Exhibit “C”
Rates
MANHOURS & LEVELS OF EFFORTS ESTIMATES
City of Signal Hill
Local Roadwat Safety Plan (LRSP) Report
MINAGAR & ASSOCIATES,INC.
TASK AND DESCRIPTION PM PE SE FM SD EA
DIRECT
COST* TOTAL
1 ProjectManagement/Administration 22 0 0 0 0 8 $0 $5,550 2 Develop Plan Goals & Objectives 20 5 0 0 0 15 $0 $6,752 3 Establish Stakeholders 13 5 0 12 0 48 $0 $9,189
4 Analyze Safety Data 7 6 10 0 0 38 $0 $7,456
5 Field Visits 16 5 0 0 0 22 $0 $6,379
6 Develop Countermeasures 10 0 0 0 0 14 $0 $3,303
7 Local Roadway Safety Plan 10 5 5 0 0 30 $0 $6,468
8 Grant Funding Application Preparation and Support 14 8 5 0 4 43 $0 $9,684 Total Hours 112 34 20 12 4 218
Hourly Rate $224.92 $224.92 $167.24 $127.36 $165.72 $75.26 $0 Total Labor Cost ($) $25,191 $7,647 $3,345 $1,528 $663 $16,407 $0 $54,781 TOTAL COST NOT TO EXCEED $54,781
8/5/2022
NOTE: All the outlined tasks and related community & partner engagements shall be performed on the TOTAL COST not exceed PM Project Manager PE Project Engineer SE Senior Engineer SD Senior Designer EA Engineering Assistant FM Field Manager/Dep Rep