CITY OF SIGNAL HILL

STAFF REPORT
2175 Cherry Avenue • Signal
Hill, California 90755-3799
7/26/2022

AGENDA ITEM
TO:

HONORABLE MAYOR

AND MEMBERS OF THE CITY COUNCIL
FROM:

THOMAS BEKELE

PUBLIC WORKS DIRECTOR

PATRICK KELLEY

PUBLIC WORKS CONTRACTS MANAGER
SUBJECT:

RESOLUTION DECLARING FINAL ACCEPTANCE OF THE 1905/1907 21ST STREET AND RESTROOM REMOVAL IMPROVEMENT (PROJECT NO. 90.21008)

PURSUANT TO THE PUBLIC WORKS AGREEMENT WITH GREEN GIANT LANDSCAPE, INC.

Summary:

Green Giant Landscape, Inc. (Green Giant) has completed work for the 1905/1907 21st Street and Restroom Removal Improvement Project No. 90.21008 to the satisfaction of the Public Works Department and in accordance with the project plans and specifications. Staff is recommending final acceptance of the work performed by Green Giant and issuance of final payment.

Recommendation:

Adopt a resolution, entitled:

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SIGNAL HILL, CALIFORNIA,

DECLARING WORK TO BE COMPLETED IN CONFORMANCE WITH THE RECORD DRAWINGS

AND STANDARD SPECIFICATIONS FOR PUBLIC WORKS DEMOLITION AND IMPROVEMENT FOR THE 1905/1907 21ST STREET AND RESTROOM REMOVAL IMPROVEMENT (PROJECT NO.

90.21008) IN THE CITY OF SIGNAL HILL, IN ACCORDANCE WITH THE CONTRACT ENTERED INTO BETWEEN GREEN GIANT LANDSCAPE, INC. AND THE CITY OF SIGNAL HILL Fiscal Impact:

The Capital Improvement Program budget for the project was $410,000, with actual costs coming in at $375,506.69, resulting in project savings of $34,496.31 (see Table 1). The project budget is divided CITY OF SIGNAL HILL Page 1 of 3 Printed on 7/21/2022
powered by Legistar™
7/26/2022
between construction costs and other project-related costs.

The project utilized Community Development Block Grant (CDBG) and Park Development funds as designated in the Fiscal Year (FY) 2021-22 Capital Improvement Program Budget. The construction contract with Green Giant was $340,922 with a $34,092 contingency. The total construction contract cost came in at $349,151, which is $8,229.00 over the initial contract cost. A change order to utilize the contract contingency has been included on the Contract Amendment Register (Agenda Item 13e) to cover these additional costs. The actual costs shown in Table 1 below also include material testing and land surveying services provided by the City’s on-call professional consultants Ninyo & Moore and KDM Meridian.

Table 1: 1905/1907 21st Steet Demolition and Restroom Improvement Project Costs Project Funding Budget Actuals Difference (underbudget) Park Development Fund $322,540.00 $288,043.69 $34,496.31 CDBG $87,460.00 $87,460.00 $0
Total $410,000.00 $375,503.69 $34,496.31
Strategic Plan Objective:

Goal No. 4: Maintain and improve the public infrastructure.

Background and Analysis:

On January 8, 2019, the City Council approved an agreement to purchase real property at 1905/1907 21st Street, located along the southern border of Signal Hill Park. The purchase was completed to advance the goals of the Parks and Recreation Master Plan which identified the need to further upgrade and enlarge Signal Hill Park to provide additional recreational open space and meet its important role as a community park. Following the approval of the purchase, staff was instructed to develop a budget for the demolition of the existing structures on the property.

On April 17, 2019, the Parks and Recreation Commission recommended the demolition of the nearby non-operational Spud Field restroom facility due to long-standing nuisance issues with litter accumulation, vandalism, and general disrepair. Due to its proximity to the 1905/1907 21st Street site and the similar nature of work required, the restroom demolition was included in the scope of the twohome demolition project.

On October 12, 2021, Council authorized the execution of a Public Works Agreement with the lowest qualified bidder, Green Giant, to complete demolition of the project.

On November 9, 2021, staff issued a Notice to proceed (NTP) instructing Green Giant to commence work. Green Giant has completed the work in conformance with the plans and specifications, detailed in the contract. The work was substantially completed on June 13, 2022 upon completion of punch list items, landscaping establishment, labor compliance requirements, and administrative closeout items. A non-compensable time extension was applied to the contract duration to allow for these items, as reflected on the CAR. Staff recommends issuance of final payment to Green Giant and adoption of the resolution declaring the acceptance by the City of the work performed by Green CITY OF SIGNAL HILL Page 2 of 3 Printed on 7/21/2022
powered by Legistar™
7/26/2022
adoption of the resolution declaring the acceptance by the City of the work performed by Green Giant.

Reviewed:
_________________________
Sharon del Rosario
Approved:
_________________________
Scott Charney
Attachment
CITY OF SIGNAL HILL Page 3 of 3 Printed on 7/21/2022
powered by Legistar™