Cities Index.
American Asphalt South Change Order No. 1

Signal Hill City Council
March 28, 2023

Document
American Asphalt South Change Order No. 1
Meeting
March 28, 2023
Body
Signal Hill City Council
Pages
3
Original file
1.7 MB
Text extracted from the city's file for reading and search. Open the original on cityofsignalhill.legistar1.com. That file is the official record.
Page 1 of 3 ends

1 Date:

Cost Working
Days
Original Contract Amount: $ 122,470.00 60
Previous Change Orders Amounts: 0
This Change Order Amount: $ 5,384.00 0
Total Increase to Contract to Date: $ 5,384.00 0
Revised Total Contract Amount: $ 127,854.00 60
Percentage of Total (Increase/Decrease) to Contract Amount to Date: 4.40% FIRST WORKING DAY………………………………...………………………..………………………….

Working days specified in Contract………………………………………………………………… 60 Administrative Delay …………...…………………………………...……………………………… 0 ORIGINAL COMPLETION DATE…………………………………………………………………………………… Non-working days due to weather delays…...…………………………………………………… 0 Non-working days due to Administrative Delay…...……………………………………………… 0 Contract Time Extensions by Previous Change Orders…...…………………………………… 0 Contract Time Extensions by This Change Order……………………………………………… 0 REVISED COMPLETION DATE…………………………………………………………………
Item No.

Change
Order
Quantity
Unit Unit Cost Change Order Cost
Add'l
Working
Days
1 11 Ton $ 550.00 $ 6,050.00 0
2 16 Ton $ 440.00 $ 7,040.00 0
3 1 LS $ 18,794.00 $ 18,794.00 0
Contractor: American Asphalt South, Inc.

This Change Order covers changes to the subject Contract as described herein. The Contractor is to furnish equipment, materials, labor and perform all work as necessary or required to complete the Change Order items at the prices agreed upon between the Contractor and the City.

February 6, 2023
DESCRIPTION OF WORK COMPLETED, ESTIMATES OF QUANTITIES, AND PRICES TO BE PAID:

Description
working days
working days
Non-working Days
May 3, 2023
Contract Change Order No. January 24, 2023
Project Number: 90.23003
Project Name: Slurry Seal 2022-2023 Program
Non-working Days
Working Days
Working Days
May 3, 2023
Construct asphalt digout repairs per limits identified on attached exhibit. This Change Order adds quantity to bid line item 4 to accommodate all of the repairs. Work to be paid based on actual field-measured quantities and delivery tickets.

Provide hot-applied type 1 crack seal at all project limits for cracks from 1/4" to 2" per attached specifications.

Construct asphalt digout repairs per limits identified on attached exhibit. This Change Order adds base material
quantity to bid line item 5 to accommodate all repairs. Work to be paid based on actual field-measured quantities and delivery tickets.

P:\@CIP - Capital Improvement Projects\2022-2023 Slurry Seal Program\Construction\Change Orders\CCO 1 DocuSign Envelope ID: F7534773-FF05-4C1A-972F-1488643FB005

Page 2 of 3 ends

1 Date:

Contractor: American Asphalt South, Inc.

Contract Change Order No. January 24, 2023
Project Number: 90.23003
Project Name: Slurry Seal 2022-2023 Program
4 1 LS $ (26,500.00) $ (26,500.00) 0
Estimated Total of This Change Order: $ 5,384.00 0

PAYMENT FOR THIS WORK WILL BE MADE BASED ON FIELD MEASURED QUANTITIES AT THE ADJUSTED CONTRACT UNIT PRICES LISTED ABOVE AND THE TOTAL COST MAY DIFFER FROM THE ESTIMATED AMOUNT SHOWN ABOVE.

Delete bid item 7 from project scope: "Remove and replace damaged cross gutter on Lemon Avenue and 23rd Street per standard plans 222 and 225. Contractor to remove and
replace cross gutter beginning at the weakened plane control joints (Joint B per standard plan no. 222). This price includes all labor, equipment, and materials, including new base material, dowels, concrete, and asphalt concrete slot
patching."
P:\@CIP - Capital Improvement Projects\2022-2023 Slurry Seal Program\Construction\Change Orders\CCO 1 DocuSign Envelope ID: F7534773-FF05-4C1A-972F-1488643FB005

Page 3 of 3 ends

1 Date:

Contractor: American Asphalt South, Inc.

Contract Change Order No. January 24, 2023
Project Number: 90.23003
Project Name: Slurry Seal 2022-2023 Program
Date:

Approved by: Date:

Accepted by: Date:

THIS CHANGE ORDER REPRESENTS FULL AND COMPLETE COMPENSATION FOR ALL DIRECT AND INDIRECT COSTS (INCLUDING, BUT NOT LIMITED TO, EXTENDED OR ADDITIONAL FIELD AND HOME OFFICE OVERHEAD, SUPERVISION,

LABOR, MATERIALS AND EQUIPMENT, INSURANCE, TAXES, BONDS AND PROFIT), ALL ESCALATION, DELAY, DISRUPTION,

ACCELERATION, INEFFICIENCIES, LOST PRODUCTIVITY, DIFFERING SITE CONDITIONS AND/OR CONSTRUCTION

INTERFERENCES ARISING OUT OF OR AS A RESULT OF THIS CHANGE ORDER OR THE RIPPLE EFFECT OR CUMULATIVE IMPACT OF THIS CHANGE ORDER ON THE PERFORMANCE OF THE OVERALL WORK UNDER THE CONTRACT. THE PARTIES

HERETO AGREE THAT THIS CHANGE ORDER CONSTITUTES A MUTUAL ACCORD AND SATISFACTION WITH RESPECT TO ALL

CLAIMS FOR IMPACTS, SCHEDULE EXTENSION OR ANY COSTS OF WHATSOEVER NATURE, WHETHER KNOWN OR UNKNOWN, ARISING OUT OF THIS CHANGE ORDER.

Patrick Kelley, E.I.T., Contracts Manager
Thomas Bekele, P.E. Director of Public Works

CONTRACTOR ACCEPTANCE STATEMENT
Tim Griffin, American Asphalt South, Inc.

Approval Recommended by:

P:\@CIP - Capital Improvement Projects\2022-2023 Slurry Seal Program\Construction\Change Orders\CCO 1 DocuSign Envelope ID: F7534773-FF05-4C1A-972F-1488643FB005 1/24/2023
1/27/2023
2/16/2023
DocuSign Envelope ID: F7534773-FF05-4C1A-972F-1488643FB005 DocuSign Envelope ID: F7534773-FF05-4C1A-972F-1488643FB005 SECTION 203 BITUMINOUS MATERIALS
Add the following sub-section:
203-17 CRACK SEALANT
303-17.1 SMALL CRACK SEALANT
203-17.1.1 GENERAL
Small crack sealant material shall consist of an asphaltic emulsion mixture used for filling/sealing cracks in asphalt concrete up to 1” wide.
203-17.1.2 MATERIAL
The small crack sealant material shall comply with section 37-6.02 MATERIALS of the CalTrans Standard Specifications 2018 edition. Type 1 for Residential/Local Streets and Type 2 for Major Streets and larger.

Material shall be per Caltrans Authorized Material List for Asphalt Concrete Pavement Crack Treatment or equal approved by the Engineer.
303-17.2 LARGE CRACK SEALANT
203-17.2.1 GENERAL Large crack sealant material shall consist of an asphaltic emulsion mixture used for filling/sealing cracks in asphalt concrete 1-2” wide.
203-17.2.2 MATERIAL Material shall be per Caltrans Authorized Material List for Asphalt Concrete Pavement Crack Treatment or equal approved by the Engineer.

SECTION 302 ROADWAY SURFACING
Add the following sub-section:
302-15 CRACK SEAL
302-15.1 GENERAL
Crack seal material shall conform to 203-17 CRACK SEALANT. 302-15.2 Site Preparation
Treat cracks from ¼ to 2 inch in width for the entire length of the crack. All cracks to be sealed shall be completely clean, dry, and free of all loose material, vegetation, and any other foreign substance which may cause the sealant not to adhere to the crack wall.

The Contractor shall treat all vegetation within the limits of the paved area to receive surface seal treatment with a post emergent herbicide. Herbicide shall be applied at least 5 (five) working days prior to sealing the street. Allowance for the five-day period shall be shown in the schedule required per Section 6-1, Construction Schedule and Commencement of the Work.

Cracks shall be cleaned using a hot compressed air lance (HCL) apparatus. The Contractor shall clean and dry all cracks with the HCL immediately before sealing. Air exiting the lance shall be heated to a DocuSign Envelope ID: F7534773-FF05-4C1A-972F-1488643FB005 temperature sufficient enough to remove the oxidized surface from the crack walls. The HCL shall meet the following requirements:
- Compressed air capacity: 90 PSI min.
- Heated air temperatures: 600 F to 2,200 F
- Exit heated air: 1,000 ft/sec.
- Propane: 5 to 20 PSI
The joints and cracks shall be inspected and approved by the Engineer prior to placing the crack sealant material. Final joint and crack cleaning will be the same day of the sealing operation except as otherwise approved by the Engineer or his designee.
302-15.3 Application
302-15.3.1 Small Cracks (¼ - 1” Wide)
Sealant shall be prepared and applied to the pavement cracks in conformance with all manufacturers’ instructions except where noted otherwise in this document. - Sealant shall be applied when the pavement surface temperature is greater than 50°F. - Containers of hot-melt rubberized sealant shall be delivered to the job-site in unopened containers that are clearly marked with data showing the manufacturer's name, the product designation and the manufacturer's batch number and lot numbers.
- The hot-melt rubberized asphalt shall be melted in a jacketed, double boiler type melting unit. - Application of the hot-melt sealant shall be made with a pressure feed applicator or pour pot. - Sealant shall be applied from the bottom of the crack up to the surface in a manner which does not result in sealant bridging or entrapping air pockets.
- Apply crack treatment with a nozzle inserted into the crack. The sealant shall be applied to a slightly overfilled condition and then leveled with a squeegee. The overband shall not exceed 1” on either side of the crack.
- If after two days the crack treatment is more than 1/4 inch below the specified level, the sealant fails, or the crack re-opens, re-treat the crack.
- Immediately remove crack treatment material that is spilled or deposited on the pavement surface. - Before opening to traffic, apply sand or the manufacturer’s recommended detackifying agent to tacky crack treatment on the traveled way.
- Sweep up excess sand before opening to traffic.
302-15.3.1 Large Cracks (1-2” Wide)
Sealant shall be installed per the manufacturer’s recommendation.

DocuSign Envelope ID: F7534773-FF05-4C1A-972F-1488643FB005 DocuSign Envelope ID: F7534773-FF05-4C1A-972F-1488643FB005

← All documents from this meeting