Contract Change Order No. 2 Date: August 18. 2022
Project Number: Capital Improvement Project No. 90.22003 Project Name: 2022 Slurry Seal Program
Contractor: Mission Paving and Sealing, Inc.
his Change Order covers changes to the subject Contract as described herein. The Contractor is to furnish equipment, materials, labor ar erform all work as necessary or required to complete the Change Order items at the prices agreed upon between the Contractor and the Cit Working
Cost
Days
Original Contract Amount: 259,725.00 40
Previous Change Orders Amounts: 35,564.40
This Change Order Amount: 3,152.00 0
Total Increase to Contract to Date: 38,716.40 0
Revised Total Contract Amount: 298,441.40 40
Percentage of Total (Increase/Decrease) to Contract Amount to Date: 14.91% FIRST WORKING DAY.. June 23, 2022
Working days specified in Contract. 40 working days
Administrative Delay 0 working days
ORIGINAL COMPLETION DATE August 19, 2022
Non-working days due to weather delays... 0 Non-working Days Non-working days due to Administrative Delay..... Non-working Days Contract Time Extensions by Previous Change Orders. Working Days Contract Time Extensions by This Change Order... Working Days REVISED COMPLETION DATE.. August 19, 2022
DESCRIPTION OF WORK COMPLETED, ESTIMATES OF QUANTITIES, AND PRICES TO BE PAID:
Change Add'l
Item No. Description Order Unit Unit Cost Change Order Cost Working Quantity Days
LS $ 3,152.000 $ 3,152.00 0
Estimated Total of This Change Order: S 3,152.00 0
PAYMENT FOR THIS WORK WILL BE MADE BASED ON FIELD MEASURED QUANTITIES AT THE ADJUSTED CONTRACT UNIT PRICES LISTED ABOVE AND THE TOTAL COST MAY DIFFER FROM THE ESTIMATED AMOUNT SHOWN ABOVE.
P: @CIP -Capital Improverent Projects12022 Slurry Seal Program\PAY MEN I Change Orders21CCO #2 - Thermoplastie Striping
Contract Change Order No. Date: August 18, 2022
Project Number: Capital Improvement Project No. 90.22003 Project Name: 2022 Slurry Seal Program
Contractor: Mission Paving and Sealing, Inc.
Approval Recommended by: Date: 8/18/2022
Patrick Kelley, E.L.T., Contracts Manager
Approved by: Date: 9/7/22.
Thomas Bekele, P.E. Director of Public Works
CONTRACTOR ACCEPTANCE STATEMENT
THIS CHANGE ORDER REPRESENTS FULL AND COMPLETE COMPENSATION FOR ALL DIRECT AND INDIRECT COSTS
INCLUDING, BUT NOT LIMITED TO, EXTENDED OR ADDITIONAL FIELD AND HOME OFFICE OVERHEAD, SUPERVISION,
LABOR, MATERIALS AND EQUIPMENT, INSURANCE, TAXES, BONDS AND PROFIT), ALL ESCALATION, DELAY, DISRUPTION,
ACCELERATION, INEFFICIENCIES, LOST PRODUCTIVITY, DIFFERING SITE CONDITIONS AND/OR CONSTRUCTION
INTERFERENCES ARISING OUT OF OR AS A RESULT OF THIS CHANGE ORDER OR THE RIPPLE EFFECT OR CUMULATIVE IMPACT OF THIS CHANGE ORDER ON THE PERFORMANCE OF THE OVERALL WORK UNDER THE CONTRACT. THE PARTIES
HERETO AGREE THAT THIS CHANGE ORDER CONSTITUTES A MUTUAL ACCORD AND SATISFACTION WITH RESPECT TO ALL
CLAIMS FOR IMPACTS, SCHEDULE EXTENSION OR ANY COSTS OF WHATSOEVER NATURE, WHETHER KNOWN OR UNKNOWN, ARISING OUT OF THIS CHANGE ORDER.
Accepted by: Date: 819-22
Mike Miller, Mission Paving and Sealing, Inc.
P.V@CIP - Capital Improvement Projects\2022 Slurry Scal Program PAYMEN/Change Orders:2ICCO #2 - Thermoplastic Striping