be an acceptance of any defective work or improper materials, or to relieve the Contractor of its obligations under the Contract Documents.
f. The Contractor shall submit with each payment request the Contractor’s conditional waiver of lien for the entire amount covered by such payment request, as well as a valid unconditional waiver of lien from the Contractor and all subcontractors and materialmen for all work and materials included in any prior invoices. Waivers of lien shall be in the forms prescribed by California Civil Code Section 8132. Prior to final payment by City, the Contractor shall submit a final waiver of lien for the Contractor’s work, together with releases of lien from any subcontractor or materialmen.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
63 SECTION 00700
GENERAL CONDITIONS
ARTICLE 42. PAYMENTS WITHHELD AND BACKCHARGES
a. In addition to amounts which City may retain under other provisions of the Contract Documents City may withhold payments due to Contractor as may be necessary to cover:
1) Stop Notice Claims.
2) Defective work not remedied.
3) Failure of Contractor to make proper payments to its subcontractors or suppliers.
4) Completion of the Contract if there exists a reasonable doubt that the work can be completed for balance then unpaid.
5) Damage to another contractor or third party.
6) Amounts which may be due City for claims against Contractor. 7) Failure of Contractor to keep the record (“as-built”) drawings up to date. 8) Failure to provide updates on the construction schedule. 9) Site clean up.
10) Failure of the Contractor to comply with requirements of the Contract Documents.
11) Liquated damages.
12) Legally permitted penalties.
b. Upon completion of the Contract, City will reduce the final Contract amount to reflect costs charged to the Contractor, backcharges or payments withheld pursuant to the Contract Documents.
ARTICLE 43. CHANGES AND EXTRA WORK
a. Change Order Work.
1) City, without invalidating the Contract, may order changes in the Work consisting of additions, deletions or other revisions, and the Contract Price and Contract Time will be adjusted accordingly. All such changes in the Work shall be authorized by Change Order, shall be performed under the applicable conditions of the Contract Documents, and shall be subject to the approval authority requirements of Article 4 of the Contract. A Change Order signed by the Contractor indicates the Contractor's agreement therewith, including any adjustment in the Contract amount or the Contract 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
64 SECTION 00700
GENERAL CONDITIONS
time, and the full and final settlement of all costs (direct, indirect and overhead) related to the Work authorized by the Change Order. 2) All claims for additional compensation to the Contractor shall be presented in writing before the expense is incurred and will be adjusted as provided herein. No work shall be allowed to lag pending such adjustment, but shall be promptly executed as directed, even if a dispute arises. No claim will be considered after the work in question has been done unless a written contract change order has been issued or a timely written notice of claim has been made by Contractor. Contractor shall not be entitled to claim or bring suit for damages, whether for loss of profits or otherwise, on account of any decrease or omission of any item or portion of Work to be done.
Whenever any change is made as provided for herein, such change shall be considered and treated as though originally included in the Contract, and shall be subject to all terms, conditions and provisions of the original Contract.
3) Owner Initiated Change. The Contractor must submit a complete cost proposal, including any change in the Contract time, within seven (7) Days after receipt of a scope of a proposed change order, unless City requests that proposals be submitted in less than seven (7) Days. 4) Contractor Initiated Change. The Contractor must give written notice of a proposed change order required for compliance with the Contract Documents within seven (7) Days of discovery of the facts giving rise to the proposed change order.
5) Whenever possible, any changes to the Contract amount shall be in a lump sum mutually agreed to by the Contractor and City.
6) Price quotations from the Contractor shall be accompanied by sufficiently detailed supporting documentation to permit verification by City. 7) If the Contractor fails to submit the cost proposal within the seven (7) Day period (or as requested), City has the right to order the Contractor in writing to commence the work immediately on a force account basis and/or issue a lump sum change to the contract price in accordance with City’s estimate of cost. If the change is issued based on City estimate, the Contractor will waive its right to dispute the action unless within fifteen (15) Days following completion of the added/deleted work, the Contractor presents written proof that City’s estimate was in error.
8) Estimates for lump sum quotations and accounting for cost-pluspercentage work shall be limited to direct expenditures necessitated specifically by the subject extra work, and shall be segregated as follows:
(a) Labor. The costs of labor will be the actual cost for wages prevailing locally for each craft or type of worker at the time the extra work is done, plus employer payments of payroll taxes and insurance, health and welfare, pension, vacation, apprenticeship funds, and 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
65 SECTION 00700
GENERAL CONDITIONS
other direct costs resulting from Federal, State or local laws, as well as assessment or benefits required by lawful collective bargaining agreements. The use of a labor classification which would increase the extra work cost will not be permitted unless the contractor establishes the necessity for such additional costs. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. (b) Materials. The cost of materials reported shall be at invoice or lowest current price at which such materials are locally available in the quantities involved, plus sales tax, freight and delivery.
Materials cost shall be based upon supplier or manufacturer’s invoice. If invoices or other satisfactory evidence of cost are not furnished within fifteen (15) Days of delivery, then the Engineer shall determine the materials cost, at its sole discretion. (c) Tool and Equipment Use. No payment will be made for the use of small tools, tools which have a replacement value of $1,000 or less. (d) Equipment Rental Rates. Equipment rental rates shall be per Section 9, Sub-section 9-1.04D “Equipment Rental”, of Caltrans 2018 Standard Specifications, using the Caltrans current “Labor Surcharge and Equipment Rental Rates” at the time the Extra Work is being performed.
(e) Overhead, Profit and Other Charges. The mark-up for overhead (including supervision) and profit on work added to the Contract shall be according to the following:
i. “Net Cost” is defined as consisting of costs of labor, materials and tools and equipment only excluding overhead and profit.
ii. The costs of applicable insurance and bond premium is included in overhead percentage below.
iii. For Work performed by the Contractor’s forces the added cost for overhead and profit shall not exceed fifteen percent (15%) of the Net Cost of the Work.
iv. For Work performed by a subcontractor, the added cost for overhead and profit shall not exceed fifteen percent (15%) of the Net Cost of the Work to which the Contractor may add five percent (5%) of the subcontractor’s Net Cost.
v. For Work performed by a sub-subcontractor the added cost for overhead and profit shall not exceed fifteen percent (15%) of the Net Cost for Work to which the subcontractor and general contractor may each add an additional five
percent (5%) of the Net Cost of the lower tier subcontractor. 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
66 SECTION 00700
GENERAL CONDITIONS
9) All of the following costs are included in the markups for overhead and profit described above, and Contractor shall not receive any additional compensation for: Submittals, drawings: field drawings, Shop Drawings, including submissions of drawings; field inspection; General Superintendence; General administration and preparation of cost proposals, schedule analysis, Change Orders, and other supporting documentation; computer services; reproduction services; Salaries of project engineer, superintendent, timekeeper, storekeeper, and secretaries; Janitorial services; Small tools, incidentals and consumables; Temporary on Site facilities (Offices, Telephones, Internet access, Plumbing, Electrical Power, lighting; Platforms, Fencing, Water), Jobsite and Home office overhead or other expenses; vehicles and fuel used for work otherwise included in the Contract Documents; Surveying; Estimating; Protection of Work; Handling and disposal fees; Final cleanup; Other incidental Work; Related warranties.
10) For added or deducted Work by subcontractors, the Contractor shall furnish to City the subcontractor’s signed detailed estimate of the cost of labor, material and equipment, including the subcontractor markup for overhead and profit. The same requirement shall apply to sub-subcontractors. 11) For added or deducted work furnished by a vendor or supplier, the Contractor shall furnish to City a detailed estimate or quotation of the cost to the Contractor, signed by such vendor or supplier.
12) Any change in The Work involving both additions and deletions shall indicate a net total cost, including subcontracts and materials. Allowance for overhead and profit, as specified herein, shall be applied if the net total cost is an extra; overhead and profit allowances shall not be applied if the net total cost is a credit. The estimated cost of deductions shall be based on labor and material prices on the date the Contract was executed. 13) Contractor shall not reserve a right to assert impact costs, extended job site costs, extended overhead, constructive acceleration and/or actual acceleration beyond what is stated in the change order for work. No claims shall be allowed for impact, extended overhead costs, constructive acceleration and/or actual acceleration due to a multiplicity of changes and/or clarifications. The Contractor may not change or modify City’s change order form in an attempt to reserve additional rights. 14) If City disagrees with the proposal submitted by Contractor, it will notify the Contractor and City will provide its opinion of the appropriate price and/or time extension. If the Contractor agrees with City, a change order will be issued by City. If no agreement can be reached, City shall have the right to issue a unilateral change order setting forth its determination of the reasonable additions or savings in costs and time attributable to the extra or deleted work. Such determination shall become final and binding if the Contractor fails to submit a claim in writing to City within fifteen (15) Days of the issuance of the unilateral change order, disputing the terms of the unilateral change order.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
67 SECTION 00700
GENERAL CONDITIONS
15) No dispute, disagreement or failure of the parties to reach agreement on the terms of the change order shall relieve the Contractor from the obligation to proceed with performance of the work, including extra work, promptly and expeditiously.
16) Any alterations, extensions of time, extra work or any other changes may be made without securing consent of the Contractor’s surety or sureties. b. Contract Unit Prices
Section 3.2.2.2 and 3.2.2.3 of the Standard Specification For Public Works Construction (Green Book) provisions are not applicable. c. Changes to Contract Time
1) The Contract Time may only be changed by a Change Order. 2) All changes in the Contract Price and/or adjustments to the Contract Times related to each change shall be included in Contractor’s change order proposal described above. All Change Orders must state that the Contract Time is not changed or is either increased or decreased by a specific number of days. Failure to include a change to time shall waive any change to the Contract Time unless the parties mutually agree in writing to postpone a determination of the change to time resulting from the Change Order. No cost or time will be allowed for cumulative effects of multiple changes.
3) Notice of the amount of the request for adjustment in the Contract Time with supporting data shall be delivered within seven (7) Days after such start of occurrence. No extension of time or additional compensation shall be given for a delay if the Contractor failed to give notice in the manner and within the time prescribed.
4) Float is for the benefit of the Project. Float shall not be considered for the exclusive use or benefit of either the City or the Contractor. Any difference in time between the Contractor’s early completion and the Contract Time shall be considered a part of the Project float. Contractor shall not be entitled to compensation, and the City will not compensate Contractor, for delays which impact early completion.
5) Contractor’s entitlement to an extension of the Contract Time is limited to City-caused extension of the critical path, reduced by the Contractor’s concurrent delays, and established by a proper time impact analysis. No time extension shall be allowed unless, and then only to the extent that, the City-caused delay extends the critical path beyond the previously approved Contract Time.
(a) Contractor shall not be entitled to an adjustment in the Contract Time for delays within the control of Contractor. Delays attributable 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
68 SECTION 00700
GENERAL CONDITIONS
to and within the control of a subcontractor or supplier shall be deemed to be delays within the control of Contractor.
(b) If Contractor is delayed in the performance or progress of the Work by fire, flood, epidemic, abnormal weather conditions (as determined by the City), Acts of God, acts or failures to act of utility owners not under the control of City, or other causes not the fault of and beyond control of the City and Contractor, then Contractor shall be entitled to a time extension when the affected Work is on the critical path. Such a non-compensable adjustment shall be Contractor’s sole and exclusive remedy for such delays. Contractor must submit a timely request in accordance with the requirements of this Article.
6) Requests for Contract Extension: Contractor’s justification for entitlement shall be clear and complete citing specific Contract Document references and reasons on which Contractor’s entitlement is based. At a minimum, each request for a time extension must include:
(a) Each request for an extension of Contract Time must identify the impacting event, in narrative form, providing a description of the delay event and sufficient justification as to why the Contractor is entitled to a time extension. Contractor must demonstrate that the delay arises from unforeseeable causes beyond the control and without the fault or negligence of both Contractor and any Subcontractors or Suppliers, or any other persons or organizations employed by any of them or for whose acts any of them may be liable, and that such causes in fact lead to performance or completion of the Work, or specified part in question, beyond the corresponding Contract Times, despite Contractor’s reasonable and diligent actions to guard against those effects.
(b) Each request for an extension of Contract Time must include a time impact analysis in CPM format to calculate the impact of the delay event.
7) Contractor’s failure, neglect, or refusal to comply with these requirements, or any portion thereof, shall bar Contractor’s request for extensions of the Contract Time. Such failure, neglect, or refusal prejudices the City’s ability to recognize and mitigate delay, and such failure, neglect, or refusal prevent the timely analysis of requests for extensions of Contract Time, and whether such extensions may be warranted. Contractor hereby waives all rights to extensions of Contract Time due to delays or accelerations that result from or occur during periods of time for which Contractor fails, neglects, or refuses to fully comply with the requirements of this Article. 8) Force Majeure: The time period(s) specified in the Schedule of Performance for performance of the services rendered pursuant to this Agreement shall be extended because of any delays due to unforeseeable causes beyond the control and without the fault or negligence of the 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
69 SECTION 00700
GENERAL CONDITIONS
Contractor, including, but not restricted to, Acts of God or of the public enemy, unusually severe weather, fires, earthquakes, floods, epidemics, pandemics, quarantine restrictions, riots, strikes, freight embargoes, wars, litigation, and/or acts of any governmental agency, including the City, if the Contractor shall within ten (10) Days of the commencement of such delay notify the Contract Officer in writing of the causes of the delay. The Contract Officer shall ascertain the facts and the extent of delay, and extend the time for performing the services for the period of the enforced delay when and if in the judgment of the Contract Officer such delay is justified. The Contract Officer's determination shall be final and conclusive upon the parties to this Agreement. In no event shall Contractor be entitled to recover damages against the City for any delay in the performance of this Agreement, however caused, Contractor's sole remedy being extension of the Agreement pursuant to this Section.
ARTICLE 44. OCCUPANCY
City reserves the right to occupy or utilize any portion of The Work at any time before completion, and such occupancy or use shall not constitute Acceptance of any part of Work covered by this Contract. This use shall not relieve the Contractor of its responsibilities under the Contract.
ARTICLE 45. RECORD (“AS BUILT”) DRAWINGS
a. Contractor shall prepare and maintain a complete set of record drawings (herein referred to as “as-builts”) and shall require each trade to prepare its own as-builts.
The as-builts must show the entire site for each major trade, including but not limited to water, sewer, electrical, data, telephone, cable, fire alarm, gas and plumbing. Contractor shall mark the as-builts to show the actual installation where the installation varies from the Work as originally shown. Contractor shall mark whichever drawings are most capable of showing conditions fully and where shop drawings are used, Contractor must record a cross-reference at the corresponding location on the contract drawings. Contractor shall give particular attention to concealed elements that would be difficult to measure and record at a later date.
Contractor shall use colors to distinguish variations in separate categories of The Work.
b. Contractor shall note related change order, request for information, request for proposals, or Architect’s Supplemental Instructions where applicable. Contractor shall organize as-builts into manageable sets, bound with durable paper cover sheets and shall print suitable title, dates and other identification on the cover of each set. Contractor to also provide an electronic version of the as-builts in .pdf or other approved format. The suitability of the as-builts will be determined by the Engineer.
ARTICLE 46. INDEMNIFICATION
Contractor shall defend (with counsel of City Council’s choosing), indemnify and hold City, its officials, officers, agents, employees, and representatives free and harmless from any and all 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
70 SECTION 00700
GENERAL CONDITIONS
claims, demands, causes of action, costs, expenses, liabilities, losses, damages or injuries, in law or equity, regardless of whether the allegations are false, fraudulent, or groundless, to property or persons, including wrongful death, to the extent arising out of or incident to any acts, omissions or willful misconduct of Contractor, its officials, officers, employees, agents, consultants and contractors arising out of or in connection with the performance of the Work or this Contract, including claims made by subcontractors for nonpayment, including without limitation the payment of all consequential damages and attorneys’ fees and other related costs and expenses. To the fullest extent permitted by law, Contractor shall defend, at Contractor’s own cost, expense and risk, with City Council’s choosing, any and all such aforesaid suits, actions or other legal proceedings of every kind that may be brought or instituted against City, its officials, officers, agents, employees and representatives. To the extent of its liability, Contractor shall pay and satisfy any judgment, award or decree that may be rendered against City, its officials, officers, employees, agents, employees and representatives, in any such suit, action or other legal proceeding. Contractor shall reimburse City, its officials, officers, agents, employees and representatives for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided. The only limitations on this provision shall be those imposed by Civil Code Section 2782.
ARTICLE 47. RESOLUTION OF CONSTRUCTION CLAIMS
a. Contractor shall timely comply with all notices and requests for additional compensation and extensions of time, including but not limited to all requirements of Article 43, as a prerequisite to filing any claim governed by this Article. The failure to timely submit a notice of delay or notice of change, or to timely a change to the Contract Price or Contract Time, or to timely provide any other notice or request required herein shall constitute a waiver of the right to further pursue the claim under the Contract or at law.
b. Intent. Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitration to resolve disputes on construction claims of $375,000 or less. Effective January 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Article is to implement Sections 20104 et seq. and Section 9204 of the California Public Contract Code.
This Article shall be construed to be consistent with said statutes. c. Claims. For purposes of this Article, “Claim” means a separate demand by the Contractor, after a change order duly requested in accordance with Article 49 has been denied by the City, for (1) a time extension, (2) payment of money or damages arising from Work done by or on behalf of the Contractor pursuant to the Contract, or (3) an amount the payment of which is disputed by the City. A “Claim” does not include any demand for payment for which the Contractor has failed to provide notice, request a change order, or otherwise failed to follow any procedures contained in the Contract Documents.
d. Filing Claims. Claims governed by this Article may not be filed unless and until the Contractor completes all procedures for giving notice of delay or change and for the requesting of a time extension or change order, including but not necessarily limited to the procedures contained in Article 49, and Contractor’s 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
71 SECTION 00700
GENERAL CONDITIONS
request for a change has been denied in whole or in part. Claims governed by this Article must be filed no later than fourteen (14) days after a request for change has been denied in whole or in part or after any other event giving rise to the Claim.
Any claim must be submitted in writing to the City and shall include on its first page the following in 16-point capital font: “THIS IS A CLAIM.” Furthermore, the claim shall include the documents necessary to substantiate the claim. Nothing herein is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims, including all requirements pertaining to compensation or payment for extra work, disputed work, and/or changed conditions. Failure to follow such contractual requirements shall bar any claims or subsequent lawsuits for compensation or payment thereon. e. Supporting Documentation. The Contractor shall submit all Claims in the following format:
1) Summary of claim merit and price, and Contract clause pursuant to which the claim is made.
2) List of documents relating to claim
(a) Specifications
(b) Drawings
(c) Clarifications (Requests for Information)
(d) Schedules
(e) Other
3) Chronology of events and correspondence
4) Narrative analysis of claim merit
5) Analysis of claim cost, including calculations and supporting documents 6) Analysis of time impact analysis in CPM format if a time extension is requested
7) Cover letter and certification of validity of the claim, including any claims from subcontractors of any tier, in accordance with the Government Code sections 12650 et seq.
f. City Response to Claim.
1) Upon receipt of a Claim pursuant to this Article, the City shall conduct a reasonable review of the Claim and, within a period not to exceed 45 days of receipt of the claim, or as extended by mutual agreement, shall provide a written statement identifying what portion of the Claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
72 SECTION 00700
GENERAL CONDITIONS
the Claim will be processed and made within 60 days after the City issues its written response.
2) If the City needs approval from City Council to provide Contractor a written statement as set forth above, and City Council does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a Claim, the City shall have up to three (3) days following the next publicly noticed meeting of City Council after the 45-day period, or extension, expires to provide Contractor a written statement identifying the disputed portion and the undisputed portion of the Claim.
3) The City may request, in writing, within 30 days of receipt of the claim, any additional documentation supporting the claim or relating to defenses or claims the City may have. If additional information is needed thereafter, it shall be provided upon mutual agreement of the City and the claimant. The City’s written response shall be submitted 30 days (15 days if the Claim is less than $50,000) after receiving the additional documentation, or within the same period of time taken by the claimant to produce the additional information, whichever is greater.
g. Meet & Confer Conference. If the Contractor disputes the City’s response, or if the City fails to respond within the statutory time period(s), the Contractor may so notify the City within 15 days of the receipt of the response or the failure to respond, and demand an informal conference to meet and confer for settlement of those portions of the Claim that remain in dispute. Upon such demand, the City shall schedule a meet and confer conference within 30 Days.
h. Mediation. Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion thereof remains in dispute, the City shall provide the Contractor with a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 Days after the City issues its written statement. Any portion of the claim that remains in dispute shall be submitted to nonbinding mediation and the City and the Contractor shall equally share the associated mediator fees. The City and Contractor shall mutually agree to a mediator within 10 business Days after the disputed portion of the claim has been identified in writing, unless the parties agree to select a mediator at a later time.
1) If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.
2) For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section. 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
73 SECTION 00700
GENERAL CONDITIONS
3) Unless otherwise agreed to by the public entity and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.
4) The mediation shall be held no earlier than the date the Contractor completes the Work or the date that the Contractor last performs Work, whichever is earlier. All unresolved claims shall be considered jointly in a single mediation, unless a new unrelated claim arises after mediation is completed.
i. Procedures After Mediation. If following the mediation, the claim or any portion remains in dispute, the Contractor must file a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code prior to initiating litigation.
For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the Contractor submits his or her written claim pursuant to subdivision (a) until the time the claim is denied, including any period of time utilized by the meet and confer conference. j. Civil Actions. The following procedures are established for all civil actions filed to resolve Claims of $375,000 or less:
1) Within 60 Days, but no earlier than 30 Days, following the filing or responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties or unless mediation was held prior to commencement of the action in accordance with Public Contract Code section 9204 and the terms of this Agreement.
The mediation process shall provide for the selection within 15 Days by both parties of a disinterested third person as mediator, shall be commenced within 30 Days of the submittal, and shall be concluded within 15 Days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court. 2) If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1114.11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration. In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible, be experienced in construction law, and (B) any party appealing an arbitration award who does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, also pay the attorney’s fees on appeal of the other party.
k. Government Code Claim.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
74 SECTION 00700
GENERAL CONDITIONS
1) In addition to any and all contract requirements pertaining to notices of and requests for compensation or payment for extra work, disputed work, construction claims and/or changed conditions, the Contractor must comply with the claim procedures set forth in Government Code section 900 et seq. prior to filing any lawsuit against the City. 2) Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra work, disputed work, construction claims, and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if the prerequisite contractual requirements are not otherwise satisfied as specified herein, Contractor shall be barred from bringing and maintaining a valid lawsuit against the City.
3) A Government Code claim must be filed no earlier than the date the Work is completed or the date the Contractor last performs Work on the Project, whichever occurs first. A Government Code claim shall be inclusive of all unresolved claims known to Contractor or that should reasonably by known to Contractor excepting only new unrelated Claims that arise after the Government Code claim is submitted.
l. Non-Waiver. The City’s failure to respond to a claim from the Contractor within the time periods described in this Article or to otherwise meet the time requirements of this Article shall result in the claim being deemed rejected in its entirety.
ARTICLE 48. CITY’S RIGHT TO TERMINATE CONTRACT
a. Termination for Cause. City may, without prejudice to any other right or remedy, serve written notice upon Contractor of its intention to terminate this Contract in whole or in part if the Contractor: (i) refuses or fails to prosecute The Work or any part thereof with such diligence as will ensure its completion within the time required; (ii) fails to complete The Work within the required time; (iii) should file a bankruptcy petition or be adjudged a bankrupt; (iv) should make a general assignment for the benefit of its creditors; (v) should have a receiver appointed; (vi) should persistently or repeatedly refuse or fail to supply enough properly skilled workers or proper materials to complete the work; (vii) should fail to make prompt payment to subcontractors or for material or labor; (viii) persistently disregard laws, ordinances, other requirements or instructions of City; or (ix) should violate any of the provisions of the Contract Documents.
The notice of intent to terminate shall contain the reasons for such intention to terminate. Unless within ten (10) Days after the service of such notice, such condition shall cease or satisfactory arrangements (acceptable to City) for the required correction are made, this Contract shall be terminated. In such case, Contractor shall not be entitled to receive any further payment until the Project has been finished. City may take over and complete The Work by any method it may deem appropriate. Contractor and its surety shall be liable to City for any excess 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
75 SECTION 00700
GENERAL CONDITIONS
costs or other damages incurred by City to complete the Project. If City takes over The Work, City may, without liability for so doing, take possession of and utilize in completing The Work such materials, appliances, plant, and other property belonging to the Contractor as may be on the Project site. b. Termination For Convenience. City may terminate performance of The Work in whole or, in part, if City determines that a termination is in City's interest.
The Contractor shall terminate all or any part of The Work upon delivery to the Contractor of a Notice of Termination specifying that the termination is for the convenience of City, the extent of termination, and the effective date of such termination.
After receipt of Notice of Termination, and except as directed by City, the Contractor shall, regardless of any delay in determining or adjusting any amounts due under this Termination for Convenience clause, immediately proceed with the following obligations:
1) Stop Work as specified in the Notice.
2) Complete any Work specified in the Notice of Termination in a least cost/shortest time manner while still maintaining the quality called for under the Contract Documents.
3) Leave the property upon which the Contractor was working and upon which the facility (or facilities) forming the basis of the Contract Documents is situated in a safe and sanitary manner such that it does not pose any threat to the public health or safety.
4) Terminate all subcontracts to the extent that they relate to the portions of The Work terminated.
5) Place no further subcontracts or orders, except as necessary to complete the remaining portion of The Work.
6) Submit to City, within ten (10) Days from the effective date of the Notice of Termination, all of the documentation called for by the Contract Documents to substantiate all costs incurred by the Contractor for labor, materials and equipment through the Effective Date of the Notice of Termination. Any documentation substantiating costs incurred by the Contractor solely as a result of City's exercise of its right to terminate this Contract pursuant to this clause, which costs the Contractor is authorized under the Contract Documents to incur, shall: (i) be submitted to and received by City no later than thirty (30) Days after the Effective Date of the Notice of Termination; (ii) describe the costs incurred with particularity; and (iii) be conspicuously identified as "Termination Costs Occasioned by City's Termination for Convenience."
7) These provisions are in addition to and not in limitation of any other rights or remedies available to City.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
76 SECTION 00700
GENERAL CONDITIONS
c. Savings Clause. If City terminates Contractor for cause, and if it is later determined that the termination was wrongful, such default termination shall automatically be converted to and treated as a termination for convenience. In such event, Contractor shall be entitled to receive only the amounts payable under this section, and Contractor specifically waives any claim for any other amounts or damages, including, but not limited to, any claim for consequential damages or lost profits. d. Exception. Notwithstanding any other provision of this Article, when immediate action is necessary to protect life and safety or to reduce significant exposure or liability, City may immediately order Contractor to cease Work on the Project until such safety or liability issues are addressed to the satisfaction of City or the Contract is terminated.
ARTICLE 49. WARRANTY AND GUARANTEE
a. Contractor warrants that all materials and equipment furnished under this Contract shall be new unless otherwise specified in the Contract Documents; and that all Work conforms to the Contract Document requirements and is free of any defect whether performed by the Contractor or any subcontractor or supplier. b. Unless otherwise stated, all warranty periods shall begin upon the filing of the Notice of Completion. Unless otherwise stated, the warranty period shall be for one year.
c. The Contractor shall remedy at its expense any damage to City-owned or controlled real or personal property.
d. Contractor shall furnish City with all warranty and guarantee documents prior to final Acceptance of the Project by City.
e. City shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage. The Contractor shall within ten (10) Days after being notified commence and perform with due diligence all necessary Work. If the Contractor fails to promptly remedy any defect, or damage; the City have the right to replace, repair, or otherwise remedy the defect, or damage at the Contractor’s expense.
f. In the event of any emergency constituting an immediate hazard to health, safety, property, or licensees, when caused by Work of the Contractor not in accordance with the Contract requirements, City may undertake at Contractor’s expense, and without prior notice, all Work necessary to correct such condition. g. With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for Work performed and Materials furnished under this Contract, the Contractor shall:
1) Obtain for City all warranties that would be given in normal commercial practice;
2) Require all warranties to be executed, in writing, for the benefit of City; and 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
77 SECTION 00700
GENERAL CONDITIONS
3) Enforce all warranties for the benefit of City, unless otherwise directed in writing by City.
h. City may elect to conduct a minimum of two site visits with the contractor prior to the end of the warranty period. City shall provide written direction to the contractor to remedy warranty related material failures that shall be corrected by the contractor within fifteen (15) Days at no cost to City.
This Article shall not limit City’s rights under this Contract or with respect to latent defects, gross mistakes, or fraud. City specifically reserves all rights related to defective work, including but not limited to the defect claims pursuant to California Code of Civil Procedure Section 337.15.
ARTICLE 50. DOCUMENT RETENTION & EXAMINATION
a. In accordance with Government Code Section 8546.7, records of both City and the Contractor shall be subject to examination and audit by the State Auditor General for a period of three (3) years after final payment.
b. Contractor shall make available to City any of the Contractor’s other documents related to the Project immediately upon request of City. c. In addition to the State Auditor rights above, City shall have the right to examine and audit all books, estimates, records, contracts, documents, bid documents, subcontracts, and other data of the Contractor (including computations and projections) related to negotiating, pricing, or performing the modification in order to evaluate the accuracy and completeness of the cost or pricing data at no additional cost to City, for a period of four (4) years after final payment.
ARTICLE 51. SOILS INVESTIGATIONS
When a soils investigation report for the Project site is available, such report shall not be a part of the Contract Documents. Any information obtained from such report as to subsurface soil condition, or to elevations of existing grades or elevations of underlying rock, is approximate only and is not guaranteed. Contractor acknowledges that any soils investigation report (including any borings) was prepared for purposes of design only and Contractor is required to examine the site before submitting its bid and must make whatever tests it deems appropriate to determine the underground condition of the soil.
ARTICLE 52. SEPARATE CONTRACTS
a. City reserves the right to let other contracts in connection with this Work or on the Project site. Contractor shall permit other contractors reasonable access and storage of their materials and execution of their work and shall properly connect and coordinate its Work with theirs.
b. To ensure proper execution of its subsequent Work, Contractor shall immediately inspect work already in place and shall at once report to the Engineer any problems with the work in place or discrepancies with the Contract Documents. 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
78 SECTION 00700
GENERAL CONDITIONS
c. Contractor shall ascertain to its own satisfaction the scope of the Project and nature of any other contracts that have been or may be awarded by City in prosecution of the Project to the end that Contractor may perform this Contract in the light of such other contracts, if any. Nothing herein contained shall be interpreted as granting to Contractor exclusive occupancy at site of the Project.
Contractor shall not cause any unnecessary hindrance or delay to any other contractor working on the Project. If simultaneous execution of any contract for the Project is likely to cause interference with performance of some other contract or contracts, the Engineer shall decide which Contractor shall cease Work temporarily and which contractor shall continue or whether work can be coordinated so that contractors may proceed simultaneously. City shall not be responsible for any damages suffered or for extra costs incurred by Contractor resulting directly or indirectly from award, performance, or attempted performance of any other contract or contracts on the Project site.
ARTICLE 53. NOTICE AND SERVICE THEREOF
All notices shall be in writing and either served by personal delivery or mailed to the other party as designated in the Bid Forms. Written notice to the Contractor shall be addressed to Contractor’s principal place of business unless Contractor designates another address in writing for service of notice. Notice to City shall be addressed to City as designated in the Notice Inviting Bids unless City designates another address in writing for service of notice. Notice shall be effective upon receipt or five (5) Days after being sent by first class mail, whichever is earlier.
Notice given by facsimile shall not be effective unless acknowledged in writing by the receiving party.
ARTICLE 54. NOTICE OF THIRD PARTY CLAIMS
Pursuant to Public Contract Code Section 9201, City shall provide Contractor with timely notification of the receipt of any third-party claim relating to the Contract.
ARTICLE 55. STATE LICENSE BOARD NOTICE
Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four (4) years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within ten (10) years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors’ State License Board, P.O. Box 26000, Sacramento, California 95826.
ARTICLE 56. INTEGRATION
a. Oral Modifications Ineffective. No oral order, objection, direction, claim or notice by any party or person shall affect or modify any of the terms or obligations contained in the Contract Documents.
b. Contract Documents Represent Entire Contract. The Contract Documents represent the entire agreement of City and Contractor.
55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
79 SECTION 00700
GENERAL CONDITIONS
ARTICLE 57. ASSIGNMENT
Contractor shall not assign, transfer, convey, sublet, or otherwise dispose of this Contract or any part thereof including any claims, without prior written consent of City. Any assignment without the written consent of City shall be void. Any assignment of money due or to become due under this Contract shall be subject to a prior lien for services rendered or Material supplied for performance of Work called for under the Contract Documents in favor of all persons, firms, or corporations rendering such services or supplying such Materials to the extent that claims are filed pursuant to the Civil Code, the Code of Civil Procedure or the Government Code.
ARTICLE 58. CHANGE IN NAME AND NATURE OF CONTRACTOR’S LEGAL ENTITY Should a change be contemplated in the name or nature of the Contractor’s legal entity, the Contractor shall first notify City in order that proper steps may be taken to have the change reflected on the Contract.
ARTICLE 59. ASSIGNMENT OF ANTITRUST ACTIONS
Pursuant to Section 7103.5 of the Public Contract Code, in entering into a public works contract or subcontract to supply goods, services, or materials pursuant to a public works contract, Contractor or subcontractor offers and agrees to assign to City all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Section 15) or under the Cartwright Act (chapter 2 (commencing with Section 16700) of part 2 of division 7 of the Business and Professions Code), arising from the purchase of goods, services, or materials pursuant to this Contract or any subcontract. This assignment shall be made and become effective at the time City makes final payment to the Contractor, without further acknowledgment by the parties.
ARTICLE 60. PROHIBITED INTERESTS
No City official or representative who is authorized in such capacity and on behalf of City to negotiate, supervise, make, accept, or approve, or to take part in negotiating, supervising, making, accepting or approving any engineering, inspection, construction or material supply contract or any subcontract in connection with construction of the project, shall be or become directly or indirectly interested financially in the Contract.
ARTICLE 61. LAWS AND REGULATIONS
a. Contractor shall give all notices and comply with all federal, state and local laws, ordinances, rules and regulations bearing on conduct of work as indicated and specified by their terms. References to specific laws, rules or regulations in this Contract are for reference purposes only, and shall not limit or affect the applicability of provisions not specifically mentioned. If Contractor observes that drawings and specifications are at variance therewith, he shall promptly notify the Engineer in writing and any necessary changes shall be adjusted as provided for in this Contract for changes in work. If Contractor performs any work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Engineer, he shall bear all costs arising therefrom. 55728.00300\33360134.1
SECTION 00700
GENERAL CONDITIONS
80 SECTION 00700
GENERAL CONDITIONS
b. Contractor shall be responsible for familiarity with the Americans with Disabilities Act (“ADA”) (42 U.S.C. § 12101 et seq.). The Work will be performed in compliance with ADA regulations.
ARTICLE 62. PATENT FEES OR ROYALTIES
The Contractor shall include in its bid amount the patent fees or royalties on any patented article or process furnished or used in the Work. Contractor shall assume all liability and responsibility arising from the use of any patented, or allegedly patented, materials, equipment, devices or processes used in or incorporated with The Work, and shall defend, indemnify and hold harmless City, its officials, officers, agents, employees and representatives from and against any and all liabilities, demands, claims, damages, losses, costs and expenses, of whatsoever kind or nature, arising from such use.
ARTICLE 63. OWNERSHIP OF DRAWING
All Contract Documents furnished by City are City property. They are not to be used by Contractor or any subcontractor on other work nor shall Contractor claim any right to such documents. With exception of one complete set of Contract Documents, all documents shall be returned to City on request at completion of The Work.
ARTICLE 64. NOTICE OF TAXABLE POSSESSORY INTEREST
In accordance with Revenue and Taxation Code Section 107.6, the Contract Documents may create a possessory interest subject to personal property taxation for which Contractor will be responsible.
END OF GENERAL CONDITIONS
55728.00300\33360134.1
81 SECTION 00750
SPECIAL CONDITIONS
SECTION 00750
SPECIAL CONDITIONS
1. SPECIFIC MATERIALS
City has made the following findings as they relate to need for the use of specific material(s), product(s), thing(s), and/or service(s) that must be utilized for the Project:
Materials utilized for this Project shall meet all American Water Works Association (AWWA) standards, Signal Hill Water Department standards, and required specifications under the Technical Specifications attached hereto.
Based on the above described findings, City requires that the following specific product(s), thing(s), and/or service(s) be utilized for the Project:
Please refer to Section 02461 and Section 15050 of the Technical Specifications for specific material listings and types.
2. [NOT USED]
3. STORMWATER SPECIFICATIONS
City has not prepared a SWPPP or other stormwater compliance plan for the Project site.
Contractor is responsible for filing the PRDs and for obtaining coverage under the Permit. This includes preparing and implementing a SWPPP for the Project site, and coordinating all submittals with the City's Legally Responsible Person and Authorized Signatory as those terms are defined in the Permit. Before any PRDs, SWPPP, or other Permit related document may be submitted to the State Board or implemented on the Project site, it must first be reviewed by the City, who retains the right to reject or require revisions thereto. If the Project is less than one acre in size, Contractor is still required to develop and implement an Erosion and Sediment Control Plan for the Work site. Contractor must include all costs of compliance with specified requirements in the Contract amount.
4. PRE-CONSTRUCTION MEETING.
After, or upon, notification of Contract Award, the Engineer will set the time and location for the Pre-Construction Meeting. Attendance of the Contractor's management personnel responsible for the management, administration, and execution of the project is mandatory for the meeting to be convened. Failure of the Contractor to have the Contractor 's responsible project personnel attend the Pre-Construction Meeting will be grounds for default by Contractor. No separate payment will be made for the Contractor 's attendance at the meeting. The Notice to Proceed will only be issued on or after the completion of the Pre-Construction meeting.
5. MODIFICATION OF HOURS OF WORK
The Contractor’s activities shall be confined to Monday through Friday, excluding City holidays and weekends. The Contractor’s activities shall be confined to the hours between 8:00 a.m. and 4:30 p.m. Working hours on arterial streets, including closure of travel lanes, will be allowed only between the hours of 9:00 a.m. and 3:30 p.m. Deviation from these hours will not be permitted without written request and the prior consent of the Engineer, except in emergencies involving 55728.00300\33360134.1
SECTION 00750
SPECIAL CONDITIONS
82 SECTION 00750
SPECIAL CONDITIONS
immediate hazard to persons or property. In the event of either a requested, or emergency deviation, inspection service fees will be charged against the Contractor. The service fees will be calculated at overtime rates, including benefits, overhead, and travel time. The service fees will be deducted from any amounts due the Contractor.
6. STREET CLOSURES, DETOURS, BARRICADES
Existing electrical systems (traffic signal, highway and street lighting, flashing beacon, sign illumination and other facilities), or approved temporary replacements thereof, shall be kept in effective operation for the benefit of the traveling public during the progress of the work, except when shutdown is permitted to allow for alterations or final removal of the systems. The traffic signal shutdowns shall be limited to normal working hours, or shall be as specified in the special provisions. Lighting system shutdowns shall not interfere with the regular lighting schedule, unless otherwise permitted by the Engineer. The Contractor shall notify the Engineer prior to performing any work on existing systems.
The Contractor shall notify the City prior to any operational shutdown of a traffic signal. The City will:
1. Continue the operation and maintenance of existing electrical facilities.
2. Continue to provide for electrical energy for the operation of existing electrical facilities.
3. Repair or replace existing facilities damaged by public traffic.
4. Pay the cost of electrical energy for the operation of existing or new facilities that are undergoing the functional tests.
The Contractor shall ascertain the exact location and depth of existing detectors, conduits, pull boxes and other electrical facilities before using any tools or equipment that may damage those facilities or interfere with any electrical system.
Where damage is caused by the Contractor’s operations, the Contractor shall, at the Contractor’s expense, repair or replace damaged facilities promptly in conformance with these specifications.
If any existing loop conductor, including the portion leading to the detector handhole or termination pull box, is damaged by the contractor’s operations, the Contractor shall immediately notify the Engineer. The affected detectors shall be replaced at the Contractor’s expense and as directed by the Engineer within 24 hours. If the Contractor fails to complete the repairs within this period, the repairs will be made by the City at the Contractor’s expense.
Should the Contractor fail to perform the required repairs or replacements, the cost of performing the repairs or replacements will be deducted from any moneys due or to become due to the Contractor.
Where roadways are to remain open to traffic and existing lighting systems are to be modified, the lighting systems shall remain in operation and the final connection to the modified circuit shall be made so that the modified circuit will be in operation by nightfall of the same day. 55728.00300\33360134.1
SECTION 00750
SPECIAL CONDITIONS
83 SECTION 00750
SPECIAL CONDITIONS
Temporary electrical installations shall be kept in effective operation until the temporary installations are no longer required for the traveling public.
During traffic signal system shutdown the Contractor shall place “STOP AHEAD” and “STOP” signs to direct vehicle and pedestrian traffic through the intersection. All signal faces shall be covered when the system is shutdown overnight. Temporary “STOP AHEAD” and “STOP” signs shall be either covered or removed when the system is turned on. “STOP AHEAD” and “STOP” signs shall be furnished by the Contractor and shall conform to the provisions in Caltrans Standard Specification section 12-3.06, “Construction Area Signs.” Minimum size of “STOP” signs shall be 30 inches.
One “STOP AHEAD” sign and one “STOP” sign shall be placed for each direction of traffic. For two-lane approaches, 2 “STOP” signs shall be placed. Location of the signs shall be as directed by the Engineer.
Barricades shall be equipped with flashing warning lights. All power required devices shall be operated by batteries, rather than generators.
Street closures will not be allowed, except as specifically permitted by the Engineer. Traffic control shall be approved by the Engineer.
Lane transitions shall conform to the latest edition of the California Manual on Uniform Traffic Control Devices (MUTCD).
Temporary traffic channelization shall be accomplished with barricades or delineators. Temporary striping will not be allowed unless specifically permitted by the Engineer. The Contractor shall prepare any plans that may be required for temporary striping to the satisfaction of the Engineer.
In no event will temporary striping be allowed on finished pavement surfaces, which are to remain.
The Contractor shall prepare any traffic control or detour plans that may be required as directed by the Engineer. The Contractor shall submit Traffic Control Plans for all work on arterial roads, prepared and signed by a California Registered Civil or Traffic Engineer at least ten (10) working days prior to commencing work.
The Contractor shall schedule an employee to police the temporary delineators and barricades within the travel way during weekday, nonworking hours, and over Saturdays, Sundays, and holidays. Any corrective work required to be done by City forces shall be back charged to the Contractor based on the actual costs, plus City overhead and withheld from the final payment.
All costs to the Contractor for street closures, detours, barricades, and associated plans shall be included in various lump sum contract bid items, and no separate payment will be made therefore.
7. SURVEY CONTROL AND REFERENCE POINTS
Prior to the start of construction, the Contractor (its licensed surveyor or qualified engineer) shall locate all monuments (both of record and not of record), bench marks, and centerline ties within one hundred feet of the construction activity. Additional ties to monuments shall be set when ties are missing (min. four ties per monument). The Contractor shall prepare and submit for review 55728.00300\33360134.1
SECTION 00750
SPECIAL CONDITIONS
84 SECTION 00750
SPECIAL CONDITIONS
to the City Engineer separate tie sheets and Corner Record sheets (monuments not of record shall have only tie sheets prepared). Corner Records shall conform to the County Engineers’ Association of California’s “Guide to the Preparation of Records of Survey and Corner Records” document as provided by the County of Los Angeles Land Surveyor’s Office and on file in the City of Signal Hill City Engineers Office. Upon review by the City Engineer, the Contractor shall file the Corner Records with the County of Los Angeles Land Surveyor’s Office. Certified Corner Records shall be filed with the City Engineer. Prior to final Acceptance by the City, the Contractor shall re-survey all field monuments and centerline ties within the construction zone, prepare tie sheets and corner record sheets as indicated above, and file them with the City Engineer for review. After review by the City Engineer, the land surveyor shall file the corner records with the County Land Surveyors Office, and file certified copies of the corner records with the City Engineer.
All survey monuments removed or altered as a result of construction shall be reset, corner records shall be filed with the County of Los Angeles Land Surveyor’s Office, and approved final corner records shall be filed with the City Engineer. Centerline ties removed as a result of construction shall be reset and tie sheets filed with the City Engineer.
Contractor shall provide a letter of certification for all monuments having four or more existing ties which are within 0.02 ft plus or minus of the original City tie sheet records. When several monuments and ties appear on one tie sheet and one of the ties has changed the land surveyor shall re-measure all of the ties and re-file a new ties sheet with the City as required herein.
County of Los Angeles permanent and temporary bench marks within the construction zone shall be located by survey, and the Contractor shall send a written notification of impending construction to the County of Los Angeles Land Surveyor’s Office two weeks prior to construction.
END OF SPECIAL CONDITIONS
55728.00300\33360134.1
85 APPENDIX
INSURANCE REQUIREMENTS
APPENDIX
INSURANCE REQUIREMENTS
1. WORKERS’ COMPENSATION AND EMPLOYER’S LIABILITY INSURANCE Contractor shall maintain Workers’ Compensation Insurance (Statutory Limits) and Employer’s Liability Insurance (with limits of at least $1,000,000) for Contractor ’s employees in accordance with the laws of the State of California, Section 3700 of the Labor Code In addition, Contractor shall require each subcontractor to similarly maintain Workers’ Compensation Insurance and Employer’s Liability Insurance in accordance with the laws of the State of California, Section 3700 for all of the subcontractor’s employees.
Contractor shall submit to City, along with the certificate of insurance, a Waiver of Subrogation endorsement in favor of City, its officials, officers, employees, agents, and volunteers. Company or companies providing insurance coverage shall be acceptable to City, if in the form and coverage as set forth in the Contract Documents.
2. COMMERCIAL GENERAL LIABILITY INSURANCE
a. Contractor shall procure and maintain during the life of this Contract and for such other period as may be required herein, at its sole expense, occurrence form Commercial General Liability insurance coverage, at least as broad as the most current ISO CGL Form 00 01 including but not limited to, premises liability, contractual liability, products/completed operations if applicable, personal and advertising injury which may arise from or out of Contractor’s operations, use, and management of the Project site, or the performance of its obligations hereunder.
Policy limits shall not be less than $1,000,000 per occurrence, $2,000,000 general aggregate, for bodily injury, personal injury and property damage, including without limitation, blanket contractual liability, and a $2,000,000 completed operations aggregate. Defense costs shall be paid in addition to the limits. b. Such policy shall comply with all the requirements of this Article. The limits set forth herein shall apply separately to each insured against whom claims are made or suits are brought, except with respect to the limits of liability. Further the limits set forth herein shall not be construed to relieve the Contractor from liability in excess of such coverage, nor shall it limit Contractor’s indemnification obligations to City, and shall not preclude City from taking such other actions available to City under other provisions of the Contract Documents or law.
c. Contractor shall make certain that any and all subcontractors hired by Contractor are insured in accordance with this Contract. If any subcontractor’s coverage does not comply with the foregoing provisions, Contractor shall indemnify and hold City harmless from any damage, loss, cost, or expense, including attorneys’ fees, incurred by City as a result thereof.
d. All general liability policies provided pursuant to the provisions of this Article shall comply with the provisions of the Contract Documents.
e. All general liability policies shall be written to apply to all bodily injury, including death, property damage, personal injury, owned and non-owned equipment, 55728.00300\33360134.1
APPENDIX
INSURANCE REQUIREMENTS
86 APPENDIX
INSURANCE REQUIREMENTS
blanket contractual liability, completed operations liability, explosion, collapse, under-ground excavation, removal of lateral support, and other covered loss, however occasioned, occurring during the policy term, and shall specifically insure the performance by Contractor of that part of the indemnification contained in these General Conditions, relating to liability for injury to or death of persons and damage to property. If the coverage contains one or more aggregate limits, a minimum of 50% of any such aggregate limit must remain available at all times; if over 50% of any aggregate limit has been paid or reserved, City may require additional coverage to be purchased by Contractor to restore the required limits. Any umbrella or excess liability policy shall include the additional insured endorsement described in the Contract Documents.
3. AUTOMOBILE LIABILITY INSURANCE
Contractor shall take out and maintain at all times during the term of this Contract Automobile Liability Insurance at least as broad as ISO CA 00 01 (Any Auto) covering bodily injury and property damage for all activities of the Contractor arising out of or in connection with Work to be performed under these Contract Documents, including coverage for any owned, hired, non-owned or rented vehicles, in an amount not less than $1,000,000 combined single limit for each accident.
Such insurance shall be provided in a form and with insurance companies acceptable to City and comply with the provisions of Section 6 below.
4. UMBRELLA OR EXCESS LIABILITY INSURANCE.
Contractor shall obtain and maintain an umbrella or excess liability insurance policy with limits of not less than $4,000,000 that will provide bodily injury, personal injury and property damage liability coverage at least as broad as the primary coverages set forth above, including commercial general liability and employer’s liability. Such policy or policies shall include the following terms and conditions:
a. A drop down feature requiring the policy to respond in the event that any primary insurance that would otherwise have applied proves to be uncollectable in whole or in part for any reason;
b. Pay on behalf of wording as opposed to reimbursement; c. Concurrency of effective dates with primary policies; and d. Policies shall “follow form” to the underlying primary policies. e. Insureds under primary policies shall also be insureds under the umbrella or excess policies.
5. POLLUTION LIABILITY INSURANCE
Environmental Impairment Liability insurance shall be written on a contractor’s pollution liability form or other form acceptable to agency providing coverage for liability arising out of sudden, accidental, and gradual pollution and remediation. the policy limit shall be no less than $1,000,000 dollars per claim and in the aggregate. all activities contemplated in this agreement shall be specifically scheduled on the policy as “covered operations.” the policy shall provide coverage for 55728.00300\33360134.1
APPENDIX
INSURANCE REQUIREMENTS
87 APPENDIX
INSURANCE REQUIREMENTS
the hauling of waste from the project site to the final disposal location, including non-owned disposal sites.
6. FORM AND PROOF OF CARRIAGE OF INSURANCE
a. Any insurance carrier providing insurance coverage required by the Contract Documents shall be admitted to and authorized to do business in the State of California unless waived, in writing, by City’s Risk Manager. Carrier(s) shall have an A.M. Best rating of not less than an A-:VII.
b. Insurance deductibles or self-insured retentions must be declared by the Contractor, and such deductibles and retentions shall have the prior written consent from City. At the election of City the Contractor shall either 1) reduce or eliminate such deductibles or self-insured retentions, or 2) procure a bond which guarantees payment of losses and related investigations, claims administration, and defense costs and expenses.
c. Contractor shall cause its insurance carrier(s) to furnish City with either 1) a properly executed original Certificates(s) of Insurance and certified original copies of Endorsements effecting coverage as required herein, or 2) if requested to do so in writing by City’s Risk Manager, provide original Certified copies of policies including all Endorsements and all attachments thereto, showing such insurance is in full force and effect. All required policies of Commercial General Liability, Automobile Liability insurance shall be endorsed to name the City, its officials, officers, employees, agents and volunteers as additional insureds. For all policies of Commercial General Liability insurance, Contractor shall provide endorsements in the form of ISO CG 20 10 10 01 and 20 37 01 01 (or endorsements providing the exact same coverage) to effectuate this requirement. Further, all policies of insurance shall contain or shall be endorsed to contain the covenant of the insurance carrier(s) that shall provide no less than thirty (30) days written notice be given to City prior to any material modification or cancellation of such insurance. d. In the event of a material modification or cancellation of coverage, City may terminate or Stop Work pursuant to the Contract Documents, unless City receives, prior to such effective date, another properly executed original Certificate of Insurance and original copies of endorsements or certified original policies, including all endorsements and attachments thereto evidencing coverages set forth herein and the insurance required herein is in full force and effect. Contractor shall not take possession, or use the Project site, or commence operations under these Contract Documents until City has been furnished original Certificate(s) of Insurance and certified original copies of Endorsements or policies of insurance including all Endorsements and any and all other attachments as required in this Section. The original Endorsements for each policy and the Certificate of Insurance shall be signed by an individual authorized by the insurance carrier to do so on its behalf.
e. All required insurance coverages shall contain or be endorsed to waive subrogation against the City, its officials, officers, employees, agents, and volunteers or shall specifically allow Contractor or others providing insurance evidence in compliance with these specifications to waive their right of recovery 55728.00300\33360134.1
APPENDIX
INSURANCE REQUIREMENTS
88 APPENDIX
INSURANCE REQUIREMENTS
prior to a loss. Contractor hereby waives its own right of recovery against City, and shall require similar written express waivers and insurance clauses from each of its Subcontractors.
f. It is understood and agreed to by the parties hereto and the insurance company(s), that the Certificate(s) of Insurance and policies shall so covenant and shall be construed as primary, and City’s insurance and/or deductibles and/or self-insured retentions or self-insured programs shall not be construed as contributory. The Contractor shall provide endorsement(s) to this effect at the City’s request. g. City reserves the right to adjust the monetary limits of insurance coverage’s during the term of this Contract including any extension thereof-if in City’s reasonable judgment, the amount or type of insurance carried by the Contractor becomes inadequate.
h. In the event any policy of insurance required by the Contract Documents does not comply with these specifications or is canceled and not replaced immediately so as to avoid a lapse in the required coverage, City has the right but not the duty to obtain the insurance it deems necessary and any premium paid by City will be promptly reimbursed by Contractor or City will withhold amounts sufficient to pay premium from Contractor payments. In the alternative, City may cancel this Contract, effective upon notice.
i. Contractor acknowledges and agrees that actual or alleged failure on the part of the City to inform Contractor of non-compliance with any requirement imposed no additional obligation on the City nor does it waive any rights hereunder. j. Requirement of specific coverage or limits contained in this section are not intended as a limitation on coverage, limits, or other requirement, or a waiver of any coverage normally provided by any insurance. If the Contractor maintains higher limits than the minimums shown above, the City requires and shall be entitled to coverage for the higher limits maintained by the Contractor. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the City.
k. Contractor shall be responsible for causing all Subcontractors of any tier working under this Contract to purchase insurance meeting the requirements contained herein, including adding the City its officials, officers, employees, agents and volunteers as Additional Insureds to the subcontractor’s policies. All policies of Commercial General Liability insurance provided by Subcontractors shall be endorsed to name the City, its officials, officers, employees, agents and volunteers as additional insureds using endorsement form ISO GC 20 38 04 13 (or an endorsement providing the exact same coverage) to effectuate this requirement.
Contractor shall not allow any Subcontractor to commence work relating to these Contract Documents until it has received satisfactory evidence of Subcontractor’s compliance with all insurance requirements under this Contract. The Contractor shall provide satisfactory evidence of compliance with this section upon request of the City.
CITY OF SIGNAL HILL
Water Services and Valve Replacements
At Various Locations
Project Number 95.18012
(AKM No. 1991546.00)
PROJECT SPECIFICATIONS
March 2022
TOC-1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\TECHNICAL SPECIFICATIONS TOC.doc
TECHNICAL SPECIFICATIONS
Division 1 - General
01010 Summary of Work
01015 General Provisions
01030 Measurement and Payment
01035 Mobilization and Demobilization
01300 Submittals
01400 Quality Control
01710 Clean-Up
Division 2 - Site Work
02461 Asphalt Concrete Paving
02560 Trench Excavation and Backfill
Division 15 - Mechanical
15041 Chlorination of Domestic Water Lines
15050 Piping, Valves and Accessories
15060 Piping – Installation
Table of Drawings
Water Services and Valve Replacements at Various Locations, Sheets 1-20 01010 - 1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01010 Summary of Work.DOC SECTION 01010
SUMMARY OF THE WORK
PART 1 - GENERAL
1. 1 WORK UNDER THIS CONTRACT AGREEMENT
The Work to be performed under this Contract shall consist of furnishing all tools, equipment, materials, supplies, and manufactured articles; and furnishing all labor, transportation, and services, including fuel, power, water, and essential communications; and performing all work, or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents. The Work shall be complete, and all work, materials, and services not expressly indicated or called for in the Contract Documents which may be necessary for the complete and proper construction of the Work in good faith shall be provided by the Contractor as though originally so indicated, at no increase in cost to the Owner.
1. 2 DESCRIPTION OF WORK
The Water Pipeline Projects, as per plans and this specification, provides for the demolition and construction following:
A. Construction of, but not limited to, the following items:
1. Construction of multiple 1-inch and 2-inch water services at various locations within the City of Signal Hill, as per contract drawings and specifications.
2. Miscellaneous improvements, including but not limited to removing existing meter boxes, pressure regulators, piping, and constructing thrust blocks, valves, AC pavement repair, concrete sidewalk/curb/gutter repair, as per contract drawings and specifications.
The Work is included in a single contract. The major components of the Work include all items shown on the drawings and specifications, to make the facility complete and operational.
1. 3 PERMITS AND ENVIRONMENTAL MITIGATION
A. The Contractor shall comply with the provisions of the City of Signal Hill. Bonding fees and inspection permit fees required by the City shall be paid by the Contractor and shall include:
1. City of Signal Hill Business License;
2. City of Signal Hill Encroachment Permit;
B. The Contractor shall adhere to all pertinent requirements of the City’s NPDES permit.
01010 - 2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01010 Summary of Work.DOC D. Work Performed Under Separate Contracts. Refer to Article 14 of Section 00700, "General Conditions" for the Contractor's responsibilities with respect to separate contracts.
1.04 CONSTRUCTION COORDINATION
A. In order that the Work shall be ready for use by the City, the work shall be completed within the time frame stated in the Notice Inviting Bids.
B. The Contractor shall cooperate fully with all utility forces of the Owner or forces of other public or private agencies engaged in the relocation, altering, or otherwise rearranging of any facilities which interfere with the progress of the Work, and shall schedule the Work so as to minimize interference with said relocation, altering, or other rearranging of facilities.
PARTS 2 AND 3 - PRODUCTS AND EXECUTION (Not applicable to this Section).
END OF SECTION
01015 - 1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01015 Genl Provisions.doc SECTION 01015
GENERAL PROVISIONS
PART 1 - GENERAL
1. 1 DESCRIPTION
This Section covers general provisions and requirements for the Work and is supplementary to the Conditions of the Contract.
1.2 ORDER OF WORK
A. General. The work shall be carried on at such places on the project and also in such order or precedence as may be found necessary by the Owner to expedite the completion of the project. After work has begun on any portion or designated part of the project, it shall be carried forward to final completion as rapidly as practicable.
B. Working Hours. All work at the project site shall be performed on regular work days between 8:00 am and 4:30 p.m. Work on holidays, weekends, or in excess of 8 hours per day may be done only when specifically approved in writing by the Owner, in which case the Contractor shall reimburse the Owner for all premium salaries paid for overtime inspection. The Contractor shall also give the Owner 48 hours prior notice of any intended overtime to enable arrangements to be made for inspection.
1. 3 APPLICABLE CODES
This article summarizes without limitation the laws and codes by which the Work has been designed and to which the Contractor shall conform in the prosecution of the Work. The Contractor shall make available for their use at the site, such copies of laws, regulations, or codes applicable to the Work as the Owner may request of him.
A. Laws and Regulations. As specified in Articles 11 and 13 of the General Conditions.
B. Codes.
1. Uniform Building Code, latest edition, as amended by the latest Supplement.
2. Title 8, Industrial Relations, California Administrative Code, Chapter 4, Division of Industrial Safety, Safety Orders.
3. Title 19, Public Safety, California Administrative Code, State Fire Marshall.
4. Title 24, California Administrative Code, Electrical Safety Orders.
5. Local Plumbing Code.
6. The National and Local Electrical Codes.
7. National Fire Protection Association.
01015 - 2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01015 Genl Provisions.doc
8. State and Local Public Health Codes.
9. California Environmental Quality Act.
C. Specifications.
1. Standard Specifications, State of California Business and Transportation Agency, Department of Transportation, latest edition, referred to in the Contract Documents as State Standard Specifications.
2. Standard Specifications for Public Works Construction, latest edition, complete with all subsequent editions of ERRATA and REVISED INDEX Supplements, adopted by Southern California Joint Committee of APWA-AGC.
1.4 ABBREVIATIONS (AS APPLICABLE OR WHERE REFERENCED)
This article summarizes without limitation the abbreviations and symbols used in the Contract Documents. Abbreviations used in the Contract Documents shall be interpreted according to their recognized and well-known technical or trade meanings; such abbreviations include, but are not limited to, the following:
AASHTO American Association of State Highway and Transportation Officials ACI American Concrete Institute
AISC American Institute of Steel Construction, Inc.
AISI American Iron and Steel Institute
ANSI American National Standards Institute
APWA American Public Works Association
ASCE American Society of Civil Engineers
ASME American Society of Mechanical Engineers
ASTM American Society of Testing and Materials
AWS American Welding Society
AWWA American Water Works Association
CEQA California Environmental Quality Act
CLFMI Chain Link Fencing Manufacturers Institute
CS Commercial Standard, US Department of Commerce
FedSpec Federal Specification
HI Hydraulics Institute
ICBO International Conference of Building Officials
IEEE Institute of Electrical and Electronic Engineers
IPCEA Insulated Power Cable Engineers Association
MIL Military Specification (leading symbol)
MSS Manufacturers Standardization Society of the Valve and Fittings Industry NEC National Electrical Code
NEMA National Electrical Manufacturers Association
NFPA National Fire Protection Association
01015 - 3
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01015 Genl Provisions.doc OSHA Occupational Safety and Health Administration, US Department of Labor, as defined in the General Conditions
PCA Portland Cement Association
UBC Uniform Building Code
UL Underwriter's Laboratories, Inc.
PART 2 - PRODUCTS (Not applicable to this Section.)
PART 3 - EXECUTION
3.1 PROJECT MEETINGS
A. Attendees. Unless otherwise specified or required by the Owner, the meetings shall be attended by the Owner, the Engineer, and the Contractor and his Superintendent.
Subcontractors may attend when involved in the matters to be discussed or resolved but only when requested by the Owner.
B. Meeting Records. The Engineer will record minutes of each meeting and will furnish copies to the Contractor within five (5) working days thereafter. If the Contractor does not submit written objection to the contents of such minutes within seven (7) days after presentation to him, it shall be understood and agreed that the Contractor accepts the minutes as a true and complete record of the meeting.
C. Meeting Schedule. The dates, times, and locations for the various meetings shall be agreed upon and recorded at the pre-construction conference. Thereafter, changes to the Schedule shall be by agreement between the Owner and the Contractor, with appropriate written notice to all parties involved.
D. Weekly Safety Meetings. Conduct weekly safety meetings and schedule such meetings in the Critical Path Schedule. To the extent practicable, schedule the weekly safety meeting at a routine time and day from week to week, and provide all personnel at least 3 working days notice of any necessary changes to the meeting date and time.
3.2 PRECONSTRUCTION CONFERENCE
Prior to issuance of the Notice to Proceed, a pre-construction conference shall be held at the location, date, and time designated by the Owner. In addition to the attendees named herein, the meeting shall be attended by the representatives of regulatory agencies having jurisdiction of the Project, if required, and such other persons the Owner may designate.
The Contractor shall submit his construction schedule and a breakdown of the bid items as a schedule of values acceptable to the Owner, one week prior to the conference to allow time for review.
A. Execution and Submittal of Documents. At the pre-construction conference, unless otherwise agreed to by the Owner the Contractor shall present to the Owner the signed Contract Agreement, bonds, certificates of insurance and all other preconstruction documents required of him by the Contract Documents. 01015 - 4
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01015 Genl Provisions.doc B. Agenda. In general, the matters to be discussed or resolved and the instructions and information to be furnished to or given by the Contractor at the pre-construction conference include:
1. Project meeting schedule.
2. Construction plans, progress schedule, schedule of values submitted by Contractor, and estimated monthly progress payments.
3. Communication procedures between the parties.
4. The names and titles of all persons authorized by the Contractor to represent and execute documents for him with samples of all authorized signatures.
5. The names, addresses, and telephone numbers of all those authorized by the Contractor to act for him in emergencies.
6. Construction permit requirements, procedures, and posting.
7. Public Notice of starting Work.
8. Procedures concerning the installation of Work on public or private property.
9. Review of construction schedule as it pertains to the interfacing of work by others.
10. Access and rights-of-way furnished by the Owner.
11. Forms and procedures for Contractor's submittals.
12. Change Order forms and procedures.
13. Payment application forms and procedures and the revised progress schedule reports to accompany the applications.
14. Designation of the Contractor's Safety Officer and his qualifications.
15. Description and discussion of Contractor's proposed safety program.
16. First-aid and medical facilities to be furnished by Contractor.
17. Contractor's provisions for barricades, traffic control, utilities, sanitary facilities, and other temporary facilities and controls.
18. Project sign for Owner if required by the Specifications.
19. Inspector and his duties.
20. Construction surveyor and initiation of surveying services.
21. Testing laboratory or agency, and testing procedures. 01015 - 5
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01015 Genl Provisions.doc
22. Construction equipment and methods proposed by the Contractor.
23. Procedures for payroll and labor cost reporting by the Contractor.
24. Procedures to ensure nondiscrimination in employment on and for the Work.
25. Permit and mitigation measures.
26. Issuance of the Notice to Proceed.
27. Health and Safety Plan.
28. Haul Routes.
29. Other administrative and general matters as needed.
3.3 PROGRESS MEETINGS
The meetings shall be held in accordance with the agreed schedule as stated in Paragraph
3.01, C, of this Section. All matters bearing on the progress and performance of the Work since the preceding progress meeting shall be discussed and resolved, including without limitation any previously unresolved matters, deficiencies in the Work or the methods being employed for the Work, and problems, difficulties, or delays which may be encountered.
3.4 REGULATORY AGENCIES
When requested, the Contractor shall attend meetings held or required by the governmental regulatory agencies having jurisdiction of the Project.
3.5 POSTCONSTRUCTION CONFERENCE
A post-construction conference shall be held prior to final inspection of the Work to discuss and resolve all unsettled matters. The Bonds and insurance to remain in force, and the other documents required to be submitted by the Contractor will be reviewed and any deficiencies determined. Schedules and procedures for the final inspection process, and for the correction of defects and deficiencies, shall be discussed and agreed.
3.6 TEMPORARY FACILITIES AND CONTROLS.
A. Requirements of Regulatory Agencies. Make all necessary arrangement, secure required permits, and pay all fees and charges required by public authorities where temporary facilities or controls are located on public property. The Contractor shall observe the requirements of the City of Signal Hill, City or State Ordinances.
B. Working Areas. Drawings indicate the areas furnished or owned by Owner for prosecution of the Work. All work shall be restricted to stay within those limits. The Contractor shall keep all areas clean, orderly, and free of hazards, and leave the areas in a clean condition acceptable to Owner, and governing public authorities.
C. Construction Utilities. Water supplied by the City will be supplied to the Contractor at construction water rates through hydrant meter, and the Contractor, at his 01015 - 6
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01015 Genl Provisions.doc expense, shall furnish and install all temporary piping facilities or equipment required to convey the water from the City's delivery points to the locations where water is needed for testing purposes. The Contractor shall make application to the City for temporary water connections.
D. Disposal Area. All construction debris shall be legally disposed of offsite.
E. Access to Work. The Owner, its inspectors, agents, and other employees, shall at all times and for any purpose have access to the work and the premises used by the Contractor, and the Contractor shall provide safe and proper facilities therefore.
F. Preservation of Property. Due care shall be exercised to avoid injury to existing improvements, adjacent property, and trees and shrubbery that are not to be moved.
Trees and shrubbery that are not to be removed, poles, fences, signs, property corners, all underground pipe and conduit, and other improvements within or near the work area shall be protected from injury or damage. If such objects, or improvements, are injured or damaged by reason of the Contractor's operations, they shall be replaced or restored, at the Contractor's expense, to a condition as good as, or better than, when the Contractor entered upon the work.
Survey Monuments. The Contractor shall not disturb any monuments or survey markers without permission from the Owner, and he shall bear the expense of resetting any monuments or survey markers, which may be disturbed without permission. The Contractor shall restore the monuments or survey markers disturbed or destroyed during contraction, under the direction of a California licensed land surveyor. The Contractor shall closely coordinate with the City during this Work.
G. Archaeological Findings. Should the discovery of a potential archeological or historical resource occur during construction, all work in the area of the find will stop and a qualified archeologist will be called in to evaluate the situation and make recommendations to the Cultural Resources Officer of the State of California. Said Cultural Resources Officer will then determine what will be necessary for construction to proceed.
H. Observing Ordinances. The Contractor shall observe all the ordinances of City, County or State, where applicable, in relation to the obstruction of streets and driveways, keeping open passageways and protecting the same where they are exposed and would be dangerous to travel. During the time that travel is allowed on the street or alley, he shall provide suitable access to adjoining private property.
I. Traffic Control. The Contractor shall be aware that transportation of any heavy construction equipment and/or materials which requires the use of over-sized transport vehicles on State highways will require a Caltrans transportation permit.
Such a permit may require that truck trips be limited to off-peak commute periods.
The Contractor shall conduct his operations in such a manner as to provide reasonable access to the adjacent properties and shall have no greater length or quantity of work under construction than he can properly prosecute with a minimum of inconvenience to the public and other contractors engaged on adjacent or related work.
01015 - 7
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01015 Genl Provisions.doc Safe temporary vehicular and pedestrian access to the affected properties and residences in the project area shall be maintained at all times during the construction of the project. Where driveways must be temporarily blocked during construction, the following restrictions shall apply:
• No driveways shall be blocked between the hours of 4:30 p.m. and 8:30 a.m. each day.
• Where sites have more than one driveway, only one driveway at any one time may be blocked during construction.
The Contractor shall notify by printed notice, the occupants of all properties within the construction zone of any access, parking and circulation restrictions and limitations that will be created by the construction at least 48 hours in advance of the commencement of construction. This notice shall be approved and signed by the City Engineer, but prepared and distributed by the Contractor.
3.7 PERMITS
The Contractor shall comply with all permit requirements of the City of Signal Hill and all other involved agencies, and all costs therefore shall be included in the prices bid.
3.8 COOPERATION BETWEEN CONTRACTORS
The Contractor is hereby notified that the Owner may award contracts for other work in the project areas. Where two or more Contractors are employed on related or adjacent work, each shall conduct his operations in such a manner as not to cause unnecessary delay or hindrance to the other. Each Contractor shall be responsible to the other for all damage to work, person, or property, or for loss caused by failure to finish within the time specified for completion, at no additional cost to the Owner.
3.9 TAXES
The Contractor shall be responsible for payment of and shall pay any and all taxes, which are applicable to the Work.
3.10 AS-BUILT DRAWINGS
The Contractor shall record the exact location, by dimension, and the exact depth, by elevation, of any exposed underground lines. All information necessary to maintain and/or service any concealed work shall be noted on these record drawings. This data shall be legibly recorded on blueline prints (furnished by the Owner) to the satisfaction of the Engineer. Records shall be kept up-to-date and kept on-site with all entries checked by the Engineer before the work is buried or covered. All changes in or additions to the contract drawings shall be noted on the as-built prints. These drawings shall be delivered to the Owner upon completion of the job.
3.11 PRECEDENCE OF CONTRACT DOCUMENTS
A. If there is a conflict between contract documents, the document highest in precedence shall control. The precedence shall be:
01015 - 8
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01015 Genl Provisions.doc
1. Permits from other agencies as may be required by law.
2. Contract Forms and Bidding Requirements
3. Contract Drawings.
4. Contract Specifications.
5. Standard Specifications.
6. Reference Specifications.
B. Change orders, supplemental agreements and approved revisions to Drawings and Specifications will take precedence over documents listed above. Detailed Drawings shall have precedence over general drawings.
3.12 PRIVATE OWNERS' RELEASE
Contractor shall provide to the Owner a written release by the owner of any property used or damaged by Contractor in conjunction with the project prior to completion of the project stating that the property has been cleaned up, repaired or restored to its original condition.
END OF SECTION
01030-1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01030 Measurement & Payment.doc SECTION 01030
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 DESCRIPTION
This Section summarizes requirements for prices to be submitted in the bids, defines work items, and describes measurement.
1.2 PRICES REQUIRED
In the appropriate places in the Bid Form, each Bidder shall quote unit prices and lump sum prices on the following items of Work in the units stated. Failure to quote on each price item may cause rejection of the Bidder's entire bid at the discretion of the Owner.
A. Unbalanced Prices. Proposed prices which are so unbalanced as to be detrimental to the Owner's interest may be rejected or cause rejection of the Bidder's entire Bid, at the discretion of the Owner.
B. Costs Included. Each proposed price shall cover all costs and charges including without limitation the costs of permits, sawcutting of all trench sections, 100% imported bedding, compacting in 8” lifts with no jetting or hydro-consolidation, material, labor, fabrication, delivery, installation or application, supervision, bond and insurance charges, overhead, profit, and taxes. Quoted prices shall be the exact amount per unit to be applied to the units of Work actually provided for the purpose of establishing the payment to the Contractor.
C. Duration of Prices. Quoted prices accepted by the Owner shall be held good and in effect until the work is completed and accepted by the Owner, unless modified by Change Order.
1.3 MEASUREMENT, PAYMENT, AND DEFINITIONS
This Section defines the work items and the manner and method of measurement and payment for all items included in the Contract. Separate payments will not be made for any work under the Contract other than under the items in the Bid Schedule and payments provided for by approved Change Order. For all work specified and shown on the Drawings, it shall be the Contractor's responsibility to include those costs among the specified Bid Schedule items. In this respect, the cost of such items as safety provisions, submittals on materials and equipment, testing, clean-up, corrections through the Guarantee Period, and all related items required, shall be distributed by Bidders among the Bid items. The bid items reflect the actual payment for all labor, equipment, and materials to provide a complete work for the project. Any work required for the satisfactory completion of the project which is not itemized shall be considered incidental to the bid items.
01030-2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01030 Measurement & Payment.doc A. Bid Item 1. Mobilization and Demobilization. (Total for this item shall not exceed 5% of Total Bid; Mobilization shall not exceed 3%) complete, shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for Mobilization and Demobilization. (Total for this item shall not exceed 5% of Total Bid; Mobilization shall not exceed 3%) complete.
B. Bid Item 2. 2141, 2143, 3145, 2147 Temple Avenue Improvements, complete and operational, shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2141, 2143, 3145, 2147 Temple Avenue Improvements, complete and operational.
C. Bid Item 3. 2199 Temple Avenue Improvements, complete and operational, shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2199 Temple Avenue Improvements, complete and operational.
D. Bid Item 4. 1918 Raymond Avenue Improvements, complete and operational, shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 1918 Raymond Avenue Improvements, complete and operational.
E. Bid Item 5. 1884 Stanley Avenue Improvements, complete and operational, shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 1884 Stanley Avenue Improvments, complete and operational.
F. Bid Item 6. 2348 East 19th Street Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2348 East 19th Street Improvements, complete and operational.
G. Bid Item 7. 2131 East 21st Street Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2131 East 21st Street Improvements, complete and operational.
H. Bid Item 8. 2508 North Palm Drive Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2508 North Palm Drive Improvements, complete and operational. 01030-3
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01030 Measurement & Payment.doc I. Bid Item 9. 25058 North Palm Drive Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2505 North Palm Drive Improvements, complete and operational.
J. Bid Item 10. 2800 Gundry Avenue Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2800 Gundry Avenue Improvements, complete and operational.
K. Bid Item 11. 2450 Cherry Avenue Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2450 Cherry Avenue Improvements, complete and operational.
L. Bid Item 12. 2550 Cherry Avenue Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2550 Cherry Avenue Improvements, complete and operational.
M. Bid Item 13. 2749 Temple Avenue Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 2479 Temple Avenue Improvements, complete and operational.
N. Bid Item 14. 1910 Saint Louis Avenue Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 1910 Saint Louis Avenue Improvements, complete and operational.
O. Bid Item 15. 1452 East 29th Street Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all 1452 East 29th Street Improvements, complete and operational.
P. Bid Item 16. East Spring Street / Junipero Avenue Intersection Improvements, complete and operational shall be paid for as a lump sum item.
Such lump sum payment shall constitute full compensation for construction of all East Spring Street / Junipero Avenue Intersection Improvements, complete and operational.
01030-4
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01030 Measurement & Payment.doc PART 2 - PRODUCTS (Not applicable to this section)
PART 3 - EXECUTION (Not applicable to this section)
END OF SECTION
01035 - 1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01035 Mobilization & Demobilization.DOC SECTION 01035
MOBILIZATION AND DEMOBILIZATION
PART 1 - GENERAL
1.1 DESCRIPTION
This Section covers the requirements for mobilization and demobilization. The requirements specified in Conditions of the Contract and in Division 1 also form a part of this Section.
A. Work Included. Mobilization is the work preparatory to the construction of the Corona Pipeline Projects, and demobilization is the final cleanup of project work areas and removal of all equipment and temporary facilities provided by the Contractor. Mobilization includes execution of the contract; submittal of all required evidence of insurance; submittal of the Work Schedule, breakdown of lump sum bid items; submittal of the list of principal equipment proposed for use in the construction; the establishment of the Contractor's yard; the obtaining of all required permits; the established presence of the Contractor's Superintendent and/or Project Manager on-site; provision and erection of project signs specified in Section 01015, General Provisions; the beginning of the marshaling of major construction equipment and erection and service of temporary facilities. Demobilization includes all work at the end of construction to clean up the site and remove all equipment and temporary facilities as shown and specified.
1.2 SUBMITTALS
Prior to the payment for Mobilization, the Contractor shall submit the following documents to the Engineer for approval.
Certificate of Insurance
Work Schedule
Breakdown of Bid Items as schedule of values, and other items as requested by the Owner
List of major equipment proposed for the construction Copy of required permits
The resume of the Superintendent and/or On-Site Project Manager nominated for the project
PART 2 - PRODUCTS (Not Applicable)
01035 - 2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01035 Mobilization & Demobilization.DOC PART 3 - EXECUTION
Mobilization will be considered complete and eligible for payment when all submittals have been made and approved by the Owner; the Contractor's field offices set up on site, the Contractor's yard established; the Superintendent is in residence in the Contractor's field office; the first piece of major equipment has been brought to the site, ready for work, and the set-up and an operational field office for the Owner, Engineer, and/or Inspector. Demobilization will be considered complete when all the above listed facilities are removed and the project work areas have been cleaned up to the satisfaction of the Owner.
END OF SECTION
01300 - 1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC SECTION 01300
SUBMITTALS
PART I - GENERAL
1.1 DESCRIPTION
This Section covers requirements for submittals in addition to those stated in the Conditions of the Contract and forms a part of all other Specification Sections in which submittals are specified or required. Refer to the specific Sections and Divisions of the Specifications for additional submittal requirements.
A. Submittal Requirements Included In This Section.
1. Number of submittal copies required.
2. CPM progress schedule.
3. Shop drawings.
4. Samples.
5. Materials lists and equipment data.
6. Instruction (operation and maintenance) manuals.
7. Installation instructions.
9. Record drawings and specifications.
10. Certificates.
11. Schedule of values.
B. Submittal Requirements In General Conditions and Other Sections.
1. Applications for payments.
2. Schedule of testing laboratory services.
3. Written guarantees and warranties.
4. General Conditions, Article 12.
5. Factory test reports.
6. Manufacturers' certified reports.
7. System validation test procedures and results.
01300 - 2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC PART 2 – PRODUCTS - (Not Applicable to this Section)
PART 3 - EXECUTION
3.1 SUBMITTAL - GENERAL REQUIREMENTS
Refer to General Conditions, Article 12. All such items required to be submitted for review shall be furnished by and at the expense of the Contractor and any work affected by them shall not proceed without such review. Except for record documents, test plans, and instructional manuals for operation and maintenance, submittal shall be approved before the material or equipment covered by the submittal is delivered to the site.
A. Number of Submittals.
1. General. Except for manufacturer's instruction manuals and samples, the Owner shall require and retain 4 copies of all submittals, specified or required in this and all other Sections of these Specifications, for his and his representatives' use, unless otherwise specifically noted in a specific Specification section. The Contractor shall submit such additional number of copies, not to exceed 3, to be reviewed and returned for his use. For submitted drawings 11 by 17 inches and larger, submittal of a reproducible copy in accordance with General Conditions Article 12.2 is preferred and encouraged. The reproducible set will be returned to the Contractor marked to show the required corrections or approval.
2. Samples. Provide the number of samples for each material or equipment item in accordance with Paragraph 3.04 herein and as required in the respective section of these Specifications.
3 Manufacturer's Instruction Manuals. Provide the number of copies of the preliminary submittals in accordance with Article 12.7.4 of the General Conditions. Upon approval of the preliminary submittals, deliver five (5) copies of each manual to the Owner, unless otherwise specified or directed.
B. Method of Submittal.
Equipment which is specified in one section of the Specifications shall not be combined in a single submittal with equipment specified in other Sections of the Specifications, unless unit responsibility for a package system is required. In each transmittal the Contractor shall state the Owner's Project Number and Name, Name and Address of Contractor, Name and Address of Subcontractor, Manufacturer, Supplier or Distributor as applicable, Plan Reference and Specification Section, Articles, and paragraphs to which the submittal pertains; accompanying data sheets, catalogs, and brochures shall be identified in the same manner. Submittal transmittals shall fully index all items submitted.
C. Piecemeal Submittals.
Except for reinforcing steel submittals, piecemeal submittals will be returned unreviewed. However, for mechanical equipment and the like, separate submittals for embedded items, embedded metal work and anchors will be accepted for review. 01300 - 3
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC
3.2 CPM PROGRESS SCHEDULE
Refer to Section 01300, Critical Path Schedule, as it concerns Construction Schedule and required use of Critical Path Method (CPM).
3.3 SHOP DRAWINGS
A. Title Block and Identification
On each shop drawing, provide a space for the Engineer's approval or correction stamp and a title block showing the following:
1. Name and address of Contractor.
2. Name and address of Subcontractor, manufacturer, supplier, or distributor, as applicable.
3. Name and address of Owner.
4. Date, scale of drawings, and identification number.
5. Contractor's review and approval stamp.
6. Owner's Project Number (if applicable).
7. Drawing Reference and Specification Section reference.
8. Project Name.
B. Preparation and Size
Details and information shall be clearly drawn, dimensioned, noted, and cross referenced. Unless otherwise approved, prepare shop drawings of the same size as the Contract Drawings or on 8-1/2 by 11 inch sheets as applicable. Refer to Paragraph 3.01.A above regarding use of a reproducible drawing copy.
C. Data
Unless the following data is included in instruction manuals or equipment data submitted prior to or with the shop drawings, submit with the shop drawings complete catalog and technical data for all manufactured products, materials, machinery, and equipment covered by the shop drawing submittal. Include data showing for each item, as applicable, the following information:
1. Manufacturer's specifications and details.
2. Applicable technical data and performance curves.
3. Preparation, assembly, and installation instruction with allowable tolerances.
4. Connection requirements.
01300 - 4
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC
5. Pre-start-up servicing and operating methods.
6. Other data and information necessary to demonstrate that the proposed items conform to the Contract Documents.
D. Information Required
Shop drawings shall contain details and information fully developing the pertinent Contract Document requirements and such other information as may be specified or required for approval, including but not limited to:
1. Related work with cross references to applicable portions of the Contract Documents.
2. Dimensions, including variations between indicated dimensions and actual conditions.
3. Physical configurations with critical dimensions for clearance, access, and servicing.
4. List of materials, including fasteners and connectors.
5. Structural construction and assemblies, welds shown by AWS symbols, and each fastener and connector shown by type and class.
6. Grouting work, including grouting space and material.
7. Concrete foundations and bases for machinery and equipment including joints, joint filler and sealer, and reinforcing.
8. Anchor bolt details showing type and class, sizes, embedments, projections, and locations measured with respect to permanent structural features. An anchor bolt template shall be shown on the Shop Drawings and shall be furnished unless waived in writing by the Owner.
9. Protective coatings and factory finishes fully described as to materials, number of coats, plated and metallic coating finishes, treatments, and similar information, all based on specified requirements. The term "as specified" is not acceptable for this purpose.
10. Machinery and equipment details. Standard catalog items need not be illustrated in detail, but indicate and detail sizes, supports, and connections.
11. Location of auxiliary items that are parts of machinery and equipment including sight glasses, petcocks, gauges, lubrication fittings and access, and maintenance monitoring devices.
12. Piping systems and piping including layout, fittings, valves, appurtenances, hangers and supports, and sleeves.
01300 - 5
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC
13. Electrical equipment showing plans, elevations, sections, arrangements, materials, anchor bolts, supports, weights, wiring and circuit diagrams, internal connections, busses, grounding, conduit spaces, layout of instruments, gauges, meters, and other components.
14. Underground duct banks showing typical details of conduits, joints, spacers, and means of securing conduits in place during concrete placement.
15. Dielectric connections, and materials and methods to be used to isolate dissimilar materials.
16. Full-size lettering layouts for data plate and nameplate inscriptions.
17. Written descriptions fully describing the operation of all control circuits, startup sequencing, shutdown sequencing, and alarms.
E. Details and Connections
Satisfactorily detail all connections required to complete the Work, including details necessary to make indicated or specified additions to existing work or to provide connections for future work. Design connections and parts of strength to withstand, without adverse deflection or stress, all loads or pressures to which they may be subjected and to develop the strength of the members or parts connected. In no case shall the connections, parts, or details be inferior to those required by the Contract Documents.
F. Related Work
The term "by others" is not acceptable for the description of related work shown in the shop drawings. Clearly note by name or description the Contractor, Subcontractor, or trade to provide such related Work; where such name or description is missing, it shall be understood and agreed that the Contractor is to furnish and install such related Work.
G. Clearances
Do not proceed with any related Work that may be affected by piping, machinery, equipment, or other work therein until shop drawings and data showing all components, with acceptable clearances have been approved.
H. Composite Shop Drawings with Installation Layouts
Prepare and submit drawings, wherever specified or required, to resolve tight or conflicting field conditions. Show dimensional plans and elevations of the materials or equipment of all trades in the involved area or space, and include complete information as to arrangements, locations, clearances, avoidance of interferences, access, sizes, supports, connections, services, assembly, disassembly, and installation. Composite shop drawings and layouts shall be coordinated in the field by the Contractor and his Subcontractors for proper relationship to the Work of all trades, based on field conditions, and shall be checked and approved by them 01300 - 6
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC before submittal. Contractor shall have competent technical personnel readily available for such coordinating and checking.
3.4 SAMPLES
A. Identification
Label or tag each sample or set of samples identifying the manufacturer's name and address, brand name, catalog number, intended use and other data specified in Article 3.01.B herein.
B. Colors, Patterns, and Textures
For items required to be of selected and approved colors, patterns, textures, or other finish, submit sufficient samples to show the range of shades, tones, values, patterns, textures, or other features corresponding to the instructions and requirements specified.
C. Field-Applied Paint and Coatings
Submit samples of finishes at least 60 days prior to start of such finishing operations in conformance with requirements specified in Section 09900, Painting and Protective Coatings.
D. Factory Finish Colors
Colors of material specified to be furnished with a factory finish are subject to approval. Submit duplicate samples of factory finishes showing the full range of available colors for selection and approval when requested by the Owner.
3.5 MATERIALS LISTS AND EQUIPMENT DATA
Materials lists and equipment data shall be submitted for all items proposed to be incorporated into the Work. In determining acceptability, consideration will be given to the availability of maintenance and replacement parts and materials, the availability of manufacturer's technical representatives, other factors that relate to the maintenance and repair of installed items without excessive inconvenience to the Owner, guarantees and warranties, as well as determination of conformance with the Contract Documents.
A. Material Lists
Submittal copies of Material Lists shall be provided in accordance with General Conditions Article 12.5, except that the number of copies submitted shall be as stated in Paragraph 3.01.A herein.
B. Equipment Data
Submittal copies of equipment data shall be provided in accordance with General Conditions Article 12.6, except that the number of submittals shall be as stated in Paragraph 3.01.A herein. Submittals for equipment incorporating logic circuits shall 01300 - 7
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC include a draft of a detailed theory of operation. Data shall be submitted in sets covering complete systems or functioning units.
3.6 INSTRUCTION (OPERATIONS AND MAINTENANCE) MANUALS
Instruction Manuals shall comply with the requirements of General Conditions Article 12.7 and as further described below.
The manufacturer's instruction, or O&M, manuals required by these Specifications shall be specific to this project and to the equipment being furnished. The requirements of General Conditions Article 12.7.2b regarding inapplicable data shall be strictly enforced.
It is the intent that the instruction manuals be a complete document on the respective equipment item(s), independent of any separate shop drawing submittals, for the information and use by operation and maintenance personnel. As such, in addition to the contents listed in General Conditions Article 12.7.1, the manuals shall contain the following:
all approved shop drawing data necessary to describe the respective equipment and conform to the requirements of General Condition Article 12.7 and this Section; wiring diagrams and detailed circuit operation description; and performance curves and data.
The index furnished for each manual shall address all of the content categories fisted in General Conditions Article 12.7.1 to facilitate their being located by the reader. Categories which are considered to be not applicable or not required shall be identified as such in the index.
For each class of equipment or machinery identify the name, address and telephone number of the manufacturer, supplier and closest authorized service organization or company. Include this information at the beginning of each respective equipment manual.
3.7 INSTALLATION INSTRUCTIONS
In addition to the instructions submitted under Article 3.06, the Contractor shall submit two copies of manufacturers' installation instructions for material and equipment incorporated in the Work to the extent specified in other Sections and Divisions of the Specifications or requested by the Owner for its review. Installation instructions will be reviewed for general adequacy only. After review, the Contractor shall distribute copies to all those involved with the installation.
Submit this information sufficiently in advance of the Work to ensure proper coordination of the respective equipment installation into the Work. In no case furnish this information later than delivery of the respective material or equipment. Payment for materials and equipment delivered will not be approved without submittal of the respective manufacturer's installation instructions.
3.8 EARTHQUAKE DESIGN AND RESTRAINT
All manufactured equipment supplied under this Contract shall be designed, constructed and attached to resist stresses produced by seismic forces specified in this Section.
Equipment that does not vibrate during normal operation shall be rigidly attached.
Equipment that vibrates during normal operation shall be attached by means of isolators with mechanical stops that limit movement in all directions unless it can be demonstrated by 01300 - 8
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC calculations that such stops are not required. Equipment or portions of equipment that move during normal operation shall be restrained with mechanical devices that prevent displacement unless it can be demonstrated by calculations that such restraints are not required.
A. Work Included
The work included in this Paragraph includes, but is not limited to, the following: All machinery, mechanical and electrical equipment, instrumentation panels, electrical panels, lighting fixtures, and all other manufactured equipment.
B. Minimum Earthquake Forces
Except as provided herein, the minimum earthquake forces shall be those prescribed for Essential Facilities by the 1994 Edition of the Uniform Building Code as published by the International Conference of Building Officials, 5360 South Workman Mill Road, Whittier, California 90601.
C. Contractor shall include seismic calculations with submittals of shop drawings, details and data specified in technical Sections of these Specifications. See Section 11005, Paragraphs 1.07B and 3.12. See also Section 16010, Paragraph 1.03A for application of these requirements to electrical work.
D. Seismic calculations shall be sealed and signed by a Professional Engineer (Civil and/or Structural) registered in the State of California.
3.9 OTHER SUBMITTALS
Provide copies of other submittals such as calculations, manufacturer's certified reports, operational demonstration and system validation reports specified in other Sections and Divisions of the Specifications.
3.10 STORAGE INSTRUCTIONS
For each equipment and material item furnished, provide for the Owner's records 2 copies of the manufacturer's recommended instructions for storage of the respective equipment or material. The instructions shall address conditions both before installation and (for mechanical, electrical and instrumentation equipment) after installation but before placing into continuous operation.
Submit manufacturer's storage instructions either prior to delivery of the material/equipment or with the request for payment of materials delivered. Payment for materials delivered will not be approved without submittal of the manufacturer's storage instructions.
3.11 FORM OF APPROVAL
A. Copies of submittals which are returned to the Contractor and which are subject to approval will be marked with notations A, B, B-R, C, D, or E, in which case the action so indicated shall be taken by the Contractor. These notations are defined as follows:
01300 - 9
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC
1. No Exceptions Noted (Resubmittal Not Required): Accepted subject to its compatibility with future submissions and additional partial submissions for portions of the work not covered in this submission. Does not constitute approval or deletion of specified or required items not shown in the partial submission.
2. Make Corrections Noted (Resubmittal Not Required): Same as A, except that minor corrections as noted shall be made by the Contractor.
3. Make Corrections Noted (Resubmit for Record Purposes): Same as B, except that resubmittal is required.
4 Amend and Resubmit: Rejected because of major inconsistencies or error which shall be resolved or corrected by the Contractor prior to subsequent review by the Design Consultant.
5. Not Acceptable (Resubmit): Submitted material does not conform to Drawings and Specifications in major respect, i.e., wrong size, model, capacity, or material.
6. Received for Record Purposes Only: Applies to submittals which are required but not reviewed, such as shoring submittals.
B. Returned copies of drawings marked with either notation A, B, or B-R authorize the Contractor to proceed with the fabrication, installation or construction, or any combination thereof, covered by such returned drawings, provided, that such fabrication, installation or construction shall be subject to the comments, if any, shown on such returned copies and to the Contract requirements whether or not specifically referenced. Although fabrication may proceed on a notation B-R, Contractor shall incorporate the comments, resubmit, and obtain notation A before release for shipment can be granted. Failure to satisfactorily address the review comments, shall result in designation of the resulting as being defective.
C. Returned copies of drawings marked with notation C or D shall be corrected as necessary and revised drawings shall be submitted in the same manner as before.
3.12 RECORD DRAWINGS AND SPECIFICATIONS
The Contractor shall maintain one record copy of all Drawings, Specifications, Addenda, Modifications, approved submittals, correspondence, and transmittals at the site trailer in good order and readily available to the Owner. The Record Drawings shall be clearly and correctly marked and the Record Specifications annotated by the Contractor to show all changes made during the construction process at the time the changed Work is installed.
No such changes shall be made in the Work unless previously authorized by a Modification or by specific approval of deviations or revisions in submittals.
A. Buried and Concealed Work
The Contractor shall record the precise location of all piping, conduits, ducts, cables, and like Work that is buried, embedded in concrete or masonry, or concealed in wood or metal framed walls and structures at the time such Work is installed and 01300 - 10
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC prior to concealment. Each feature of the concealed Work, such as the beginning and end of straight runs, radius center point of curved runs, angles, connections, plugged tees or other fittings for future connections, and like items shall be accurately located by not less than 2 dimensions to permanent structures. The depth below finish grade, slab, or paving shall be noted for buried pipe, conduit, or ducts at the beginning and end of straight grade runs and at all grade change points, excepting sewer or drain lines run between manholes. Should the Contractor fail to record such buried or concealed Work, he shall uncover the unrecorded Work to the extent required by the Owner and shall satisfactorily restore and reconstruct the removed Work with no change in the Contract Price or the Contract Time.
B. Delivery
Upon completion and prior to final inspection of the Work and as a condition of final payment, the Contractor shall submit the Record Drawings and Specifications to the Owner for review, and shall make such revisions or corrections as may be necessary for them to be a true, complete, and accurate record of the Work in the opinion of the Owner. When approved, the Contractor shall deliver the Record Drawings and Specifications to the Owner.
3.13 CERTIFICATES
Each certificate required under the Contract or in any of the following Sections shall be signed by the individual, office, or agent lawfully authorized to execute the certificate, and such authority shall be cited in the certificate by title, description, or other acceptable evidence. All certificates shall be sworn as to the correctness and validity of the contents.
Where specifically required in the respective Section of the Specifications, certificates shall be notarized and duplicate copies of required certificates shall be notarized to be true copies.
3.14 SCHEDULE OF VALUES
The Contractor shall submit to the Owner for acceptance, in the form directed by or acceptable to the Owner, a complete schedule of the values of the various portions of the Work, including quantities and unit prices if required by the Owner, aggregating the Contract Price (except in cases and to the extent that accepted unit prices form the basis for payment). The schedule shall subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during construction and to coordinate with the progress schedule required for this Work, and shall be supported by such data to substantiate its correctness as the Owner may require. Each item in the schedule of values shall include its proper share of overhead and profit. An unbalanced breakdown providing for overpayment to the Contractor on items of Work which would be performed first will not be approved. The schedule of values, when accepted by the Owner, shall be used only as a basis for the Contractor's applications for payment and not for additions to or deductions from the Contract Price. The initial submittal for the schedule of values shall be provide at the preconstruction conference as per Section 01200, or within 10 days of the Notice to Proceed, whichever comes sooner.
3.15 HEALTH AND SAFETY PLAN
01300 - 11
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01300 Submittals.DOC Ensure the health and safety of all on-site Contractor personnel, and comply with federal, state and local health and safety requirements. This includes preparation of a Health and Safety Plan (HASP) relating to Contractor activities conducted in the performance of this Work. Submit a copy of the HASP to the Owner for his records and maintain a copy in the possession of the CONTRACTOR's field personnel while working on site. All on-site CONTRACTOR personnel, City Inspector(s) and Project Manager shall attend a job-site informal health and safety meeting prior to initiation of Work. Supply equipment specified in CONTRACTOR's HASP, including required industrial hygiene monitoring. Contractor shall hold weekly tailgate safety meetings with Contractor forces, City Inspector(s) and City Project Manager, in accordance with Section 01015, General Provisions.
3.16 FACTORY TEST OBSERVATIONS
The Contractor shall provide access for Owner and Engineer to observe factory testing of well pumps, motors and piping and appurtenances. Contractor shall notify Owner at time of manufacturer of such equipment specified and used in the project for observation of fabrication and testing.
3.17 TRAFFIC CONTROL PROGRAM
The Contractor shall develop and submit a Traffic Control Program which satisfies the requirements of Section 01015, “General Provisions,” of these Specifications, and which is in accordance with the City of Signal Hill, and the W.A.T.C.H. Manual.
END OF SECTION
01400-1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01400 QC.doc SECTION 01400
QUALITY CONTROL
PART 1 - GENERAL
1.1 DESCRIPTION
This Section covers quality control requirements supplementary to those of the Conditions of the Contract and other Sections of the Specifications.
1.2 QUALITY ASSURANCE
A. Testing Laboratory Qualifications. Whether employed by the Owner or Contractor, the Testing Laboratory shall be licensed to conduct and perform testing services in the State and jurisdiction where the Work is located. All testing shall be performed under the direct supervision and control of a qualified registered professional engineer employed by the laboratory.
B. Foundation or Soils Engineer. The Owner will employ and pay for the services of Civil Engineer registered in California specializing in Foundation or Soils Engineering to observe the specified portions of the Work and to supervise or perform testing pertaining to the observed Work.
C. Requirements of Regulatory Agencies. Refer to paragraph 17.6 of Section 00700, "General Conditions." The Testing Laboratory will perform tests required by the regulatory agencies at no cost to the Contractor. All other inspections, permits, and approvals required by the agencies shall be furnished by the Contractor at his expense.
D. Source Quality Control. To the extent specified herein or in other Sections, the Testing Laboratory shall obtain samples of various materials at the source of supply and test the materials for compliance with the Contract Documents. The Testing Laboratory shall tag, seal, label, or otherwise suitably identify the bulk materials so sampled, and no such materials shall be used in the Work until the test reports are submitted to and approved by the Engineer. The applicable tests shall be repeated at the specified intervals, whenever the source of supply is changed, or whenever the characteristics of the materials change or vary in the opinion of the Engineer.
E. Factory Test Witnessing. To the extent specified or ordered by Owner, the Testing Laboratory shall witness testing performed at the factory or supplier's test facility.
Unless otherwise specified, the Owner will pay the cost of factory test witnessing.
F. Inspection. Refer to paragraph 17.2 of Section 00700 "General Conditions." The Contractor shall give the Engineer not less than two (2) working days written notice whenever his operations require the services of more than one Inspector. To the extent specified, the Testing Laboratory shall furnish specially qualified inspectors for various field inspections.
01400-2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01400 QC.doc
1.3 SUBMITTALS
A. Laboratory Test or Inspection Reports. Each report shall be signed and certified by the supervising engineer of the Testing Laboratory. Unless otherwise specified, the Testing Laboratory shall submit five (5) copies of each report to the Engineer.
B. Foundation or Soils Engineer's Reports. These reports shall be certified and submitted to the Engineer. A copy of each report will be furnished to the Contractor by the Engineer.
C. Schedule of Testing Laboratory Services. The Contractor shall submit a schedule giving the dates and duration that the Testing Laboratory shall perform testing services or furnish special inspections. After this, the Contractor shall give the Engineer and Testing Laboratory not less than ten (10) working days written notice of any change in the schedule.
PART 2 - PRODUCTS (Not applicable to this Section)
PART 3 - EXECUTION
3.1 SAMPLING
Field samples will be selected and obtained by the Testing Laboratory or Inspector unless otherwise specified.
3.2 LABORATORY TEST PROCEDURES
Testing shall conform to the requirements specified. If no procedure or test method is specified, testing shall comply with the material specification referenced unless otherwise directed by the Engineer.
3.3 CONTRACTOR FURNISHED ASSISTANCE
When requested, furnish access, facilities, and labor assistance at the site as necessary for the duties to be performed by the Testing Laboratory and Inspector, including ladders, hoisting, temporary lighting, temporary water supply, and like services. Furnish a temporary concrete test cylinder curing cabinet conforming to ASTM C31, located as directed.
3.4 TEST SCHEDULE AND TEST COSTS
The Owner will pay the cost of testing scheduled in this Article. The Contractor shall perform all other certifying and testing requiring by the Contract Documents, at his expense.
The Contractor shall pay the Owner, in accordance with Paragraph 20.12 of Section 00700, "General Conditions", any cost the Owner incurs for tests when the tested material or equipment fails the test and for retesting caused by failure disclosed in previous tests.
3.5 TEST COSTS PAID BY OWNER
A. Optimum moisture and compaction tests for backfills; B. Sampling and testing of reinforced bars.
01400-3
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01400 QC.doc C. Testing of pipe bedding materials
D. Making and testing concrete test cylinders.
E. Sampling and testing of Portland Cement and concrete aggregates, field slump tests and air entrainment test.
F. Concrete inspection
END OF SECTION
01710-1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 01710 Clean Up.doc SECTION 01710
CLEAN-UP
PART 1 - GENERAL
1.1 REMOVAL OF DEBRIS DURING CONSTRUCTION
A. During its progress, the work and the adjacent areas affected thereby shall be kept cleaned up and all rubbish, surplus materials and unneeded construction equipment shall be removed and all damage repaired.
B. Where material or debris has washed or flowed into or has been placed in watercourses, ditches, gutters, drains, catch basins, or elsewhere as a result of the Contractor's operations, such material or debris shall be entirely removed and disposed of during progress of the work, and the watercourses, ditches, gutters, drains, catch basins, and other facilities cleaned and kept in a neat, clean and functioning condition.
1.2 FINAL CLEANING
A. On or before the completion of the work, the Contractor shall, unless otherwise directed in writing by the Owner's representative, tear down and remove all temporary buildings and structures built by him; shall remove all temporary works, tools and machinery or other construction equipment furnished by him; shall remove, acceptably disinfect, and cover all organic matter and material containing organic matter in, under and around privies, houses and other building used by him; shall remove all rubbish from any grounds which he has occupied; and shall leave the roads and all parts of the premises and adjacent property affected by his operations in a neat and satisfactory condition.
B. The Contractor shall restore or replace, subject to the approval of the Owner, any property damaged by his work, equipment or employees, to a condition at least equal to that existing immediately prior to the beginning of operations. Suitable materials, equipment and methods shall be used for such restoration as approved by the Owner, or as required elsewhere in these specifications.
END OF SECTION
02461 - 1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\02461 Asphalt Pavement.doc SECTION 02461
ASPHALT CONCRETE PAVING
PART 1 - GENERAL
1.1 DESCRIPTION
Requirements specified in Conditions of the Contract and Division 1 form a part of this Section. Provide all tools, equipment, materials, labor and services for furnishing, placing and compacting of asphalt concrete pavement and base to the lines, grades and dimensions shown on the Drawings and as specified herein. Where any permit requirements exceed the requirements of this Section, the permit requirements shall govern.
1.2 SYSTEM
The Work of this Section shall include the construction of asphalt concrete pavement, including all asphaltic tack coats, prime coats, seal coats and traffic striping as required, specified herein, or indicated on the Drawings. Subgrade preparation is included elsewhere in Division 2 of these specifications.
1.3 STANDARD SPECIFICATION
Except as supplemented or specifically modified herein or shown otherwise on Drawings, the entire work under this Section shall be in compliance with the provisions in the applicable Sections of the latest Edition and Supplement of the Standard Specifications for Public Works Construction of the Joint Cooperative Committee of the APWA-AGC, (SSPWC), also known as the “Green Book”. In case of conflict between any requirements set forth in this Section and any provisions of the foregoing Standard Specifications the requirements set forth herein shall govern.
PART 2 - PRODUCTS
2.1 BASE COURSE
Aggregate base where required by the Engineer shall consist of crushed aggregate base materials graded to conform to Section 200 of the latest Edition of the Standard Specifications for Public Works Construction.
2.2 ASPHALT CONCRETE
Asphalt concrete shall conform to the requirements of Section 203 of the SSPWC for C1-AR-4000, unless otherwise shown on the Drawings or required by local conditions. 02461 - 2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\02461 Asphalt Pavement.doc
2.3 ASPHALT BINDER
Asphalt binder to be mixed with aggregate shall be liquid asphalt or paving asphalt AR 4000, in accordance with Standard Specifications, Section 203, "Paving Asphalt" of the SSPWC. Liquid asphalt shall conform to the provisions in Standard Specification Section 203, "Liquid Asphalt", of the SSPWC Paving asphalt to be mixed with aggregate shall be a steam-refined asphalt conforming to the provisions in Section 203, "Paving Asphalt" of the SSPWC.
2.4 PRIME COAT
Prime coat shall be SC-250 liquid asphalt conforming to the requirements of Section 203 of the SSPWC, or as determined by the Owner.
2.5 PAINT BINDER
Paint binder for tack coat shall be emulsified asphalt conforming to the provisions in Section 203 "Emulsified Asphalt" of the SSPWC.
2.6 TACK COAT
Tack coat shall be type SS-1h grade emulsified asphalt conforming to the requirements of Section 203 of the SSPWC.
PART 3 - EXECUTION
3.1 GENERAL
Conform to the requirements of Sections 203 and 301 of the SSPWC, and as stated herein.
A. Pavement Thickness. Asphalt concrete shall be spread and compacted in a single layer to provide a uniform compacted thickness of 0.40 feet or 0.10 feet greater than the existing paving, whichever is greater.
B. Pavement Width. Base and asphalt concrete pavement shall be a minimum of 18 inches (9 inches each side) wider than the trench width at the existing grade.
3.2 COLD PLANE EXISTING AC (2" UNIFORM DEPTH)
All roadway excavation operations shall conform to sections 401-2 and 404 of the SSPWC, the plans and these Special Provisions. Existing AC pavement within the project limits shall be removed and excavated at the locations and to the dimensions and details shown on the plans or as directed by the Engineer. The final cut shall result in a uniform surface conforming to the typical cross section. Contractor’s attention is directed to the condition that if presence of pavement fabric. It is the Contractor responsibility to remove all the thermoplastic pavement markings prior to the excavation operation and no additional compensation will be allowed therefor.
The City has made every reasonable effort to locate and mark on the plans all known metal roadway improvements such as sewer manhole covers, water valve covers, and catch basin covers. The City makes no guarantee that it has successfully located all said items therefore; the Contractor shall thoroughly inspect the work site in advance of the excavation operation to minimize the risk of striking any these items.
02461 - 3
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\02461 Asphalt Pavement.doc
3.3 3.4
BASE COURSE
Specified aggregate base shall be constructed where the Engineer directs and shall be graded and compacted to provide the designated uniform grades and cross sections to receive asphalt concrete paving. Conform with the applicable requirements of Section 301 of the SSPWC. Base course shall be eight (8) inches compacted thickness or one (1) inch greater than the existing base, whichever is greater, unless otherwise indicated on the drawings.
PRIME COAT
Application of prime coat shall comply with the applicable requirements of Sections 203 and 302 of the SSPWC. Prime coat shall be uniformly distributed over completed subgrade and/or aggregate base course at the application rate of 0.25-gallons per square yard, unless the Owner specifies a different application rate at the time the work is performed.
ASPHALT CONCRETE PAVING
Asphalt concrete paving of total thicknesses shown on the Drawings for various locations shall be constructed over completed and primed subgrade and/or aggregate base course.
Construction shall conform to the applicable requirements of Section 302 of the SSPWC.
TACK COAT
In conformance with the applicable requirements specified in Sections 203 and 302 of the SSPWC, tack coat shall be applied to all vertical surfaces of walls, headers, concrete slabs, pavement joints, and similar faces against which asphalt concrete pavement is to be placed.
Care shall be exercised not to damage adjacent concrete curbs or gutters. Curb or gutter damaged due to excavation work shall be replaced as approved by the Engineer at the Contractor's expense.
Residue from excavation shall not be permitted to flow or travel into gutters, onto adjacent street surfaces or parkways. All residues shall be completely removed by sweeping and properly disposed. No washing of residue into drainage structures will be allowed. All catch basins and curb inlets shall be covered, utilizing the BMP which most appropriately fits the situation, and as approved by the Engineer. The Contractor shall make every effort to control all dust created by his operations by utilizing the Best Management Practice approved by the State Water Resource Control Board.
Temporary ramping, where required by the Engineer for traffic control or other purposes, and shall be considered included in the price bid item "Traffic Control", and no additional compensation will be allowed.
Payment for “COLD PLANE EXISTING AC (2" UNIFORM DEPTH)” shall be at the unit price bid per square foot, and shall be based on the actual area of surface planed regardless of the number of passes required. The contract unit price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in “COLD PLANE EXISTING AC (2" UNIFORM DEPTH)” including disposing of material removed and no additional compensation will be allowed therefor.
3.5 3.6
3.7 3.8
SEAL COAT
A fog seal coat shall be required on all new asphalt concrete surfaces. After 14 days following placement of the asphalt surfacing, the fog seal coat shall be applied at a rate of
0.05 gallon-per-square-yard. Asphalt emulsion shall conform to Sections 37, 39 and 94 of the State Standard Specifications.
PAVEMENT TRAFFIC STRIPING
Following completion of all paving operations, the Contractor shall replace all pavement striping disturbed or destroyed during construction, to match the original markings.
Materials for painting shall be in accordance with the City’s Standard Plans and Special Provisions.
END OF SECTION
02461 - 4
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\02461 Asphalt Pavement.doc 02560-1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 02560 Trench Excavation and Backfill.doc SECTION 02560
TRENCH EXCAVATION AND BACKFILL
PART 1 - GENERAL
Trench excavation and backfill shall include all necessary excavation for pipelines, backfilling, compaction and disposing of excess excavated material, all as required for the complete performance of the work for the installation of pipe as indicated on the plans and as specified herein.
Trench excavation and backfill as referred herein or in connection herewith shall be construed as including any or all of the following described operations:
Excavating all materials of whatever nature encountered; backfilling; subgrading for pipe and performing any operation which may be necessary to properly complete the entire work as indicated and specified.
PART 2 - PRODUCTS
2.1 EQUIPMENT
Equipment used for trench excavation and backfill shall be at the Contractor's option.
PART 3 - EXECUTION
3.1 EXCAVATION
All trench excavation, backfill, pipeline placement, compaction, etc. shall be constructed per City of Signal Hill Standard Drawing 401.
3.2 PAYMENT
Payment for complying with the requirements of this section shall be included in the appurtenant bid items of the proposal and no additional compensation shall be allowed therefor.
END OF SECTION
15041-1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15041 Chlorination of Dom. Water Lines.doc SECTION 15041
CHLORINATION OF DOMESTIC WATER LINES
PART 1 - GENERAL
1.1 SCOPE
All domestic water mains, domestic water services, attached appurtenances and connections, if any, shall be disinfected by an approved testing firm and as prescribed by in AWWA Specification C651, and as specified herein. The Contractor shall furnish all equipment in good operating condition, labor and materials, and water necessary for chlorinating and flushing the pipeline and for the certification of the pipeline disinfecting.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Sodium hypochlorite by injection
PART 3 - EXECUTION
3.1 DISINFECTION
A. Before being placed in service, all facilities shall be chlorinated and flushed.
Chlorine shall be applied by sodium hypochlorite by injection.
B. All required corporation stops and other plumbing materials necessary for chlorination or flushing of the main shall be installed by and, abandoned as necessary, at the expense of the Contractor.
C. Disinfection must be in accordance with Standard Plans for Public Works Construction (Greenbook), latest edition.
D. All pipelines shall be thoroughly flushed prior to disinfection. After the required period of retention of the chlorine solution, the City will test the water for residual chlorine and will make any additional test which may be necessary.
E. For liquid sodium hypochlorite, the chlorinating agent shall be applied at the beginning of the section to be chlorinated and shall be injected through a corporation stop, a hydrant or other connection to ensure treatment of the entire system being disinfected. Water shall be fed slowly into the pipeline with chlorine applied in amounts to produce a dosage of 100 ppm in all sections of the pipeline and appurtenances. Treated water shall be retained in the system for a minimum period of 24 hours and shall produce at the end of the retention period not less than 50 ppm in all sections being disinfected.
E. During the chlorination process, all valves and facilities shall be operated. 15041-2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15041 Chlorination of Dom. Water Lines.doc F. If the tests are not satisfactory, the Contractor shall provide additional disinfection as required, at no additional cost.
G. Every service connection served by a main which is being disinfected shall be tightly shut off at the curb stop before water is turned into the main. Care shall be taken to expel all air from the main and services during the filling operation.
H. After chlorination, the water shall be flushed from the line at its extremities until the replacement water tests are equal chemically and bacteriologically to those of the permanent source of supply. The chlorinated water shall be flushed and dechlorinated by the Contractor. The City will not be responsible for loss or damage resulting from such disposal.
PART 4 - PAYMENT
Payment for disinfecting and dechlorinating the water mains and appurtenances shall be included in the appurtenant bid items and no additional compensation shall be allowed therefor.
END OF SECTION
15050-1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15050 Piping, Valves and Accessories.doc SECTION 15050
PIPING, VALVES AND ACCESSORIES
PART 1 - GENERAL
1.1 DESCRIPTION
A. Work included in this Section: The Contractor shall furnish and install all piping, including fittings, valves, supports, and accessories as shown on the Drawings, described in the Specifications and as required to completely interconnect all equipment with piping for complete and operable systems.
1.2. QUALITY ASSURANCE
All materials and equipment furnished under this Section shall be of a manufacturer who has been engaged in the design and manufacture of the specific materials and equipment for a period of at least 5 years.
1.3 SUBMITTALS
A. Shop Drawings:
1. Verify by excavation, inspection and measurement all installation conditions for shop fabricated pipe before preparation of Shop Drawings. Submit field measurements and photos with Shop Drawings where exposed conditions are significantly different than indicated on the Drawings.
2. Layouts and Schematics: Submit detailed installation drawings of all piping.
Schematics may be submitted for piping 4-inches and smaller. The drawings shall include pipe support locations, and types if different than shown on the Drawings and specifications, all fittings, valves, and other appurtenances.
3. Submit data to show that the following items conform to the Specification requirements:
a. Pipe, fittings, and accessories.
b. Fabricated pipe supports and other pipe supports as required herein. c. Flexible couplings and flanged adapters.
d. Valves.
4. Submit certified test reports as required herein and by the referenced standard specifications.
5. Pipe, fittings and joint fabrication details for welded steel pipe.
B. Affidavits: The Contractor shall furnish affidavits from the manufacturers for valves. 15050-2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15050 Piping, Valves and Accessories.doc
1.4 APPURTENANCES
Furnish and install all necessary guides, inserts, anchors and assembly bolts; washers nuts, hangers, supports, gaskets, and flanges; all other appurtenant items shown on the Drawings, specified or required for the proper installation and operation of the piping; devices included in or on the piping equipment; and piping accessories. Provide insulation for dissimilar metals with the use of insulating bushings, gasket sets or wrappings, as appropriate.
PART 2 - PRODUCTS
2.1 GENERAL
A. Pipe and valve sizes are nominal inside diameter unless otherwise noted.
B. All materials delivered to the job site shall be new, free from defects, and marked to identify the material, class, and other appropriate data such as thickness for piping.
C. Acceptance of materials shall be subject to strength and quality testing in addition to inspection of the complete product. Acceptance of installed piping systems shall be based on inspection, hydrostatic tests and successful completion of the disinfection process as specified hereinafter and Sections 15041 and 15043.
D. Cutoff Flanges: Provide at all pipe penetrations for pipes 4-inches and greater in nominal diameter, and at all penetrations of 3-inch and smaller nominal diameter pipe in wet or potentially wet locations as indicated on the Drawings. Cutoff flange outside diameter shall be at least 85% of the standard connection flange's outside diameter. Link type seals may be substituted for cutoff flanges.
E. Materials/Products/Equipment used on the project must be listed on the “Approved List of Materials” in Appendix A of the Corona City Standards.
F. All pipe, fittings, valves, appurtenances, etc. shall be rated for a minimum working pressure of (pump discharge pressure noted on the plans + 50-psi)
2.2 GENERAL MATERIAL REQUIREMENTS
A. Gaskets: Unless specifically specified otherwise, all gaskets shall be full face Garlock Model No’s 3000, 3700. and 3760.
B. Bolts and Tie Rods: Unless specifically specified otherwise, flange bolts and nuts, tie rods and other flange hardware shall conform to AWWA C110, and be as follows:
1. Exposed: Type 316 stainless steel (with anti-seize lubricant).
2. Encased: Type 316 stainless steel (with anti-seize lubricant).
3. Buried: Type 316 Stainless Steel (with anti-seize lubricant). 15050-3
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15050 Piping, Valves and Accessories.doc
2.3 MATERIALS
A. PVC Pipe
1. 2 inches and Smaller
PVC pipe shall meet the following requirements:
Pipe PVC SCH 80 as identified on plans
Joints Solvent Weld
Unions PVC, SCH 80, Solvent Weld
Ball Valves 150 PSI, with TFE true union ends with TFE seats and seals
Check Valves 150 PSI, true union ball check with TFE seats and seals
2. PVC Pipe 4-Inch through 12-Inch
PVC pipe 4-inches and larger in diameter shall meet the requirements of AWWA C900, DR 35. Bedding shall be in accordance with the plans.
B. Copper Pipe 1-inches through 2½-inches
Copper pipe and appurtenances shall be in accordance with the following:
Pipe Seamless, Type K copper tubing, ASTM B88 below
grade
Pipe Joints Soldered, 3-piece, screwed
Fittings Wrought copper soldered
Gate Valves 200 psi, WOG, bronze, ends, screwed bonnet, rising stem, solid wedge
Globe Valves 200 psi, WOG, bronze, screwed bonnet, renewable seat
Check Valves 200 psi, WOG, bronze, screwed ends, swing type, bronze disc, screwed cap
C. Pipe and Appurtenances ¼-inch through 1-inch shall be 316 SS with Swagelock fittings.
D. Ductile Iron Pipe
1. Materials: Pipe, fittings and appurtenances shall conform to the thickness class Ductile Iron Pipe as designated on the Plans.
15050-4
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15050 Piping, Valves and Accessories.doc All ductile iron pipes shall be new and shall conform to all requirements of Federal Specification WW-P-421C, ANSI A21.51 (latest revision) and AWWA C151 (latest revision).
All pipe and fittings shall be clearly marked with the name of the manufacturer or with a trademark of the size and type that has been approved by and filed with the Owner.
a. Lining and Coating: All ductile iron pipe and fittings, unless otherwise prescribed in another item of the Contract Documents, shall be coated with bituminous not less than one mil thick and shall be cement mortar lined.
b. Type of Joints: Ductile iron pipe shall have any of the following types of joints as specified in drawings: Push-on, flanged, mechanical with restraint or equal.
c. Specials and Fittings: All fittings for ductile iron pipe, unless otherwise required by the Drawings or Specifications, shall conform in all respects to AWWA C110 (latest revision).
d. Delivery and Handling: All pipe and fittings shall be manufactured, handled, loaded and shipped in such a manner that it is delivered undamaged, in sound condition, and conforming in all respects to these Specifications. Care shall be taken in loading and handling the pipe so as not to injure the pipe coating. No other pipe or material of any kind shall be placed inside any pipe or fitting at any time after the coating has been applied and prior to installation. All pipe and fittings installed on the work shall be new material which has never been previously used for any purpose whatsoever.
E. Steel Pipe (8 inches and larger)
Steel pipe shall be seamless (¼-inch thick) conforming to ANSI B36.10. Fittings shall be forged, standard weight conforming to ASTM A-105. Fusion bonded epoxy lining shall be 16-mils conforming to AWWA C213. Cement mortar lining shall be ½- inch, conforming to AWWA C205. Cement mortar coating shall be ¾-inch conforming to AWWA C205. Flanges shall be AWWA 300 lb.
2.4 PIPE COUPLINGS AND FLEXIBLE PIPE PIECES
A. General: For typical pipe joints refer to pipe material specifications. Other joint devices shall be furnished where called for as specified below.
B. Flexible Couplings and Flange Coupling Adaptors:
1. Sleeve: Ductile iron or fabricated steel.
2. Followers: Ductile iron, ductile iron, or steel.
15050-5
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15050 Piping, Valves and Accessories.doc
3. Sleeve Bolts: ASTM A325, Type 3; malleable iron; or equivalent.
4. Coating: Fusion epoxy line and coat sleeve and followers.
5. Pressure Rating: Pressure rating shall be equal to or greater than that of pipe being connected as determined by Barlow's Formula.
6. Manufacturers:
a. Flexible Couplings:
1. Connecting Pipe with Identical Outside Diameters: Rockwell 411 or 431; Dresser Style 38 or 53; or equal.
2. Connecting Pipe with Slightly Different Outside Diameters:
Rockwell 413; Dresser Style 162; or equal.
b. Flange Coupling Adaptors: Rockwell 912 or 913; Dresser Style 127 or 128; or equal.
c. Victaulic Couplings: Style 44 Type D Vic Ring coupling with ductile iron housing and grade E gasket.
7. Flex Coupling and Flanged Coupling Adapter Gaskets: Oil and grease resistant; Rockwell Grade 60; Dresser Grade 42; or equal.
8. Joint Restraint: Provide joint harnesses (tie rod lug or attachment plate assemblies) across all flexible couplings, flange coupling adaptors, except where specifically indicated otherwise on the Drawings. For flanged coupling adaptors, anchor studs may be substituted for the harnesses on pipe up to 12-inch. Design restraint for 1-1/2 times the test pressure of the applicable service.
2.5 VALVES AND ACCESSORIES
A. General Requirements for Valves:
1. All valves of each type shall be the product of one manufacturer, and shall be listed on the City’s Approved Materials List.
2. All valves shall be epoxy lined and coated; and furnished with operators, handwheels, levers, or other suitable type wrench including handles as specified herein or as shown on the Drawings.
2. All threaded stem valves shall open by turning the valve stem counterclockwise.
4. All valves and valve operators shall have a nonbleeding shop coat.
B. Valves and Accessory Systems:
1. Valves 4-12 inches.
15050-6
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15050 Piping, Valves and Accessories.doc a. All valves shall be new and of current manufacture.
b. Valves shall be furnished and installed with the type of ends suitable for connecting to the type of pipe shown on the plans or as specified herein. c. Valves shall be manufactured to meet all applicable requirements of the latest edition of AWWA C509-94. Flange drilling shall be in accordance with ANSI B16-1 standard for cast-iron flanges. All valves 12-inches and smaller shall be bubble tight at 200-psi water working pressure. d. Valves shall have nonrising stems, opening by turning left and provided with a handwheel or operating nut where buried. Valve stems shall be cast integral with stem collar and furnished of cast, forged, or rolled bronze. Stem nuts shall be independent of the wedge and shall be made of solid bronze.
All body bolts shall be 316 stainless steel.
e. Each valve shall have a smooth unobstructed waterway free from any sediment pockets.
f. Stuffing boxes shall be o-ring seal type with two rings located in stem above thrust collar.
g. Low friction torque reduction thrust bearings shall be located both above and below the stem collar.
h. Valves shall have hydrostatic shell test of 400 psi and shutoff test of 200 psi.
At the 200 psi shutoff test the valve must be bubble tight-zero leakage.
END OF SECTION
15060-1
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15060 Piping - Installation.doc SECTION 15060
PIPING - INSTALLATION
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work included in this section of the specifications consists of furnishing, installing and testing all piping, fittings and appurtenances, as indicated on the Drawings and specified herein or as required to complete the work.
B. Whenever the word "piping" is used in this section, it shall be understood to refer to all exposed and buried pipes, fittings, valves, flanges gasketing, hangers and supports or bedding comprising any given system, plastic piping and instrument tubing included.
C. All piping shall be installed to the lines and grades shown on the Drawings or as required for the mechanical equipment. All piping shall be properly supported and provisions shall be made for expansion and contraction.
D. Dissimilar metals shall be properly insulated with the use of insulating bushings, gasket sets or wrappings.
1.2 RELATED WORK SPECIFIED ELSEWHERE
A. Piping Materials Classifications - Section 15050.
B. Earthwork - Section 02200.
1.3 CODES AND PERMITS
A. Installation shall comply with all applicable federal, state and local laws whether or not explicitly specified.
B. The Contractor shall furnish to the City a certificate of final inspection and approval from the inspecting authority having jurisdiction.
1.4 INSPECTIONS AND TESTING
A. The quality of all materials, the process of manufacture and finished pipe shall be subject to inspection and approval of the City. Pipe may be inspected at the place of manufacture, and on the work site, and shall be subject to rejection at any time even though submitted samples may have been approved. In addition, the City reserves the right to have any or all pipe or fittings inspected or tested, or both, by an independent inspection service at either the manufacturer's plant or elsewhere. Such inspections and/or tests shall be at the City's expense. 15060-2
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15060 Piping - Installation.doc B. All pipe, fittings and appurtenances shall be carefully inspected in the field before installation. All piping found to be defective, as determined by the City, shall be pulled out and not installed. Such rejected pipe shall be clearly tagged in such a manner as not to deface or damage it, and the pipe shall then be removed from the job site by the Contractor at his own expense. Results of shop tests which may be required shall be submitted to the City prior to installation of the pipe for which such tests were ordered.
PART 2 - PRODUCTS
2.1 MATERIALS
Piping materials shall conform to requirements specified in Section 15050.
PART 3 - EXECUTION
3.1 GENERAL PIPING INSTALLATION PRACTICES
A. Any conflict arising during the erection of piping shall be brought to the attention of the City. No improvising or field changes shall be permitted without the approval of the City.
B. All piping shall be erected in such a manner as to obtain sufficient flexibility and to prevent excessive stresses in materials and excessive bending moments at joints or connections to equipment.
C. Full lengths of pipe shall be used wherever possible. Short lengths of pipe with couplings will not be permitted, except as may be approved by the City to eliminate overstressing or misalignment. All pipes shall be cut to exact measurement and shall be installed without forcing or springing.
D. Tool marks and unnecessary pipe threads shall be avoided. Burrs formed when cutting pipe shall be removed by reaming. Before installing any pipe, care shall be taken that the inside is thoroughly cleaned and free of cuttings and foreign matter.
E. Where piping is pitched for drainage, an accurate grade shall be maintained.
Piping shall be supported in such a manner as to prohibit deflection due to gravity that would be sufficient to pocket the lines when full of liquid. All changes in direction shall be made by using pipe fittings unless otherwise shown on the Drawings or as approved by the City.
F. Unions shall be installed in all piping connections to equipment, regulating valves, and wherever necessary to facilitate the dismantling of piping and removal of valves and other items requiring maintenance. Flanges on equipment may be considered as unions. At least one union shall be provided in every straight run of pipe unless otherwise noted or permitted. 15060-3
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15060 Piping - Installation.doc G. Raised face flanges shall not be used for connection to 125-psi cast iron flanges.
The raised face shall be removed before use and full-face gaskets shall be employed.
H. In general, all service piping shall come off the top of headers, and if possible, service piping shall slope for drainage.
I. Pipe anchors, thrust blocks, expansion joints, loops and bends shall be installed as indicated on the Drawings, and as required to properly protect the piping against vibration, misalignment and overstressing.
J. Exposed piping shall be neatly arranged, straight, run parallel to or at right angles to walls and shall be so graded that the entire system can be drained.
Drain valves shall be installed at the low points of piping. Vent valves shall be installed at all high points of the piping.
K. Installed piping shall not interfere with the operations or accessibility of doors or windows and shall not encroach on aisles, passageways and equipment and shall not interfere with the servicing or maintenance of any equipment. Adjacent piping shall be grouped in the same horizontal or vertical plane.
L. All buried bolts, nuts, lugs, rods, brackets, etc., shall be stainless steel. All exposed steel pipe supports and hangers shall be cleaned and painted similar to structural steel items as specified under Section 09900.
M. When a pipe joint is made at the intersection of a pipeline with a pump nozzle, all bolts and nuts shall be installed loose until after the entire pipeline has been installed, aligned and checked.
N. All piping shall be installed in such a manner that it shall be free to expand and contract without injury to itself, structural steel or anchors. On all piping, selfequalizing type expansion joints of an approved make and quality shall be installed in all straight runs of 90 feet or more, unless otherwise shown on the Contract Drawings.
O. When pipe is cut in the field, the cut end shall be tapered back approximately 1/8 inch, at an angle of 30 degrees with the centerline of the pipe, with a coarse file or grinder to remove any rough edges which might injure a gasket, where applicable.
P. Dissimilar metals shall be properly insulated to preclude galvanic corrosion.
3.2 BURIED PIPING INSTALLATION PRACTICES
A. Installation shall be in accordance with AWWA Standard for Installation of Ductile-Iron Water Mains and Their Appurtenances, AWWA C600-93, AWWA C900-89 and WPCF Manual of Practice No. 9, Design and Construction of Sanitary and Storm Sewer, except as otherwise noted in the Specifications.
B. Joining Push-On, Mechanical Joint and Restraint Joint Piping: After placing a length of pipe in the trench, the spigot end shall be centered in the socket and 15060-4
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15060 Piping - Installation.doc the pipe forced "home" and brought to correct line and grade. The pipe shall be secured in place with approved backfill material tamped under and around it.
Wherever it is necessary to deflect pipe from a straight line, either in the vertical or horizontal plane, the amount of deflection allowed shall not exceed that required for making a satisfactory joint and shall be subject to the approval of the City.
C. Where it is necessary to join pipes of different types, the Contractor shall furnish and install the necessary adapter. Adapters shall have ends conforming to specifications for the appropriate type of joint to receive the adjoining pipe.
D. The Contractor shall furnish and install all supports necessary to hold the piping and appurtenances in a firm, substantial manner at the lines and grades indicated on the Drawings or as directed by the City.
E. Underground bends, tees and other pipeline fittings shall be restrained type joints per plans and City approved list of materials, Appendix A.
F. All buried ductile iron pipe shall be polyethylene wrapped in accordance with ANSI/AWWA C105/A21.5.
3.3 PUSH-ON TYPE JOINTS
A. Inspect gasket, socket and spigot for cleanliness. Remove any foreign matter and excessive coating. When cast iron or ductile iron pipe is cut in the field, the cut end can be readily conditioned so that it may be used to make up the joint.
The outside of the cut end should be tapered back approximately 1/4 inch, at an angle of about 30 degrees with the centerline of the pipe, with a coarse file or a portable grinder. All sharp or rough edges which otherwise might injure the gasket shall be removed.
B. Insert the gasket in the socket, bulb end toward the inside. Heel of gasket shall be uniformly seated around the inside of the socket.
C. Lubricate the exposed face of the gasket and the spigot using push-on joint lubricant. Do not use lubricant other than that furnished with pipe and fittings.
D. The fittings and the pipe shall be aligned and the spigot entered into the socket until it just makes contact with the gasket. Joint assembly shall be completed by forcing the spigot of the entering pipe past the gasket (which is thereby compressed) until it makes contact with the bottom of the socket.
E. If assembly is not accomplished with the application of reasonable force by the methods indicated, the spigot end of the pipe shall be removed to check for the proper positioning of the gasket. The joint shall be kept in straight alignment during assembly.
15060-5
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15060 Piping - Installation.doc
3.4 MECHANICAL JOINT PIPING
Spigot ends and bells of pipe and the rubber gaskets shall be washed thoroughly with soapy water to remove all foreign matter which may damage the gaskets. The gaskets shall be either plain rubber, metal tipped, duck tipped, polysulfide rubber tipped, or other special type. The gland shall be placed on the pipe with its raised lip facing the spigot end and at least 3-1/2 inches from that end. The spigot shall be inserted in the socket until it is "home". The gasket shall be pushed into position with the fingers, making sure that it is evenly seated in the socket. Place the gland against the face of the gasket, insert the tee head bolts and tighten the nuts on all bolts by opposite pairs until they are finger-tight. The bolts shall then be tightened in a similar manner until they are snug and bearing evenly against the gland around the circumference of the pipe.
3.5 RESTRAINED JOINT PIPING
Restrained joint piping shall be integrally restrained joint ductile iron pipe of the mechanical joint type with low steel alloy bolting. Installation shall be in accordance with the manufacturer's recommended procedures.
3.6 PVC PIPING
PVC piping shall be installed in accordance with the manufacturer's recommended procedures.
3.7 COPPER PIPING
A. Solder joints for copper tubing shall be prepared by cleaning the ends of the tubing and the inner surfaces of the fittings with steel wool until they are bright.
The cleaned surfaces shall be given a thin coating of approved soldering flux, and the tubing end inserted into the fitting as far as possible. Heating and finishing of the joint shall be done in accordance with the recommendations of the manufacturer of the fittings, using solid string or wire solder. The use of cored solder will not be permitted. All joints shall be allowed to self-cool to prevent chilling of solder.
B. All changes in direction shall be made by using the pipe and fitting unless other means are approved by the City.
3.8 APPURTENANCES
A. The Contractor shall furnish and install all valves and piping not mentioned in the piping classification, but shown on the Drawings.
B. All valves and drains not mentioned in the classification of piping material specifications and furnished under this specification shall be as specified on the Drawings.
C. Flanged joints shall be made up with approved full-face gaskets and 316 SS bolts and nuts and coated with non-oxide type grease, except where otherwise noted in the Specifications.
15060-6
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15060 Piping - Installation.doc D. All joints shall be made drop tight under all pressures up to the specified field test pressure of the line in which installed.
3.9 FIELD TESTING
A. All pressure piping shall be subjected to hydrostatic pressure of 200 psi (or the pump shut-off pressure) but not exceeding the maximum allowable working pressure of the piping. The normal operating pressures shall be defined by the City. No air testing shall be permitted.
B. Pressure mains shall be tested at 200 psi. Gravity lines shall be subjected to hydrostatic pressure 150 percent of the maximum head that can be imposed upon the piping during operation as defined by the City.
C. Test of buried piping shall be made only after completion of partial or complete backfill as specified and not until at least 36 hours after the last joint to be tested has been made, and at least 36 hours after the last concrete thrust or reaction blocking has been cast with high early strength cement, ASTM C150 Type III.
Joints shall be left clear for examination during tests on pressure pipe.
D. Each section of pipeline shall be slowly filled with water and the specified test pressure measured at the point of lowest elevation. Pressure shall be applied by means of a pump connected to the pipe in a manner satisfactory to the City. The pump, pipe connection, gauges, pipe taps and all necessary apparatus, shall be furnished by the Contractor. The Contractor shall provide all necessary assistance for conducting the test. The duration of the test shall be 2 hours, unless otherwise directed by the City. All air must be expelled from the pipeline prior to the test period.
E. During the test, all pipes, fittings, valves, hydrants and joints shall be carefully examined. If found to be cracked or defective, they shall be removed and replaced by the Contractor with sound material in the manner prescribed. The test shall then be repeated until satisfactory to the City.
F. After the pressure test, the pipe shall be tested for leakage. The pressure during the leakage test shall be at the normal operating pressure. The duration of the leakage test shall be 2 hours unless otherwise directed by the City. The test shall be conducted in the same manner as the pressure test except that the Contractor shall provide suitable equipment for measuring the amount of leakage.
G. No pipe installation will be accepted until or unless the leakage for the section of line tested is less than the rate of leakage specified below:
Flanges, welded or screwed piping – No measurable leakage Push-on, mechanical joints or caulked – In accordance with AWWA Standard for Installation of Cast-Iron Water Mains, AWWA C600, Sect. 13.7 15060-7
R:\SPECS\Signal Hill\Waterline and Valve Replacement\02 Tech Specs\Sect 15060 Piping - Installation.doc H. Should any test of a section of pipeline disclose leakage greater than that permitted, the Contractor shall, at his own expense, locate and repair the defective joints and/or pipe until the leakage is within the permitted allowances.
3.10 PIPE SUPPORT DETAILS
Pipe support shall be selected and furnished as required for proper installation and in accordance with the Drawings.
END OF SECTION