Cities Index.
Att A - Final PMP

Signal Hill City Council
August 23, 2022

Document
Att A - Final PMP
Meeting
August 23, 2022
Body
Signal Hill City Council
Pages
31
Original file
1.2 MB
Text extracted from the city's file for reading and search. Open the original on cityofsignalhill.legistar1.com. That file is the official record.

FINAL REPORT

UPDATE OF

PAVEMENT MANAGEMENT PROGRAM
(Citywide)
2022-2027
Submitted to:

City of Signal Hill, CA
February 18, 2022
Attachment A
February 18, 2022
Mr. Steve Badum
Contract City Engineering Services
City of Signal Hill
2175 Cherry Avenue
Signal Hill, CA 90755
Subject: Final Report - Update of the Pavement Management Program Dear Steve:

As part of the 2022 Update of the Pavement Management System for the City of Signal Hill, Bucknam Infrastructure Group, Inc. is pleased to submit the Final Report for the City’s pavement network.

The information contained in this report was used to develop the recommended improvement program for the pavement network. The report covers the following categories:
• Executive Summary (Section I)
• Pavement Management Program Development and Reporting (Section II) • Pavement Conditions For Each Segment in the Network (PCI Report – Section III) The Pavement Condition Index report shows the present condition of each street in the pavement network. In addition, the report shows the basic geometry of each street segment. • Forecast Maintenance Reports (Section IV)
• Recommended Maintenance and Repair Strategies
The recommended maintenance and repair strategies were used to generate the Forecasted Maintenance Report and were based on our 2018 inspections.

Additionally, we have assessed and incorporated unit cost and maintenance application practices/types with our strategies.
• Projected Projects based on M&R Strategies
The Forecasted Maintenance Report projects the street maintenance activities required for the next five years, broken down to show maintenance levels for Arterials, Collectors and Local streets. The report included in this section is broken down by fiscal year.

Our thorough analysis of previous and current Signal Hill PMP strategies enabled our staff to make proactive recommendations to the City’s pavement CIP. All comments received from the City have been incorporated in the reports that follow. All of the City’s issues and needs that were brought to our attention are included in the report. It has been a pleasure working with you and the City on updating your Pavement Management Program. We look forward to the continued success of this project and future teamwork with City staff.

Sincerely,
Bucknam Infrastructure Group, Inc.

Peter J. Bucknam
Project Manager
Infrastructure Management – GIS Services
City of Signal Hill, CA Page i
2022 Pavement Management Program
Final Report – February 18, 2022

TABLE OF CONTENTS
I. Executive Summary
A. City’s Pavement Network
B. Current Citywide Conditions
C. Maintenance Strategy Development
D. Annual Budget Projections
E. Quality Control Efforts
F. Findings and Recommendations
III. Pavement Management Program-Capital Improvement Program A. PMP Scope of Work
B. Maintenance Strategy Assignments
C. Multi-Year Annual Work Program Projects
i. Maintain PCI Budget Scenario
ii. Increase PCI to 80 Budget Scenario
III. Pavement Condition Index (PCI) Reports
A. PCI Report Definitions
B. Signal Hill 2022 PCI Map
C. A to Z Order
D. PCI Order
IV. Forecast Maintenance Report
A. Increase PCI Budget, Five Year Plan (2022-2027)
City of Signal Hill, CA Page ii
2022 Pavement Management Program
Final Report – February 18, 2022
Table and Figure Reference Page #
Figure 1 – Pavement Area (SF) by Street Classification Sec 1-2 Figure 2 – PCI Distribution by Section Mileage for All Streets Sec 1-5 Figure 3 – Sample Pavement Life Cycle / Deterioration Rate Sec 2-16 Figure 4 – Resulting Network PCI (Maintain PCI Budget) Sec 2-20 Figure 5 – Resulting Network PCI (Increase PCI to 80 Budget) Sec 2-22 Figure 6 – PCI Calculation Worksheet Sec 2-25
Figure 7 – Arterial Condition Distribution Sec 2-26
Figure 8 – Local Condition Distribution Sec 2-26
Figure 9 – Signal Hill 2022 PCI Map Sec 3-30
Table 1 – Past and Present PCI Results and Comparisons Sec 1-3 Table 2 – Condition Distribution by Mileage for All Streets Sec 1-3 Table 3 – Necessary Funding to Maintain Citywide PCI of 73.7 Sec 1-9 Table 4 – Necessary Funding to Increase Citywide PCI to 80 Sec 1-9 Table 5 – PCI Range Sec 2-14
Table 6 – Strategy Assignments Table Sec 2-15
Table 7 – Necessary Funding to Maintain Citywide PCI of 73.7 Sec 2-19 Table 8 – Necessary Funding to Increase PCI to 80 Sec 2-21 Acronym Listing
Asphalt Concrete (AC)
Army Corps of Engineers (ACOE)
Capital Improvement Program (CIP)
Geographic Information System (GIS)
Government Accounting Standards Board Statement 34 (GASB 34) Los Angeles County MTA (METRO)
Maintenance and Repair (M&R)
Pavement Condition Index (PCI)
Pavement Management Program (PMP)
Portland Cement Concrete (PCC)
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 1 ends

Section I

SECTION I

EXECUTIVE SUMMARY
2022 PAVEMENT MANAGEMENT PROGRAM
This report reflects the continued dedication and proactive management of the City’s Pavement Management Program (PMP); the last major update to the City’s PMP was performed over ten (10) years ago. As the City of Signal Hill continues to show limited growth with its population, demographics, infrastructure and maintenance needs, the street network has been running parallel as the system matures and capital street projects widen streets. Through this project, the City of Signal Hill developed its PMP with the use of an automated online PMP program (MicroPAVER). This system is essential to the City in that it assists Public Works staff in capturing funding for its arterial street system as well as costeffectively manages the local network through proactive maintenance and scheduling. Under this project, the City has incorporated the development of a unique Pavement Management – GIS layer that will assist the City in spatially analyzing pavement conditions and other attribute information that resides in the MicroPAVER database.

The Signal Hill PMP has been developed to assist City personnel by providing current data on the City’s street network and to develop cost-effective maintenance strategies to maintain a desirable level of pavement performance on a network scale, while optimizing the expenditure of limited fiscal resources.

The PMP efforts in 2022 consisted of analyzing the City’s previous PMP dataset/maps for quality and usability. City staff also provided key information pertaining to the ongoing maintenance that has occurred throughout the City since 2019. In doing this, we were tasked to generate an updated Capital Improvement Program report that identified recommendations and deficiencies in the current operating and maintenance efforts put forth by the City.

For the 2022 project, our staff surveyed all arterial and collector routes to assist the City in complying with Los Angeles County MTA (METRO) PMP requirements as well as surveyed all local streets and analyzed historical maintenance operations.

Specifically, the program provides administrators and maintenance personnel with:
• The present condition status of the pavement network (arterial, collector, and local streets), as a whole and of any grouping or individual component within the City; • A ranked list of all streets, or segments of streets, by condition within the network; • Rehabilitation/maintenance needs of each street segment by year; • An optimized priority maintenance and rehabilitation program based on cost/benefit analysis and various levels of funding;
• Optimum annual budget levels for pavement maintenance for the current and the following five (5) years;
• Prediction of the future performance ofthe City’s pavement network and each individualstreet section;
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 2 ends

Section I
• Updated PMP data to assist the City with GASB 34 compliance; and • Pavement condition data and analysis presented in ArcGIS that is compatible with City’s existing GIS (GIS map provided within Section III and shapefiles delivered to the City) Pavement is a dynamic structure where deterioration is constantly occurring; thus the pavement management system needs to be updated on a regular basis to reflect these changes in pavement conditions, pavement maintenance histories, and maintenance strategies based upon budgetary constraints. In our approach to develop the City’s forecasted maintenance recommendations we worked with Signal Hill staff in identifying unit costs for all maintenance practices used on an annual basis.

Currently, based upon the City’s maintenance practices and their associated unit costs, the total replacement value of the Signal Hill pavement network is $76,195,100. This value clearly indicates that the City’s pavement network is the most valuable and essential asset to Signal Hill. The City’s use of slurry seal, ARHM Overlay and R&R practices are typically applied at a five year, ten year and 25 year frequency respectively. These frequencies are typical but the City may see increases in deterioration rates due to environmental, load and high average daily traffic (ADT) volumes. For example, high ADT volumes along one of Signal Hill’s arterial streets will increase deterioration rates for a previously applied AC Overlay compared to a small local street. These deterioration rates are monitored through frequent inspections and functional class deterioration analysis within the City’s PMP database.

This report reflects our findings and recommendations for the PMP and the current state of the City’s pavement network. Furthermore, we have recommended detailed funding and maintenance strategies for the arterial/collector and residential networks for next five (5) years.

CITY’S PAVEMENT NETWORK
Within the Signal Hill Arterial/Collector pavement
management network consist of approximately 18.9
section miles of streets, 3,954,801 SF of pavement that is made up of 101 pavement sections. The Local
network consists of approx. 17.4 section miles ofstreets, 3,302,163 SF of pavement which consists of 160
pavement sections. Combined, the entire network
consists of 36.3 section miles of streets, 7,256,964 SF and 261 total pavement sections.

The City’s pavement network is broken down into manageable groups that have similar characteristics, such as pavement street classification, surface type and logical segmentation. Pavement segments are identified by their branch and section numbers. Pavement “branches” that have a common usage, such as Cherry Ave, defines a “branch” within MicroPAVER. Pavement “sections” are pavement segments within the defined branch that have consistent pavement street classifications, construction/maintenance histories and use. Representative inspection samples are then selected and visually surveyed to locate distress data. This data is used to calculate the pavement sections Pavement Condition Index (PCI) which includes distress type, extent of the distress and its severity.

Figure 1
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 3 ends

Section I
The PCI is a condition rating that ranges from 100 (a new pavement section or recently overlaid or reconstructed) to 0 for a section that has structurally failed and deteriorated dramatically. Weighted average PCI of a given area/zone = pavement section PCI * its own area divided by the totalsquare footage of the given area/zone. Table 2 summarizes the section conditions found within the City of Signal Hill pavement network by street classification.
• The weighted average PCI for the City of Signal Hill Arterial / Collector network is 77.7 • The weighted average PCI for the City of Signal Hill Local network is 68.8 The weighted PCI value associated with the Arterial and Local routes shown through our survey analysis is timely in that it is showing that a large amount of preventive, slurry seal, and overlay work will continue to be needed over the next several years to proactively increase the PCI level to ultimately achieve a “preventive maintenance” state (typically a weighted PCI of 65 or higher).

Table 1 –Past and Present PCI Results and Comparisons

CURRENT CITYWIDE CONDITIONS (ARTERIALS AND LOCALS)
The overall condition of the City’s pavement network is “Very Good” with a weighted average PCI of

73.7 based on the surface area of each segment. The distribution of the City’s overall pavement network is shown in Section III of this report (Condition Distribution).

For comparison, Bucknam performed pavement management studies for several other Los Angeles County agencies and have included their weighted PCI values; El Segundo (64.5), Culver City (64.5), and Compton (58.1).

Table 2 – Condition Distribution by Mileage for All Streets As shown above, a large majority of segments are evenly distributed through Excellent to Good condition categories (81%). For a network in “preventive” condition status you would typically see Excellent and Good section percentage totals at the 60 to 70% range.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 4 ends

Section I
These findings indicate that the proper rehabilitation maintenance needs have been well managed over the past 8+ years, however, with a current preventative status proper pavement maintenance/rehabilitation needs to be applied network in the near/immediate future. The condition ranges shown above are defined by the Army Corps of Engineers.

Citywide, approximately 19% of the City’s pavement sections within a condition level of “Fair to Failed” (approximately 7.0 section miles), a proactive overlay rehabilitation program needs to be implemented and funded; this will improve the citywide weighted PCI to a higher network condition level while reducing deferred maintenance costs in fiscal years 2022 and beyond.

Local conditions show that 44% of its network requires slurry seal maintenance while 35% qualifies for overlay/reconstruction; in total, this accounts for approximately 12.9 section miles of streets. With the high amount of local sections needing maintenance the City should proactively appropriate more funding to the Local street network in order to increase the overall condition. The Local network will remain at low condition levels (PCI 60-69) over the next several years and will continue to contribute to the high amount of deferred overlay maintenance unless additional pavement funding is appropriated.

The Arterial network is showing higher condition levels compared to the Local network. This is clear by looking at the number of arterial sections that fall within the Excellent to Very Good condition categories (approximately 12.2 miles of the 19.0 mi., which accounts for approx. 64% of the arterial network compared to 53% of the local network.

Through our assessment of the City’s annual pavement maintenance budget allocation lacks the necessary CIP funds will allow the City’s current citywide weighted PCI will decrease over the next five years if additional funding is not appropriated.

Furthermore, as large overlay and rehabilitation projects are considered for funding, the City should also consider using sub-grade R - Values, structural design, distress severities and extents as parameters for determining whether a pavement section that lies within the Fair to Very Poor condition range should be overlaid or reconstructed. PCI conditions reflect “surface” conditions; additional sub-surface data such as coring data, R-Values and asphalt depths will provide City to with a better approach to the maintenance that should be applied.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 5 ends

Section I
Figure 2 – PCI Distribution by Section Mileage for All Streets

MAINTENANCE STRATEGY DEVELOPMENT
Based on the results of the condition survey and input from the City, pavement maintenance/rehabilitation strategies were developed. From the onset, the City and Bucknam staff identified a distribution of City maintenance funds that would be applied to the network over the next five years. This was based upon the desire to prevent the decrease in street conditions and not allow an increase in the maintenance backlog funds over the five-year program.

Through our assessment and discussions with the City we were requested to identify what level of funding would be required to maintain the current PCI as well as identify the level of funding needed to increase the PCI to 75. With this approach, Bucknam has recommended a “minimal level of service” which creates a major dividing line in determining between preventive maintenance and major pavement rehabilitation.

Generally, within pavement management programs, a PCI range between 55 to 70 determines the threshold of when preventive or major overlay rehabilitation is activated. Based on the City’s weighted average PCI, condition distribution, maintenance practices, our team has identified a PCI of “65” as the minimum level of service. This means, in most cases, that any pavement section with a PCI greater than 65 will be recommended for preventive maintenance (i.e. slurry seal). This recommendation is indicated in Table 6, Section II.

Bucknam developed two multi-year Capital Improvement Programs for the City based on the pavement records, yearly capital expenditures, available funding and the most recent 2022 inspections. These recommendations and results are shown in Section II of this report where, for example, we have demonstrated what level of funding is necessary to improve the current weighted City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 6 ends

Section I
condition level of 73.7 to a level of 80 by FY 2027.

As shown above in Figure 2, 61% of the City’s streets are in Excellent to Very Good condition. These sections will be targeted for “preventive” maintenance within our Capital Improvement Program (CIP) recommendations. The reasoning in doing this is to extend the life cycles of those “good” pavement sections which accrues capital saving to aggressively rehabilitate those pavement sections that are below the “minimal level of service”.

In order to achieve the most effective and optimum program for the City, certain strategies have been selected and/or analyzed. Below is a listing of the maintenance activities utilized in strategy development.

Each activity is representative of the types of work that have been programmed as part of the long-term maintenance requirements of the City’s street network.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 7 ends

Section I
General Repairs-Stop Gap (Localized Maintenance*)
For this maintenance type,small localized surface treatments are utilized as “holding action” solutions (stop gaps) to delay the need for pavement structural strengthening. They typically include activities such as crack sealing, AC deep patching, AC skin patching, PCC slab replacement, grinding and leveling.

The City of Signal Hill may consider an Asphalt Zipper to apply proactive localized surface patch repairs. In doing this, they prevent portions of pavement sections (high severity distress locations) from deteriorating at a continuously fast rate.

High Density Mineral Bond (HDMB) - (Global Maintenance*); PCI range – 75 to 95 This alternative application should be applied to Local pavement sections that are within a PCI range of 75 to 95; the benefit of applying HDMB is the extension of life it provides prior to having a slurry seal applied. HDMB is comprised of a mixture of fine aggregates and UV-blocking polymers suspended in a non-ionic asphalt emulsion. HDMB application life-cycles are averaging 7 to 8 years without surface oxidation and are preventing 400% less cracking within a section during that timeframe.

HDMB can be applied on conventional and/or rubber asphalts, retains its aesthetics longer than Type 1 / Type 2 slurry and does not require the sweeping or removal of loose aggregate. It is applied through specialized equipment that can uniformly disperse a thixotropic material along a retractable spray bar; applications are guaranteed for five (5) years.

Slurry Seals (Global Maintenance*); PCI range – 60 to 85 Surface treatments applied to pavements with minimal surface distress to provide new wearing surfaces and extend pavement life. Generally consists of a mixture of conventional or latex-modified emulsified asphalt, well-graded fine aggregate, mineral filler and water placed over an existing AC surface; Slurry seal application life-cycles are averaging 4 to 5 years. Type II Slurry is recommended for Local streets.

Cape Seals (Global Maintenance*); PCI range – 40 to 60
This is an application of a single layer of asphalt binder to a road surface immediately followed by a single layer of cover aggregate (chips). The single layer chip seal is then followed with a slurry seal application; Conventional cape seal application life-cycles are averaging 6 to 7 years. For sections that have lower PCI’s in this range, leveling courses should be considered.

Overlays (Major Maintenance*); PCI range – 20 to 60
AC Overlay – Placement of a layer of hot-mixed asphalt concrete over the existing pavement surface (may include pavement fabric). Grinding (milling) is performed prior to the overlay to reduce the total height of asphalt and assure alignment with existing gutter lines. This also includes “dig-outs” and crack sealing prior to the application of an overlay. This treatment provides a new wearing surface and increases structural strength to the pavement section. A conventional overlay should be designed for a ten-year life.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 8 ends

Section I
Asphalt Rubber Hot-Mix Overlay - The ASTM definition is: Asphalt-Rubber is a blend of asphalt cement, reclaimed tire rubber and certain additives in which the rubber component is at least 15% by weight of the total blend and hasreacted in the hot asphalt cementsufficiently to cause swelling of the rubber particles. Specifically, using crumb rubber modified binders in pavement application benefit local agencies in that cities find:
• Pavement resists cracking by being more flexible;
• Cost savings come from a longer life cycle (from Bucknam’s experience typically 20% longer), decreased maintenance and the use of less material
• Improvement in skid resistance;
• Decreased noise; and
• It provides long-lasting color contrast for marking and striping • Life cycles are averaging 8 to 12 years
Reconstruction (Major Maintenance*); PCI range – 0 to 20 Removal of the existing pavement section to a prescribed depth followed by the placement of a conventional flexible pavement section using a structural AC Hot Mix or AR Hot Mix or a full depth asphalt. Each classification of road has a typical design cross-section upon anticipation traffic loading.

By performing a reconstruction the sections PCI resets at 100 and restarts the life-cycle deterioration of the section.
*Localized, Global and Major maintenance activities are default terms used within the MicroPAVER pavement software. Specific pavement repair applications are placed within each maintenance activity in order to develop multi-year maintenance forecast recommendations.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 9 ends

Section I

ANNUAL BUDGET PROJECTIONS
The budgeting process was approached with the following in mind; generate two unique work programs for the next five (5) years based upon actual road pavement conditions in order to:

1. Demonstrate whatlevel of annual funding is needed to maintain the current 73.7 PCI until FY 2027

2. A “Increase PCI to 80” budget was generated for the City to demonstrate what level of annual Public Works maintenance and rehabilitation CIP funding is necessary to increase the citywide weighted PCI to 80 by FY 2027.

3. Identify current and future deferred preventative and rehabilitation levels based on both funding models
Based on current and future pavement maintenance needs, three annual work programs have been prepared and summarized below. Table 3 demonstrates the annual funding needed to maintain today’s current conditions until FY 2027. Table 4 demonstrates a $1.7 million/yr that is necessary to increase the City’s PCI to 80 by FY 2027. The revenues shown below account for the cost of pavement preventive maintenance and rehabilitation, a 35% contingency applied to unit costs and 3% annual inflation.

Table 3 – Necessary Funding to Maintain Citywide PCI of 73.7 Table 4 – Necessary Funding to Increase Citywide PCI to 80 Additional detail and breakdown of budget projections are demonstrated in Section IV of this report.

All work program budgets generated are presented in terms of current 2022 dollars. All repair activities were based on distresses observed at the time of the field survey. These are recommendations and are to be used as “the best-case scenario” for improving the City of Signal Hill street network.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 10 ends

Section I

QUALITY CONTROL EFFORTS
As indicated in our scope of work, Bucknam performed numerous quality control checks in the field during survey efforts as well as specific site investigations requested by the City. Field check efforts were performed at the end of each week of survey. The City did not have a previous electronic copy of the previous PMP database; Bucknam developed the new MicroPAVER database through the use of the City’s previous MS Excel spreadsheet database, available city maps and hardcopy reports. During in-house and field operations, we came across a minor number of issues with the previous pavement segmentation and hard copy reports. These included public v. private streets designations, missing streets, incorrect pavement section widths, lengths, and true areas; these were corrected through our field inspections.

Utilizing the City’s centerline GIS data provided solutions to segment length issues and total section area measurements.

Through our internal quality control efforts, we believe we have found all the necessary publicly owned streets that needed to be reported on under this project.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 11 ends

Section I

FINDINGS AND RECOMMENDATIONS
Arterials
The actual workload requirements identified indicate that the Arterial street network is currently in “Very Good” condition. To maintain this condition, it is critical that preventive maintenance and overlay activities are funded at the levels identified in Table 3 to maintain a Very Good network weighted average PCI value.

Our arterial/collector findings for conditional data and recommendations for revenue expenditures are shown below:
• The Arterial/Collector network has a weighted PCI of 77.7; • Currently, 25% of the arterial network (approx. 4.8 miles) qualify for overlay/reconstruction maintenance; 34% (approx. 6.5 miles) qualify for slurry seal preventive maintenance; • Develop a proactive fiscal and planned approach to identify future arterial overlay projects based on the deterioration modeling within MicroPAVER;
• Appropriate the necessary arterial CIP revenues at the levels shown within the Section IV Forecasted Maintenance Report for a minimum of five years to generate the results identified within this report.
• Reassess/re-evaluate the arterial rehabilitation budget program every two years to improve on CIP forecasts for 2022-23 and beyond to ensure the results shown in Table 3; • Perform pavement inspections on the arterial network every two years in order to proactively track pavement deterioration rates and to improve upon the planning modes shown within this report.
• Demonstrated budget shown in Table 4 is ample improve upon the Arterial weighted PCI of 77.7 after five years, additionally, the citywide deferred backlog decreases from a level of $11.6 million to $6.9 million after five years;
o This is an indication that additional arterial overlay/rehabilitation funding is necessary to reduce the amount of deferred CIP projects on the network; • Bucknam recommends that the City proactively budget pavement maintenance at the levels shown in Table 4 in order to improve upon the conditions found today; o This includes Arterial projects such as Spring St, and 33rd St City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 12 ends

Section I
Locals
The actual workload requirements identified indicate that the Local street network is currently in “Good” condition. To proactively increase this condition, it is critical that preventive maintenance and overlay activities are funded at the levels identified in Table 4 to obtain a Very Good network weighted average PCI value.

Our Local findings for conditional data and recommendationsfor revenue expenditures are shown below:
• The Local network has a weighted PCI of 68.8;
• Currently, 64% of the local network (approx. 11.2 miles) qualify for overlay/reconstruction maintenance; 15% (approx. 2.7 miles) qualify for slurry seal preventive maintenance; • Follow the proactive Local preventive/overlay fiscal plan approach shown in the Section IV reporting;
• Reassess/re-evaluate the Local rehabilitation budget program every two years to improve on budget forecasts for 2022-23 and beyond to ensure the results shown in Table 4; • Perform pavement inspections on the Local network every three years to build a solid planning model within MicroPAVER to track PCI deterioration (1/3 of the City each year); • Demonstrated budget shown in Table 4 is ample to improve upon the Local weighted PCI; additionally, the citywide deferred backlog decreases from a level of $11.6 million to $6.9 million after five years;
o This is an indication that additional local overlay/rehabilitation funding is necessary to reduce the amount of deferred CIP projects on the network; • Additional overlay/rehabilitation funding should focus on pavement sections within the PCI range of Good to Poor (PCI 11 to 65).

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 13 ends

Section II

SECTION II
PAVEMENT MANAGEMENT PROGRAM – CAPITAL IMPROVEMENT PROGRAM Bucknam performed the following services in accordance with the scope of services that was contracted with the City of Signal Hill. As a quick overview, the following tasks were performed to complete the work over the past several months:
2022 Pavement Management Work Efforts:

Task 1: Project Kickoff-Data Management
Task 2: Update of Maintenance Activities
Task 3: Pavement Condition Survey (approx. 36.3 miles)
Task 4: Budgetary Analysis and Capital Improvement Reports Task 5: Executive Summary and Final CIP Reports
Task 6: Mapping of the Pavement Network
Pavement Management Update 2022
As a part of the 2022 update of the pavement management program, a major element of work was to complete a comprehensive assessment of the existing street network and PMP data within the City. This included assessing the City’s existing MS Excel spreadsheets, GIS centerline, street naming conventions and work history information. From there, Bucknam worked with the City to confirm public and private street listings which set the foundation for accurate CIP reporting. All data was then updated into the City’s current MicroPAVER database.

Work history information was provided by the City in the form of institutional knowledge, maps and Excel documents. This information was entered into the proper pavement segments that match the limits of those projects. From there, CIP pavement recommendations were performed (discussed and demonstrated below) where the pavement maintenance information the City provided (PMP material practices, unit costs, and capital budgets) were used to generate recommendations through the MicroPAVER system.

Table 5 demonstrates PCI ranges identified within MicroPAVER. Once a pavement inspection is complete, a PCI is calculated for each pavement section. Each PCI calculated falls within a defined PCI range category (Very Good, Poor, etc.). Furthermore, a weighted PCI was calculated for the each functional class within the network (arterials, locals, alleys).

The PCI is a condition rating that ranges from 100 (a new pavement section or recently overlaid or reconstructed) to 0 for a section that has structurally failed and deteriorated dramatically. Weighted average PCI of a given area/zone = pavement section PCI multiplied by its own area divided by the total square footage of the given area/zone. This information can also be represented through MicroPAVER to show how much square footage or percentage of area falls within a PCI range category.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 14 ends

Section II

PCI RANGE CONDITION
86-100 Excellent
71-85 Very Good (Signal Hill Network 2022 = 73.7)
56-70 Good
41-55 Fair
26-40 Poor
11-25 Very Poor
0-10 Failed
Table 5 - PCI Range
(Additionally, see page 24 for detailed description of PCI ranges) These condition ranges are defined by the Army Corps of Engineers and defaulted within the MicroPAVER software. The summary of all roads condition data and their representative PCI's can been seen in the Pavement Condition Report in Section III.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 15 ends

Section II

STRATEGY ASSIGNMENT TABLE
Once the appropriate activities from the above listings were selected by the City, a Maintenance Strategy Table was defined within the system that allocated the appropriate actions to the specific repair needs of the street. In defining the maintenance strategy list, emphasis was placed on defining pavement condition thresholds and using the PCI for the specific maintenance activities within these categories.

Strategy Assignment Table
Table 6 - Strategy Assignment Table
The Strategy Assignments List, shown in Table 6 was developed to identify the most critical segments in each of the work programs (Arterial, Collector and Local). Segment priorities were established by determining the range of PCI's requiring first attention based on the relative value of each segment’s PCI, thus maximizing the annual maintenance budget. Also, distress quantity, area extent, type (load / climate) and distress severity levels were critical elements in the decision process for recommending maintenance.

The assignment table is used as a guide within MicroPAVER to recommend maintenance, however, further assessment by City staff and/or outside parties can override maintenance recommendations. This can be done by reviewing and assessing distress extents and their weighted percentages.

Once the strategy assignments were set within the system, budgets and work assignments were generated for each work program on an annual basis. Using pavement deterioration curves for each type of pavement surface and class of road, both current year and future years work requirements for each pavement segment within the City were determined. In forecasting the maintenance requirements in future years, the current PCI value is reduced annually for each pavement segment based on the MicroPAVER deterioration curves within the City’s database.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 16 ends

Section II
Likewise, maintenance activities performed in a given year increase the PCI value as they are applied to the segment. The overall program is dynamic in that each strategy consists of a cyclic series of actions that simulates the pavement anticipated life cycle.

Figure 3 – Sample Pavement Life Cycle / Deterioration Rate City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 17 ends

Section II

MULTI-YEAR ANNUAL WORK PROGRAM PROJECTIONS
The goal of these projections is to assist City policy makers in utilizing the recommendations of the MicroPAVER system. By using the City of Signal Hill’s current budgets and maintenance practices the system will develop “section unique” improvements and strategies. Each segment will be tied to a specific fiscal year. As shown in the following pages, we have assessed the budgets that have been projected to meet the maintenance and rehabilitations needed to maximize the City’s return on investment. The budget forecasting goal for the City network focused on:
❖ Establishing a proactive multi-year Maintenance & Rehabilitation Program; ❖ Developing a preventive maintenance program; and
❖ Selecting the most cost-effective repairs based on City strategies MAINTAIN PCI BUDGET – This budget was generated for the City to demonstrate what level of annual funding is necessary to “maintain” today’s current PCI of 73.7.

The City’s annual potential/planned budget is funded through the following sources:
• Gas Tax
• SB1
• Measure R
• Measure M (Potential reimbursement revenue to payback Street Bonds) • General Fund
• Proposition C
INCREASE PCI TO 80 BUDGET – A “Increase PCI to 80” budget was generated for the City to demonstrate what level of annual Public Works maintenance and rehabilitation CIP funding is necessary to increase the citywide weighted PCI to 80 by FY 2027.
*All multi-year budget projections include a 3% inflation rate for the term of the budget forecast.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 18 ends

Section II

ARTERIAL-COLLECTOR / LOCAL

BUDGET PROJECTIONS
The annual projected revenues shown below only account for the cost of pavement maintenance and rehabilitation activities. A 35% contingency was applied to the pavement costs. Additional soft costs not included within the cost of pavement maintenance include:
• Right-of-way;
• Utility improvements;
• Design, construction management, inspection, testing; • Tree removals;
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 19 ends

Section II

MAINTAIN PCI PROGRAM (FIVE YEAR MODEL)
With the City striving to show proactive maintenance across all City pavements, a budget program was generated to show the greatest return on investment through the application of slurry seal, mill & cap, and alternative overlay maintenance. Our goal under this model is to maintain the current 2022 weighted PCI of 73.7 through a five-year program. This model will demonstrate the necessary funding to achieve this goal.

The Maintain Program incorporates pavement sections that have a functional class of Arterial (A), Collector (B, C) and Local (E).

Table 7 – Necessary Funding to Maintain Citywide PCI of 73.7 By modeling the existing pavement conditions against an annual average funding of $681,200/yr, we have found that one positive and one negative result occurs over the five year CIP. (See Figure 5 below). First, the weighted PCI for the entire network sustains at a level of 73.7 over the five year CIP.

Secondly, the resulting deferred maintenance backlog increases from $12.7 million to $13.6 million after the five years program which indicates that an annual $681,200 pavement budget is not ample enough to decrease the high amount of deferred rehabilitation maintenance on the pavement network.

Limited funding equals deferred projects which does not allow necessary overlay projects to be completed on the arterial, collector, and local networks; if the City continues to fund rehabilitation maintenance at these levels, high deferred maintenance costs will create a stagnation in the network PCI where it will remain at a level within the low-70’s for numerous years.

DEFERRED MAINTENANCE
Delaying repairs on streets where pavement condition indicates a need creates deferred maintenance. Deferred maintenance includes pavement maintenance / rehabilitation that is needed across the entire network but cannot be performed due to the lack of available funding and is pushed to the next budget cycle. The actual repairs that are being deferred are often referred to as a “backlog”.

As maintenance is deferred, the opportunity to apply life extending preventive pavement applications is lost and the ultimate cost of rehabilitation multiples.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 20 ends

Section II
Currently, within the calculated citywide deferred maintenance, 9% of the costs are for slurry, cape and stop gap maintenance and 91% for grind/overlay and reconstruction.

As shown, this projection model does increase PCI but does not meet the initial goal of maintaining or decreasing the City’s deferred maintenance/rehabilitation. In order for these scenarios to produce these results proactive continuous funding is necessary; on an annual basis, the City should monitor the management of overlay deferred maintenance. The potential delay in projects and the resulting buildup of more overlay work in the five-year time frame is not a debt that City will want to accept.

Through Bucknam’s analysis of the previous pavement database, work history dates and our experience with AC Overlay deterioration rates, it is important to point out that pavement sections that were overlaid in the early part of the mid-2000’s (FY’s 2007-2008) will need proper overlay maintenance approximately around fiscal year 2022-23 and beyond.

Figure 4 – Resulting Network PCI (Maintain PCI Budget)
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 21 ends

Section II
INCREASE PCI TO 80 PROGRAM (FIVE YEAR MODEL)
With the City striving to show proactive rehabilitation across all qualifying pavements, the $2.1 Million budget program was applied to current conditions to show the potential return on investment.

Building upon the short falls of the previous reporting model we increased the amount of funding available for overlay/rehabilitation efforts and focused our recommendations within geographic zones/neighborhoods.

This program incorporates pavement sections that have a functional class of Arterial (A, C) and Local (L).

Table 8 – Necessary Funding to Increase PCI to 80
Referring to Table 8, it is noted that the weighted PCI increases proactively through the five-year projection (73.7 to 81.4). Additionally, the annual deferred maintenance total decreases from $11.6 million to $6.9 million at the end of the five-years. If the City utilizes an average annual budget of $1,784,700/yr for slurry, overlay, and reconstruction maintenance as shown above, the City will be able to “increase” the current conditions and will continue to see an ample decrease in deferred maintenance (mostly overlay maintenance) by fiscal year 2027.

We recommend that a stronger focus be placed on the Local network improvements due to the fact that the Local network conditions are nine (9) PCI points lower than the Arterials. We still recommend consistent maintenance to the arterial network (i.e. localized patching, ARHM) through the use of awarded SB 1. Proposition C and Measure R funds. But again, with the Local network showing a higher degree of negative results, a new focus for neighborhood area maintenance and proactive overlays should be considered.

The resulting “increase of the weighted PCI” shown above for the entire network demonstrates how applying adequate capital funds to specific areas of the network allows the City’s pavement conditions to increase at a rate that is conducive to a successful PMP. Additionally, even with the limited budget, the City should continue to implement localized maintenance (i.e. alternative High Density Mineral Bond (HDMB) applications, Asphalt Zipper deep patching, leveling courses, crack sealing, etc.) prior to any major slurry seal and/or overlay maintenance. By performing stop gap measures to individual pavement sections prior to conventional slurry and overlay applications the overall performance of the sections condition sustain itself longer than if no stop gap maintenance was performed.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 22 ends

Section II
Figure 5 – Resulting Network PCI (Increase PCI to 80 Budget) The City should consider establishing a Local slurry/cape seal maintenance “neighborhood” strategy for several reasons. First, preventive maintenance applications applied five plus (5+) years after rehabilitation, like those mentioned above, will help to sustain high levels of condition while reducing annual expenditures. Secondly, with a citywide maintenance neighborhood methodology established, four beneficial impacts occur:
1) Planned / Maintenance areas are addressed through a multi-yr maintenance cycle which creates a dedicated project schedule for City staff and constituent inquiries; 2) Deferred overlay maintenance can be addressed in a more effective manner due to accrued savings of revenues (reduced construction logistical costs, volume-based costs, etc.) 3) A preventive maintenance strategy is more cost-effective in a long-term PMP rather than implementing a maintenance approach that addresses only the “worst-first” streets. 4) All maintenance alternatives are available due to the increased funding and focused maintenance per year.

The Local maintenance model that has been developed can be used as a benchmark to monitor the City’s annual budget allocations as the network continues to mature and age; the proper amount of funding for overlay maintenance needs to be the City’s highest priority.

Again, it is recommended that the City continue to monitor the deterioration rates for the applications of Grind & Overlay, Cape Seal and Type II slurry seal to ensure the City is generating the greatest return-oninvestment and extend life-cycles; this should be done through frequent inspections and deterioration studies.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 23 ends

Section II

PAVEMENT MANAGEMENT PROGRAM REPORTS
In addition to the annual budget scenario, this report contains a comprehensive and complementary assemblage of pavement management reports ranging from summary reports to annual maintenance and rehabilitation schedules (Forecasted Maintenance Report, Section IV). Collectively as well as individually, the reports represent reasonable projections of pavement maintenance needs and performance based on visual condition assessments, unit cost estimates, and pavement deterioration models.

It is important to note that pavement segment dimensions and surface area (recorded during the 2022 inspections), along with the action and repair costs, as presented within the reports are accurate within tolerable limits. This is noteworthy due to the "implied" accuracy of reporting length and width to the nearest foot, surface area to the nearest square foot, and action and repair unit costs and project estimates to the nearest penny and dollar, respectively.

NEXT STEPS
As with any infrastructure management software program, time investments need to be made by key Public Works staff to maintain the integrity of the data as well as the accuracy. Bucknam can perform training sessions in the use of the MicroPAVER system and demonstrate how to generate standard maintenance reports to assist City staff in developing yearly budgets, project level analysis, and CIP projections. This will be key to future staff management of the pavement program and reporting. City personnel need to maintain their commitment to the preventive maintenance system, while working toward reducing the City's present backlog of rehabilitation projects.

In order to ensure that report outputs are accurate and credible, it is essential that the integrity of all data files be maintained. This will require performing all necessary updates when changes are made to scheduling scenarios, unit cost information, historical data, etc. In addition, the entire pavement network will have to be re-inventoried at regular intervals. This typically includes surveying arterial and collectors every two years and Locals every three. One recommendation the City may consider to keep the program “managed” is:
• Survey arterials every two years; and
• Survey Locals every three years
This will not only allow work to be scheduled based on the most current condition data available, but will provide City personnel with a means to monitor actual rates of pavement deterioration so appropriate modifications can be made to the system curves. To be compliant with the METRO requirements, the City must generate a triennial Arterial and Collector network pavement management report indicating condition ratings.

Bucknam will be supporting the City with staff level support to assist in the continuous updates with the MicroPAVER system. This will include work history updates, generating reports from the system, unit cost updates, and future inspections.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 24 ends

Section II

CONDITION DISTRIBUTION REPORT
This report graphically depicts the distribution of the pavement condition throughout the street network by area.

The condition scheme ranges from “Excellent” to “Failed”; with a “Excellent” condition corresponding to a pavement at the beginning of its life cycle, and a “Failed” condition representing a badly deteriorated pavement with virtually no remaining life.

The table below shows the general description for each pavement condition:

Condition Description – PCI Range – Description
2022 City of Signal Hill weighted average PCI is 73.7 (Very Good).

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 25 ends

Section II

CALCULATION OF PCI
In order to calculate a Pavement Condition Index (PCI) value within MicroPAVER, specific street section data needs to be inputted into MicroPAVER to define the survey limits, asphalt types, pavement age and metrics. Pavement “sections” are pavement segments within the defined branch that have consistent pavement street classifications, construction/maintenance histories and use. Representative inspection samples are then selected and visually surveyed to locate distress data. This data is used to calculate the pavement sections Pavement Condition Index (PCI) which includes distress type, extent of the distress and its severity.

The PCI is a condition rating that ranges from 100 (pavement section that is in perfect condition) to 0 for a section that has structurally failed and deteriorated dramatically. The PCI is calculated from three major data entries from our inspectors:

1. Distress Type (one of 20 AC or 19 PCC types); these include alligator cracking, bleeding, block cracking, corrugations, depressions, long/trans cracking, patch/utility cut, potholes, rutting, weathering, raveling, etc.

2. Distress Quantity (the square footage, length or count of a specific distress)

3. Distress Severity (the level of severity determined for each distress found; low, medium or high)
Figure 6 – PCI Calculation Worksheet
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 26 ends

Section II
Figure 7 – Arterial Condition Distribution
Figure 8 – Local Condition Distribution
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 27 ends

Section III

SECTION III

CITYWIDE

PAVEMENT CONDITION INDEX REPORT
A. PCI Report Definitions
B. Signal Hill 2022 PCI Map
C. A to Z
D. PCI Order
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 28 ends

Section III

PAVEMENT CONDITION INDEX REPORT
Listed alphabetically by street name or PCI, this report provides the City with a listing of pertinent inventory and pavement condition data for each inventory unit within the City's pavement network. The Pavement Condition Index (PCI) Report notes the names, limits, classification, dimension, surface type, and lane configuration of each inventory unit.

Detailed descriptions of the information appearing on this report are presented below:

BRANCH NAME - The name of each inventory unit appears in this column. Generally, the inventory unit name is taken directly from a street sign; however, where no street signs are posted, the name appearing on the network map is noted instead.

A sample set ofstreet name suffix abbreviation definitions is presented below:

AVE - Avenue CT - Court CIR - Circle
DR - Drive LN - Lane RD - Road
ST - Street WY - Way EB - East Bound
NB - North Bound SB - South Bound WB - West Bound
TER - Terrace PL - Place
FROM - A description of the beginning limit of each inventory unit appears in this column. If the beginning limit exists between intersections, then the beginning limit description may be an address, post mile marker, or a distance from a known point of reference (e.g., "500' N/MAIN ST").

TO - A description of the ending limit of each inventory unit appears in this column. Like BEGIN limit, the END limit description may consist of a street name, an address, or a distance from a known point of reference. In the case of cul-de-sacs, or dead-ends, the END limit consists of and address, or a directional reference, such as "NORTH END," when no address is available.

STREET CLASSIFICATION - The codes for four street classifications are represented below. Basically, units are classified according the LA County MPAH and City classifications.

CODE DESCRIPTION
A Primary Arterial
B Arterial
C Collector / Secondary
E Local
SURFACE TYPE - A code was assigned to each inventory unit to describe surface type.

CODE DESCRIPTION
AC Asphalt Concrete
PCC Concrete
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 29 ends

Section III
LENGTH - The length of the section within each branch.

UNITS - The unit of measurement for the section length, typically linear feet (LF).

AREA - The area of each section within a branch.

UNITS - The unit of measurement for the section area, typically square feet (SF).

PCI - Pavement Condition Indices were calculated for inventory units based on severity and extent of distress manifestations observed within the inventory unit. Ranging between 0 and 100, a PCI of "100" corresponds to a pavement at the beginning of its life cycle, while a PCI of "0" corresponds to a badly deteriorated pavement which is at or near the end of its life cycle.

PCI CLIMATE, LOAD AND OTHER – reflects “Section Extrapolated Distress”; these values are shown within the Sample Distresses tab within the PCI window. Distresses are aggregated based on the type and severity level. For random samples, distress quantities are adjusted to reflect the extrapolated value based on the sections total area. Extrapolated distress deducts are classified as resulting from Climate, Load and Other distresses. The Distress Classification portion of the tab shows the “percent” of extrapolated distress deduct belonging to Climate, Load and Other (these %’s are shown within the PCI reports herein). These values are beneficial in that they support the decision whether recommend slurry seal, overlay or reconstruction project for street sections.

INSPECTION DATE – Represents the most recent inspection date performed on a given sections. PCI shown is historical in value and may not indicate what “today’s” PCI is due to variance in time. Pavement deterioration calculations can be performed on a section(s) to demonstrate a deteriorated PCI based upon a new current date.

City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 30 ends

Section III
Figure 9 – Signal Hill 2022 PCI Map
City of Signal Hill, CA
2022 Pavement Management Program
Final Report – February 18, 2022

Page 31 ends

Section IV

SECTION IV

FORECASTED MAINTENANCE REPORT
A. Increase PCI Budget, Five Year Plan (2022-2027)

FORECASTED MAINTENANCE REPORT
Section by section street listing sorted by street classification, plan year then alphabetically; this report presents the year and action corresponding to the next scheduled work activity for specific segments within the pavement network. Sections not shown are considered as deferred maintenance.

Increase PCI Budget – This budget was generated for the City to demonstrate how the City’s 5-Year Roadway Infrastructure funding allocation performs against the current citywide conditions. The City’s annual potential/planned budget is funded through the following sources:
• Gas Tax
• SB1
• Measure R
• Measure M (Potential reimbursement revenue to payback Street Bonds) • General Fund
• Proposition C
We have sorted the following report by street classificationsfor easy review (Arterial – Local, A to Z order).

The annual projected revenues shown below only account for the cost of pavement maintenance and rehabilitation activities. A 30% contingency was applied to the pavement costs. Additional right-of-way, utility, curb & gutter, ADA ramps, tree removals, etc. were not included in these cost projections.

In general sections are chosen first and foremost on available budget; secondly, the square footage of each section plays a large factor. The software initially chooses the draft sections that will increase PCI, sustain PCI or slow PCI deterioration within the budgeted timeframe. Additionally, the types of distress, extents of distress and severities of distress (high, medium, low) also determine how sections are/can be selected.

← All documents from this meeting